@ Bharat Sanchar Nigam Ltd. (0/0 Divisional Engineer Phones (CMTS. ‘Albert Road Amite To, Me. Devesh Sharma M/s ZTE Networks Chandigarh ‘No. CMTSANCirle/Cor/201415/27 Dated-09/07/2015, ‘Sub Pending Works by M/s ZTE at Amwitsar SSA ‘The below mentioned works are pending in respect of Phase-Vil site Imegration, 1 2 3 3G sites ae not installed at Ajnala, chaba, Gall Bhatrian, Garden Colony, GGolden Avenue, inside Chat win gate & Sarl. ‘One sectors faulty of 36 site at Nag alan 3G site at TE Majitha Is integrated but not radiating due to FCU cards faut BB and PP are not installed at Baba Bakala ‘Swapping of 2202 BTS by 2968 BTS is pending at Balsaral, Tarn Taran Exg, Tarn taran bye pass Amritsar, Patt xg and Pat grain Market You are requested to expedite the pending work as integration of sites i delayed at your end. : ; rerun copy to oe (cHs.19 Albert Road Anvitsar 11. GMTD BSNL Amritsar for info pz 2. DGM [NWO.P} Amvitsar fr info pe 3. Add GM(NWP-CM) for info pl