Local Space Housing Association: Schedule of Rates
Local Space Housing Association: Schedule of Rates
PROVISION OF
RESPONSIVE REPAIRS AND
MAINTENANCE SERVICE
Schedule of Rates
It should be noted that the following information is provided as guidance only, and not all items
may be covered.
(BOT)
(BS)
(OS)
2L
3L
A
AA
AC
BASEC
BCC
BCMC
BF
BS
Btu
BWF
CA
CCTV
CCU
CI
CLG
CM
CORGI
CP
CT/ct
CWST
DC
dia
DIR
DP
dpc
dpm
EC7
EP
EPDM
F&E
FL&B
FLR
GC
GRP
GWCG
GWPP
HO
HOFR
horizon
HP
HR
)
Hr
)
hr
)
HRC
Bottom
Both Sides
One Side
Two layer
Three layer
Amp
Anodised aluminium
Alternating current
British Approvals Service for Cables
British Coal Corporation
British Cable Manufacturers Confederation
Both faces
British Standard
British thermal unit
British Woodworking Federation
Client Representative
Closed circuit television
Consumer control unit
Cast Iron
Ceiling
Cubic metres
Council for Registered Gas Installers
Chromium Plated
Coat
Cold water storage tank
Direct current
diameter
Direct
Double Pole
Damp proof course
Damp proof membrane
Economy 7
Ethylene propylene
Ethylene Propylene Diene Monomer
Feed and expansion
Framed, ledged and braced
Floor
Gas chimney
Glass fibre reinforced polyester
Georgian wired cast glass
Georgian wired polished plate
Home Office
Heat, oil and flame retardant
horizontal
High performance
Half round or hour depending on context
High rupturing cartridge
1
Height
Heater
Hardwood
Institute of Electrical Engineers
Indirect
Per Item i.e. comprising the whole of the works as detailed
Kilogram
Kilowatts
Layer(s)
Ledged and braced
Linear metres
Litres
Low voltage
Miniature circuit breaker
Medium density fibreboard
Mineral insulated copper cable
Millimetres
Mild steel
not exceeding
National Inspection Council for Electrical Installation Contracting
Natural stone
Occupancy
Precast concrete
Purpose Made
Polyvinyl Chloride
Unplasticised Polyvinyl Chloride
Residual current device
Reconstructed stone
Satin anodised aluminium
Security
Square metres
Standard
Softwood
Twin and earth
Tongued, grooved and V jointed
Television
Unplasticised Polyvinyl Chloride
Volts
Watt
Water closet
Wash hand
Wash hand basin
Waterproofing
For items in the Schedule of Rates which are measured (indicated in LM/SM/CM), the Client will
reimburse the Service Provider for works on the following basis.
The use of an item and the usage rate is less than 1 (one) the charge shall be as for 1 (one)
whole. Where however, more than 1 (one) whole is used reimbursement shall be pro-rata the
item schedule rate i.e. 1.27 LM, SM, or CM = 1.27 to two decimal places, (multiplied) by the
unit schedule rate.
.2
For Items in the Schedule of Rates where the Unit of Measure is per No. (Number) or IT (Item),
then the charge shall be as for 1 (one) whole multiplied by the unit schedule rate.
.3
For Items in the Schedule of Rates where the Unit of Measure is per HR (Hour) then the charge
shall be to two decimal places, recorded to the nearest 15 mins, irrespective of whether more or
less than 1 (one) whole i.e. 0.50, 1.25 etc., multiplied by the unit schedule rate.
Specific rules for the measurement of scaffolding, only where reimbursable by operation of the provisions contained
in the Addendum to the Clients Requirements on Operational Matters - Scaffolding, Trestles, Hoardings,
Barriers, Ladders etc, are as follows:
.1
General scaffolding is designated in ranges of girth and height. The girth shall mean the
horizontal length measured along the face of the structure to which access is required. The
height shall mean the vertical height measured from average scaffold base plate level to the
upper surface of the top working platform. In the case of a scaffolding with top working
platforms at differing levels the average height shall be used.
.2
Scaffold towers is itemised and designated by vertical height irrespective of plan dimensions. The
height shall mean the vertical height measured from the tower base plates/wheels as
appropriate to the upper surface of the top working platform. The items are deemed to include
for providing towers of any suitable dimensions to suit access available.
.3
Chimney scaffolding is itemised and designated by height above ground level, irrespective of the
girth. The height shall mean the vertical height measured from ground level to the upper surface
of the working platform.
.4
Working platforms to general scaffolding are deemed to be four boards wide and shall be
measured per linear metres of platform.
.5
For any type of scaffolding the additional height above working platforms due to handrails,
screens, gantries and the like is deemed to be included.
MEASUREMENT PREAMBLES
The following are provided as indicative examples only and should be reviewed and adapted as necessary by the
Client, prior to incorporation into any tender or other Contract documentation, to ensure that they are fully
compatible with the maintenance service to be provided and the particular Schedule of Rates with which they are
to be used.
Generally Rates Deemed to Include
A.
Rates for all Schedule of Rates items in all trades generally are deemed to include as appropriate for the
following:
.1
All work that can reasonably be deemed to be included either as good workmanship, including
the provision of materials and plant, or accepted practice whether or not specifically referred to
in this document, the Client Representatives decision on this will be final.
.2
Clearing away all arisings, redundant materials, debris, rubbish etc., from site including damping
down to reduce dust, loading into skips at ground level, skip hire or equivalent, transport and
landfill and other waste disposal charges including any recycling costs. .
.3
Scaffolding, staging, towers, hoists, cradles and access ladders etc., as required up to and
including second storey eaves level above ground level (including chimneys, gables, dormers and
the like to two storey structures and below), including maintaining in accordance with
appropriate safety regulations, clearing away on completion and making good all work damaged
or disturbed.
.4
.5
Temporary dustproof, weatherproof and security screens, etc., as required complete with doors
including maintaining, adapting and clearing away on completion and making good all work
damaged or disturbed.
.6
.7
Taking up any necessary boarding, de-nailing timbers, relaying boarding and punching in nail
heads.
.8
Taking off and re-fixing gutters, downpipes, TV/radio aerials, satellite dishes, electricity, TV,
British Telecom cables and the like to facilitate the renewal or repair of any component.
.9
Removing all screws, nails, plugs and the like associated with the removal of any item.
.10
Setting aside, storing, cleaning and subsequently re-fixing items described as re-fixed.
.11
Setting aside, protecting and reinstating tenants goods, chattels, fixtures, fittings and other
property and clearing roof space where necessary to undertake the works ordered.
.12
Fixing to any surface with nails, screws, blocks, glue, bolts etc., as required including drilling,
packing and scribing.
.13
.14
.15
.16
.17
Seeking the approvals of the Client and or Client Representative in respect of any Works
including any reasonable waiting or other down time whilst awaiting approval.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
Rates for scaffolding are additionally deemed to include as appropriate for the following:
.1
Basing out, preparing and levelling of ground, provision of additional support, base plates,
spreaders and the like as necessary.
.2
Protection of the structure fabric, finishings, roof coverings and the like.
.3
Provision of all requisite tubes and fittings of every description, delivery, handling and removal.
.4
.5
.6
.7
Fans, gantries, hoardings, sheeting and double boarding of working platforms to afford
protection around/over entrances, paths, rights of way and other forms of access or
thoroughfare.
.8
.9
Toe boards, guard-rails, handrails, safe ladder access, ladders, brickguards, elevational debris
netting/sheeting and the like.
.10
Ancillary plant and equipment such as tower feet/wheels, out-riggers, cross bracing, gin wheels,
ropes and the like.
.11
Lighting and/or alarming where deemed necessary or appropriate and/or as specifically directed
by the Client Representative.
.12
.13
Fixed handholds and physical ties to the structure where necessary, subsequent removal and
making good.
.14
Provision of certified structural design calculations and erection certificates to the Client
Representative where required under the Contract.
.15
Reinstatement of ground and making good any damaged surfacing and/or pavings if necessary.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
Rates for excavation and earthwork are additionally deemed to include as appropriate for the following:
.1
Clearing all site vegetation, lifting turf for preservation, storing, maintaining and subsequently
preparing ground, relaying and watering and application of weedkiller.
.2
Grubbing up vegetation, roots, uncharted drains and services, etc., that may be encountered.
.3
.4
.5
.6
Levelling and compacting formation level, backfilling and compacting selected material and
disposal of all surplus excavated material from site.
.7
Excavating by hand or mechanical means, no additional cost will be entertained if it is found that
the proposed method is impractical.
.8
.9
.10
Earthwork support including everything necessary to uphold the sides of the excavations.
.11
.12
Blinding surfaces of hardcore beds and filling to excavations with approved fine material.
.13
.14
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
Rates for demolition are additionally deemed to include as appropriate for the following:
.1
Adequate strutting, propping and other protection to maintain stability of adjacent structures or
parts of structures both during and after completion of demolition works.
.2
Removal of all insitu and applied finishings in conjunction with the taking down of all structural
and non-structural walls, partitions and the like.
.3
Removal of all timbers, fixtures and fittings including stripping out all associated cleats, bearers
and fillets and withdrawing all plugs and all subsequent making good to finishes disturbed.
.4
.5
Cutting out, cutting back and plugging off as appropriate any redundant piping, tubing, conduit,
wires, bars etc., encountered during any demolition works.
.6
Extending finishings, decorations, skirtings, picture rails, cornices and the like into or over newly
formed or infilled openings.
.7
Draining down and subsequent refilling of any heating or water services necessary in conjunction
with demolition works being undertaken.
.8
Disconnecting all mechanical and electrical services and temporary diverting and reconnecting of
same or capping off at a suitable location to leave the existing installations in a safe working
order.
.9
Giving the required notices to Local Authorities, gas water or electricity companies and
complying with any specific instruction from them.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
Rates for fencing and gates are additionally deemed to include as appropriate for the following:
.1
Clearing all site vegetation, lifting turf for preservation, storing, maintaining and subsequently
preparing ground, relaying and watering and application of weedkiller.
.2
Grubbing up vegetation, roots, uncharted drains and services, etc., that may be encountered.
.3
.4
.5
.6
Levelling, compacting, grading and shaping formation level, backfilling and compacting selected
material and disposal of all surplus excavated material from site.
.7
Excavating by hand or mechanical means, no additional cost will be entertained if it is found that
the proposed method is impractical.
.8
.9
.10
Earthwork support including everything necessary to uphold the sides of the excavations.
.11
.12
.13
.14
.15
.16
.17
.18
.19
All labour, materials, fixing or hanging, glue, nails, screws, plugs, and everything necessary for
the proper completion of the works.
.20
.21
Framing up, welding, drilling, bolts, nuts and fabrication and fixing of metal gates.
.22
All other relevant items covered by other sections of the measurement preambles to the
Schedule of Rates generally.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
Rates for drainage are additionally deemed to include as appropriate for the following:
.1
Clearing all site vegetation, lifting turf for preservation, storing, maintaining and subsequently
preparing ground, relating and watering and application of weedkiller.
.2
Excavation by hand or machine as necessary and appropriate for the location of the work.
.3
.4
.5
.6
Levelling and compacting formation level, backfilling and compacting selected material and
disposal of all surplus excavated material from site.
.7
Earthwork support including everything necessary to uphold the sides of the excavations.
.8
Allowances for working space as necessary for formwork, brickwork, rendering, tanking or similar
work including additional excavation, earthwork support, backfilling and disposal.
.9
Blinding surfaces of hardcore beds and filling to excavations with approved fine material.
.10
.11
Breaking up and removing concrete, brickwork, blockwork, rock and other obstructions.
.12
.13
.14
.15
.16
.17
.18
Coring, cleaning and flushing all drains, gullies and manholes etc., on completion.
.19
Testing all drainage, commissioning and providing all certificates required by the relevant
authorities, bodies or the Client.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
10
Rates for concrete work are additionally deemed to include as appropriate for the following:
.1
.2
Ordinary and fair face formwork and temporary supports to all concrete where required.
.3
.4
.5
.6
.7
Cutting, bending or forming reinforcement to required shape and for all hooks, tying wire,
spacers, chairs and the like.
.8
Reinforcement to cast insitu concrete (where require0 and all precast concrete.
.9
.10
Provision of a polythene DPC laid on sand blinding for all internal solid floor constructions or
repairs, whether specifically stated or not.
.11
.12
Lintels, cills and the like including the provision of all cast-in fixing blocks, slips or strips as
required.
.13
Bedding precast concrete lintels, padstones etc., in cement or cement lime mortar and pointing
as required.
.14
Provision of all cast-in fixing blocks, slips or strips required by other trades into cast insitu and
precast components.
.15
Provision of hand or machine mixed concrete as appropriate to the nature and circumstances of
work being undertaken.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
11
Rates for brickwork and blockwork are additionally deemed to include as appropriate for the following:
.1
.2
Forming rough and fair grooves, throats, mortices, chases, rebates and holes, stops and mitres.
.3
Raking out joints and hacking faces to form key for finishings.
.4
.5
.6
.7
.8
.9
.10
.11
Finishing fair face and pointing with any type of joint as required.
.12
Labour and facing to returns, ends and angles to copings, cills and the like.
.13
Forming cavities between skins of hollow walls including stainless steel ties and insulation as
required.
.14
Cutting, pinning and wedging load bearing work to soffits of existing work.
.15
Extending plaster, decorations, skirtings etc., where any openings filled in or cut through existing
walls.
.16
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
12
Rates for woodwork are additionally deemed to include as appropriate for the following:
.1
Levelling, packing and adjusting to present a perfectly level, even and true frame or backing.
.2
All labours, grounds, battens, packings, noggins, cleats, holes, bolts, etc., and treating cut ends
with brush applied preservative to structural timbers.
.3
All grounds, battens, noggins and the like and for all necessary packing and adjustment to
present a perfectly level, even and true frame or backing.
.4
Taking off and renewing defective battens, bituminous felt underlays and vapour barriers where
replacing roof or weatherboarding.
.5
Ends, angles, mitres, scribing and other labours for all items of woodwork.
.6
.7
Taking down and refixing as required bath panels, duct casings, support framework to bath
panels and duct casings etc.
.8
.9
Splicings, piecing in and all making good in repairing and overhauling or replacing doors,
windows, frames, ironmongery and the like.
.10
.11
Dovetail and scarfed joints, notchings and fitting ends of timbers to metal sections, shoes and
heads, trimming floor joists, ceiling joists and rafters to openings for hearths, chimneys, trap
doors and the like.
.12
Blocking, dowelling, pelleting and gluing and any additional labours required in relation to
staircase or similar item repairs.
.13
.14
Notching, cutting holes, scribing etc., to ducts, kitchen worktops, fittings and the like.
.15
Sealant at junction of worktops, vanity unit tops and adjacent wall finishes.
.16
Fitting new ironmongery to all new external doors or refitting existing as specified, including all
necessary parts and fixings so as to be fully operational.
.17
Pre-priming or factory priming all finished timber and joinery (irrespective of whether standard
or purpose made) and painting two undercoats and one gloss oil colour finishing coats following
installation of the work whether described in the Schedule of Rates descriptions or not.
.18
Unless specified otherwise, sourcing all new ironmongery to match existing removed so far as is
practicable.
.19
Overhauling ironmongery is to include for taking off, dismantling, renewing any defecting parts,
oiling as required, assembling and refixing with new screws or fixings to leave in perfect working
order.
13
Rates for woodwork are additionally deemed to include as appropriate for the following: (contd)
.20
Overhauling, easing and adjusting doors, windows etc., is to include for all repairs required to
the complete door or window and their associated frames, linings, architraves, stops etc., and
not just one repair. The work includes for taking off all ironmongery, carrying out all repairs to
the item, easing and adjusting the door or window to fit its frame or lining, fully repairing or if
specified renewing all ironmongery, including oiling to leave the whole item to be repaired in full
and good working order.
.21
Rates for ironmongery generally include for fitting and fixing, including cutting, sinking, boring,
morticing etc., lubricating and adjusting all locks, catches, etc., and all making good as required.
.22
The rates for all new doors includes for either supplying the doors to the exact size or cutting
down a larger door to suit the existing frame or lining size, including the provision and
adaptation of door blanks where necessary. No extra payment will be made due to difficulties in
accurately fitting any door to existing linings.
.23
Rates for all doors and windows shall include for framing, studding, packing, sticking, screwing,
cramping, welding, glazing and all materials not specifically mentioned, but required to make
and fix the whole to work perfect.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
14
Rates for metalwork are additionally deemed to include as appropriate for the following:
.1
Welding, riveting, drilling and tapping etc., including provision of fixing components such as
rivets, bolts, rag bolts, rawl bolts, screws and the like, together with all nuts, washers etc., as
required.
.2
Sealant pointing around screens, fixtures and other situations wherever appropriate.
.3
Priming and painting two undercoats and one gloss finishing coat of oil colour on all new
metalwork to match existing decorations.
.4
Overhauling, easing and adjusting doors, etc., is to include for all repairs required to the
complete door and its associated frame and not just one repair. The work includes for taking off
all ironmongery, carrying out all repairs to the item, easing and adjusting to fit its frame or
lining, fully repairing or if specified renewing all ironmongery including oiling to leave the whole
item to be repaired in full and working order.
.5
Rates for grab bars, grab rails, shower curtains, shower head riser rails and all like accessories
are deemed to include for provision of all necessary brackets, flanges, pattresses and similar
items where specifically stated or not in Schedule of Rates descriptions.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
15
Rates for finishings are additionally deemed to include as appropriate for the following:
.1
.2
.3
.4
Preparing backgrounds to receive any finish, such as dry brushing off to remove all loose
particles, dust and efflorescence, washing off any grease and mould oil, hacking, raking out
joints in brick and blockwork, wetting and rewetting surfaces, appliocation of all priming
solutions/coats, all to ensure that an adequate bond between the background and adhesive,
plaster or any other finish is obtained.
.5
Making good of all damaged sub-floors and other surfaces in preparation to receive any applied
finishes, including application of proprietary self levelling latex cement compound where
necessary.
.6
All dubbing out to walls or ceilings as required to provide the correct levels and to maintain
planes with existing surrounding plasterwork, making fair joints between new plasterwork and
existing surrounding plasterwork.
.7
.8
Working or cutting and fitting any finishings around all pipes, electrical fittings, appliances, into
rebates in frames, around openings, protections, and all like components, fittings, obstructions
or voids, including any additional making good necessary.
.9
De-nailing existing timbers and providing all necessary battens or noggins to support edges and
joints of plasterboard.
.10
Cement and sand backing, adhesive, special tiles, narrow widths, jointing and grouting to any
tiling work.
.11
.12
All work in narrow widths, patches and the like irrespective of the size or girth.
.13
Cutting of metric floor, wall or ceiling tiles where required to replace imperial sized equivalents or
vice versa
.14
Priming, pre-caulking, scrimming, caulking and all other preparatory treatment relevant to
surfaces to receive decorative finishes.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
16
Rates for painting and decorating are additionally deemed to include as appropriate for the following:
.1
Preparation of surfaces and the requisite type and number of paint coatings to be in accordance
with the manufacturers recommendations and/or these preambles, which ever constitutes the
highest performance specification.
.2
.3
.4
.5
.6
.7
.8
.9
.10
.11
Work includes all narrow widths and patches irrespective of the girth or size.
.12
All rubbing down and preparation of wall surfaces and for sizing walls prior to hanging wall or
lining paper.
.13
Hanging of wall or lining paper strictly in accordance with the manufacturers instructions.
.14
Protection of all furniture and fittings, the provision of dust sheets and the removal of items such
as curtains etc., prior to commencing the works, together with the rehanging or reinstatement of
the same.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
17
Rates for glazing are additionally deemed to include as appropriate for the following:
.1
.2
.3
Replacement of all breakages of new or existing glass including whilst cutting out for or fitting
window moulded extractor/ventilation fans and the like fittings.
.4
.5
Taking off and rebedding or renewing washleather strips, rubber seals and the like.
.6
Sealing or priming all rebates and backs of beads prior to inserting/fixing glazing.
.6
.7
.8
.9
.10
All work to be undertaken in accordance with the current Building Regulations Approved
Document L as appropriate by FENSA registered operatives.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
18
Rates for plumbing and heating are additionally deemed to include as appropriate for the following:
.1
Stripping out redundant or defective pipework, fittings and the like not specifically referred to in
the priced Schedule of Rates descriptions.
.2
Cutting or forming holes, mortices, chases and the like in the existing structure and making good
all work disturbed.
.3
Renewing, installing or repairing any valves, taps, cocks, fittings, sanitaryware and the like shall
include for shutting any external or internal valves to isolate the relevant circuit or sub-circuit
and draining any residual water from the circuit or sub-circuit pipework.
.4
Draining down any or part of any water services installations and subsequently refilling, venting
adjusting and setting temperature and controls.
.5
Removing and subsequently replacing or renewing insulation, access panels, floor boarding,
shelving and the like in order to gain access to the work.
.6
Extending, altering and adapting existing pipework to suit any new work including all directional
changes, providing any additional pipework, fittings or other materials required.
.7
All fittings, angles, ends, stop ends, swannecks, outlets, brackets, clips, spacers, etc., all joints
and connections including adaptors, joints to existing and to drains.
.8
Knotting, priming, stopping, filling and painting two undercoats and one gloss finishing coat of oil
colour on all new woodwork replaced in connection with this section to match existing
decoration.
.9
Priming and painting two undercoats and one gloss finishing coat of oil colour on all new
exposed pipework or radiators to match existing decorations.
.10
.11
Items of sanitaryware include for all accessories such as overflow, waste, chains, plugs etc.,
sealing joints between fitting and adjacent surfaces with a neat bend of anti-mould jointing
silicone, and leaving the fitting in pristine condition and full working order.
.12
Cleaning of all sanitaryware and other fittings, upon completion to remove all marks and leave in
a pristine condition.
.13
Removal of all swarf and foreign matter from storage tanks, cisterns, cylinders and the like on
completion, thoroughly flushing throughout to clean and resetting any valves, ballvalves and the
like to ensure correct water level.
.14
Installing, repairing or renewing cisterns, tanks and cylinders and the like include where
appropriate for the transfer of any functional electric immersion heater from the existing to new
component.
.15
Rates for grab bars, grab rails, shower curtains, shower head riser rails and all like accessories
are deemed to include for provision of all necessary brackets, flanges, pattresses and similar
items where specifically stated or not in Schedule of Rates descriptions.
19
Rates for plumbing and heating are additionally deemed to include as appropriate for the following
(Contd)
.16
Overhauling any item is to include for removing, dismantling and replacing any work or
defective part, greasing or oiling where appropriate, reassembling to leave in perfect working
order and refixing.
.17
Earthing and bonding all plumbing and associated metalwork in conjunction with Schedule items
whether specifically stated or not in Schedule of Rates descriptions.
.18
Testing all services, fittings, appliances, etc., commissioning and providing all certificates
required by the relevant gas, water or electrical authorities, bodies or the Client.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
20
Rates for electrical work are additionally deemed to include as appropriate for the following:
.1
Stripping out redundant or defective cables, conduits, fittings and the like, not specifically
referred to in the priced Schedule of Rates descriptions.
.2
Stripping out, builders work and the like associated with complete with re-wiring of existing
properties.
.3
Where necessary, the removal and reinstating of electrical voltage supply by appropriate
supply/service provider to facilitate the progression of works. Service Provider to arrange
attendance and pay all charges incurred in connection with supply/service providers work.
.4
Draining down, refilling, venting, adjusting and setting controls in connection with repairs or
replacement of cylinder heater elements and the like.
.5
Renewal of equipment includes for disconnecting and removing old equipment supplying and
fixing new equipment specified and connecting to adjacent outlet point. Should a new outlet
point be required it shall be deemed to be included.
.6
Cutting or forming holes, mortices, chases and the like in the existing structure and making good
all work disturbed.
.7
.8
Removing and subsequently replacing or renewing insulation, access panels, floor boarding,
shelving and the like in order to gain access to the works.
.9
Removal and reinstating of lids, covers, accessories, equipment, locating junction boxes,
withdrawing or disconnecting old cables, threading new cables through old conduits or providing
and fixing new conduits/mini trunking complete shall be deemed to be included in rates for
wiring.
.10
Altering and adapting existing installation to suit any new work including providing any additional
cables, fittings or other materials required.
.11
Preparing new or existing fittings and supplying and connecting all cables, screws, clips and
accessories.
.12
Providing and fixing blank plates as necessary to fuse boards and outlets.
.13
Rates for Consumer Control Units (CCUs) are deemed to include for providing and fixing fuses,
miniature circuit breakers (mcbs), blany way plates, residual current device (rcd) and the like.
.14
Providing and fixing new backboxes, pattresses, earth fly leads and other items normally
associated with any fitting being renewed.
.15
.16
Supply and fixing new cable, conduit and trunking where not possible to use existing cable,
conduit and trunking is to include dressing, bends, angles, conduit boxes, outlets and all other
accessories and fixings.
21
Rates for electrical work are additionally deemed to include as appropriate for the following: (contd)
.17
Overhauling any item is to include for removing, dismantling and replacing any worn or defective
part, greasing or oiling where appropriate, reassembling to leave in perfect working order and
refixing.
.18
Priming and painting two coats oil colour on new exposed conduit to match existing.
.19
Earthing and bonding all plumbing and associated metalwork in conjunction with Schedule of
Rates items whether specifically stated or not in Schedule of Rates descriptions.
.20
Inspection and testing of all services, fittings, appliances etc., when completed to ensure
satisfactory functional operation and safety, including temporary supply, commissioning and
providing all certificates (including test results) required by the relevant electrical authorities,
bodies or the Client.
The Service Provider is to allow in his tender for any additional costs that he considers may be necessary.
22
FOUNDATIONS ............................................................................................................ 1
GROUNDWORKS .......................................................................................................... 2
DRAINAGE................................................................................................................. 22
Drainage Below Ground ........................................................................................................................ 22
Drainage - New - Clay Pipes .............................................................................................................. 22
Drainage - New - Plastic Pipes ........................................................................................................... 22
Drainage - Existing - Repairs.............................................................................................................. 22
Gullies.............................................................................................................................................. 23
Extra Over for Breaking Out and Reinstatement .................................................................................. 24
Manholes ............................................................................................................................................. 24
Manholes - Brick ............................................................................................................................... 24
Inspection Chambers - Polypropylene ................................................................................................. 24
Manhole - Covers and Slabs ............................................................................................................... 25
Clearing Blockages, CCTV and Testing ................................................................................................... 26
Clearing Blockages ............................................................................................................................ 26
CCTV Drains ..................................................................................................................................... 26
1
BRICKWORK .............................................................................................................. 28
Brick/Block Walling ............................................................................................................................... 28
Walls - Demolition ............................................................................................................................. 28
Walls - Construction .......................................................................................................................... 28
Walls - Rebuilding ............................................................................................................................. 29
Piers ................................................................................................................................................ 30
Brick/Block Repairs ........................................................................................................................... 31
Repointing........................................................................................................................................ 32
Tell Tales ......................................................................................................................................... 32
Cavities ............................................................................................................................................ 32
Openings - Minor .............................................................................................................................. 32
Openings - Internal Door ................................................................................................................... 32
Openings - External Door/Window ..................................................................................................... 33
Lintols and Arches............................................................................................................................. 35
Cills and Thresholds .......................................................................................................................... 35
Copings ............................................................................................................................................ 36
Damp Proof Courses ......................................................................................................................... 37
Anti-Fungicide Treatment .................................................................................................................. 37
Airbricks and Vents ............................................................................................................................... 38
Airbricks ........................................................................................................................................... 38
Ventilators ........................................................................................................................................ 38
Chimneys............................................................................................................................................. 39
Chimney Stacks ................................................................................................................................ 39
Flue Sundries.................................................................................................................................... 40
Chimney Pots, Caps, Cowls Etc. ......................................................................................................... 41
Meter Cupboards .................................................................................................................................. 42
Gas/Electric Meter Cupboards ............................................................................................................ 42
Fireplaces ............................................................................................................................................ 42
Fire Surrounds and Hearths ............................................................................................................... 42
Fire Openings etc .............................................................................................................................. 44
Fire Parts ......................................................................................................................................... 45
Cookers (Rayburn or Similar) ............................................................................................................. 46
MASONRY.................................................................................................................. 47
Natural Stone ................................................................................................................................... 47
Reconstructed Stone ......................................................................................................................... 47
Stone Repairs ................................................................................................................................... 48
ROOFING .................................................................................................................. 50
Clay/Concrete Roof Tiling ...................................................................................................................... 50
Concrete Interlocking Roof Tiles to Match Existing ............................................................................... 50
Concrete or Clay Plain Tiles to Match Existing ..................................................................................... 50
Concrete or Clay Verges .................................................................................................................... 51
Concrete or Clay Bedded Ridges, Hips and Valley Tiles ........................................................................ 51
Dry Verge, Ridge and Hip Tiles .......................................................................................................... 52
Roof Ventilation ................................................................................................................................ 52
Slate Roofing ....................................................................................................................................... 53
Fibre Cement Slating ......................................................................................................................... 53
Natural Slating .................................................................................................................................. 53
Fibre Cement Slating - Ridge, Verge and Hips Tiles ............................................................................. 53
Vertical Coverings................................................................................................................................. 54
Vertical Tile Hanging ......................................................................................................................... 54
Vertical Fibre Cement Slating ............................................................................................................. 54
Sheet Roofing ...................................................................................................................................... 55
Sheet Roof Coverings ........................................................................................................................ 55
Remedial Works ................................................................................................................................... 56
Liquid Applied Waterproof Roof Covering ............................................................................................ 56
Inspections....................................................................................................................................... 56
Temporary Repairs............................................................................................................................ 56
2
PLUMBING............................................................................................................... 178
Rainwater Pipework ............................................................................................................................. 178
Rainwater Pipework - PVCu .............................................................................................................. 178
Rainwater Pipework - Cast Iron Repairs ............................................................................................. 179
Rainwater Gutters ............................................................................................................................... 179
Rainwater Gutters - PVCu ................................................................................................................. 179
Rainwater Gutters - Cast Iron ........................................................................................................... 180
Gutters/Downpipes - Clean Out ......................................................................................................... 181
Foul Drainage Above Ground ................................................................................................................ 182
Soil and Vent Stacks - External - PVCu............................................................................................... 182
Soil and Vent Stacks - Internal - PVCu ............................................................................................... 184
Soil and Vent Stacks - Cast Iron - Repairs .......................................................................................... 186
Waste Pipework and Fittings ................................................................................................................ 186
Waste Pipework and Fittings - Plastic ................................................................................................ 186
6
11
PRI DESCRIPTION
UNIT
RATE
FOUNDATIONS
Floor - Concrete Internal Renewal
015003
SM
146.91
SM
134.67
LM
279.46
049001
PRI DESCRIPTION
UNIT
RATE
GROUNDWORKS
Kerbs, Channels and Edgings
Kerbs - Precast Concrete
001101
LM
34.53
001103
LM
26.02
001105
LM
21.27
CHANNEL:RENEW NE 250X125MM
Channel:Renew precast concrete channel, take up existing including
haunching, remove waste and debris, clean up existing bed, supply
and lay new ne 250x125mm precast concrete channel including
haunch both sides, pointing, formwork and make good to existing
finishes
LM
25.88
001303
CHANNEL:REBED NE 250X125MM
Channel:Rebed precast concrete channel, take up existing including
haunching, remove waste and debris, clean up existing bed, and
clean and relay ne 250x125mm precast concrete channel including
haunch both sides, pointing, formwork and make good to existing
finishes.
LM
21.27
LM
26.19
001503
LM
19.11
PRI DESCRIPTION
001505
UNIT
RATE
LM
16.51
LM
7.76
Edgings - Timber
001507
003003
SM
71.32
003007
SM
82.26
003009
SM
3.97
003011
SM
51.69
SM
49.45
005003
SM
53.82
PRI DESCRIPTION
UNIT
RATE
SM
55.95
007005
NO
8.56
007007
SM
23.26
007009
NO
12.54
007011
SM
36.50
007019
SM
10.56
007021
LM
2.33
Paving - Brick
009001
SM
79.11
009005
SM
87.16
009009
SM
103.11
PRI DESCRIPTION
UNIT
RATE
Paving - Gravel
009013
SM
7.01
IT
33.07
SM
30.53
011101
013001
IT
38.93
013005
IT
45.60
013009
LM
20.24
013011
IT
19.68
013013
IT
7.42
013015
LM
100.82
PRI DESCRIPTION
UNIT
RATE
LM
7.88
027103
LM
195.57
027105
LM
70.65
Handrails - Associated
027303
LM
36.36
027305
LM
37.60
027307
LM
15.61
027309
LM
10.19
LM
17.87
027503
LM
13.31
PRI DESCRIPTION
UNIT
RATE
Miscellaneous Fittings
Clothes Lines
029101
NO
102.89
029103
NO
197.89
029105
NO
73.41
029107
NO
168.42
029109
NO
22.42
029111
NO
57.10
029115
NO
69.26
029117
NO
42.16
029119
NO
38.23
029123
LINE:RENEW PULLEY
Line:Renew pulley wheel and bracket to clothes line, including
fixing to any background.
IT
18.71
029125
IT
11.74
PRI DESCRIPTION
UNIT
RATE
Signs
029301
NO
13.85
029303
SIGN:NEW NO PARKING
Sign:Supply standard 'No Parking' sign and screw to timber, plug or
screw to masonry or bolt to metal posts.
NO
60.79
029305
NO
60.79
029307
SIGN:NEW NO DOGS
Sign:Supply standard 'No Dogs' sign and screw to timber, plug or
screw to masonry or bolt to metal posts.
NO
60.79
Bollards
031001
NO
184.99
031005
NO
125.11
031009
NO
97.04
031013
NO
63.40
IT
658.11
Garden Sheds
070101
PRI DESCRIPTION
UNIT
070102
070105
070107
NO
198.41
070109
NO
72.04
070111
NO
10.52
070113
NO
19.79
070115
NO
24.63
IT
RATE
519.81
177.21
Coal Bunkers
080001
NO
45.13
080003
NO
57.06
080005
NO
51.45
PRI DESCRIPTION
UNIT
080007
NO
201.11
080009
NO
63.65
10
RATE
PRI DESCRIPTION
UNIT
RATE
LM
86.16
017111
LM
80.89
017113
LM
122.63
017114
LM
123.91
017117
NO
23.91
017119
NO
7.71
017121
NO
5.44
11
PRI DESCRIPTION
UNIT
RATE
017122
LM
53.40
017123
NO
7.29
017124
LM
70.06
017125
LM
9.27
017127
NO
15.53
017128
NO
17.13
LM
18.25
017205
LM
12.97
017209
LM
8.75
12
PRI DESCRIPTION
UNIT
RATE
017211
NO
6.22
017213
LM
2.85
017215
NO
15.15
NO
52.53
017302
NO
50.19
017308
NO
50.19
017314
NO
48.00
017303
LM
59.63
017304
LM
54.11
13
PRI DESCRIPTION
UNIT
RATE
017316
LM
48.51
017305
LM
65.67
017306
LM
59.48
017318
LM
53.57
017307
LM
7.96
LM
41.78
Fencing - Chainlink
017401
14
PRI DESCRIPTION
UNIT
RATE
017403
LM
47.39
017405
LM
13.02
017407
LM
15.12
017409
LM
7.96
017411
LM
1.46
LM
33.10
017503
LM
5.77
LM
49.07
PRI DESCRIPTION
UNIT
RATE
017603
LM
56.40
017604
LM
65.12
017609
LM
10.15
Fencing - Palisade
017605
LM
54.01
017607
LM
62.86
017611
FENCING:REMOVE PALISADE
Fencing:Remove any palisade type of fencing including posts and
remove waste and debris, fill post holes with top soil and reinstate
paving and gardens as necessary.
LM
11.28
LM
38.76
16
PRI DESCRIPTION
017653
UNIT
RATE
LM
42.91
LM
25.91
017903
LM
5.77
017905
LM
2.06
LM
10.15
017801
LM
14.58
017803
NO
7.02
017805
NO
2.33
017807
NO
7.36
17
PRI DESCRIPTION
UNIT
RATE
Fencing - Posts
019001
NO
9.09
019003
NO
10.20
019005
NO
33.85
019007
NO
30.61
019009
NO
29.39
019011
NO
36.81
019013
NO
47.31
019015
NO
17.56
019021
NO
19.96
18
PRI DESCRIPTION
UNIT
RATE
NO
87.01
021003
NO
104.18
021005
NO
241.15
021002
NO
163.42
021004
NO
187.40
021006
NO
317.56
19
PRI DESCRIPTION
UNIT
RATE
021007
NO
26.93
021013
LM
5.06
021021
NO
102.75
021023
NO
116.78
NO
85.86
023003
NO
177.56
023009
NO
18.96
20
PRI DESCRIPTION
UNIT
RATE
NO
59.08
025003
NO
40.00
025005
LM
32.25
025011
NO
44.20
021011
NO
8.39
019018
NO
14.55
21
PRI DESCRIPTION
UNIT
RATE
DRAINAGE
Drainage Below Ground
Drainage - New - Clay Pipes
033101
LM
120.99
033103
LM
204.89
LM
117.95
033303
LM
198.92
NO
272.07
22
PRI DESCRIPTION
UNIT
RATE
033503
NO
442.76
033505
NO
312.87
033507
NO
476.99
Gullies
035001
NO
146.23
035003
NO
88.71
035005
NO
15.88
035007
NO
21.34
035009
GULLY:RENEW GRATING
Gully:Renew missing or damaged any size or type of gully grating,
remove waste and debris.
NO
15.60
035013
NO
33.73
23
PRI DESCRIPTION
UNIT
RATE
LM
56.55
047003
LM
33.11
047005
LM
10.73
047007
LM
46.62
Manholes
Manholes - Brick
037001
IT
974.50
037003
IT
1011.15
IT
118.93
24
PRI DESCRIPTION
UNIT
RATE
037007
IT
142.55
037009
IT
216.76
037011
IT
235.86
NO
80.65
037017
NO
18.99
037019
NO
25.91
037021
NO
36.41
037027
NO
75.78
25
PRI DESCRIPTION
037029
UNIT
INSPECTION COVER:RENEW-300X300MM
Inspection Cover:Renew galvanised inspection cover and frame size
300x300mm including bed frame in cement mortar (1:3), remove
waste and debris, and reinstate paving, gardens and the like as
necessary.
RATE
NO
47.65
NO
11.82
039004
DRAIN:JET BLOCKAGE
Drain:Clear blocked drain run by pressure jet, remove and refix
manhole covers and gratings, attend upon Client Representative
during any inspection, including all hire charges and any temporary
relocation, remove on completion, flush out, test and remove waste
and debris (to be charged for hours worked on site only, rate
includes for travelling and other non- productive time).
HR
68.25
039006
DRAIN:ROD BLOCKAGE
Drain:Rod blocked drain run by rodding, remove and refix manhole
covers and gratings as necessary, flush out, test and remove waste
and debris.
IT
26.26
039009
IT
13.13
HR
68.25
IT
32.44
LM
263.59
CCTV Drains
039015
DRAIN:CCTV SURVEY
Drain:Undertake CCTV survey of drain runs to identify fault or
following repairs or jetting, remove and refix manhole covers and
gratings as necessary, including all hire charges and any temporary
relocation, remove on completion, supply report and video to Client
Representative (to be charged for hours worked on site, rate
includes for travelling and other non-productive time)
Drain Testing
039018
041001
26
PRI DESCRIPTION
UNIT
RATE
Soakaways
041005
SOAKAWAY:EXCAVATE NEW
Soakaway:Excavate for new soakaway ne 2.00m deep, lift turf and
set aside, excavate soakaway, remove excavated material to
temporary spoil heap where directed, fill excavation with hard, dry,
broken, masonry, stone or gravel ne 100mm gauge to within
250mm of existing ground level, backfill as necessary with
excavated material from temporary debris heap, remove waste and
debris from temporary spoil heap, relay turfs.
CM
204.65
041007
SOAKAWAY:CLEAR EXISTING
Soakaway:Excavate to locate soakaway ne 2.00m deep, lift turf and
set aside, excavate soakaway, remove excavated material to
temporary spoil heap where directed, clear debris from soakaway,
refill with new and existing soakaway medium to within 250mm of
existing ground level, backfill with excavated material from
temporary debris heap, remove waste and debris from temporary
spoil heap, relay turfs.
CM
204.65
27
PRI DESCRIPTION
UNIT
RATE
BRICKWORK
Brick/Block Walling
Walls - Demolition
101101
SM
19.35
101103
SM
32.07
101105
SM
52.24
101107
SM
30.44
101109
SM
13.28
101111
SM
23.32
101121
SM
33.28
101123
SM
53.10
Walls - Construction
101301
SM
69.64
101303
SM
121.36
101305
SM
172.91
28
PRI DESCRIPTION
UNIT
RATE
101307
SM
131.29
101309
SM
96.71
101311
SM
173.30
101313
SM
176.67
101317
SM
41.56
101319
SM
72.17
Walls - Rebuilding
101501
SM
82.77
101503
SM
145.43
101505
SM
112.03
101507
SM
195.18
101511
SM
48.12
101513
SM
78.73
29
PRI DESCRIPTION
UNIT
RATE
101515
SM
176.06
101517
SM
176.06
Piers
101701
LM
27.97
101703
LM
98.00
101705
LM
48.67
101707
LM
132.65
101709
LM
38.98
101711
LM
111.20
101713
LM
64.18
30
PRI DESCRIPTION
101715
UNIT
RATE
LM
157.86
Brick/Block Repairs
101901
WALL:REPAIR FRACTURE
Fracture:Remove any applied finish and cut out bricks as necessary
to either side of fracture, one face only, stitch in new bricks, bed
and point to match existing in cement lime mortar (1:1:6), and
make good any applied finishes, and remove waste and debris.
(measured over mean general line of fracture).
LM
60.21
101903
IT
25.73
101905
IT
132.65
101907
IT
29.57
101909
IT
153.48
101911
NO
7.49
101913
NO
5.30
101915
NO
13.15
101917
NO
10.96
31
PRI DESCRIPTION
UNIT
RATE
Repointing
102103
SM
27.86
102105
LM
3.66
NO
13.01
IT
71.69
Tell Tales
102301
102503
102719
NO
7.00
102721
NO
3.79
IT
160.21
102733
IT
216.52
32
PRI DESCRIPTION
UNIT
RATE
102741
IT
178.80
102743
IT
234.72
102745
IT
350.94
SM
219.35
102753
SM
278.79
33
PRI DESCRIPTION
UNIT
102761
SM
248.38
102763
IT
175.61
102765
SM
271.89
102771
SM
147.50
102773
SM
158.63
34
RATE
PRI DESCRIPTION
UNIT
RATE
LM
97.63
102905
NO
208.90
102907
LM
59.88
102911
LM
64.26
NO
11.68
103103
LM
49.55
103105
NO
53.21
35
PRI DESCRIPTION
UNIT
RATE
103107
LM
49.81
103109
NO
4.10
103111
LM
29.41
103113
LM
43.24
103115
LM
27.22
103117
LM
41.05
103119
NO
44.11
103121
NO
61.85
NO
4.57
Copings
103301
36
PRI DESCRIPTION
UNIT
RATE
103303
LM
29.41
103305
LM
29.10
103307
LM
8.36
103311
LM
17.69
103315
LM
12.71
103317
LM
27.61
LM
47.33
110003
LM
72.93
SM
2.89
Anti-Fungicide Treatment
114001
37
PRI DESCRIPTION
UNIT
RATE
NO
13.68
115003
NO
54.76
115005
NO
14.85
115007
NO
55.78
115009
NO
11.10
Ventilators
115011
NO
10.77
115012
NO
66.78
115014
NO
54.08
38
PRI DESCRIPTION
UNIT
RATE
Chimneys
Chimney Stacks
120001
IT
137.52
120003
IT
17.05
120005
IT
253.19
120007
IT
33.87
120009
IT
430.39
120011
IT
57.32
120013
IT
687.98
120015
IT
77.71
39
PRI DESCRIPTION
UNIT
RATE
120017
IT
905.17
120019
IT
97.22
120021
IT
303.50
120023
CHIMNEY:SEAL FLUE
Chimney:Remove pot and seal flue opening to chimney stack with
slates bedded in mortar (1:1:6) cut out and insert air vent in
chimney breast, make good all works disturbed and remove waste
and debris.
IT
66.73
120025
NO
5.01
120027
NO
91.03
120029
SM
31.12
120031
SM
46.59
Flue Sundries
125001
IT
34.89
125003
IT
45.82
40
PRI DESCRIPTION
UNIT
RATE
125005
IT
107.33
125007
IT
124.08
125010
IT
60.45
125011
IT
22.23
NO
151.57
130007
NO
137.04
130009
CHIMNEY:REBED POT
Chimney:Remove and refix existing pot including clean off pot and
flaunching, prepare and rebed in mortar (1:3) and make good
flaunching and remove waste and debris.
NO
21.18
130011
NO
53.19
130013
NO
84.60
130015
NO
41.09
130017
NO
59.62
130019
NO
30.11
41
PRI DESCRIPTION
130021
UNIT
RATE
NO
17.51
Meter Cupboards
Gas/Electric Meter Cupboards
135001
NO
68.31
135003
NO
33.70
395201
NO
6.37
395203
NO
17.29
Fireplaces
Fire Surrounds and Hearths
140001
FIREPLACE:RENEW COMPLETE
Firplace:Take out existing fire surround and hearth complete, clear
recess, alter and build in new firebase, fireback and throat unit,
prepare for, supply and build in new tiled fireplace surround size
not exceeding 1220x900x100mm with opening size 510x575mm
and tile returns 50x50x6mm stainless steel angle around opening, 2
No. stainless steel eyes on either side of opening and
1100x500x50mm tiled hearth with tiled return on three sides
bedded in cement mortar, make good finishings and remove waste
and debris.
NO
358.83
140002
FIRE:RENEW COMPLETE
Fire:Take out existing fire surround and hearth complete, clear recess,
rebuild opening complete with back base, firebase, fireback and lintel,
prepare for, supply and build in new tiled fireplace surround size not
exceeding 1220x900x100mm with opening size 510x575mm and tile
returns 50x50x6mm stainless steel angle around opening, 2 No. stainless
steel eyes on either side of opening and 1100x500x50mm tiled hearth
with tiled return on three sides bedded in cement mortar, make good
finishings and remove waste and debris.
NO
444.50
140003
FIRE:RENEW SURROUND
Fire:Take out fire surround and clear away, prepare for, supply and
build in new tiled fire place surround size ne 1220x900x100mm
with opening size 510x575mm, and tile returns 50x50x6mm
stainless steel angle around opening, 2 No. stainless steel eyes on
either side of opening, make good all finishings and remove waste
and debris.
NO
145.48
42
PRI DESCRIPTION
UNIT
140005
NO
248.52
140007
NO
122.06
140008
NO
150.83
140010
NO
194.19
140050
IT
187.56
140014
FIRE:RENEW FIRECHEEK
Fire:Take out and renew single fire-cheek including any cutting out and
rebuilding of brickwork and point with fire cement, clean off and remove
waste and debris.
IT
14.69
140032
NO
46.41
140036
NO
34.87
140038
IT
65.55
140043
FIRE:REFLAUNCH FLUE
Fire:Clean out mortar from throat of flue and and remove waste and
debris, and reflaunch with fire cement mortar.
IT
29.50
43
RATE
PRI DESCRIPTION
UNIT
140045
IT
15.58
140047
IT
30.11
140049
IT
42.29
140051
FIRE:RENEW FIREBACK
Fire:Remove existing defective fireback and fix new fireback, ease and
clean damper and remove waste and debris.
IT
79.13
140053
IT
140055
IT
140057
IT
IT
140011
IT
140013
IT
140015
FIRE:RENEW FIRECHEEKS
Fire:Take out and renew pair of fire-cheeks including any cutting
out and rebuilding of brickwork and point with fire cement and
remove waste and debris.
IT
140017
IT
140019
NO
44
RATE
193.10
14.33
9.04
113.63
44.34
8.92
25.01
36.34
6.78
PRI DESCRIPTION
UNIT
RATE
140021
NO
26.74
140025
NO
4.89
140027
SM
139.57
Fire Parts
140023
IT
36.52
708001
NO
251.89
140028
NO
38.98
140029
NO
26.10
140031
NO
32.13
140033
NO
18.56
140035
NO
27.24
140037
NO
28.23
140039
FIRE:RENEW GLASS
Fire:Take out and renew glass strip to door of closed room heater,
clean out rebates, and remove waste and debris and make good.
IT
52.34
140041
IT
71.09
45
PRI DESCRIPTION
UNIT
RATE
46
IT
354.27
PRI DESCRIPTION
UNIT
RATE
MASONRY
Natural Stone
102201
SM
219.10
102203
SM
275.38
102205
SM
260.68
102207
SM
327.90
Reconstructed Stone
102211
SM
164.69
102213
SM
209.47
102215
SM
193.13
47
PRI DESCRIPTION
UNIT
RATE
102217
SM
244.48
102219
SM
178.95
102221
SM
146.60
102223
SM
27.74
102225
SM
108.07
Stone Repairs
146101
SM
129.61
146103
LM
26.80
146107
SM
232.96
48
PRI DESCRIPTION
UNIT
146109
LM
47.03
146113
SM
336.31
146115
LM
67.26
49
RATE
PRI DESCRIPTION
UNIT
RATE
ROOFING
Clay/Concrete Roof Tiling
Concrete Interlocking Roof Tiles to Match Existing
201101
IT
17.70
201103
SM
50.24
201107
IT
13.92
201109
SM
34.83
201113
SM
35.50
201150
SM
24.77
201301
IT
26.29
201303
SM
137.99
201307
IT
18.22
201309
SM
76.37
50
PRI DESCRIPTION
201313
UNIT
RATE
SM
35.50
LM
31.90
201503
LM
41.17
201505
LM
35.49
LM
78.13
201711
LM
128.39
201715
LM
63.05
201717
LM
48.61
201719
NO
173.41
201725
LM
173.32
201727
NO
23.43
51
PRI DESCRIPTION
UNIT
RATE
201731
LM
121.51
201735
LM
174.99
LM
42.95
209003
LM
21.49
209005
NO
9.32
209015
LM
61.24
209017
NO
155.04
Roof Ventilation
211001
NO
54.75
211003
NO
106.06
211009
LM
97.57
52
PRI DESCRIPTION
211011
UNIT
RATE
LM
37.65
Slate Roofing
Fibre Cement Slating
203101
IT
30.97
203103
SM
64.28
203107
IT
24.45
203109
SM
42.12
Natural Slating
203301
IT
48.73
203303
SM
124.66
203307
IT
24.38
203309
SM
42.12
LM
71.04
53
PRI DESCRIPTION
UNIT
RATE
203511
LM
126.71
203517
NO
119.07
203519
LM
31.90
Vertical Coverings
Vertical Tile Hanging
205001
IT
26.36
205003
SM
121.55
205006
SM
24.77
205007
TILE:REFIX HANGING NE 10 NO
Tile:Remove and refix loose plain concrete or clay hanging tiles (in
group ne 10 No. ).
IT
18.15
205009
SM
60.30
205013
NO
16.50
205015
LM
99.58
IT
30.97
54
PRI DESCRIPTION
UNIT
RATE
207003
SM
64.28
207007
IT
24.45
207009
SM
42.12
Sheet Roofing
Sheet Roof Coverings
213001
SM
40.40
213003
SM
37.20
213005
SM
28.57
213007
SM
31.86
213009
SHEETING:RENEW TRANSLUCENT
Sheeting:Renew corrugated fire resisting glass fibre reinforced
translucent sheeting fixed with hook bolts or drive screws complete
with caps and washers and remove waste and debris.
SM
51.36
213011
SM
46.03
213013
LM
23.88
213015
LM
36.67
55
PRI DESCRIPTION
UNIT
RATE
Remedial Works
Liquid Applied Waterproof Roof Covering
215001
SM
23.05
215003
LM
5.88
215005
SM
22.52
215007
SM
12.13
215009
IT
48.82
215011
SM
29.69
215013
LM
20.24
Inspections
221001
IT
41.54
221003
SM
2.77
Temporary Repairs
223001
IT
22.54
223003
IT
26.57
56
PRI DESCRIPTION
UNIT
RATE
223005
NO
59.81
223009
IT
23.67
223011
IT
97.88
223013
IT
142.46
Sundry Items
225001
LM
10.83
225003
ROOFING:SCREED ROOF
Roofing:Screed roof in cement and sand (1:3) including fixing and
striking shuttering and applying new bonding agent to surface.
SM
32.81
Felt Roofing
Felt Roofing - Two Layer
217001
SM
42.06
217003
SM
54.19
57
PRI DESCRIPTION
UNIT
217005
SM
37.51
217007
SM
49.64
217009
IT
40.94
217013
IT
50.50
217019
LM
27.12
217021
LM
26.54
217023
NO
8.67
217025
LM
25.16
217027
LM
15.44
217029
SM
12.31
58
RATE
PRI DESCRIPTION
217031
UNIT
FELT:RENEW CHIPPINGS
Felt:Renew chippings to roof including remove old chippings and
clear away, apply cold compound and spread new chippings. (as
sole job), and remove waste and debris
RATE
SM
24.99
SM
60.55
217103
SM
72.68
217105
SM
53.27
217107
SM
65.41
217109
IT
80.22
217113
IT
67.92
217119
LM
35.82
59
PRI DESCRIPTION
217121
UNIT
RATE
LM
41.87
Asphalt Roofing
Asphalt Roof Coverings
219001
IT
239.57
219003
ASPHALT:RENEW IN AREAS
Asphalt:Renew 20mm asphalt roof finish in areas comprising
isolating membrane, asphalt laid in two layers and bond to existing
asphalt and finish smooth to match existing levels, and remove
waste and debris.
SM
99.02
219005
SM
120.40
219009
ASPHALT:RENEW SKIRTING
Asphalt:Renew asphalt skirting ne 225mm high comprising 13mm
two coat asphalt laid direct to structural background including all
angles, coves and fillets, turn top edge into prepared groove, and
remove waste and debris.
LM
47.55
219011
LM
156.28
219013
IT
24.49
219015
LM
21.11
219017
NO
31.84
219019
IT
19.40
60
PRI DESCRIPTION
UNIT
RATE
219023
NO
52.11
219025
SM
12.31
Sundry Works
Loft Insulation
227005
SM
14.84
227007
SM
6.92
Roof Boarding
229001
SM
36.24
229003
SM
34.30
229005
SM
26.44
229007
SM
27.98
229009
LM
4.35
61
PRI DESCRIPTION
UNIT
RATE
Leadwork
Lead Roof Coverings and Flashings - Code 4
231001
NO
89.33
231003
NO
83.85
231005
LM
36.25
231009
LM
71.30
231011
LM
67.48
231013
LM
17.48
231015
LM
10.56
231017
LM
87.58
231020
LM
89.55
231021
LM
106.44
62
PRI DESCRIPTION
UNIT
231023
LM
160.75
231025
IT
21.78
231027
NO
16.00
231031
SM
157.57
231033
SM
171.41
231035
SM
181.80
231037
IT
521.64
231039
IT
587.41
63
RATE
PRI DESCRIPTION
UNIT
RATE
LM
11.84
301107
LM
21.02
301109
NO
33.91
301122
SM
16.90
301123
SM
136.34
301125
SM
82.20
301127
SM
86.42
64
PRI DESCRIPTION
UNIT
RATE
301129
SM
66.89
301131
SM
71.10
Wall or Partitions
301301
SM
73.69
301303
SM
84.09
301305
SM
4.42
301307
SM
7.51
301311
SM
50.29
301313
SM
57.10
301315
SM
95.50
65
PRI DESCRIPTION
301317
UNIT
RATE
IT
101.01
Wall Plates
301501
LM
9.31
301503
LM
11.63
Roof Members
301701
LM
11.60
301703
LM
15.98
Joist Hangers
301901
NO
6.96
301903
IT
10.46
66
PRI DESCRIPTION
UNIT
RATE
LM
36.03
303003
LM
33.94
303007
LM
35.45
303009
LM
34.56
303011
LM
48.67
303015
FASCIA/SOFFIT/BARGE:REFIX
Fascia/Soffit/Barge:Refix any size fascia, soffit or bargeboard to
existing roof timbers including remove and refix rainwater goods
and cabling as necessary, renewal of support battens, all cutting
and packing and make good decorations.
LM
26.98
303017
NO
46.00
LM
25.67
67
PRI DESCRIPTION
UNIT
RATE
303013
LM
30.27
303019
NO
45.90
LM
24.72
303102
LM
10.20
303103
NO
8.57
303104
GUTTER:FORM OUTLET
Gutter:Cut hole in timber gutter, form outlet and fix nozzle spitter.
NO
38.56
303105
NO
7.85
303106
NO
13.96
Flooring
Flooring - Rigid Sheet - WPB Plywood
305101
SM
29.91
305103
SM
20.20
305105
SM
20.20
68
PRI DESCRIPTION
UNIT
RATE
SM
27.10
305303
SM
33.14
SM
9.73
305701
FLOORBOARD:RENEW NE 1.0SM
Floorboard:Renew to match existing any flooring with 19mm
tongued and grooved or square edged flooring in area ne 1.00sm,
including denail joists, and remove waste and debris, punch in
nails, level level to existing and make good including any extra
support noggins required.
IT
56.77
305703
SM
54.62
305704
SM
18.23
305705
LM
4.42
305706
IT
5.10
305709
SM
9.05
69
PRI DESCRIPTION
UNIT
RATE
IT
152.11
306003
SM
101.40
External Cladding
Cladding - Timber Weatherboarding - Shiplap
307101
IT
69.31
307103
SM
37.64
307105
SM
9.04
IT
65.42
307303
SM
35.51
70
PRI DESCRIPTION
UNIT
RATE
IT
81.78
307503
SM
47.21
IT
81.37
307703
SM
44.94
307705
SM
10.20
SM
275.73
Windows
Windows - Casement - Standard Softwood Double Glazed
310101
71
PRI DESCRIPTION
UNIT
RATE
310105
SM
316.47
310109
SM
392.02
310113
SM
426.27
SM
307.06
310305
SM
380.51
72
PRI DESCRIPTION
UNIT
RATE
310309
SM
490.84
310313
SM
563.81
SM
474.38
SM
384.60
SM
370.75
310701
311101
73
PRI DESCRIPTION
UNIT
RATE
311105
SM
443.76
311109
SM
599.61
311113
SM
648.62
SM
404.26
311305
SM
527.43
74
PRI DESCRIPTION
UNIT
RATE
311309
SM
770.15
311313
SM
889.50
SM
735.70
SM
554.81
SM
320.90
311701
312001
75
PRI DESCRIPTION
UNIT
RATE
SM
419.34
SM
333.23
SM
437.44
SM
255.36
341501
313501
76
PRI DESCRIPTION
UNIT
RATE
NO
251.23
313605
SM
354.43
313609
SM
446.24
313613
SM
486.61
77
PRI DESCRIPTION
UNIT
RATE
SM
193.77
313705
SM
298.15
313709
SM
448.34
313713
SM
460.04
SM
267.86
PRI DESCRIPTION
UNIT
RATE
SM
-20.72
NO
13.49
315007
NO
117.10
315009
NO
101.86
315011
NO
178.59
315013
NO
219.44
314005
SM
20.72
315015
LM
9.49
315019
IT
23.86
79
PRI DESCRIPTION
UNIT
315021
NO
33.31
315023
NO
60.58
315025
IT
105.47
315027
LM
47.58
315029
IT
39.46
315031
LM
54.93
315035
LM
7.40
315039
LM
5.86
315041
LM
16.15
315043
LM
49.70
315045
LM
7.52
80
RATE
PRI DESCRIPTION
UNIT
RATE
315047
LM
55.32
315049
WINDOW:OVERHAUL CASEMENT
Window:Overhaul timber casement window, dismantle as necessary
and subsequently reassemble including freeing, easing and
adjusting casements to give correct operation, renew sealing
gaskets, renew fixing screws, remove, refit or renew ironmongery
as necessary, rake out and renew defective putty and mastic, touch
up decorations externally and internally to match existing and
remove waste and debris.
NO
39.35
315051
WINDOW:OVERHAUL SASH
Window:Overhaul timber sash window, renew staff and parting
beads, take out sashes and later rehang on appropriate sized new
undyed plaited nylon sash cords, renew pocket pieces, wedge and
cramp loose sash frames, oil pulleys, ease and adjust sashes,
remove, refit or renew ironmongery, rake out and renew defective
putty and mastic, touch up decorations externally and internally to
match existing and remove waste and debris.
NO
48.08
LM
41.52
315107
NO
29.16
315109
NO
37.85
315111
NO
31.33
315113
NO
34.95
81
PRI DESCRIPTION
UNIT
RATE
315115
NO
29.88
315117
NO
36.40
315119
NO
37.85
LM
28.89
316401
NO
6.71
316405
IT
17.21
316407
WINDOW:OVERHAUL METAL
Window:Overhaul any type of metal window, dismantle as
necessary and subsequently reassemble including freeing, easing,
oiling and adjusting casements to give correct operation, including
file and grind edges, renew fixing screws, remove, refit or renew
ironmongery as necessary, rake out and renew defective putty and
mastic, touch up decorations internally to match existing and
remove waste and debris.
NO
38.62
82
PRI DESCRIPTION
UNIT
RATE
NO
8.01
317205
WINDOW:OVERHAUL ALUMINIUM
Window:Overhaul any type of aluminium window, dismantle as
necessary and subsequently reassemble including freeing, easing
and adjusting casements to give correct operation, renew fixing
screws, remove, refit or renew ironmongery as necessary, rake out
and renew defective sealants and mastic, make good.
NO
38.62
NO
47.23
318103
NO
86.45
318105
IT
11.16
318107
NO
16.10
318108
NO
20.88
318109
NO
10.24
318111
IT
21.94
318113
IT
7.17
318115
IT
6.71
318117
IT
11.16
83
PRI DESCRIPTION
UNIT
318119
NO
18.74
318121
NO
102.05
318123
NO
10.27
318125
WINDOW:OVERHAUL PVCU
Window:Overhaul any type of PVCu window, dismantle as
necessary and subsequently reassemble including freeing, easing
and adjusting casements to give correct operation, renew fixing
screws, remove, refit or renew ironmongery as necessary, check,
lubricate operating mechanism, renew gaskets, make good and
test.
NO
38.62
318151
LM
6.13
318155
LM
2.49
318157
NO
8.58
318159
NO
3.04
318161
NO
10.27
318163
NO
14.31
318165
LM
5.43
318167
LM
4.12
318169
LM
5.52
84
RATE
PRI DESCRIPTION
UNIT
RATE
318171
LM
5.80
318173
LM
5.52
318175
LM
5.80
318177
IT
2.02
318179
LM
3.97
318181
LM
5.31
318185
LM
18.99
318187
LM
14.61
318189
NO
2.33
IT
42.29
318303
IT
53.95
85
PRI DESCRIPTION
UNIT
318305
IT
60.95
318307
IT
70.43
318309
IT
77.43
318311
IT
33.83
318313
IT
37.55
318315
IT
51.62
86
RATE
PRI DESCRIPTION
UNIT
RATE
318317
IT
63.43
318319
IT
65.91
IT
14.23
318203
IT
15.12
318207
IT
21.24
Windows - Roof
319001
NO
618.92
319003
NO
704.83
87
PRI DESCRIPTION
319005
UNIT
RATE
NO
794.62
NO
31.32
319103
NO
28.43
319105
NO
28.37
External Doors
Doors - External Panelled or Glazed - Hardwood - Standard
321105
NO
450.52
321107
NO
582.94
NO
693.67
88
PRI DESCRIPTION
321307
UNIT
RATE
NO
826.08
NO
381.64
321507
NO
509.67
NO
616.98
321707
NO
740.64
89
PRI DESCRIPTION
UNIT
RATE
NO
548.95
322103
NO
659.04
NO
428.92
323103
NO
526.34
323105
NO
303.74
90
PRI DESCRIPTION
323107
UNIT
RATE
NO
361.11
NO
230.57
328103
NO
248.10
NO
560.31
323503
NO
642.23
323505
NO
462.69
91
PRI DESCRIPTION
UNIT
RATE
323507
NO
462.69
323509
IT
1413.27
NO
576.92
323603
NO
666.59
NO
13.56
324107
NO
7.74
324109
NO
28.78
92
PRI DESCRIPTION
UNIT
324111
NO
28.81
324113
IT
66.08
324115
NO
18.13
324117
NO
14.03
324119
LM
8.97
324121
IT
105.59
324123
NO
87.47
324125
NO
111.82
328105
IT
22.49
93
RATE
PRI DESCRIPTION
328107
UNIT
RATE
IT
13.85
NO
13.51
325103
IT
11.30
325105
NO
107.36
325107
NO
26.33
325109
NO
32.28
325111
NO
13.93
325113
NO
14.58
325115
NO
65.40
325117
DOOR:OVERHAUL PVCU
Door:Overhaul any PVCu or glazed PVCu door, including remove
door from frame, ease and adjust foot of door, adjust door locking
mechanisms and hinges to ensure that door operates correctly,
rehang door to existing frame.
NO
43.65
325123
NO
87.08
94
PRI DESCRIPTION
325125
UNIT
RATE
NO
126.50
NO
13.27
326107
NO
71.07
NO
8.90
327103
NO
71.07
327105
NO
1625.16
NO
125.55
330003
NO
108.42
95
PRI DESCRIPTION
UNIT
RATE
330005
NO
129.88
330011
NO
120.65
330019
NO
44.22
330021
IT
12.51
NO
286.31
330009
NO
428.06
NO
179.07
96
PRI DESCRIPTION
UNIT
RATE
330015
NO
298.80
330017
NO
226.43
330023
NO
63.50
NO
28.46
335005
IT
43.80
335009
IT
52.95
335011
IT
34.10
335091
NO
35.72
97
PRI DESCRIPTION
UNIT
RATE
NO
166.48
341103
NO
172.58
341105
NO
261.91
NO
180.93
341203
NO
193.27
98
PRI DESCRIPTION
UNIT
RATE
341205
NO
302.82
341207
NO
315.16
WATERBAR:RENEW
Waterbar:Renew ne 914mm long proprietary waterbar screwed to
timber or concrete including plugging and bedded in sealant.
NO
15.60
341705
WATERBAR:REFIX WATERBAR
Waterbar:Lift existing proprietary waterbar, clean and refix, screw
to timber and bed in sealant.
NO
9.12
NO
26.05
341903
NO
30.42
341905
NO
52.29
341907
NO
8.90
341921
LM
2.54
341923
LM
7.04
99
PRI DESCRIPTION
UNIT
RATE
NO
105.71
342107
NO
126.12
342115
NO
171.34
NO
59.47
342303
NO
68.22
342307
NO
34.59
100
PRI DESCRIPTION
UNIT
RATE
342309
NO
33.85
342311
NO
17.94
342313
LM
2.25
342315
NO
83.40
342317
NO
47.07
342321
NO
24.90
342323
NO
22.10
342325
NO
9.04
IT
21.21
342505
IT
3.72
342507
IT
22.32
101
PRI DESCRIPTION
UNIT
RATE
LM
4.45
343107
LM
5.16
343111
LM
10.48
343113
LM
9.39
IT
711.72
345203
NO
62.72
IT
623.67
345601
IT
66.08
345603
IT
42.29
102
PRI DESCRIPTION
UNIT
RATE
345605
NO
44.03
345607
NO
25.40
345609
NO
33.69
345611
NO
19.22
345613
IT
196.09
345615
NO
74.32
345617
NO
20.73
345619
IT
52.84
IT
109.17
345703
NO
40.82
103
PRI DESCRIPTION
UNIT
RATE
328109
NO
168.03
328111
LM
11.15
Internal Joinery
Cladding or Linings - Internal Wall
350001
SM
3.06
350005
PANELLING:RENEW IN HARDBOARD
Panelling:Remove existing hardboard panelling and renew with
3.2mm faced hardboard panelling fixed to softwood with brass cups
and screws and remove waste and debris..
SM
20.61
350007
SM
18.38
Staircases
351001
NO
23.32
351003
NO
49.18
351004
STAIRCASE:RENEW TREAD
Staircase:Renew softwood tread to staircase housed into strings,
including all wedges and blocks, glued and screwed, prepare for
redecoration.
NO
48.37
351005
NO
46.25
104
PRI DESCRIPTION
UNIT
RATE
351007
NO
112.05
351009
NO
16.15
351011
NO
40.14
351013
NO
8.83
351015
NO
15.61
351017
NO
4.52
351019
STAIRCASE:OVERHAUL
Staircase:Overhaul existing staircase, clean off stair treads and
landings, punch in all nail heads, screw down all loose boards etc.,
securely fix all existing balustrades, wedge treads and risers and
make good all works disturbed.
IT
86.03
Handrails
352001
LM
33.29
352003
LM
41.95
352005
LM
14.15
352007
LM
16.58
105
PRI DESCRIPTION
UNIT
RATE
352009
LM
26.68
352011
NO
16.53
352017
HANDRAIL:REFIX ON BRACKETS
Handrail:Refix handrail, fixed to existing brackets and make good decorate
to match existing.
LM
7.59
352013
NO
8.97
352015
NO
6.93
NO
69.59
Miscellaneous Fixtures/Fittings
Stool for Hot Water Cylinder
361001
STOOL:RENEW TO CYLINDER
Stool:Renew or supply and fix wrot softwood stool for hot water
cylinder, finished sizes 515x515x610mm high, formed of four
50x50mm legs, eight 69x32mm horizontal runners and 19mm
plywood top, remove and replace cylinder as necessary and test
existing and remove waste and debris..
Tank Stands
361021
NO
65.73
361023
NO
148.01
106
PRI DESCRIPTION
UNIT
RATE
IT
35.83
362003
NO
4.63
362050
IT
23.02
IT
18.74
363011
LM
16.87
NO
102.43
371003
NO
140.16
371005
NO
148.77
371007
NO
156.24
107
PRI DESCRIPTION
UNIT
RATE
371009
NO
79.18
371011
NO
97.07
371013
NO
121.55
NO
89.75
371023
NO
98.90
371025
NO
86.70
371027
NO
91.46
371029
NO
102.43
371031
NO
105.24
108
PRI DESCRIPTION
UNIT
371033
NO
146.26
371035
NO
149.07
371037
NO
169.80
371039
NO
140.16
371041
NO
140.16
371043
NO
181.99
371045
NO
149.68
371047
NO
161.41
371049
NO
161.41
371051
NO
57.84
109
RATE
PRI DESCRIPTION
UNIT
371053
NO
64.06
371055
NO
68.45
371057
NO
74.30
371059
NO
97.07
371061
NO
101.09
371063
NO
136.22
371065
NO
152.31
371067
NO
89.97
371069
NO
118.50
371071
NO
148.16
110
RATE
PRI DESCRIPTION
371073
UNIT
RATE
NO
130.59
Worktops
372001
LM
31.48
372002
LM
34.65
372005
LM
10.51
372007
LM
5.57
372009
NO
64.42
372011
NO
17.60
372013
NO
22.73
372017
NO
17.28
372019
LM
5.41
372021
WORKTOP:PROVIDE COVERBEAD
Worktop:Supply and fix proprietary aluminium L shaped cover
bead rounded at end, screwed to edge of chipboard worktop.
NO
12.69
111
PRI DESCRIPTION
UNIT
RATE
NO
19.25
373005
NO
60.66
373007
NO
67.36
373009
NO
67.22
373011
NO
82.92
373013
NO
27.02
373015
NO
11.89
373019
NO
14.08
373021
NO
53.65
373023
NO
4.19
373027
NO
63.95
112
PRI DESCRIPTION
UNIT
RATE
373045
IT
19.50
373049
NO
27.71
Wardrobe Units
Fitted Wardrobe - Repairs
375003
NO
17.43
375005
WARDROBE:PATCH OR REPAIR
Wardrobe:Carry out any patch or repair to door, framing or
casework of any fitted wardrobe including cut out and splice in new
timber upto 600mm long, make good and decorate to match
existing.
NO
15.81
375007
WARDROBE:RENEW HINGE
Wardrobe:Renew butt or concealed hinge to door including
removing existing, adjustment and realignment of door, make good
and touch up decorations as necessary.
NO
8.21
375009
IT
27.71
375011
IT
46.77
375013
NO
8.39
375015
NO
18.03
LM
20.06
113
PRI DESCRIPTION
381003
UNIT
RATE
LM
6.71
LM
3.65
Picture Rail
382001
383001
IT
25.57
383003
IT
10.06
383007
IT
6.78
IT
15.84
384003
THRESHOLD:RESECURE LOOSE
Threshold:Resecure loose door threshold.
IT
8.01
Shelving
385001
LM
5.11
385003
IT
42.52
385005
LM
9.36
385007
LM
17.90
114
PRI DESCRIPTION
385009
UNIT
RATE
LM
18.59
Windowboards
386001
WINDOWBOARD:RENEW SOFTWOOD
Windowboard:Renew ne 25x300mm softwood windowboard
plugged, screwed and pellated to brickwork, make good
plasterwork and decorations and decorate to match existing and
remove waste and debris.
LM
34.78
386003
WINDOWBOARD:RENEW MDF
Windowboard:Renew ne 25x300mm MDF windowboard plugged,
screwed and pellated to brickwork, make good plasterwork and
decorations and decorate to match existing and remove waste and
debris.
LM
33.19
386005
WINDOWBOARD:RENEW HARDWOOD
Windowboard:Renew ne 25x300mm hardwood windowboard
plugged, screwed and pellated to brickwork, make good
plasterwork and decorations and decorate to match existing and
remove waste and debris.
LM
45.72
386009
WINDOWBOARD:RENEW PVCU
Windowboard:Renew existing with PVCu ne 25x300mm
windowboard fixed with approved adhesive or other approved
concealed fixing method to brickwork, make good plasterwork and
decorations.
LM
37.62
386007
WINDOWBOARD:REFIX LOOSE
Windowboard:Refix any size or type of loose windowboard to
window including removing if necessary, making good and touching
up decorations.
NO
6.93
Duct Casings
387001
LM
21.52
387003
SM
56.16
387007
LM
51.03
387009
LM
27.00
115
PRI DESCRIPTION
UNIT
RATE
387011
SM
60.22
387015
LM
55.16
387017
LM
9.12
387019
IT
47.04
IT
64.37
388003
IT
40.16
388005
IT
94.75
388007
IT
24.68
388009
IT
15.19
388011
IT
34.04
116
PRI DESCRIPTION
UNIT
RATE
388013
IT
47.73
388015
IT
29.42
388017
IT
69.14
388019
NO
8.90
Ironmongery
Butts, Hinges, etc.
390101
PR
9.97
390105
PR
46.99
390107
IT
15.63
390109
IT
25.49
390111
PR
16.49
390113
PR
11.40
NO
13.31
390307
NO
9.08
117
PRI DESCRIPTION
UNIT
RATE
390309
NO
19.06
390311
PR
52.17
390313
PR
34.39
Door Closers
390501
NO
49.00
390503
NO
64.46
390505
NO
12.89
390509
NO
18.22
390507
NO
6.71
Floor Springs
390601
NO
213.93
390603
NO
294.34
390605
FLOOR SPRING:OVERHAUL
Floor Spring:Overhaul and maintain floor spring to door, including
ease and adjust, oil moving parts
NO
22.59
118
PRI DESCRIPTION
UNIT
RATE
NO
29.16
390703
NO
63.17
Locks
390901
RIMLOCK:RENEW COMPLETE
Rimlock:Renew rimlock, keep and set of rimlock furniture, including
altering door as necessary for new lock and housing out existing
frame as necessary and provide two new keys.
NO
88.52
390903
NO
37.84
390907
NO
5.00
390909
NO
32.54
390911
NO
29.49
390915
NO
76.08
390917
NO
10.97
390919
NO
46.99
390921
NO
168.34
119
PRI DESCRIPTION
UNIT
RATE
390923
NO
41.13
390927
NO
40.69
Latches
391101
NO
22.21
391107
NO
9.04
NIGHTLATCH:RENEW COMPLETE
Nightlatch:Renew cylinder rim night latch, keep and pull handle,
including altering door as necessary for new latch and provide two
new keys.
NO
62.84
391305
NO
23.55
391307
NO
12.80
391309
NIGHTLATCH:OVERHAUL COMPLETE
Nightlatch:Remove any type of cylinder nightlatch, dismantle,
overhaul, repair, oil and assemble and refix to door.
NO
10.97
391313
NIGHTLATCH:RENEW PULL
Nightlatch:Renew nightlatch finger full, dismantle latch, install new
pull, oil and reassemble and refix to door.
NO
14.14
NO
11.50
391503
NO
17.88
391505
NO
8.45
391507
NO
6.88
120
PRI DESCRIPTION
UNIT
RATE
NO
9.88
391703
NO
8.18
391705
NO
4.63
391707
NO
13.57
391709
NO
41.27
391711
NO
60.06
391713
NO
59.13
391715
NO
8.53
391719
NO
4.41
391723
NO
10.52
391725
NO
17.61
391727
NO
24.63
NO
14.60
391905
NO
15.21
391909
NO
19.01
121
PRI DESCRIPTION
UNIT
RATE
391913
NO
11.63
391917
NO
10.16
391921
NO
14.56
391925
NO
20.78
391927
NO
19.58
391929
NO
25.66
391931
NO
36.96
391933
NO
3.57
391937
NO
25.12
391939
NO
28.56
391941
NO
25.92
391943
NO
3.36
NO
28.35
122
PRI DESCRIPTION
UNIT
RATE
392103
NO
16.14
392109
NO
9.48
392111
NO
23.76
NO
19.15
392303
NO
13.59
392309
NO
9.48
NO
13.39
392505
NO
15.33
392509
NO
12.11
392511
NO
9.77
392513
NO
2.77
392515
NO
60.35
392517
NO
9.96
392519
NO
18.27
123
PRI DESCRIPTION
UNIT
RATE
392521
NO
4.27
392523
NO
5.98
392525
NO
9.86
392527
NO
19.39
Letterplates
392701
NO
46.46
392702
NO
72.72
392703
NO
50.57
392705
NO
31.02
IT
8.25
NO
2.74
Door Numerals
392901
DOOR NUMERAL:RENEW NE 3 NO
Door Numeral:Renew or replace ne 3 No. letters or numerals.
Door Stop
393101
393301
NO
7.74
393303
NO
9.87
393305
NO
2.33
393307
CUPBOARD:RENEW KNOB
Cupboard:Renew satin anodised aluminium knob handle.
NO
3.24
124
PRI DESCRIPTION
UNIT
RATE
Miscellaneous Works
Ceiling Access Hatch
395101
IT
149.32
395103
IT
71.70
395105
IT
194.05
395107
IT
138.69
395109
IT
13.84
395111
IT
12.08
Gain Entry
396001
DWELLING:GAIN ACCESS
Dwelling:Gain access for eviction or for tenant locked out or
emergency works, including force access to door, cut out and splice
in new piece to external door frame, touch up decorations, provide
new barrel and two keys as necessary or gain access through
window including remove existing glass, gain access, reglaze
including make good and touch up decorations.
IT
53.45
396006
GARAGE:GAIN ACCESS
Garage:Gain access for tenant, including force access including
redrill for fixing bolts and alter door, provide new lock and collect
and return keys to tenant.
NO
45.08
NO
27.89
Boarding Up/Nailing Up
397001
125
PRI DESCRIPTION
UNIT
RATE
397003
NO
7.29
397005
NO
5.61
397007
NO
3.21
IT
64.58
397023
NO
7.53
397024
NO
6.48
397025
NO
13.92
397026
NO
7.53
126
PRI DESCRIPTION
UNIT
RATE
397027
NO
25.38
397029
IT
50.93
397031
NO
20.13
397033
NO
34.92
397035
NO
7.53
IT
13.13
127
PRI DESCRIPTION
UNIT
RATE
IT
13.88
411107
SM
10.82
411113
IT
32.62
411115
SM
28.24
411121
IT
48.97
411123
SM
42.41
411133
IT
20.78
411135
SM
17.72
411137
IT
4.39
411139
WALL:BONDING AGENT
Wall:Apply bonding agent to wall
SM
4.04
128
PRI DESCRIPTION
UNIT
RATE
Plasterboard - Walls
411309
IT
14.80
411311
SM
12.24
411313
IT
26.85
411315
SM
22.18
411321
IT
37.35
411323
SM
29.62
411325
IT
48.11
411327
SM
36.88
IT
16.07
Plasterwork - Ceilings
413105
129
PRI DESCRIPTION
UNIT
RATE
413107
SM
13.00
413109
IT
24.82
413111
SM
21.76
413117
IT
30.07
413119
SM
25.70
413121
IT
5.57
413122
CEILING:BONDING AGENT.
Ceiling:Apply bonding agent to ceiling
SM
5.14
Plasterboard - Ceilings
413305
IT
29.04
413307
SM
23.49
413309
IT
44.32
413311
SM
35.28
130
PRI DESCRIPTION
UNIT
RATE
413317
IT
44.35
413319
SM
35.31
413321
IT
53.08
413323
SM
41.84
413325
SM
25.71
LM
4.67
415003
LM
9.44
415005
LM
3.79
415011
LM
8.81
131
PRI DESCRIPTION
UNIT
RATE
415013
LM
9.12
415015
LM
8.00
415017
NO
5.61
415019
NO
11.55
IT
21.88
421003
SM
17.51
421021
IT
30.77
421023
SM
27.70
421025
IT
36.44
421027
SM
33.81
421029
IT
43.09
132
PRI DESCRIPTION
UNIT
RATE
421031
SM
39.06
421033
IT
45.62
421035
SM
41.24
LM
9.48
423003
LM
12.75
423005
LM
15.16
423007
LM
14.92
Coatings to Ceilings
425001
SM
11.17
425002
IT
9.42
133
PRI DESCRIPTION
UNIT
RATE
Dry Lining
427003
SM
33.27
427005
SM
64.93
427007
SM
86.34
427009
SM
62.20
427011
SM
80.10
Plaster Coving
429001
LM
8.39
429003
LM
6.85
134
PRI DESCRIPTION
UNIT
RATE
Floor Screeds
431301
IT
26.26
431303
SCREED:HACK UP SCREED
Screed:Hack up any thickness of floor screed and remove waste
and debris.
SM
19.70
431305
LM
7.04
431307
IT
30.56
431309
SM
26.18
431311
SM
23.09
431315
SM
17.03
135
PRI DESCRIPTION
UNIT
RATE
SM
11.08
431005
NO
1.76
431007
SM
51.56
431011
LM
20.22
431013
IT
18.03
431015
LM
17.01
431017
LM
17.90
431019
LM
13.68
136
PRI DESCRIPTION
UNIT
RATE
431021
NO
1.05
431023
SM
60.14
431025
SM
11.76
431041
SM
56.81
431043
SM
56.81
IT
107.45
431503
SM
97.78
431505
IT
75.50
431507
SM
75.02
137
PRI DESCRIPTION
UNIT
RATE
431509
NO
1.90
431513
NO
2.64
431511
SM
71.51
NO
4.93
431703
LM
21.14
431705
NO
4.05
431707
LM
16.76
431709
NO
5.40
431711
LM
22.18
IT
91.13
138
PRI DESCRIPTION
UNIT
RATE
431903
SM
94.31
431905
IT
58.31
431907
SM
70.24
431909
NO
1.43
431911
SM
60.05
Skirtings - Ceramic
432101
NO
3.95
432103
LM
17.02
432105
NO
3.51
432107
LM
13.52
432109
NO
4.49
139
PRI DESCRIPTION
432111
UNIT
RATE
LM
18.32
NO
0.93
432303
SM
7.20
432305
NO
2.82
432307
SM
27.14
432309
SM
42.97
432311
NO
2.38
432313
SM
22.76
432314
SM
36.87
432315
NO
2.31
432317
SM
20.95
140
PRI DESCRIPTION
UNIT
RATE
Sheet Flooring
432501
SM
35.46
432503
SM
49.10
432505
SM
31.09
432507
SM
44.73
432509
SM
10.85
'Polysafe' Flooring
432601
SM
42.03
432603
SM
55.67
432605
SM
37.66
432607
SM
51.30
141
PRI DESCRIPTION
UNIT
RATE
432609
SM
50.79
432611
SM
44.22
432617
SM
9.77
432604
SM
51.76
432608
SM
48.70
432613
SM
37.66
432615
SM
44.22
IT
9.03
432703
LM
11.47
142
PRI DESCRIPTION
UNIT
RATE
432705
IT
7.24
432707
LM
9.07
SM
14.70
432803
SM
18.38
432805
SM
17.06
Nosings
432901
NO
45.74
432903
NO
41.37
432905
NOSING:REFIX TO STEP
Nosing:Take off and refix any size or type of nosing to step
including drilling and plugging as necessary.
NO
13.42
143
PRI DESCRIPTION
UNIT
RATE
LM
2.19
SM
9.55
435103
LM
3.30
435113
SM
19.97
435119
SM
4.99
435121
SM
6.27
SM
2.33
SM
10.84
436051
144
PRI DESCRIPTION
UNIT
RATE
436053
SM
12.32
436061
SM
10.84
436063
SM
12.32
436071
SM
10.84
436072
SM
11.71
436073
SM
12.59
436074
SM
13.46
436081
SM
12.32
436082
SM
12.59
436083
SM
14.51
436084
SM
15.39
IT
98.91
145
PRI DESCRIPTION
UNIT
RATE
436203
LM
6.76
436205
IT
62.68
436207
IT
74.31
436209
SM
24.73
436215
IT
28.84
436217
SM
27.18
436219
SM
26.60
436221
LM
3.43
436223
LM
2.94
IT
91.36
436603
LM
7.29
436605
IT
65.49
146
PRI DESCRIPTION
UNIT
RATE
436607
IT
76.31
436609
SM
26.47
436615
IT
32.17
436617
SM
30.79
436619
SM
31.01
436621
LM
3.96
436623
LM
3.12
436625
SM
20.28
436627
SM
18.97
436629
SM
16.56
IT
71.68
436703
LM
7.09
147
PRI DESCRIPTION
UNIT
436705
IT
46.83
436707
IT
37.98
436709
IT
23.92
436715
IT
44.48
436717
SM
34.74
436719
SM
37.61
436721
LM
4.72
436723
LM
4.18
436725
SM
26.43
436727
SM
25.11
436729
SM
22.93
148
RATE
PRI DESCRIPTION
UNIT
RATE
SM
24.66
438002
LM
6.66
438003
SM
35.86
438009
LM
8.41
438011
IT
28.54
438013
IT
57.08
438015
IT
35.30
438017
IT
70.48
438019
LM
8.75
438020
LM
8.41
438053
SM
20.72
149
PRI DESCRIPTION
UNIT
RATE
438055
SM
18.75
438021
SM
22.37
LM
4.87
438169
LM
5.31
438171
SM
11.19
438173
SM
10.28
438175
SM
9.19
LM
6.41
438119
LM
6.46
438121
SM
16.81
438123
SM
15.16
150
PRI DESCRIPTION
438125
UNIT
RATE
SM
13.62
SM
15.45
438203
IT
19.91
438209
LM
6.76
438211
IT
25.02
438213
IT
44.17
438215
IT
18.39
438217
IT
32.41
438219
LM
7.63
438221
IT
11.89
SM
3.62
PRI DESCRIPTION
UNIT
RATE
439203
SM
3.21
439205
SM
3.50
439207
SM
3.78
439211
SM
5.36
439213
SM
4.77
439215
SM
5.13
439217
SM
5.64
Internal Decoration
Wash Down
441001
IT
21.37
441003
IT
40.48
SM
17.94
SM
11.20
442001
152
PRI DESCRIPTION
UNIT
RATE
442003
SM
9.18
442009
SM
16.69
442011
SM
11.92
IT
162.55
450019
IT
203.18
450023
IT
243.82
450027
IT
284.46
450009
HALLSTAIRS:REDECORATE 2 STOREY
HallStairs:Rub down, prepare for and apply two coats of emulsion
to ceilings and walls, one undercoat and gloss on all previously
painted surfaces of hall, landing and staircase area complete. (2
storey) (classified as a single area).
IT
493.90
450010
HALLSTAIRS:REDECORATE 3 STOREY
HallStairs:Rub down, prepare for and apply two coats of emulsion
to ceilings and walls, one undercoat and gloss on all previously
painted surfaces of hall, landing and staircase area complete (3
storey) (classified as a single area).
IT
740.85
450011
IT
276.34
153
PRI DESCRIPTION
UNIT
RATE
450017
IT
140.44
450031
CORRIDOR/COMMUNAL AREA:REDECORATE
Corridor/Communal Room:Rub down, prepare for and apply two coats of
emulsion to ceilings and walls, one undercoat and gloss on all previously
painted surfaces of corridors, open communal areas etc [measured per
square metre of ceiling area.]
SM
17.73
IT
104.78
450519
IT
128.48
450523
IT
153.17
450527
IT
177.87
450509
IT
287.59
450510
IT
431.38
450511
IT
183.18
450517
IT
72.52
154
PRI DESCRIPTION
450529
UNIT
RATE
SM
12.35
IT
55.77
450615
IT
69.71
450617
IT
85.65
450619
IT
100.59
450609
IT
125.66
450610
IT
181.43
450611
IT
55.77
450612
IT
23.09
450621
SM
4.16
IT
209.02
Strip Paper
451007
155
PRI DESCRIPTION
UNIT
RATE
451015
SM
11.60
451009
IT
247.54
451010
IT
358.69
451011
IT
171.04
451012
IT
53.24
451017
SM
10.72
IT
501.82
451115
SM
28.23
451109
IT
596.36
156
PRI DESCRIPTION
UNIT
RATE
451110
IT
864.63
451111
IT
416.13
451112
IT
204.60
451117
SM
25.82
IT
141.52
452041
SM
7.66
452009
IT
169.72
452010
IT
258.30
452008
IT
82.22
452033
IT
27.36
157
PRI DESCRIPTION
UNIT
452043
SM
7.00
452017
IT
85.21
452045
SM
4.38
452019
IT
75.45
452020
IT
112.74
452018
IT
74.04
452047
SM
4.16
452027
IT
46.96
452049
SM
3.06
452029
IT
45.68
452030
IT
69.26
452031
IT
57.83
158
RATE
PRI DESCRIPTION
UNIT
RATE
452037
IT
18.41
452051
SM
2.93
IT
120.55
453037
SM
7.63
453009
IT
231.46
453008
IT
347.40
453010
IT
143.96
453032
IT
52.03
453039
SM
12.00
IT
132.80
453041
SM
10.13
453019
IT
237.10
159
PRI DESCRIPTION
UNIT
453018
IT
355.85
453020
IT
146.78
453033
IT
61.98
453043
SM
14.50
453027
IT
76.32
453045
SM
10.38
453029
IT
149.65
453030
IT
227.47
453031
IT
85.20
453034
IT
80.33
453047
SM
9.95
160
RATE
PRI DESCRIPTION
UNIT
RATE
IT
659.55
470002
IT
787.08
470003
IT
914.62
470010
IT
1013.40
470011
IT
1140.93
470012
IT
1268.46
470040
IT
448.86
470041
IT
508.25
470042
IT
633.29
161
PRI DESCRIPTION
UNIT
RATE
470045
IT
858.03
470046
IT
1012.76
470047
IT
1167.50
IT
429.43
470502
IT
512.32
470503
IT
595.22
470510
IT
649.55
470511
IT
732.45
470512
IT
813.16
162
PRI DESCRIPTION
UNIT
470520
IT
244.26
470521
IT
292.27
470522
IT
338.09
470530
IT
370.73
470531
IT
418.74
470532
IT
464.57
470540
IT
279.88
470541
IT
333.27
470542
IT
394.41
470545
IT
535.82
163
RATE
PRI DESCRIPTION
UNIT
RATE
470546
IT
630.22
470547
IT
724.62
SM
7.57
164
PRI DESCRIPTION
UNIT
RATE
IT
77.65
460003
IT
65.22
460004
IT
69.52
460009
IT
203.57
460010
IT
443.11
460006
IT
62.95
External Clearance
460025
GARDEN:CLEAR DEBRIS
Garden:Clear away all litter and rubbish including scrap metal, timber,
broken glass, garden debris, fallen leaves, dumped materials and stones,
load up and remove from site to an approved tip.
IT
37.45
460026
IT
112.34
165
PRI DESCRIPTION
UNIT
RATE
460027
SM
1.75
460028
SM
2.19
460029
GARAGE:CLEAR DEBRIS
Garage:Clear out, and remove all contents to an approved tip or recycling
centre and make ready for new tenant.
IT
50.74
460031
SHED:CLEAR DEBRIS
Shed:Clear out, and remove all contents to an approved tip or recycling
and make ready for new tenant.
IT
35.18
NO
120.75
460035
NO
181.13
460037
IT
78.78
460039
IT
135.53
460041
NO
338.69
NO
345.93
166
PRI DESCRIPTION
460103
UNIT
RATE
NO
203.88
TURF:RENEW
Turf:Lift existing mown turf, make good existing area with top soil,
removal of spoil to tip including landfill tax, lay new "Standard" quality
turves, with broken joints tight to its neighbour, roll and brush-in sandy
compost
SM
7.31
460403
SM
14.50
Shrubs
460451
SHRUB:PRUNE
Shrub:Prune any variety of shrub, by hand or using power hedge trimmer
including raking up cuttings and removal of debris to approved tip or
recycling centre including landfill tax.
NO
4.98
460453
NO
16.31
LM
9.60
Hedges
460461
HEDGES:CUT OVERGROWN
Hedges:Cut back and neatly trim top and sides of overgrown hedge and
remove all clippings from site to approved tip or recycling centre including
landfill tax.
Trees
460471
TREE:PRUNE
Trees:Prune base and side growth for a height not exceeding 2.40m high
of tree including basal growth and suckers, including painting at pruning
cuts with approved compound and remove all clippings from site to
approved tip or recycling centre including landfill tax.
IT
22.11
460473
IT
236.48
167
PRI DESCRIPTION
460475
UNIT
RATE
IT
39.41
LM
3.50
Fence Lines
460481
460201
NO
35.00
460203
NO
10.00
460205
NO
7.00
460207
NO
9.00
460209
NO
4.50
460211
NO
6.00
168
PRI DESCRIPTION
UNIT
RATE
460213
NO
12.00
460215
NO
1.00
460217
NO
0.50
NO
65.81
460303
NO
24.11
460305
NO
17.41
460307
NO
14.60
169
PRI DESCRIPTION
UNIT
RATE
460309
NO
13.10
460311
NO
15.41
460313
NO
27.81
460315
NO
3.26
460317
NO
3.76
Carpet Cleaning
460507
IT
58.87
460509
IT
58.32
460511
CARPET:CLEAN TO HALL
Carpet:Thoroughly clean, scrub as necessary vacuum carpet including dry
by dehumidifier to hall area complete.
IT
35.72
IT
104.23
Disinfestation
461001
DWELLING:DISINFESTATION WORKS
Dwelling:Seal and secure void dwelling and carry out disinfestation works.
170
PRI DESCRIPTION
UNIT
RATE
NO
26.38
463003
IT
19.70
171
PRI DESCRIPTION
UNIT
RATE
GLAZING
Reglaze Doors and Windows
Glass - Clear and Obscured
515005
NO
77.01
515007
SM
84.88
515013
NO
103.40
515015
SM
109.97
NO
87.01
520007
SM
94.01
NO
146.09
525007
SM
153.09
172
PRI DESCRIPTION
UNIT
RATE
Glass - Toughened
530005
NO
145.41
530007
SM
153.29
Glass - Laminated
535005
NO
135.24
535007
SM
139.62
535015
NO
114.09
535017
SM
121.97
Glass - Polycarbonate
540005
NO
128.67
540007
SM
133.05
173
PRI DESCRIPTION
UNIT
RATE
NO
123.80
551007
SM
128.18
NO
175.88
556007
SM
180.26
IT
34.56
573093
NO
40.48
Domelights
560001
NO
70.68
560003
NO
249.26
560005
NO
302.18
174
PRI DESCRIPTION
560007
UNIT
RATE
NO
333.54
Mirrors
565001
MIRROR:RENEW 450X450X4MM
Mirror:Renew 450x450x4mm silvered float glass mirror with
polished edges and predrilled holes and fix to any background
including all drilling and plugging and making good, and remove
waste and debris.
NO
38.48
565003
MIRROR:RENEW 900X600X4MM
Mirror:Renew 900x600x4mm silvered float glass mirror with
polished edges and predrilled holes and fix to any background
including all drilling and plugging and making good, and remove
waste and debris.
NO
73.76
Shower Screens
570001
NO
14.22
570003
NO
187.16
570011
IT
502.52
570013
IT
665.65
570015
IT
16.13
570017
IT
20.13
LM
4.67
575001
175
PRI DESCRIPTION
UNIT
575003
LM
9.43
575005
LM
6.19
575007
LM
3.11
575009
LM
2.05
575011
NO
17.93
575013
NO
33.25
575015
NO
38.92
575017
NO
20.80
575019
NO
28.86
575021
LM
7.86
575023
SM
89.01
575025
SM
74.89
176
RATE
PRI DESCRIPTION
575027
UNIT
RATE
NO
72.92
SM
7.54
Curtains
575501
177
PRI DESCRIPTION
UNIT
RATE
PLUMBING
Rainwater Pipework
Rainwater Pipework - PVCu
601101
IT
104.48
601103
IT
188.95
601105
LM
17.98
601107
NO
30.57
601109
NO
25.37
601111
NO
9.44
601113
NO
30.09
601125
IT
11.63
601119
NO
5.98
178
PRI DESCRIPTION
601121
UNIT
RATE
LM
15.89
IT
103.50
601505
LM
21.51
601507
NO
30.17
601509
NO
5.49
601511
IT
13.28
Rainwater Gutters
Rainwater Gutters - PVCu
603101
LM
31.73
603103
LM
41.86
179
PRI DESCRIPTION
UNIT
603105
LM
20.08
603107
LM
27.02
603109
LM
8.52
603111
NO
6.89
603115
NO
12.10
603119
NO
12.56
603123
NO
11.36
603127
NO
6.35
603131
NO
7.85
603133
NO
5.28
LM
59.21
RATE
180
PRI DESCRIPTION
UNIT
RATE
603303
LM
66.97
603305
LM
11.12
603307
NO
18.26
603309
NO
38.51
603311
NO
38.36
603313
NO
33.10
603315
NO
19.59
603317
NO
26.22
603319
NO
11.84
IT
11.43
181
PRI DESCRIPTION
UNIT
RATE
603902
IT
23.39
603903
IT
23.39
603905
NO
9.35
603907
IT
12.99
IT
333.55
610103
IT
515.79
610105
LM
20.96
610107
NO
7.56
182
PRI DESCRIPTION
UNIT
610109
NO
83.98
610111
NO
20.48
610113
NO
43.86
610115
NO
45.29
610117
NO
25.47
610119
NO
56.50
610121
NO
28.15
610123
NO
22.14
610125
NO
23.54
610127
NO
15.29
610129
IT
99.81
183
RATE
PRI DESCRIPTION
UNIT
RATE
610131
IT
38.43
610133
NO
18.78
IT
411.50
610303
IT
593.74
610305
LM
26.16
610307
NO
12.75
610309
NO
94.37
610311
NO
25.68
184
PRI DESCRIPTION
UNIT
610313
NO
51.65
610315
NO
50.49
610317
NO
30.66
610319
NO
33.87
610321
NO
28.73
610323
NO
19.45
610325
IT
112.81
610327
IT
63.31
610329
IT
20.48
185
RATE
PRI DESCRIPTION
610331
UNIT
RATE
NO
16.00
NO
135.87
610503
NO
24.11
610505
NO
68.46
610507
NO
103.59
NO
48.95
620103
NO
57.32
620105
NO
69.49
620107
NO
148.56
620117
NO
12.43
186
PRI DESCRIPTION
UNIT
RATE
620119
NO
12.60
620121
NO
17.79
620123
NO
87.10
620109
NO
11.48
620111
NO
14.07
620113
NO
8.01
620115
NO
2.93
620131
LM
69.82
620133
LM
16.80
620135
LM
19.68
NO
11.12
187
PRI DESCRIPTION
UNIT
RATE
IT
26.71
620503
IT
39.70
620505
NO
18.91
620507
NO
11.12
620509
NO
8.52
620513
NO
32.63
620515
NO
21.51
NO
187.12
188
PRI DESCRIPTION
UNIT
630103
NO
238.22
630105
NO
331.41
630107
NO
40.26
630109
NO
5.92
630111
NO
31.00
630113
NO
41.24
630115
NO
41.25
189
RATE
PRI DESCRIPTION
UNIT
RATE
NO
187.12
630119
NO
238.22
630121
NO
310.62
NO
171.27
630203
NO
160.88
190
PRI DESCRIPTION
UNIT
RATE
NO
171.27
630213
NO
160.88
NO
193.66
630303
NO
248.75
630305
NO
277.06
191
PRI DESCRIPTION
UNIT
RATE
WC Suites
630501
NO
200.61
630503
NO
213.57
630505
NO
210.14
630507
NO
239.09
630509
NO
229.07
192
PRI DESCRIPTION
UNIT
630511
WC PAN:RENEW COMPLETE
WC Pan:Renew wc pan fixed with brass or non-ferrous screws to
floor, including any plugging, renew wc cone, remake flush pipe
and soil pipe joints with and including Easy-Fit' connectors, fix new
plastic seat and lid to pan, make good to all wall and floor finishes,
and remove waste and debris.
NO
108.33
630513
NO
32.16
630515
WC PAN:REMOVE COMPLETE
WC Pan:Remove wc pan complete, including disconnect and seal
off, make good existing sub floor and make good to all wall and
floor finishes, and remove waste and debris.
NO
19.21
630516
NO
42.17
630521
NO
13.14
630533
NO
64.53
630535
NO
80.08
630537
NO
71.80
630539
NO
103.35
193
RATE
PRI DESCRIPTION
UNIT
RATE
630541
NO
77.13
630543
NO
92.68
630545
NO
24.83
630551
NO
30.33
630559
WC CISTERN:RENEW OVERFLOW
WC Cistern:Renew polypropylene overflow pipe to cistern,
disconnect, and remove existing defective overflow pipe and fit new
overflow pipe, including fittings, clips, cut and make good holes and
finishes as necessary, and remove waste and debris.
NO
45.13
630571
IT
21.99
NO
193.75
194
PRI DESCRIPTION
UNIT
630703
NO
222.81
630705
NO
78.56
630707
NO
27.73
630713
NO
52.44
630715
NO
3.32
630717
NO
14.26
630719
NO
25.24
630721
NO
19.94
195
RATE
PRI DESCRIPTION
UNIT
RATE
Baths
630901
NO
440.07
630909
NO
451.77
630917
NO
91.56
630919
NO
3.45
630921
NO
33.51
630923
NO
61.69
630931
NO
30.02
196
PRI DESCRIPTION
UNIT
RATE
630933
NO
39.97
630935
NO
19.94
630925
NO
96.60
630927
BATH:TOUCHUP CHIP
Bath:Prepare and touch up chip to any steel or cast iron bath
including removing/refixing all fittings as necessary.
IT
39.90
630929
BATH:RE-ENAMEL
Bath:Prepare, grind, re-enamel and repolish completely any steel or
cast iron bath.
IT
85.05
Shower Trays
631101
NO
272.28
631103
NO
232.56
NO
21.08
631107
NO
201.85
197
PRI DESCRIPTION
UNIT
RATE
631109
NO
118.42
631111
IT
28.37
631113
IT
29.50
631115
IT
21.33
631117
IT
14.47
631119
IT
94.25
631121
NO
7.94
631127
IT
30.08
IT
70.22
631125
SHOWER:RENEW CURTAIN
Shower:Renew any type of shower curtain to existing rails including
remove and refix rails as found expedient, and remove waste and
debris.
IT
27.52
631129
SHOWER:RENEW RAILS
Shower:Renew any size and type of shower rail including remove
defective rails, fix new rails with plastic plugs and matching non-ferrous
screws including remove and rehang curtains, make good all finishes, and
remove waste and debris.
IT
46.71
198
PRI DESCRIPTION
UNIT
RATE
IT
56.49
631309
IT
71.48
631313
IT
79.47
631319
NO
43.90
631341
NO
58.27
631321
NO
10.61
IT
65.67
631311
IT
110.46
199
PRI DESCRIPTION
631315
UNIT
RATE
IT
90.50
IT
86.76
631363
IT
75.37
631365
IT
107.16
Taps - Mixers
631335
IT
86.97
631337
IT
105.62
631339
IT
67.28
631353
IT
69.18
631355
IT
36.68
200
PRI DESCRIPTION
UNIT
RATE
IT
8.44
631503
IT
8.44
631505
IT
3.13
631507
LM
3.13
631515
IT
14.65
Upstands
631701
LM
12.14
631703
LM
6.76
IT
57.78
631903
IT
71.20
631905
NO
17.29
201
PRI DESCRIPTION
631907
UNIT
RATE
IT
34.57
Supply Pipework
Copper Pipework - Renewals
635001
LM
18.54
635003
LM
22.54
635005
LM
27.36
635013
NO
3.48
635015
NO
5.29
NO
7.26
635303
NO
10.22
635305
NO
12.07
NO
51.74
202
PRI DESCRIPTION
UNIT
RATE
640003
NO
36.26
640005
NO
54.04
Pipe Insulation
Moulded Foam Pipe Insulation
645007
LM
1.04
645101
LM
4.39
645103
LM
4.58
650001
NO
29.65
650003
NO
42.40
650005
NO
34.08
203
PRI DESCRIPTION
UNIT
RATE
650007
NO
53.79
650009
NO
49.36
650013
NO
21.51
Gatevalves
655001
NO
29.09
655003
NO
30.39
655005
NO
31.58
655009
NO
21.51
NO
57.06
656001
NO
24.78
656003
NO
25.71
204
PRI DESCRIPTION
656005
UNIT
RATE
NO
20.93
Ballofix Valves
657001
NO
31.13
657003
NO
31.91
657005
NO
80.24
NO
12.06
Draincocks
660001
665001
IT
128.04
665003
IT
144.63
NO
149.24
205
PRI DESCRIPTION
UNIT
RATE
NO
24.25
665007
NO
33.83
665009
NO
48.24
665011
NO
21.09
665015
NO
20.79
705003
NO
36.07
665017
NO
10.54
665019
IT
45.05
665021
IT
17.64
665023
IT
23.43
665025
IT
27.78
NO
12.51
Insulation Tank
670001
206
PRI DESCRIPTION
UNIT
RATE
670003
NO
15.98
706001
NO
9.19
NO
374.73
675003
NO
358.79
NO
359.76
675011
NO
343.82
NO
312.22
PRI DESCRIPTION
675007
UNIT
RATE
NO
296.28
NO
304.03
675015
NO
288.09
NO
542.13
675019
NO
526.19
NO
484.93
208
PRI DESCRIPTION
675023
UNIT
RATE
NO
467.54
NO
507.84
675027
NO
491.90
NO
446.38
675031
NO
415.34
NO
1100.52
209
PRI DESCRIPTION
675035
UNIT
RATE
NO
1069.49
NO
13.29
675039
CYLINDER:REPAIR LEAK
Cylinder:Drain down copper cylinder as necessary, remove jacket,
shelves etc., prepare and wipe patch to repair leak, refill, vent and
test system, including all newly made joints, refix jacket, and test
on completion, and remove waste and debris.
NO
35.44
675041
NO
54.86
675043
CYLINDER:RENEW FLANGE
Cylinder:Isolate supply, drain down copper cylinder, remove jacket,
shelves etc., disconnect, clear away and renew immersion heater
flange, refix jacket, shelves etc., refill, vent and test system, and
remove waste and debris.
NO
55.57
675045
IT
58.69
675047
NO
31.18
675049
CYLINDER:RENEW JACKET
Cylinder:Renew insulating jacket set fixed securely to cylinder, and
remove waste and debris.
NO
15.68
210
PRI DESCRIPTION
UNIT
RATE
NO
607.31
677003
NO
761.27
677011
NO
770.76
677013
NO
788.88
211
PRI DESCRIPTION
UNIT
RATE
677021
NO
483.99
677023
NO
192.63
677025
NO
177.89
Scale Reducers
680001
IT
61.81
680003
IT
89.46
680005
IT
130.04
680007
IT
32.83
680009
IT
126.45
212
PRI DESCRIPTION
UNIT
RATE
Sundry Works
Airlocks
685001
IT
31.18
IT
20.79
690003
IT
46.77
690005
IT
23.39
NO
5.61
696001
NO
25.64
696003
NO
15.14
696005
TOWEL RAIL:RENEW
Towel Rail:Renew or supply and fix new chromium plated towel rail
610mm long securely fixed to structure including plugging as
necessary.
NO
42.71
696007
TOWEL HOLDER:RENEW
Towel Holder:Renew or supply and fix new chromium plated two
arm towel holder securely fixed to structure including plugging as
necessary.
NO
36.05
696009
SOAP DISH:RENEW
Soap Dish:Renew or supply and fix new chromium plated soap dish,
with concealed fixing, securely fixed to structure including plugging
as necessary.
NO
18.90
213
PRI DESCRIPTION
UNIT
RATE
696011
TOOTHBRUSH/TUMBLER HOLDER:RENEW
Toothbrush/Tumbler Holder:Renew or supply and fix new chromium
plated toothbrush and tumbler holder with concealed fixing,
securely fixed to structure including plugging as necessary.
NO
20.77
696013
NO
62.09
696015
NO
9.33
696017
BATHROOM CABINET:RENEW
Bathroom Cabinet:Renew or supply and fix new lockable double
bathroom/first aid cabinet of any type complete with shelves and
two keys, remove existing defective unit and clear away if
necessary, fix cabinet securely to structure including plugging,
screwing and making good as necessary.
NO
50.05
696021
GLASS SHELF:RENEW
Glass Shelf:Renew or supply and install new bathroom glass shelf
ne 600mm long x 127mm wide existing brackets.
NO
11.09
696022
NO
37.33
696023
NO
16.84
696025
BATHROOM:REFIX ANCILLARY
Bathroom:Securely refix any ancillary fitting, toilet roll holder, towel
holder, soap dish, shelf, cabinet etc, having up to 4 No. screws, to
structure of any background including plugging, screwing and
making good as necessary.
NO
7.73
IT
66.74
698003
IT
100.54
698005
IT
44.20
214
PRI DESCRIPTION
UNIT
RATE
698007
IT
59.36
698009
IT
89.45
698011
IT
30.93
LM
98.79
043103
LM
166.24
NO
100.68
NO
111.73
NO
82.59
043503
045001
215
PRI DESCRIPTION
UNIT
RATE
045003
NO
19.43
045007
NO
28.21
IT
15.59
CLIENT INSPECTION:PLUMBING
216
PRI DESCRIPTION
UNIT
RATE
NO
93.05
702003
NO
164.87
702005
NO
177.10
702007
NO
36.21
702009
NO
50.70
702010
NO
91.22
NO
97.21
217
PRI DESCRIPTION
UNIT
RATE
702502
NO
114.50
702506
NO
49.74
702511
NO
91.75
702512
NO
110.48
Radiators
Radiators Repairs
703001
RADIATOR:VENT RADIATORS
Radiator:Vent all radiators to any property and balance system.
IT
28.75
703003
IT
79.19
703005
NO
27.59
703007
IT
89.07
703009
IT
27.66
218
PRI DESCRIPTION
UNIT
RATE
703011
IT
69.43
703013
NO
19.01
703015
NO
33.19
IT
72.68
703019
IT
104.41
703021
IT
158.04
703023
IT
218.04
IT
70.98
703027
IT
98.66
219
PRI DESCRIPTION
UNIT
RATE
703029
IT
155.32
703031
IT
270.23
IT
93.44
703035
IT
144.61
703037
IT
248.50
703039
IT
444.05
IT
157.50
Relocate Radiators
760001
RADIATOR:RELOCATE POSITION
Radiator:Relocate position of radiator, isolate, drain down, remove,set
aside radiator for reuse, cut back flow and return pipework to floor or
ceiling void and run new pipework to relocated position including all
bends, connectors, clips etc, refix existing radiator in new position,
connect to new new flow and return pipework, refill and recommission the
heating system, including installing corrosion inhibitor, vent and test, and
remove waste and debris.
220
PRI DESCRIPTION
UNIT
RATE
IT
198.95
Radiator - Valves
701001
IT
47.02
701003
IT
9.80
701005
IT
51.74
701007
IT
13.95
701011
NO
46.86
Airlocks/Reprime
704001
AIRLOCKS:CLEAR AIRLOCKS
Airlocks:Clear airlocks from heating system including venting
radiators and balance system.
IT
51.75
704005
IT
20.13
IT
126.50
Power Flushing
760101
221
PRI DESCRIPTION
UNIT
RATE
NO
519.54
707003
NO
18.70
707005
BACKBOILER:RESET THERMOSTAT
Backboiler:Reset thermostat to any backboiler when appliance is
cold.
IT
11.50
707007
BACKBOILER:RENEW THERMOSTAT
Backboiler:Renew thermostat to any backboiler, and remove waste
and debris.
IT
42.76
IT
622.08
711003
IT
621.98
222
PRI DESCRIPTION
UNIT
RATE
IT
753.68
712015
IT
782.68
712017
IT
814.18
712019
IT
844.28
IT
376.52
709003
IT
80.23
709007
IT
90.16
223
PRI DESCRIPTION
UNIT
RATE
709009
IT
224.04
709011
IT
166.47
709013
IT
28.93
709015
IT
76.48
709017
IT
93.99
BOILER:RENEW THERMOSTAT
Boiler:Renew thermostat to central heating boiler including make
connections, make good finishes and test, and remove waste and
debris.
IT
30.18
710003
IT
33.43
710005
BOILER:RENEW PROGRAMMER
Boiler:Renew central heating programmer with microelectric time
controller including make all connections and test, and remove
waste and debris.
IT
82.10
710007
IT
73.97
710009
IT
23.72
224
PRI DESCRIPTION
UNIT
RATE
NO
18.25
721003
IT
237.75
721004
IT
532.00
721005
IT
611.26
721007
IT
278.24
721009
IT
677.64
721011
IT
35.75
IT
168.38
PRI DESCRIPTION
UNIT
RATE
722003
IT
300.63
722005
IT
223.49
722007
IT
351.05
IT
133.50
IT
1293.36
723201
226
PRI DESCRIPTION
UNIT
RATE
723203
IT
1313.86
723205
IT
1293.36
IT
1307.85
227
PRI DESCRIPTION
UNIT
RATE
723303
IT
1351.35
723305
IT
1376.85
IT
17.25
722103
IT
105.34
NO
380.30
228
PRI DESCRIPTION
UNIT
RATE
722131
NO
37.47
722132
NO
9.38
722133
NO
45.84
722134
NO
11.55
722135
NO
24.76
722136
NO
9.95
722137
NO
17.14
722138
NO
29.96
722139
NO
18.01
NO
31.88
722143
NO
39.93
NO
8.77
740003
NO
9.90
229
PRI DESCRIPTION
UNIT
RATE
740005
NO
6.90
740007
NO
11.50
740043
NO
9.69
740045
NO
13.66
740047
NO
28.01
Void Works
Void Property Works
730001
IT
28.77
730003
IT
10.80
730005
IT
34.50
730007
IT
23.00
730009
IT
51.75
730011
IT
18.71
230
PRI DESCRIPTION
UNIT
RATE
Draining Down
713001
IT
14.38
713003
IT
61.94
231
PRI DESCRIPTION
UNIT
RATE
ELECTRICAL
Space Point and Water Heating Appliances
Storage Heaters
810001
NO
255.03
810002
NO
202.71
810003
NO
322.41
810005
NO
376.69
NO
329.23
811003
NO
383.45
811005
NO
485.85
232
PRI DESCRIPTION
UNIT
RATE
IT
30.41
813019
NO
29.01
813021
NO
24.88
813035
NO
22.80
813039
NO
18.48
NO
133.45
815003
NO
78.64
815005
NO
94.46
233
PRI DESCRIPTION
UNIT
815007
NO
97.25
815009
NO
116.63
815011
NO
111.80
815013
NO
133.35
815015
NO
132.44
815017
NO
152.91
815019
NO
59.27
815020
NO
18.48
234
RATE
PRI DESCRIPTION
UNIT
RATE
815021
NO
64.04
815023
NO
110.29
815025
NO
81.25
NO
41.84
817003
NO
29.45
817007
HEATER:RENEW DP SWITCH
Heater:Isolate supply, disconnect, clear away and renew double
pole control switch to heater, including dismantle and reassemble
any access covers, reconnect electricity supply, test and leave in
working order and remove waste and debris.
NO
16.12
817011
NO
18.48
NO
120.55
235
PRI DESCRIPTION
UNIT
RATE
Immersion Heaters
820003
NO
41.61
820007
NO
61.48
820009
NO
14.11
820011
IMMERSION HEATER:DISCONNECT
NO
11.39
820013
IT
22.78
820015
IT
19.87
820017
IT
10.22
820019
NO
132.98
820021
NO
18.21
236
PRI DESCRIPTION
UNIT
RATE
820023
NO
31.44
820025
NO
24.19
NO
145.15
825003
NO
549.82
825005
NO
368.17
825007
NO
38.37
825009
NO
34.75
237
PRI DESCRIPTION
UNIT
RATE
NO
44.79
NO
92.30
830001
NO
325.42
830003
NO
257.47
830005
NO
65.26
830007
NO
19.89
830009
NO
25.98
238
PRI DESCRIPTION
UNIT
RATE
830011
SHOWER:RENEW CIRCUIT
Shower:Isolate supply, disconnect, strip out, clear away and renew
shower circuit including mini-trunking or rigid PVC conduit chased
into wall etc, incorporating RCD protection, 40 amp DP switch and
make all necessary connections, reconnect electricity supply,
undertake electrical tests, provide certificate, make good on
completion, and remove waste and debris.
NO
141.15
830013
NO
36.32
NO
6.86
835003
NO
8.52
IT
34.06
IT
72.83
882011
882021
NO
437.76
882023
NO
138.56
882031
NO
39.82
239
PRI DESCRIPTION
UNIT
RATE
882032
NO
9.62
882033
NO
52.00
882034
NO
13.64
882035
NO
10.62
882036
NO
10.51
882037
NO
71.25
882038
NO
53.74
NO
36.96
835007
NO
117.59
835009
NO
62.24
240
PRI DESCRIPTION
UNIT
RATE
835011
NO
36.94
835013
NO
55.25
835015
NO
36.72
835019
NO
10.63
NO
23.02
882121
WASHING MACHINE:RENEW
Washing Machine:Isolate supply, disconnect existing, clear away,
supply and install new domestic type electric washing machine,
reconnect electric supply, water supply and waste pipework,
electrical test, make good on completion and leave in working order
and remove waste and debris.
NO
301.36
882123
TUMBLE DRYER:RENEW
Tumble Dryer:Isolate supply, disconnect existing, clear away,
supply and install new domestic type electric tumble dryer,
reconnect electric supply, electrical test, make good on completion
and leave in working order and remove waste and debris.
NO
243.06
NO
206.76
PRI DESCRIPTION
UNIT
RATE
882223
NO
270.56
882225
NO
402.56
882231
NO
39.03
882232
NO
24.91
882233
NO
22.81
882234
NO
49.03
882235
NO
21.94
882236
NO
31.21
882237
NO
20.77
882238
NO
22.51
NO
311.26
882323
NO
371.76
242
PRI DESCRIPTION
UNIT
RATE
NO
11.35
IT
19.87
882505
IT
84.78
882507
IT
174.26
NO
11.35
NO
89.86
872523
243
PRI DESCRIPTION
UNIT
RATE
Ventilation
Fans - Ventilating
840001
NO
103.67
840003
NO
106.45
840005
NO
180.65
840007
NO
105.78
840009
NO
129.21
840011
NO
144.15
244
PRI DESCRIPTION
UNIT
RATE
840013
NO
143.69
840015
NO
59.78
840017
NO
88.60
840019
NO
18.21
840031
NO
114.97
NO
153.07
841003
NO
165.60
245
PRI DESCRIPTION
UNIT
RATE
841005
NO
179.71
841007
NO
21.38
841009
NO
118.80
841011
NO
127.32
841013
NO
161.59
IT
454.98
246
PRI DESCRIPTION
UNIT
RATE
841103
IT
522.18
841105
VENT UNIT:OVERHAUL
Vent Unit:Overhaul ventilation unit, clean out, renew filters as
necessary, and remove waste and debris.
IT
35.51
LM
6.55
LM
7.07
851003
851505
LM
2.35
851507
LM
2.77
851509
LM
3.61
851513
LM
2.71
851515
LM
4.02
247
PRI DESCRIPTION
UNIT
RATE
LM
2.61
852005
LM
3.59
852007
LM
4.58
852009
LM
5.42
852013
LM
3.38
852015
LM
4.17
852017
LM
5.60
LM
15.53
852511
LM
17.66
248
PRI DESCRIPTION
UNIT
RATE
LM
9.98
853011
LM
10.73
LM
12.20
853505
NO
16.08
Final Circuits
Final Circuits - Lighting
854501
NO
70.09
854503
NO
111.04
854505
NO
64.93
854507
NO
101.99
249
PRI DESCRIPTION
854709
UNIT
RATE
NO
129.28
NO
307.61
855003
NO
363.62
855004
NO
411.25
855005
NO
279.30
855007
NO
328.06
855008
NO
393.04
250
PRI DESCRIPTION
UNIT
855009
NO
90.31
855010
NO
102.85
855011
NO
79.97
855012
NO
82.98
855013
NO
87.02
855015
NO
74.53
855017
NO
77.25
251
RATE
PRI DESCRIPTION
855019
UNIT
RATE
NO
84.11
NO
150.07
855503
NO
193.24
855551
NO
169.94
855553
NO
194.11
855509
NO
106.86
855510
IT
26.98
252
PRI DESCRIPTION
UNIT
855511
NO
89.33
855512
IT
107.03
855513
NO
14.86
855515
NO
12.74
855521
NO
18.25
855525
NO
72.24
855527
CCU:MODIFY BACKBOARD
CCU:Modify backboard to accept new cables, cut hole through brick
or block wall to accommodate new cables, and make good on
completion, and remove waste and debris.
NO
35.51
CCU:Isolate supply and supply and fit any size RCD to existing
consumer unit to protect all circuits to bathroom, reconnect
supply, undertake electrical tests, test operation of RCD, make
good on completion, and remove waste and debris.
RATE
Pendants
Pendants and Lampholders
856103
NO
16.23
856105
NO
11.39
253
PRI DESCRIPTION
UNIT
RATE
Luminaires - Bulkheads
Bulkhead - Fittings
856603
NO
48.24
856605
NO
118.43
856607
NO
33.19
856609
NO
45.29
856611
NO
54.73
856613
NO
20.09
856615
NO
45.54
NO
3.58
Bulkhead - Lamps
857001
PRI DESCRIPTION
UNIT
RATE
857003
NO
6.53
857006
NO
5.94
857005
NO
6.16
857007
NO
9.39
857015
NO
13.76
857017
NO
8.51
857019
NO
12.55
NO
14.08
Bulkhead - Diffuser
857501
858101
NO
26.40
858103
NO
45.06
858107
NO
10.26
255
PRI DESCRIPTION
858111
UNIT
RATE
IT
14.98
Fluorescent - Diffusers
858301
NO
19.36
858303
NO
20.27
NO
5.11
Fluorescent - Tubes
858501
858701
NO
5.39
858703
NO
18.42
858705
NO
9.50
Accessories
Accessories - Generally
860501
NO
10.37
860503
NO
10.68
860505
NO
18.09
256
PRI DESCRIPTION
860507
UNIT
RATE
NO
2.56
NO
17.63
861003
NO
9.41
861005
NO
9.47
861007
NO
14.10
861009
NO
19.25
861011
NO
23.55
861013
NO
16.59
861015
NO
6.58
257
PRI DESCRIPTION
UNIT
RATE
NO
17.63
861503
NO
10.27
861505
NO
10.74
861507
NO
11.87
861509
NO
20.51
861511
NO
30.16
861513
NO
73.69
861515
NO
20.24
258
PRI DESCRIPTION
861517
UNIT
RATE
NO
30.74
Accessories - DP Switches
862001
NO
22.21
862003
NO
28.79
862005
NO
15.50
862007
NO
19.53
Shaver Points
863001
NO
37.50
863003
NO
91.43
863005
NO
44.39
863007
NO
4.77
259
PRI DESCRIPTION
UNIT
RATE
Special Installations
Door Bell Installation
870501
LM
2.66
870503
NO
17.35
870505
NO
27.91
870507
NO
10.74
870509
NO
11.72
870511
NO
27.10
870513
NO
59.69
NO
126.54
871007
NO
48.80
260
PRI DESCRIPTION
UNIT
RATE
871009
NO
37.19
871011
LM
2.68
NO
27.47
871103
NO
49.03
871105
NO
37.86
871107
NO
58.69
871109
NO
39.37
871111
NO
62.31
871113
NO
67.14
871115
NO
93.40
261
PRI DESCRIPTION
UNIT
RATE
871117
IT
448.28
871118
IT
170.30
IT
170.30
871403
IT
45.41
TV Aerial Installation
871501
NO
5.68
871503
NO
13.84
871505
IT
29.17
871507
IT
46.99
871509
IT
66.83
262
PRI DESCRIPTION
UNIT
RATE
871513
IT
88.22
871515
IT
68.12
IT
68.12
CCTV Service
871603
872003
NO
18.24
872008
NO
81.43
872010
NO
74.48
872015
NO
104.54
263
PRI DESCRIPTION
UNIT
RATE
872017
NO
77.38
872020
NO
81.43
872023
NO
74.48
872025
IT
12.85
872027
IT
12.85
NO
95.03
NO
103.81
Heat Detectors
872101
HEAT DETECTOR:INSTALL
Heat Detector:Isolate, supply and install mains operated rate of rise
or fixed temperature heat detector including make all necessary
connections to supply including junction box, reconnect, test and
make good on completion, and remove waste and debris.
Carbon Monoxide Detectors
872201
264
PRI DESCRIPTION
UNIT
RATE
872203
NO
12.85
872205
NO
33.12
NO
71.69
Gas Detectors
872301
GAS DETECTOR:INSTALL
Gas Detector:Isolate, supply and install mains operated gas detector
including make all necessary connections to supply including junction box,
reconnect, test and make good on completion, and remove waste and
debris.
Landlords Lighting etc.
Time Switches
880101
NO
5.68
880103
NO
12.80
880105
NO
34.87
880107
NO
41.96
880109
NO
64.85
880111
NO
44.51
265
PRI DESCRIPTION
UNIT
RATE
880115
NO
55.40
880113
NO
79.12
880112
NO
66.06
880114
NO
70.06
NO
68.96
881003
NO
96.20
881004
NO
18.60
881009
NO
33.12
266
PRI DESCRIPTION
UNIT
RATE
Inspections
885001
IT
24.28
885003
IT
25.55
885005
IT
25.55
POWER:TEMPORARY CONNECTION
Power:Switch off supply, install suitable temporary power circuit,
energise and later remove temporary connections for power circuit.
NO
24.39
891003
LIGHT:TEMPORARY CONNECTION
Light:Switch off supply, install suitable temporary lighting circuit,
energise and later remove temporary connections for lighting
circuit.
NO
18.60
891005
NO
37.32
20.17
891007
WK
891009
WK
30.67
891011
WK
82.36
891013
WK
32.67
267
PRI DESCRIPTION
UNIT
RATE
Earthing
Earthing - Plumbing Installations
892001
IT
20.51
892019
IT
25.81
892023
NO
112.91
892025
EARTH:REFIX ELECTRODE
Earth:Refix earth electrode and galvanised inspection box and lid.
NO
17.03
892027
IT
207.78
892050
IT
49.69
892107
IT
14.21
892109
LM
9.74
IT
6.40
debris.
892111
268
PRI DESCRIPTION
UNIT
RATE
Testing
Testing - Occupied Property
895001
IT
100.91
895002
IT
56.77
895003
IT
75.37
NO
17.03
895503
NO
6.81
895505
NO
5.11
895507
NO
3.97
269
PRI DESCRIPTION
UNIT
RATE
IT
116.67
896003
IT
82.61
IT
76.93
IT
18.73
Water Penetration
897003
898001
CLIENT INSPECTION:ELECTRICAL
Lighting:Locate fault in any lighting circuit including any necessary
testing and report to Client Representative (any repairs required to
be ordered separately, can only be claimed if instructed by Client
Representative).
270
PRI DESCRIPTION
UNIT
RATE
IT
26.25
910003
NO
100.83
910005
NO
127.05
IT
57.07
IT
49.32
NO
9.55
Electrical Works
Consumer Unit
921001
CONSUMER UNIT:REPOSITION
Consumer Unit:Disconnect, remove and reposition any consumer
unit to suit wheelchair access and reconnect, test and make good,
and remove waste and debris.
Socket Outlets
922001
923001
271
PRI DESCRIPTION
923003
UNIT
RATE
IT
44.49
IT
24.67
Thermostat
924001
THERMOSTAT:LOWER POSITION
Thermostat:Lower height of room thermostat with wiring run in
plastic mini-trunking including blanking plate to existing thermostat
outlet and refix existing thermostat in lower position including make
all connections, electrical tests and make good finishes, and remove
waste and debris.
Communication Systems
Door Entry
931001
IT
225.33
931003
IT
210.36
931005
IT
53.93
IT
104.25
NO
55.78
Smoke Detector
932001
941001
272
PRI DESCRIPTION
UNIT
941002
NO
61/57
941003
NO
67.98
941005
NO
112.39
941007
NO
78.18
941009
NO
107.70
941011
NO
126.68
941013
NO
145.41
941015
NO
189.30
941017
NO
227.50
273
RATE
PRI DESCRIPTION
UNIT
941019
NO
179.89
941021
NO
229.58
941023
NO
261.77
941025
NO
216.01
941027
NO
271.93
941029
NO
187.58
941031
NO
209.25
941033
NO
226.19
274
RATE
PRI DESCRIPTION
UNIT
RATE
941035
NO
236.35
941037
NO
368.96
941039
NO
128.15
941045
NO
231.37
941041
NO
17.48
941043
NO
18.22
Handrails
943001
LM
95.18
943009
LM
25.84
943017
LM
25.47
275
PRI DESCRIPTION
UNIT
RATE
Balustrading
943005
LM
292.59
943019
LM
68.93
Plumbing Works
Sanitary Fittings
951001
NO
302.82
951003
NO
343.82
951005
NO
197.83
951007
NO
463.91
276
PRI DESCRIPTION
UNIT
RATE
951009
NO
729.49
951011
NO
508.53
Taps
952001
IT
96.86
952003
IT
95.87
952005
IT
130.26
952007
IT
55.44
NO
106.24
Showers/Bath Aids
Shower Seat
961001
277
PRI DESCRIPTION
961019
UNIT
RATE
NO
284.23
NO
35.94
Soap Dish
962001
963001
IT
338.15
963003
IT
415.32
IT
1711.48
Shower Rooms
964001
278
PRI DESCRIPTION
964003
UNIT
RATE
IT
1750.32
IT
70.08
965003
SHOWER:RENEW CURTAIN
Shower:Renew any type of shower curtain to existing rails including
remove and refix rails as found expedient, and remove waste and
debris.
IT
27.52
Kitchen Units
Kitchen Units - Adjustable Specification for Special Needs
970001
NO
6.57
970003
NO
181.19
970005
NO
223.84
970007
NO
244.88
970009
NO
261.43
279
PRI DESCRIPTION
UNIT
RATE
970011
NO
352.96
970013
NO
367.35
970015
NO
90.21
970017
NO
92.35
970019
NO
108.49
970021
NO
121.50
970023
NO
159.70
Windows
Window Adaptations and Ironmongery
975001
NO
7.29
975003
NO
25.02
280
PRI DESCRIPTION
UNIT
RATE
975005
NO
257.26
975007
NO
89.22
Doors
Door Adaptations and Ironmongery
980001
NO
56.11
980003
IT
12.31
980005
IT
54.99
980007
IT
40.84
980009
NO
21.37
Access Facilities
Ramps
985001
LM
92.86
985003
LM
73.08
281
PRI DESCRIPTION
UNIT
RATE
Steps
985501
IT
45.09
985503
IT
40.74
Thresholds
986001
NO
10.93
986003
IT
24.75
282
PRI DESCRIPTION
UNIT
RATE
SPECIALIST TREATMENTS
Fungus and Beetle Eradication and DPC Works
Reduce Existing Ground Level in Conjunction with DPC Wall
Injection
048001
SM
73.17
048003
SM
98.30
048005
SM
18.79
048007
SM
94.33
CM
76.82
101601
LM
29.91
101603
NO
20.70
283
PRI DESCRIPTION
UNIT
RATE
LM
51.07
112003
LM
72.06
112005
LM
96.44
112007
LM
117.82
112009
LM
27.49
112011
LM
51.07
112013
LM
27.49
112015
LM
65.49
112018
LM
62.87
112020
IT
78.75
112022
IT
78.75
SM
18.79
Irrigation of Walls
113001
284
PRI DESCRIPTION
UNIT
RATE
SM
10.94
301203
CM
34.58
301205
NO
7.02
301207
NO
9.51
IT
45.22
301403
SM
94.37
IT
18.06
374003
IT
27.80
374005
LM
14.75
285
PRI DESCRIPTION
UNIT
RATE
SM
52.60
411203
SM
60.80
411205
SM
20.34
411207
SM
39.87
411209
SM
10.82
IT
53.09
640601
IT
46.91
SM
39.81
Timber Treatment
Flooring Treatment
305803
286
PRI DESCRIPTION
UNIT
RATE
305804
IT
1150.50
305805
SM
52.10
305806
IT
1298.34
305808
DWELLING:PRESERVATIVE GUARANTEE
Dwelling:Provision of 30 year insurance backed guarantee for floor
preservation treatment.
IT
52.50
305820
DWELLING:TIMBER TREATMENT
Dwelling:Take up 20% of floorboards as necessary to dwelling to
facilitate access for timber preservative treatment by Specialist,
refix floorboards, allow for upto 50% renewal as required, punch in
nail heads, nail down loose boards, clean off on completion, and
remove waste and debris.
IT
919.34
305832
DWELLING:WOODWORM TREATMENT
Dwelling:Take up 20% of floorboards as necessary to dwelling to
facilitate access for and undertake woodworm treatment by
approved Sub-Contractor, refix floorboards, allow for upto 50%
renewal as required, punch in nail heads, nail down loose boards,
clean off on completion, and remove waste and debris.
IT
1286.84
305834
DWELLING:WOODWORM GUARANTEE
Dwelling:Provision of 30 year insurance backed guarantee for
woodworm treatment.
IT
52.50
Roof Treatment
305822
IT
239.94
305824
ROOF:PRESERVATIVE GUARANTEE
Roof:Provision of 30 year insurance backed guarantee for roof
timber preservation treatment.
IT
52.50
287
PRI DESCRIPTION
UNIT
RATE
305836
ROOF:WOODWORM TIMBER
Roof:Remove and set aside Tenants personal affects and stored
items in loft area, lift and set aside all roof insulation, clean down
all timbers to remove surface dust and debris, undertake
woodworm treatment by approved Sub-Contractor to accessible
structural timbers, leave all areas clean and tidy on completion,
relay roof insulation, reinstate Tenants affects and stored items,
and remove waste and debris.
IT
242.84
305838
ROOF:WOODWORM GUARANTEE
Roof:Provision of 30 year insurance backed guarantee for roof
timber woodworm treatment.
IT
52.50
NO
22.12
415021
SM
7.44
425003
SM
9.63
425005
TEST:SAMPLE OF ARTEX
Test:Collect sample of artex texture coating removed from ceiling
or walls, arrange and test asbestos content, provide Client
Representative with written report.
IT
110.26
Specialist Treatments
Graffiti Removal - External Surfaces
435501
SM
12.18
435511
SM
9.46
SM
12.09
PRI DESCRIPTION
UNIT
RATE
LM
10.83
SM
15.89
490001
SM
49.71
490003
SM
68.53
490005
SM
71.41
IT
98.14
114103
SM
78.36
289
PRI DESCRIPTION
UNIT
RATE
Mould Eradication
Mould Treatment
442501
SM
13.88
442503
NO
6.02
442505
SURFACES:REDECORATE TREATMENT
Surfaces:Prepare, wash down with RLT Bactdet solution, fill in small
holes, cracks etc, and apply one liberal coat of IDP by brush to any
badly stained areas and apply RLT Halophen to walls or ceilings as
specified and in accordance with manufacturers directions.
SM
13.06
442507
SM
7.59
442509
SM
4.92
442511
SM
6.37
442513
SM
4.46
442515
SURFACES:APPLY HALOPHEN
Surfaces:Prepare, and apply one coat RLT Halophen solution to
walls or ceilings in accordance with manufacturers directions.
SM
4.76
442517
WALLS:APPLY SEMPATAP
Surfaces:Wash down surfaces of walls and fill in small holes, cracks
etc, apply one coat of Sempatap primer to any loose paint or
plaster, prepare and apply Sempatap to wall with Sempatap
adhesive, cut around all sockets, switch plates, pipes, brackets and
the like, fill open joints with Sempatap sealant, fix Sempatap
external tape to external angles all in accordance with the
manufacturers directions and leave ready for redecoration as
specified and remove waste and debris.
SM
38.30
442519
FLOORS:APPLY SEMPAFLOOR
Floors:Wash down all floors, make good surfaces as necessary, fix
Sempafloor to floor with Sempafloor adhesive, cut around pipes and
the like, fill open joints with Sempatap sealant, all in accordance
with the manufacturers directions and leave ready for new floor
covering and remove waste and debris.
SM
33.92
290
PRI DESCRIPTION
UNIT
RATE
Pest Control
Pest Control
461201
NO
65.00
461203
NO
80.00
461205
RODENTS:MICE ERADICATION
Rodents:Eradicate mice internally from any type of dwelling,
including engagement of Specialist if necessary, initally attend
property, lay trap bait, subsequently return and and remove waste
and debris.
IT
60.00
461209
RODENTS:RAT ERADICATION
Rodents:Eradicate rats internally or within the garden confines of
any type of dwelling, including engagement of Specialist if
necessary, initially attend property, lay trapbait, subsequently
return and and remove waste and debris.
IT
70.00
461217
RODENTS:SQUIRREL ERADICATION
Rodents:Eradicate squirrel internally or within the garden confines
of any type of dwelling, including engagement of Specialist if
necessary, initially attend property, lay trapbait, subsequently
return and and remove waste and debris.
IT
60.00
461213
LICEANTS:ERADICATE
LiceAnts:Eradicate wood lice, ants or similar infestation from any
type of dwelling, including engagement of Specialist if necessary,
initially attend property, provide insecticide over affected area.
IT
20.00
291