Vol2 93 - Construction Documents
Vol2 93 - Construction Documents
Process
BoT
Construction
Scoping
Feasibility
Programming
Schematic
Design
Design
Development
Construction
Documents
Construction
Closeout
GMP Buyout
Permitting
Goal
The Construction Documents (CD) phase is the last stage of the design process. The Consultant
Group is focused on finalizing the drawings and specifications for all components and systems of the
building producing the Contract Documents. A complete set of Contract Documents provides a
comprehensive, fully coordinated set of construction documents and specifications that the Contractor
uses to determine a Guaranteed Maximum Price or lump sum price, obtain necessary permits and
construct the project.
During this phase, the Technical Group performs an interim review of the drawings and specifications
at 50% CD completion for constructibility and advises the Consultant Group of any conflicts from the
previously signed-off Design Development drawings. When the construction documents are 95%
complete, the Technical Group and Structural Peer Group review the drawings for content and
provide final comments. Because the Consultant Group is tasked with delineating the signed-off
building design (signed-off at the end of the Design Development phase), changes to the scope or
program in this phase will incur budget impacts and schedule delays.
The completed Contract Documents and schedule are bid priced and the information is summarized
in a Write-up which is presented by CP&M to the Board of Trustees for Construction Approval.
Tasks
Finalize specifications
Commissioning Plan
Project Manager
Facility Coordinator
Resources
PDP 8/01
11.1
Project #:
Project Manager:
Date:
Task List
Volume 2
Remarks
Site Utilities
o Steam
o Sanitary Sewer
o Storm
o Site electrical
o High volt
o Domestic Water
o Fire Water
o Irrigation
HVAC systems
Plumbing systems
Process Piping
Site Lighting
Electrical Power
Electrical Lighting
Fire Sprinklers
Fire Alarm
Telecommunications (Tel/Data/Networking,
Audio Visual)
Remarks
PDP 8/01
11.2
Project #:
Project Manager:
Date:
Remarks
Remarks
Site Utilities
High Voltage
Civil
Landscape
Architectural
Interiors
Mechanical
Plumbing
Electrical Power
Electrical Lighting
Telecommunications
Fire Sprinklers
Fire Alarm
PDP 8/01
11.3
Project #:
Project Manager:
Date:
Remarks
Remarks
11.4
Project #:
Project Manager:
Date:
Data
Networking
Audio Visual
Web Casting
Security
Card Readers
CCTV
Site Lighting
Parking & Transportation
Public Safety/Security
ADA
Planning Office, University Architect
Risk Management (FM Global, if required)
Review coordination of sustainability
components to ensure the design intent is
satisfied
Remarks
11.5
Project #:
Project Manager:
Date:
Site Lighting
Parking & Transportation
Public Safety/Security
ADA
Planning Office, University Architect
Risk Management (FM Global, if required)
Remarks
Remarks
Remarks
Remarks
11.6
Project #:
Project Manager:
Date:
process
Identify roles and responsibilities within the
Design and Technical Groups (and in some
cases PIs)
Determine lines of communications between
each group
Establish a commissioning schedule
Evaluate the operating condition of the
system at the completion of functional testing
Identify deficiencies during testing and
measures taken to correct them
Identify uncorrected deficiencies that are
accepted by the University
Report on field activities and testing
procedures
Estimate schedule for required deferred
testing
Remarks
Remarks
PDP 8/01
11.7
Project #:
Project Manager:
Date:
Remarks
15. Sign-off on mock-ups (these mock-ups are geared toward evaluating constructibility
issues and are additional to the mock-ups that may have been developed in the SD and
DD phases to aid in design)
Task
Remarks
Deliverables
1. Complete Set of Construction Documents and Project Manual (specs)
Refer to Drawing checklist which follows this section
Task
Remarks
Coordinated Drawings
Project Manual
Remarks
Remarks
PDP 8/01
11.8
Project #:
Project Manager:
Date:
4. Commissioning Plan
Task
Remarks
Remarks
Budget (GMP)
Confirm 100% CDs or indicate percentage
completed
Buyout date
Schedule
Approvals
Task
Remarks
Facility Coordinator
Associate Vice Provost of CP&M
Dean
Provost
Board of Trustees - Construction Approval
PDP 8/01
11.9
Project #:
Project Manager:
Date:
General Information
Life Safety Plan with egress routes, ADA
accessibility and Title 24 calculations
Occupant Loads
Fire apparatus access
Sheet Index
Site
Site Plan
Parking stall types and locations
Bike rack locations
Site Furnishings
Landscaping
Irrigation Plan and Details
Plans
1/8 Floor Plans with dimensions
Enlarged Plans
Enlarged Stair and Elevator Plans
1/8 Roof Plan with roof pads, drains,
equipment screens and OSHA compliance
Utility main locations
Utility entrance locations
Mechanical single line Distribution Plan
Mechanical, Electrical and Telecom Room
layouts.
Electrical Power Plans
Electrical Lighting Plans
Structural plan with column spacing and
shear walls locations
Furniture Plans
Interior Finish Plans
Lab Equipment Plan
Kitchen and Specialty Equipment Plan
Reflected Ceiling Plans with dimensions and
heights above finished floor
Casework location
Rated wall locations
Door locations and handing
Vertical Circulation locations and sizes
Specialty locations (whiteboards, projections
screens, etc.)
Audio Visual Equipment locations
Card Reader locations
Security/CCTV locations
Fire Alarm and Sprinkler Shop Drawings
Elevations
Exterior Elevations indicating location of
fixed and operable windows, doors, overall
dimensions and floor-to-floor heights
Casework elevations
Exterior finish materials
Exterior cladding systems
Exterior lighting locations
Roof profile and finish material
Interior Elevations of major/complicated
spaces
Sections
Building Sections showing floor-to-floor
heights, space relationships, and
mechanical plenums
Exterior Wall Sections
Stair, elevator and shaft sections
Details
Exterior Wall Details
Roof Details
Floor Details
Wall Types
Casework Details
Ceiling Details
Interior Details
Significant Structural Details
Window types
Door and Door Frame types
Door and Window Schedule
Mechanical Equipment Schedules
Mechanical Details
Electric Panel Schedules
Electrical Details
Plumbing riser diagrams
Plumbing Details
ADA and Title 24 code required details
Specialty Walls (blast walls, dust barriers
etc.)
PDP 8/01
11.10
Project #:
Project Manager:
Date:
Project Manual
Preliminary Specifications
MEPS Basis of Design Narratives with load requirements and distribution plan
Cable tray/J-hook requirements
Fume Hood and Lab equipment inventory
Signage Narrative
Vibration Analysis
Soils Report
Acoustical requirements
Lighting level requirements
Hardware Schedule with Types
General Requirements with Bidding Instructions
PDP 8/01