Professional Documents
Culture Documents
Manejo Contingencia PS Feb 07
Manejo Contingencia PS Feb 07
1, FEBRUARY 2007
205
II. INTRODUCTION
ESTRUCTURING of the electric power industry has resulted in the unbundling of main and ancillary services
(AS) such as real power, reactive power, and reserve provision.
Unlike the centralized reliability management used in conventional vertically integrated power systems, these main and ancillary services are traded as products in a power market to provide
an opportunity for both Gencos and customers to participate in
system reliability management. In the process of realization of
self-desired reliability, the participants objective in this competitive environment is to maximize their individual benefits.
206
(2)
The total power purchased by customer
market is
(3)
There is also an AS market for reserve and load curtailment
bidding in a hybrid market. Gencos submit their reserve bids
to the reserve market. It is assumed that the reserve units cannot
participate in the energy market, and they are available to take up
load when requested. The reserve bid prices are awarded when
the reserve units are called upon to supply in case of contingencies.
The total reserve in the AS market is
(4)
Customers bid for load curtailment in the AS spot market and
for
through bilateral contracts. A customer submits price
GOEL et al.: FRAMEWORK TO IMPLEMENT SUPPLY AND DEMAND SIDE CONTINGENCY MANAGEMENT
207
208
(8)
The curtailment limits for the Gencos in the spot market:
(9)
The curtailment limits for the Customers in the spot
market:
(10)
The limits for the available generation from the Gencos:
(11)
The limits for reserve:
(12)
In conventional power systems, the minimum system interruption cost is determined based on the system-wide curtailment cost due to system-wide supply shortage and reserve cost.
In restructured power systems, the reserves supplied by Gencos
and the activation of customers load curtailment bids are determined by market forces. During contingency state , the ISO
has to determine the reserve units to be dispatched and the customers to be interrupted under the minimum total cost of load
curtailment and reserve dispatched. The contingency management problem by the ISO is formulated as a linear programming
problem with the objective of minimizing the total cost, which
includes the curtailment costs of bilateral customers, the curtailment costs of the spot market customers, and the cost of the
reserve dispatched.
Problem Formulation
(5)
Subject to the following constraints:
The power balance constraints:
(6)
The reserve constraint of the spot market:
(7)
(13)
where is the power flow and
is the upper limit of
for line ; optimal dc power flow [16] is used to solve
the problem if transmission is considered.
The variables (or output) for this optimization problem for the
,
contingency state are the bilateral contract curtailments
, Gencos spot transcustomers spot transactions curtailment
, and the dispatch from reserve units
actions curtailment
. The contingency state transactions
,
,
are determined by subtracting the curtailments
,
,
from
,
,
. The sum of the continthe original transactions
gency state spot transactions
and bilateral transactions
of a Genco is equal to its total generation after re-dispatch
.
It should be noted that energy and ancillary services are dispatched separately. However, energy and ancillary services can
be optimized simultaneously in a single market. One of the possible situations is the Poolco market structure. For example, the
power market in Singapore includes both energy and ancillary
services in a single market clearing process to minimize the total
market cost.
VI. RELIABILITY EVALUATION PROCEDURE USING
NONSEQUENTIAL MONTE CARLO SIMULATION
A nonsequential Monte Carlo simulation (MCS) technique
for the reliability evaluation of restructured power systems in
hybrid market models was developed based on the proposed
framework for contingency management. A two-state model
of generating units was used in the simulation. Exponentially
GOEL et al.: FRAMEWORK TO IMPLEMENT SUPPLY AND DEMAND SIDE CONTINGENCY MANAGEMENT
209
distributed times to failure are assumed for each unit, and the
outage replacement rate (ORR) [11] is used.
The procedure to determine the system state for sample is
as follows.
is
A uniformly distributed random number
generated for each unit scheduled in the energy and reserve
market to determine the state of the unit
Operating state
Failure state
if
if
(14)
units is determined based
The state of Genco with
on the state of each unit of the Genco
(15)
The total available generation from Genco
by
is determined
(16)
The available reserve from each unit in the primary reserve
market is determined by
Fig. 2. IEEE reliability test system.
(17)
The state of the system is determined based on the state of
the Gencos and the transmission lines.
If
for sample and there are no transmission
for
outages, then the system is in the normal state. If
sample , or if there is transmission congestion, then the system
is in contingency state . If sample results in a contingency
state , then all the symbols with subscript are represented by
subscript .
The procedure to evaluate the customer reliability is as follows.
Step 1) Input transactions, reserve and curtailment bids,
and the reliability data determined from the hybrid
market.
Step 2) Generate the sample state of all the units scheduled
in the market by using (14).
Step 3) Determine the states of each Genco using (14) and
(15).
,
using (16) and (17), respecStep 4) Evaluate
tively.
Step 5) Check the state of the Gencos and transmission lines
to determine the system state. If the system is in a
contingency state, go to Step 6; else, if the system is
in the normal state, go to Step 9.
,
,
, and
using the optiStep 6) Determine
mization technique for the contingency state.
Step 7) Inform the Gencos about the reserve units dispatch
and contingency state transactions.
Step 8) Inform the customers about the load curtailments and
contingency state transactions.
, go to Step 2; else, go to Step 10.
Step 9) If
Step 10) Calculate the customer reliability indexes, reserve
dispatched, and market interruption cost.
is
(18)
The expected reserve dispatched (ERD) from the reserve market
is
(19)
The expected market interruption cost (EMICOST) is
(20)
210
TABLE I
ELNS (MW) OF THE CUSTOMERS
TABLE II
ELNS (MW) OF THE CUSTOMERS
TABLE III
ELNS (MW) OF THE CUSTOMERS
The curtailment bids are shown in Table VI. The energy and reserve units participating in the market are shown in Table VII.
Three different cases of reserve bids submitted by the Gencos
are shown in Table VIII. The lead-time is assumed to be four
hours.
A. Customer Reliability Indexes
The customer reliability indexes for the reserve bids of Case I
(of Table VIII) are presented in Table I. The solutions converge
after 2500 Monte Carlo samples. It can be observed from Table I
that the ELNS of customers depend on the curtailment bids of
customers and the portion of spot and bilateral transactions. The
difference between spot and bilateral transactions curtailments
is that the bilateral transaction curtailment of a customer is based
on the generation inadequacy resulting from the corresponding
Genco, whereas in the case of spot market transactions, the customer curtailment is based on the generation inadequacy of the
pool. For instance, aggregated customer L15 has 80% bilateral
transactions and 20% spot transactions. The spot transactions
have low ELNS, and the bilateral transactions have high ELNS.
Therefore, the ELNS of L15 in the hybrid market is very high.
The expected reserve dispatched (ERD) from G1, G9, and
G10 is 65.45 MW. The costs for the reserve dispatched by
Gencos G1, G9, and G10 and the costs for the curtailment of
customers L1 to L17 are shown in Fig. 3.
B. Effect of Reserve Bid Price
The impact of reserve bid price on the ELNS of customers
was investigated. The ELNS of customers for the three cases of
reserve bid prices of Table VIII are presented in Table II. The
ELNS of customers L1L6 show high values when their curtailment bids are lower than the reserve bids. Similarly the ELNS
of customers L1L6 show lower values when their curtailment
bids are higher than the reserve bids. The ELNS of customer
L7L17 who have bid higher than the reserve bids do not show
wide variations of ELNS in all the three reserve bid price cases.
C. Effect of Transmission Lines
The impacts of transmission lines on the ELNS of customers
for reserve bids of Case I were investigated and are shown in
Table III.
Three cases of a transmission network were considered. In
Case A, the transmission network was not considered; in Case
GOEL et al.: FRAMEWORK TO IMPLEMENT SUPPLY AND DEMAND SIDE CONTINGENCY MANAGEMENT
TABLE IV
FAILURE RATE DATA OF THE GENERATING UNITS
211
TABLE VI
CURTAILMENT BID DATA IN THE HYBRID MARKET
TABLE VII
ENERGY AND RESERVE UNITS PARTICIPATING IN THE HYBRID MARKET
TABLE V
TRANSACTIONS (MW) IN THE HYBRID MARKET
TABLE VIII
DIFFERENT SET OF RESERVE BIDDING PRICES ($/MW)
B, the transmission lines were considered in load flow calculations; and in Case C, three lines between bus 13 and 23, bus 14
and 16, and bus 16 and 19 were removed. The ELNS of customers for the three cases are shown in Table III. The results
clearly show that transmission outages result in higher ELNS of
customers.
VIII. CONCLUSIONS
This paper proposes a framework to implement supply side
reserve bids and demand side load curtailment bids for contingency management in reliability assessment of restructured
power systems with hybrid market models. The IEEE RTS has
been analyzed to illustrate the proposed technique. The impacts
on customer reliability indexes of factors such as the spot and
bilateral transactions of customers, reserve prices, and transmission constraints have been discussed. The reliability indexes
provide the expected demand curtailed for a particular customer.
The customers can bid for load curtailment more judiciously
based on 1) the reliability indexes and 2) their ability to reduce
or shift the load. The developed framework and the technique
provide a possible tool for the ISO to implement the participation of Gencos and customers in reliability management.
212
[6] E. H. Allen and M. D. Ilic, Reserve markets for power systems reliability, IEEE Trans. Power Syst., vol. 15, no. 1, pp. 228233, Feb. 2000.
[7] L. A. Tuan and K. Bhattacharya, Competitive framework for procurement of interruptible load services, IEEE Trans. Power Syst., vol. 18,
no. 2, pp. 889897, May 2003.
[8] M. Fahrioglu and F. L. Alvarado, Designing incentive compatible contracts for effective demand management, IEEE Trans. Power Syst., vol.
15, no. 4, pp. 12551260, Nov. 2000.
[9] , Using utility information to calibrate customer demand management behavior models, IEEE Trans. Power Syst., vol. 16, no. 2,
pp. 317322, May 2001.
[10] J. Wang, N. E. Redondo, and F. D. Galiana, Demand-side reserve offers in joint energy/reserve electricity markets, IEEE Trans. Power
Syst., vol. 18, no. 4, pp. 13001306, Nov. 2003.
[11] R. Billinton and R. N. Allan, Reliability Evaluation of Power Systems,
2nd ed. New York: Plenum, 1996.
[12] R. Billinton and W. Li, Reliability Assessment of Electric Power Systems using Monte Carlo Methods. New York: Plenum, 1994.
[13] W. Li and R. Billinton, A minimum cost assessment method for composite generation and transmission system expansion planning, IEEE
Trans. Power Syst., vol. 8, no. 2, pp. 628635, May 1993.
[14] G. Tollefson, R. Billinton, G. Wacker, E. Chan, and J. Aweya, Canadian customer survey to assess power system reliability worth, IEEE
Trans. Power Syst., vol. 9, no. 1, pp. 443450, Feb. 1994.
[15] Reliability Test System Task Force, IEEE reliability test system,
IEEE Trans. Power App. Syst., vol. PAS-98, no. 6, pp. 20472054,
Nov./Dec. 1979.
[16] A. J. Wood and B. F. Wollenberg, Power Generation Operation, and
Control. New York: Wiley, 1994.
Lalit Goel (SM95) was born in New Delhi, India, in 1960. He received the
B.Tech. degree in electrical engineering from the Regional Engineering Col-
lege, Warangal, India, in 1983 and the M.Sc. and Ph.D. degrees in electrical
engineering from the University of Saskatchewan, Saskatoon, SK, Canada, in
1988 and 1991, respectively.
He joined the School of Electrical and Electronic Engineering at the Nanyang
Technological University (NTU), Singapore, in 1991, where he is presently
Head of the Division of Power Engineering.
Dr. Goel received the 1997 and 2002 Teacher of the Year Awards for
the School of Electrical and Electronic Engineering, NTU. He served as
Vice-Chairman of the IEEE Power Engineering Societys Winter Meeting
2000 and as Chairman of the IEEE PES Powercon 2004 conference held
in Singapore. He received the IEEE Power Engineering Society Singapore
Chapter Outstanding Engineer Award in 2000. He is the Regional Editor for
Asia for the International Journal of Electric Power Systems Research and a
Deputy Director at NTUs Protective Technology Research Center (PTRC).
Peng Wang (M00) received the B.Sc. degree from Xian Jiaotong University,
Xian, China, in 1978, the M.Sc. degree from Taiyuan University of Technology,
Shanxi, China, in 1987, and the M.Sc. and Ph.D. degrees from the University of
Saskatchewan, Saskatoon, SK, Canada, in 1995 and 1998, respectively.
Currently, he is an Associate Professor of Nanyang Technological University,
Singapore.