Professional Documents
Culture Documents
02.10.2012
2012.10.02.
Requirements:
structural requirements: safe, be able to carry the load of
the building
constructional requirements: schedule, minimal
resources, minimal cost
2012.10.02.
The specialities:
it is expensive and difficult to repair
usually it is constructed under the ground, so it is out of
sight
an bad/ misapplied foundation could demolish the building
The mistakes:
construction technology mistakes
bad or not proper digestion (always necessary!!!)
planning mistakes: the type of foundation is inadequate
2012.10.02.
pad foundation
mat foundation
foundation framework
cofferdam
2012.10.02.
slurry wall
pile foundations
2012.10.02.
When is it applicable?
The load-bearing layer is near to bottom floor level
The loads of the building are light-medium
Types
Strip foundations
Pad foundations Bucket foundations
Beam foundations
Mat (slab) foundations
2012.10.02.
Materials
brick
stone
reinforced
concrete
concrete
in case of
asymmetrical load
lightweight
concrete
2012.10.02.
2012.10.02.
2012.10.02.
10
2012.10.02.
11
2012.10.02.
Materials:
(Wood)
Monolithic reinforced concrete
Design
12
2012.10.02.
Design
13
2012.10.02.
14
2012.10.02.
Large, open-ended
compartments
shell or box with
cutting edge at the
bottom
Sunk into the ground
by digging the soil
out of the centre and
loading the walls
Filled with concrete
(and compacted
gravel)
concrete
gravel
RC shell
concrete
clamshell
15
2012.10.02.
16
2012.10.02.
When is it necessary?
The load-bearing layer is in deeper location
The loads of the building are too heavy
Other special cases
Types
Piles
Slurry wall
Other
(RC beam)
pile cap
pile cutoff
pile
pile foot
loadbearing
soil
end bearing
friction
17
2012.10.02.
Prefabricated piles
pile shoe
pile ring or
driving head
Precast pile
18
2012.10.02.
Cast-in-place piles
0. alignment
1. creating a test-pile
2. checking the load-bearing capacity (endurance test)
3. making the piles
4. removing the top of the piles
4. constructing the pile caps
5. connecting the pile caps with RC beams if necessary
CFA technology
Drilling continuously
until planned depth
(using guiding tube if
necessary)
Placing the concrete and
removing the drill
Placing reinforcement
(vibration)
19
2012.10.02.
Soil-Mec technology
20
2012.10.02.
Other technologies
21
2012.10.02.
What is?
guiding walls
Functions
slurry wall
groundwater level
watertight soil
22
2012.10.02.
23
2012.10.02.
concrete
groundwater
end pipes
Excavation
24
2012.10.02.
25
2012.10.02.
Tie-back
Anchorage to brace against
earth and water pressure
Steel and concrete ties
Tie-backs
26
2012.10.02.
27
2012.10.02.
Strengthening foundations
28
2012.10.02.
29
2012.10.02.
By grouting methods
Jet grouting (soil-concrete piles)
from a shaft
30
2012.10.02.
http://cee.engr.ucdavis.edu/faculty/boulanger/
http://en.wikipedia.org/wiki/Foundation_(engineering)
http://www.foundationengineering.info/photo_galleries/
08/footing_construction/
31