Unit-6 overhaul was planned for a period of 35 days to carry out Boiler &Aux OH, 28% Eco coil
addition, IPT OH, TG brgs. insp., UAT-B repl. works. Accordingly Engineering Declaration was
prepared, Overhaul Plan was released. Unit-6 overhaul started from 22.07.2016. As planned
all the works were completed and Unit was synchronized on 22.08.2016 with duration of 31.79
days. Bar chart Planned / Actual for Critical activity of IPT OH ,Boiler 28% Eco surface area
addition is given in Annexure.
OVERHAUL HISTORY :
Cumul.
Sl.
Run From To Days Major Works Carried Out
No.
hours
LPT +GEN+BLR
1 13209 18.09.92 21.10.92 34 OH+CONDENSER CHEMICAL
CLEANING
O/H of Boiler and Aux.,
2 21627 13.10.93 15.11.93 33 Generator seals replacement,
LPT-Generator realignment.
Overhaul of Boiler and Aux.,
3 28858 03.09.94 24.09.94 21
TDBFP-6B & MDBFP overhaul
4 38689 21.11.95 08.12.95 18 Boiler & Auxiliaries Overhaul
HPT/IP Turbine, Boiler & Unit
5 44640 16.08.96 08.10.96 54
auxiliaries overhaul.
Boiler & Unit auxiliaries
6 49778 03.05.97 23.05.97 21
overhaul, TG High vibrations
rectification