Professional Documents
Culture Documents
(BSR)
Overview/ General Procedure
SRLDC, Bangalore
Outline
Introduction
Largest outages in History
State Transition
BSR in IEGC & RLDC documents
Grid Incident & Grid Disturbance
Start up power requirement
Restoration problems
Restoration strategies
Restoration tasks- steps to be followed
Do’s & Don’ts
Introduction
• Definition Of Blackout
• Need for Black start restoration procedures
• Causes For Blackout
Blackout??
It refers to the total loss of power to an area
and is the most severe form of power outage
that can occur
How long it takes ??
Outages may last from a few minutes to a few
weeks depending on the nature of the blackout
and the configuration of the electrical network
Need for Black Start Restoration
Procedures (BSRP)
People
Sl. Year Cause affected Country Restorati
No. on time
1 Oct.2012 Hurricane Sandy- 8.2 million 17 states 2 weeks
Flooding & downed in US
trees cut power to
3 June 2012 Wind storm cut power 4.2 million 12 states 7-10 days
to in USA
9
State Transition Diagram
Normal(Secure)
Restorative Alert(In-Secure)
Extremis Emergency
11
Power System Restoration Cycle
Actual
Actual
Restoration
Restoration
Event
Event
Restoration
RestorationDrills
Drills
Assess
Assess
Restoration Lessons
Lessons
RestorationTraining
Training Learned
Learned
Revise
Revise Engineering
Restoration Engineering
RestorationPlan
Plan Analysisand
Analysis andStudies
Studies
And Procedures
And Procedures
Emphasis of Black Start Restoration in
IEGC
5.2 (n) System Security Aspects:
Procedures shall be developed to recover from partial/total
collapse of the grid and periodically updated in accordance
with the requirements given under section 5.8. These
procedures shall be followed by all the Regional
constituents to ensure consistent, reliable and quick
restoration.
5.8 (a) Recovery Procedures:
Detailed plans and procedures for restoration of the
regional grid under partial/total blackout shall be
developed by RLDC in consultation with all Regional
constituents / RPC Secretariat and shall be 12
Emphasis of Black Start Restoration in IEGC
17
Categorization of Grid Disturbance (GD)
Category GD-1
When less than 10% of the, antecedent generation or load
in a regional grid is lost.
Category GD-2
When 10% to less than 20% of the antecedent generation
or load in a regional grid is lost.
Category GD-3
When20% to less than 30% of the antecedent generation
or load in a regional grid is lost.
Category GD-4
When 30% to less than 40% of the antecedent generation
or load in a regional grid is lost.
Category GD-5
When 40% or more of the antecedent generation or load
in a regional grid is lost.
18
Plant Start-up Power Requirement
21
Restoration Strategies
22
“TOP DOWN” STRATEGY
23
Steps involved in the
“Top-down Strategy”
24
“Bottom up” Strategy
25
Steps involved in the
“Bottom-up Strategy”
26
RESTORATION TASKS- STEPS TO BE FOLLOWED
Network Preparation
Network Energization
Load Restoration
System Rebuilding
28
System Status Determination
29
Network Preparation
• De- energise all buses
30
Starting up Black start/ Self start Units
31
Network Energization - Considerations
• Identify the Important and Essential Loads to be
Restored First
• At Every Stage it Should Satisfy
– Reactive Power Balance (Voltage Control)
– Load Generation Balance (Frequency Control)
– Protection and Plant Control System Requirements
• Paralleling of Islands through Strong Links
32
Network Energization – Reactive Power Balance
33
Network Energization– Load Generation Balance
34
Network Energization – Protection &Plant Control
System Considerations
35
Load Restoration
36
Load Restoration-Considerations
37
Restoration Planning – Common Concerns
38
Do’s and Don’ts during Black Start Restoration
46
Thank You