Item

Estimated Date

1
2
3
4

Mooring system
8/8/2015
Ballast system
8/12/2015
Bilge system
8/8/2015
Testing procedure for main engine Done with a
record.

Balack out test

6
7
8
9

Bow thruster
Communication test
Anchor procedure test
Accomodation lighting system

8/8/2015

8/7/2015
8/5/2015
8/5/2015
Done with a
record.

10 Remote control system & Steering


gear system
11 Cooling system
12 Compress air system
13 CO2 system (blow test and alarm
system)

8/5/2015

14 Fire detection system

8/8/2015

15 Navigation equipment
16 Radio communication
17 Inclining test procedure
18 Mechanical fan system
19 Emergency battery

8/5/2015
8/5/2015
8/9/2015

8/8/2015
8/8/2015
Done with a
record.
8/6/2015
8/6/2015

Note
It is not ready, there are addition line to be install.
It is not ready.
Done, but the result has not been submited.

Manual generator equipment has not been replaced with


automatic ones. The equipment ordered from PT. GPS.
Commisioning procedure is required to be submitted.
It can be done when sea trial.
Done, but the result has not been submited.

The result will be submited soon.


The result will be submited soon.

It is not ready, the equipment will be replaced by the


equipment ordered from PT. GPS.

Done, but the result has not been submited.