Professional Documents
Culture Documents
Technical Sheet: On Plot Sewage Disposal
Technical Sheet: On Plot Sewage Disposal
Technical Sheet
TECHNICAL SHEET
On Plot Sewage Disposal
Compliance with this
Technical Sheet is to be seen
as a minimum standard to be
achieved and all installations
must be approved by the
WMA and constructed strictly
in accordance with the
approved design.
To
absorption
pit or
leaching
field
Scum
layer
Sludge
Min 1m
waterproof construction
Septic Tank Design
TECHNICAL SHEET
On Plot Sewage Disposal
Design parameters and suggested
good practice for septic tanks.
PARAMETER
GOOD PRACTICE
24hrs minimum
24hrs minimum
3 cubic metres
1 metre
30 metres
15 metres
75 milimetres
INSTITUTION/PREMISES
Schools
Pensionat, Homes
Cinema, Theatre
Hotels
* septic tanks are only to be used for the treatment of domestic sewage from factories and similar businesses. Industrial
effluent should normally be treated using a dedicated wastewater treatment plant to achieve the standards required
prior to discharge to the environment.
TECHNICAL SHEET
On Plot Sewage Disposal
Purification
1.2m min
PARAMETER
GOOD PRACTICE
infiltration rates
natural ground)
Effluent flow rate
1.2 metres
1.2 metres
30 metres
2 metres
boundary
Minimum distance between absorption pits,
TECHNICAL SHEET
On Plot Sewage Disposal
50>K>20
30>K>20
20>K>20
SOIL PERMEABILITY
High
Good
Average
Poor
Very low
50
30
20
10
From
septic
tank
25
10>K>6
0.6- 1.0m
Topsoil, grass
20-40mm gravel
1.5m
0.6m trench
30m max
Pipes at max 1% gradient
Purification
1.2m
min
30m minimum
TECHNICAL SHEET
On Plot Sewage Disposal
Principal design parameters for
leaching fields
PARAMETER
GOOD PRACTICE
600mm
Diameter of pipes
Minimum 100mm
30m
1%
Pipe perforations
1500mm
1.2 metres
1.2 metres
30 metres
1 metre
boundary
Minimum distance between leaching fields, either
2 metres
50>K>20
30>K>20
20>K>20
SOIL PERMEABILITY
High
Good
Average
Poor
Very low
50
30
25
20
10
10
13
20
10
20
10>K>6
TECHNICAL SHEET
On Plot Sewage Disposal
DESIGN CHECKLIST
Are there mains sewers
nearby or planned for
future installation?
Is the plot large enough
to permit on-site sewage
disposal?
Is the plot outside any
flood hazard area?
Is there a sufficient depth
of soil to bedrock or any
impermeable layer to
allow a leaching field
or absorption pit to be
constructed and used
safely?
Is the groundwater table
deep enough to allow an
absorption pit or leaching
field to be used?
Is there a minimum
distance of 30m to any
water body?
Is there a minimum
distance of 200m to any
borehole, spring or well?
Is the ground slope
and local geography
satisfactory to prevent
effluent rising to the
surface on the plot or on
any nearby properties?
Is the proposed
installation at least
the correct minimum
distances from other
installations and
structures etc?
Is there sufficient space
available to allow the
construction of a second
pit or leaching field when
the initial one becomes
clogged?
TECHNICAL SHEET
On Plot Sewage Disposal
Keep rainwater from roofs and drives etc away from
the leaching field or absorption pit and dont let it
enter the septic tank
Wastewater Management
Authority
The Operation and
Maintenance Unit and/or
The Pollution Control Unit
5th Floor, Aisha Building
Louis Pasteur Street
Port louis
Mauritius
Dont
Allow vehicles or heavy equipment to drive over the
septic tank, leaching field or absorption pit, or pipelines
Plant trees or shrubs on or near to the leaching field
or absorption pit. The roots damage and block the
system.
Possible Arrangement of Services
Telephone:
217 0300
Fax:
216 1925
E-mail: wwa@bow.intnet.mu
NOTE
The siting of Absorption Pits can
have an effect upon adjoining
plot layouts. It is important to
be aware of the dimensions of
adjoining pits and their locations
x = 2m minimum
x
Absorption Pit
Approx 2.5m
diameter typically
x
Absorption Pit
House
e.g. 5 occupants
1000 litres per day
Indicative layout
Minimum of 2
times diameter
of largest
absorption pit
x
Septic Tank
Min 3m3
capacity
TECHNICAL SHEET
On Plot Sewage Disposal
Boundary
Boundary
1m minimum
2m minimum
Leaching Field
Min 20m2 Area
2m minimum
Septic Tank
Min 3m3 capacity
Flow from
house
1m minimum
NOTE
No impermeable surfacing should be
placed over the leaching field
2m minimum
1m minimum
House
e.g. 5 occupants
1000 litres per day
Boundary
1m minimum
2m minimum
Leaching Field
Min 20m2 Area
2m minimum
Septic Tank
Min 3m3 capacity
2m minimum
House
e.g. 5 occupants
1000 litres per day
1m minimum