This document defines the steps to setup Outside Processing and the procedure
steps to run the OSP process. First you must have setup the OSP Resource and
OSP Item. Setting up the item is just like setting up any other item except you
must use the Outside Processing Item Template. You must also be sure to let
the List Price item attribute for the requisition import process to work properly.
Now you need to setup the OSP resource. Use the navigation below to setup the
resource.
Always setup the OSP
resource with a type of
Amount and the
charge type as PO
Receipt and the UOM
to USD. Link the
resource to the OSP
item you setup
previously. Make sure
the resource is costed
and set the rate to 1
dollar.
Once you have setup the resource and saved it, you now need to assign it to a
department. Use the screen below for navigation.
When the department form
opens you can query up the
department you wish to add
the resource too. You can
then press the
RESOURCES button to
open the resources form.
Confidential
Page 1
5/27/2011
Confidential
Page 2
5/27/2011
Run Requisition
Import
Perform Autocreate in
Purchasing to create PO
Inspect Material
Confidential
Page 3
5/27/2011