THERMAL POWER STATION II

MAINTENANCE PROGRAMME - INTERNAL PLAN - 2007 - 2008


Sl.No. UNIT FROM
TO
No. of Days
Works proposed
11/12/07

20

Statutory Boiler Inspection, RS duct refractory rectification, Furnace & coil cleaning, RAPH basket
change, Retrofitting of dense phase pneumatic fly ash handling system

22/06/07 24/06/07

Statutory Boiler Inspection

12/12/07 31/12/07

20

RS duct refractory rectification, Furnace & coil cleaning , ABG change, Retrofitting of dense phase
pneumatic fly ash handling system

24/08/07 02/10/07

40

Statutory Boiler Inspection, RS duct refractory rectification, Furnace & coil cleaning , ABG change,
DCS implementation, Retrofitting of dense phase pneumatic fly ash handling system

03/06/07 05/06/07

Statutory Boiler Inspection

23/09/07 12/10/07

20

RS duct refractory rectification, Furnace & coil cleaning, Retrofitting of dense phase pneumatic fly
ash handling system

25/05/07 27/05/07

Statutory Boiler Inspection

13/10/07 26/11/07

45

Boiler O/H, ABG change,TG overhaul, Gen. Overhaul, Retrofitting of dense phase pneumatic fly ash
handling system, Retrofitting of GRP

21/11/07

II
3

III

5
IV

V
8

VI

08/09/07 27/09/07

20

Statutory Boiler Inspection, RS duct refractory rectification, Furnace & coil cleaning, Retrofitting of
dense phase pneumatic fly ash handling system

10

VII

15/07/07 13/08/07

30

Statutory Boiler Inspection, Boiler O/H, RAPH basket change, IS / OS upgradation work,
Retrofitting of dense phase pneumatic fly ash handling system, Retrofitting of GRP