This document defines the steps to setup Outside Processing and the procedure
steps to run the OSP process. First you must have setup the OSP Resource and
OSP Item. Setting up the item is just like setting up any other item except you
must use the Outside Processing Item Template. You must also be sure to let
the List Price item attribute for the requisition import process to work properly.
Now you need to setup the OSP resource. Use the navigation below to setup the
resource.
Always setup the OSP
resource with a type of
Amount and the
charge type as PO
Receipt and the UOM
to USD. Link the
resource to the OSP
item you setup
previously. Make sure
the resource is costed
and set the rate to 1
dollar.
Once you have setup the resource and saved it, you now need to assign it to a
department. Use the screen below for navigation.
When the department form
opens you can query up the
department you wish to add
the resource too. You can
then press the
RESOURCES button to
open the resources form.

Confidential

Page 1

5/27/2011

Standard Operating Procedure:

OSP Setup and Processing


Revision: 001

Release Date: 07/20/2007

The form below will appear.


Enter the resource and the
number of units. Use 10000
for OSP resources.
This completes the setup for
the OSP resource. You can
now use the resource in your
routing.
To enter the routing, use the
navigation shown below.

Once you have entered your


operation information, press
the Operation Resources
button.
The screen below will
appear.
Here you will set the usage
to the dollar amount per item
it will cost for the OSP
operation.
This completes the setup of
the OSP Routing. You can
now release work orders
from the MRP workbench to
generate the requisitions for
the OSP items. Refer to the
Workbench to Receipt
document for the details of
how to process the
requisitions into purchase
orders and receipts.

Confidential

Page 2

5/27/2011

Standard Operating Procedure:

OSP Setup and Processing


Revision: 001

Release Date: 07/20/2007

The only differences you will see are the following:


When the work orders are released from the workbench, if there are OSP
operations, then a background process called requisition import will run
to create the requisitions for the OSP items.
When the OSP items are received, they are NOT received into stock but
instead into the Work Order.
Below is a flow diagram of the OSP process.

Release the WO off of the


MRP workbench

Run Requisition
Import

Perform Autocreate in
Purchasing to create PO

Receive Material from OSP


Suppler

Inspect Material

Deliver Material back to the


WO