The document summarizes a project to improve a wastewater treatment plant in Yorkshire, England. To support the construction of a new activated sludge plant comprising a large concrete tank, over 5,000 vibro stone columns and 600 vibro concrete columns were installed. This design solution was able to provide the required bearing capacities of 75-180kPa and limit settlement to specifications, by taking into account the varying soil conditions found at the site. The £300,000 ground improvement contract supported a total £64 million project to meet new EU regulations.
The document summarizes a project to improve a wastewater treatment plant in Yorkshire, England. To support the construction of a new activated sludge plant comprising a large concrete tank, over 5,000 vibro stone columns and 600 vibro concrete columns were installed. This design solution was able to provide the required bearing capacities of 75-180kPa and limit settlement to specifications, by taking into account the varying soil conditions found at the site. The £300,000 ground improvement contract supported a total £64 million project to meet new EU regulations.
The document summarizes a project to improve a wastewater treatment plant in Yorkshire, England. To support the construction of a new activated sludge plant comprising a large concrete tank, over 5,000 vibro stone columns and 600 vibro concrete columns were installed. This design solution was able to provide the required bearing capacities of 75-180kPa and limit settlement to specifications, by taking into account the varying soil conditions found at the site. The £300,000 ground improvement contract supported a total £64 million project to meet new EU regulations.
treatment works in Yorkshire require a new activated sludge plant comprising a massive reinforced concrete tank, 204m long 80m wide with perimeter walls 6.5m high.
Working in conjunction with consultant Carl
Bro and main contractor Morgan Est Pennines geotechnical engineers were able to design a scheme using 5000 vibro stone columns and 600 vibro concrete columns. Close co-operation including programming additional site investigation following land remediation, enabled the reuse of excavated material from other areas of the site as well as providing data to enable Pennine to rationalise their design to suit the varying ground conditions and the range of bearing capacities.
Soil conditions below the tank range from
competent sand and gravel overlying coal measures and bedrock of variable quality, to made ground and weak alluvial clay and sand and gravel. The site had also been used for waste tipping as well as a slurry lagoon. The sludge plant required bearing capacities ranging from 75kPa to 180kPa, total settlement was to be less than 30mm with differential settlement limited to 1 in 500.
The 300,000 subcontract will support
Yorkshire Waters total spend of 64million to meet new EU discharge regulations.