IMPROVEMENT OF QUALITY MANAGEMENT FOR

HIGHWAY AND BRIDGE CONSTRUCTION AND


MAINTENANCE, PHASE II

ROAD PROJECT MANAGEMENT


AND SUPERVISION MANUAL
VOLUME I: MAIN TEXT

2014

Department of Public Works and Highways

IMPROVEMENT OF QUALITY MANAGEMENT FOR


HIGHWAY AND BRIDGE CONSTRUCTION AND
MAINTENANCE, PHASE II

ROAD PROJECT MANAGEMENT AND


SUPERVISION MANUAL
VOLUME I: MAIN TEXT
SECOND EDITION

SEPTEMBER 2014

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


JAPAN INTERNATIONAL COOPERATION AGENCY

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE SECRETARY
Manila

TABLE OF CONTENTS
FOREWORD

TABLE OF CONTENTS..................................................................................

ii

LIST OF TABLES ...........................................................................................

viii

LIST OF FIGURES .........................................................................................

xi

ACKNOWLEDGEMENT .................................................................................

xiv

ACRONYMS .................................................................................................

xv

DEFINITION OF TERMS................................................................................

xxi

Chapter 1

Introduction ...............................................................................

1-1

1.1

Background ..................................................................................................

1-1

1.2

Purpose ........................................................................................................

1-1

1.3

Outline ..........................................................................................................

1-2

Chapter 2

Contracts and Guidelines ..........................................................

2-1

2.1

Locally-funded Contract ...............................................................................

2-1

2.2

Foreign-funded Contract ..............................................................................

2-1

2.2.1

Asset Management Approach .................................................................

2-1

2.2.2

Long-Term Performance Based Maintenance ........................................

2-2

Guidelines, Manuals and Practices ..............................................................

2-7

2.3

2.3.1

Basic Guidelines and Manuals................................................................

2-7

2.3.2

Standard Procurement and Implementation Guidelines .........................

2-8

2.3.3

International Standard Practices .............................................................

2-10

2.3.4

Standard Practices of DPWH..................................................................

2-11

Chapter 3
3.1

Implementing Organizations and Role of Entities .......................

3-1

Organization of Central Office ......................................................................

3-1

3.1.1

Bureau of Construction ...........................................................................

3-3

3.1.2

Bureau of Maintenance ...........................................................................

3-5

3.1.3

Project Management Office ....................................................................

3-6

3.1.4

Planning Service .....................................................................................

3-7

3.1.5

Bureau of Research and Standards........................................................

3-9

Road Project Management and Supervision Manual Vol.1 Main Text

ii

3.1.6

Bureau of Design ....................................................................................

3-10

3.1.7

Bureau of Quality and Safety (BQS) .......................................................

3-12

3.2

Organizations of RO and DEO .....................................................................

3-13

3.3

Organizations for Construction Supervisions ...............................................

3-16

3.3.1

For Foreign-funded Projects through International Competitive Bidding.

3.3.2

For Locally and Foreign-funded Projects through Local Competitive

3-16

Bidding ....................................................................................................

3-20

3.4

Administrative Penalties/Sanctions ..............................................................

3-23

3.5

Authorities of DPWH Officials .......................................................................

3-24

3.7

Reforms in DPWH ........................................................................................

3-25

Chapter 4

Procurement ..............................................................................

4-1

4.1

Bids ..............................................................................................................

4-1

4.2

Contract ........................................................................................................

4-5

4.2.1

Contract Documents ...............................................................................

4-5

4.2.2

Subcontract/Sublease .............................................................................

4-8

Facilities and Land Acquisition .....................................................................

4-8

4.3

4.3.1

Facilities for the Engineer........................................................................

4-8

4.3.2

Right-of-Way Acquisition .........................................................................

4-9

4.3.3

Possession of Site ..................................................................................

4-9

4.3.4

Relocation of Utilities ..............................................................................

4-10

Performance Security and Insurance ...........................................................

4-10

4.4

4.4.1

Performance Security .............................................................................

4-10

4.4.2

Contractor's All Risk Insurance (CARI) ...................................................

4-11

Notice to Proceed (NTP) ..............................................................................

4-11

4.5

Chapter 5

Public Information, Road Safety and Environmental Management

5-1

5.1

Public Information System............................................................................

5-1

5.2

Relations with Local Communities and Road Users.....................................

5-2

5.3

Road Safety..................................................................................................

5-3

iii

5.3.1

Road Safety Program .............................................................................

5-3

5.3.2

Road Safety Manual ...............................................................................

5-4

5.3.3

Provision of Road Safety Devices ...........................................................

5-5

5.3.4

Traffic Management ................................................................................

5-6

Road Project Management and Supervision Manual Vol.1 Main Text

5.3.5
5.4

Safety Officer ..........................................................................................

5-6

Safety and Health Programs ........................................................................

5-6

5.4.1

Obligation of the Contractor ....................................................................

5-6

5.4.2

Load Restriction ......................................................................................

5-7

5.4.3

Coordination during Emergency .............................................................

5-7

Environmental Management ........................................................................

5-8

5.5

5.5.1

Legal Framework and Process ...............................................................

5-8

5.5.2

Environmental Impact Assessment (EIA) ................................................

5-8

5.5.3

Environmental Compliance Certificate (ECC) .........................................

5-10

5.5.4

Environmental Management Plan (EMP)................................................

5-14

5.5.5

Environmental and Social Considerations ..............................................

5-15

Risk Management ........................................................................................

5-17

5.6

Chapter 6
6.1

Construction Management and Supervision ...............................

6-1

Preliminary Activities ....................................................................................

6-1

6.1.1

Study of Design Reports, Design Drawings, Specifications and


Contract Documents ...............................................................................

6-1

6.1.2

Study on Meteorological Condition .........................................................

6-3

6.1.3

Pre-construction Survey..........................................................................

6-3

6.1.4

Joint Site Inspection ................................................................................

6-4

6.1.5

Conduct of Pre-construction Meeting ......................................................

6-5

6.1.6

Conduct of Joint As-stake Survey and Preparation of As-staked Plan ....

6-12

6.1.7

Preparation and Processing of Variation Order (VO) ..............................

6-14

Project Management ....................................................................................

6-18

6.2

6.2.1

Mobilization/Demobilization ....................................................................

6-19

6.2.2

Provision of Project Billboard ..................................................................

6-19

6.2.3

Work Program .........................................................................................

6-20

6.2.4

Straight Line Diagram .............................................................................

6-26

6.2.5

Value Engineering ...................................................................................

6-26

6.2.6

Construction Drawings ............................................................................

6-28

6.2.7

Shop Drawings........................................................................................

6-28

6.2.8

Establishment of Communication Network .............................................

6-28

6.2.9

Conduct of Coordination Meetings..........................................................

6-28

6.2.10 Maintenance Work during Contract Period .............................................

6-29

Road Project Management and Supervision Manual Vol.1 Main Text

iv

6.2.11 Delay of Work and Action Plans ..............................................................

6-30

6.2.12 Suspension of Works ..............................................................................

6-34

6.2.13 Extension of Contract Time .....................................................................

6-35

6.2.14 Termination of Contract ...........................................................................

6-37

6.3

Cost Management ........................................................................................

6.3.1

Advance Payment ...................................................................................

6-42

6.3.2

Interim Payment ......................................................................................

6-44

6.3.3

Payment of Materials on Site ..................................................................

6-46

6.3.4

Disbursement Estimate and Monitoring of Payment ...............................

6-46

6.3.5

Cost Reduction .......................................................................................

6-46

6.3.6

Price Adjustments ...................................................................................

6-49

6.3.7

Provisional Sum and Daywork ................................................................

6-50

6.3.8

Claims .....................................................................................................

6-51

Quantity Control ...........................................................................................

6-54

6.4

6.4.1

Objectives ...............................................................................................

6-54

6.4.2

Duties of Quantity Engineer ....................................................................

6-54

6.4.3

Inspection Techniques ............................................................................

6-55

6.4.4

Bill of Quantities (BOQ)...........................................................................

6-55

6.4.5

Measurement and Evaluation .................................................................

6-56

6.4.6

Monitoring and Estimate of Final Quantity ..............................................

6-57

Documentation .............................................................................................

6-57

6.5

6.5.1

Progress Reports ....................................................................................

6-58

6.5.2

Project Logbook ......................................................................................

6-59

6.5.3

Correspondence .....................................................................................

6-62

6.5.4

Progress Photographs ............................................................................

6-62

Chapter 7

Quality Control ...........................................................................

7-1

7.1

General.........................................................................................................

7-1

7.2

Quality Control Program ...............................................................................

7-3

7.3

Quality Control Specifications.......................................................................

7-5

7.4

Project Laboratory ........................................................................................

7-6

7.5

Accreditation of AC and PCC Batching Plants .............................................

7-9

7.6

Quality Control Activities ...............................................................................

7-13

7.6.1

6-39

Category of Activities and Frequency of Tests ........................................

7-13

Road Project Management and Supervision Manual Vol.1 Main Text

7.6.2

Quality Control on Construction Materials...............................................

7-17

7.6.3

Production of Aggregates........................................................................

7-18

7.6.4

Submission and Approval of Concrete Pouring Permit ...........................

7-22

7.6.5

Quality Control Logbook .........................................................................

7-24

Design Mix and Trial Construction ................................................................

7-24

7.7

7.7.1

Design Mix and Trial Construction for PCC Pavement ...........................

7-24

7.7.2

Job-Mix Formula and Trial Construction for AC Pavement .....................

7-27

7.7.3

Design Mix and Trial Construction for Other Major Work Items ..............

7-30

7.8

Calibration of Testing Equipment ..................................................................

7-32

7.9

Accreditation of New Product and Technology .............................................

7-32

7.9.1

PCCP Reinforced with Welded Wire Mesh .............................................

7-32

7.10 Recycling of Pavement Materials .................................................................

7-33

7.11 Roller Compacted Concrete Pavement (RCCP) ..........................................

7-33

7.12 Electrical Density Gauge ..............................................................................

7-34

7.13 ISO Accreditation of Large Contractors ........................................................

7-35

Chapter 8

Field Inspections .......................................................................

8-1

8.1

Objectives of Field Inspection.......................................................................

8-1

8.2

Categories of Field Inspection ......................................................................

8-4

8.3

Field Inspection Plan ....................................................................................

8-6

8.4

Standard Inspection Check Sheet ................................................................

8-8

8.5

Request for Inspection .................................................................................

8-10

Chapter 9

Project Completion ....................................................................

9-1

9.1

Pre-final Inspection for Completion ..............................................................

9-1

9.2

Final Inspection for Completion ....................................................................

9-1

9.2.1

Submission of Request for Final Inspection for Completion ...................

9-1

9.2.2

Participants for the Final Inspection for Completion ................................

9-2

9.2.3

Remedial Works......................................................................................

9-4

9.3

Issuance of Certificate of Completion ...........................................................

9-4

9.4

Final Payment ..............................................................................................

9-6

Chapter 10

Defects Liability Period, Final Acceptance and Warranty Period .

10-1

10.1 Defects Liability Period .................................................................................

10-1

Road Project Management and Supervision Manual Vol.1 Main Text

vi

10.2 Pre-final Inspection for Acceptance ..............................................................

10-1

10.3 Final Inspection for Acceptance....................................................................

10-1

10.3.1 Remedial Works......................................................................................

10-1

10.4 Issuance of Certificate of Acceptance ..........................................................

10-1

10.5 Release of Remaining Retention Money ......................................................

10-2

10.6 Release of Performance Security .................................................................

10-2

10.7 Warranty Period............................................................................................

10-2

Chapter 11

Maintenance after Final Acceptance ...........................................

11-1

11.1 Maintenance by DPWH after Final Acceptance............................................

11-1

11.2 Maintenance Inspection and Remedial Measure Design .............................

11-8

11.3 Overloaded Vehicle Control ..........................................................................

11-10

vii

Road Project Management and Supervision Manual Vol.1 Main Text

LIST OF TABLES
Table 1.1

Classifications of Projects and Programs ..........................................

1-2

Table 2.1

Scope of LTPBM Contract .................................................................

2-3

Table 2.2

Road Condition Category ..................................................................

2-4

Table 2.3

International Roughness Index and Road Condition Category ..........

2-4

Table 2.4

Typical Intervention Pattern on LTPBM .............................................

2-5

Table 2.5

Advantages and Disadvantages of Design-Built Contract .................

2-6

Table 2.6

Reference Guidelines and Manuals ..................................................

2-8

Table 2.7

DPWH Procurement Manuals ...........................................................

2-9

Table 2.8

Comparison of GCC between FIDIC and DPWH Conditions of


Contract .............................................................................................

2-13

Table 3.1

Bureaus' Roles and Functions ...........................................................

3-3

Table 3.2

Limits of Authority ..............................................................................

3-13

Table 3.3

Duties and Responsibilities of Consultants........................................

3-18

Table 3.4

Limits of assignment of Project Engineer and Project Inspector........

3-21

Table 3.5

Limits of Assignment of Materials Engineer .......................................

3-21

Table 3.6

Duties and Responsibilities of Project Engineer ................................

3-22

Table 3.7

Duties and Responsibilities of Project Inspector ................................

3-22

Table 3.8

Duties and Responsibilities of Materials Engineer .............................

3-23

Table 3.9

Points against Negative Slippage ......................................................

3-24

Table 4.1

Bid Documents ..................................................................................

4-1

Table 4.2

List of Contract Documents ...............................................................

4-5

Table 5.1

Safety Programs ................................................................................

5-3

Table 5.2

Road Safety Manual and Handbook ..................................................

5-4

Table 5.3

Project Grouping Matrix for Determination of EIA Report Type


- New Single and Co-located Projects (Group I)................................

Table 5.4

5-12

Project Grouping Matrix for Determination of EIA Report Type


- New Single and Co-located Projects (Group II)...............................

5-13

Table 6.1

Checklist of Reports for Review.........................................................

6-2

Table 6.2

Participants for Site Inspection ..........................................................

6-4

Table 6.3

Scope of Inspection ...........................................................................

6-5

Table 6.4

Agenda for Pre-construction Meeting ................................................

6-6

Table 6.5

Attendees for Meeting .......................................................................

6-10

Table 6.6

Control Points and Tolerances ...........................................................

6-13

Table 6.7

Agenda for Coordination Meeting ......................................................

6-29

Table 6.8

Stages of Negative Slippage .............................................................

6-31

Table 6.9

Types of Payments ............................................................................

6-41

Road Project Management and Supervision Manual Vol.1 Main Text

viii

Table 6.10

Payment Guidelines ..........................................................................

Table 6.11

Actions and Supporting Documents for Advance Payment

6-41

(Regional and District Offices) ...........................................................

6-43

Table 6.12

Payment Procedure ...........................................................................

6-44

Table 6.13

Actions and Supporting Documents Required for Interim


Payment (Regional and District Offices) ............................................

6-45

Table 6.14

Cost Reduction due to Deficiency in Strength ...................................

6-47

Table 6.15

Cost Reduction due to Deficiency in Thickness.................................

6-49

Table 6.16

Contractors Claim for Time Extension ..............................................

6-53

Table 6.17

Checklist of Project Documents .........................................................

6-58

Table 6.18

Progress Report ................................................................................

6-59

Table 6.19

Responsible Office for Securing the Documents ...............................

6-62

Table 7.1

Quality Control Activities ....................................................................

7-4

Table 7.2

Specifications/Standards ...................................................................

7-6

Table 7.3

Material Testing Equipment/Apparatus ..............................................

7-8

Table 7.4

Quality Control Categories ................................................................

7-14

Table 7.5

Minimum Test Requirements .............................................................

7-16

Table 7.6

Categories of Materials ......................................................................

7-17

Table 7.7

Types of Aggregates Required for Road Projects..............................

7-19

Table 7.8

Types of Crushers .............................................................................

7-20

Table 7.9

Classes of Concrete ..........................................................................

7-30

Table 7.10

Grading Requirement for Coarse Aggregate .....................................

7-30

Table 7.11

Strength Requirements for Cement Concrete ...................................

7-31

Table 7.12

Composition and Strength of Concrete for Use in Structure ..............

7-31

Table 7.13

Comparison between PCCP and RCCP ...........................................

7-34

Table 8.1

Criteria for acceptance ......................................................................

8-4

Table 9.1

Composition of Inspectorate Team ....................................................

9-2

Table 9.2

Procedures and Supporting Documents for Final Payment (Regional


and District Offices) ...........................................................................

9-7

Table 10.1

Warranty Security ..............................................................................

10-3

Table 11.1

Main Goals of Preventive/Periodic and Routine Maintenance ...........

11-2

Table 11.2

Required Maintenance Activities for Road Facilities ..........................

11-3

Table 11.3

Calculation of Maintenance Share .....................................................

11-6

Table 11.4

Monitoring for Maintenance Works ....................................................

11-7

Table 11.5

Pavement Distress, Major Causes and Common Repair Methods


for AC Pavement ...............................................................................

ix

11-8

Road Project Management and Supervision Manual Vol.1 Main Text

Table 11.6
Table 11.7

Pavement Distress, Major Causes and Common Repair Methods


for PCC Pavement.............................................................................

11-9

Maximum Allowable Gross Vehicle Weight........................................

11-10

Road Project Management and Supervision Manual Vol.1 Main Text

LIST OF FIGURES
Figure 2.1

Asset Management Approach ...........................................................

2-2

Figure 2.2

Sequence of Project Delivery ............................................................

2-6

Figure 2.3

Procurement and Contract Guidelines...............................................

2-7

Figure 2.4

DPWH Procurement Manuals Cover Pages......................................

2-9

Figure 2.5

FIDIC Conditions of Contract Cover Pages .......................................

2-11

Figure 3.1

Organizational Chart of DPWH CO ...................................................

3-2

Figure 3.2

Organizational Chart of BOC .............................................................

3-4

Figure 3.3

Organizational Chart of BOM ............................................................

3-5

Figure 3.4

Organizational Chart of PS ................................................................

3-8

Figure 3.5

Organizational Chart of BRS .............................................................

3-10

Figure 3.6

Organizational Chart of BOD .............................................................

3-11

Figure 3.7

Organizational Chart of BQS .............................................................

3-12

Figure 3.8

Organizational Chart of RO ...............................................................

3-14

Figure 3.9

Organizational Chart of DEO .............................................................

3-15

Figure 3.10 Typical Assignment Schedules of Consultants ..................................

3-16

Figure 3.11 Typical Organizational Chart of Consultants for Construction


Supervision ........................................................................................

3-17

Figure 3.12 Typical Organizational Chart for Construction Supervision of


Project conducted thru Force Account ...............................................

3-20

Figure 5.1

Project Information ............................................................................

5-2

Figure 5.2

Traffic Control Information .................................................................

5-2

Figure 5.3

Traffic Accident Recording and Analysis System ...............................

5-3

Figure 5.4

Road Safety Manual and Highway Safety Design Standards Cover


Pages ................................................................................................

5-4

Figure 5.5

Road Safety Devices and Signages ..................................................

5-5

Figure 5.6

Summary Flowchart of EIA Process ..................................................

5-9

Figure 5.7

Overview of Stages of the Philippine EIA Process ............................

5-10

Figure 5.6

Risk Management Diagram ...............................................................

5-17

Figure 6.1

Stages of Implementation ..................................................................

6-1

Figure 6.2

Example of Rainfall Record ...............................................................

6-3

Figure 6.3

Typical Organizational Chart of Contractor for Foreign-Funded Project

6-8

Figure 6.4

Typical Organizational Chart of Contractor for Locally-Funded Project

6-9

Figure 6.5

Typical Weekly Work Schedule .........................................................

Figure 6.6

Flowchart of activities for As-stake Survey and Approval of

Figure 6.7

xi

6-11

As-staked Plan ..................................................................................

6-14

Executive Summary...........................................................................

6-17

Road Project Management and Supervision Manual Vol.1 Main Text

Figure 6.8

Project Management .........................................................................

6-18

Figure 6.9

Example of Pert/CPM ........................................................................

6-21

Figure 6.10 Example of Bar Chart with S-Curve ...................................................

6-22

Figure 6.11 Example of Manpower Schedule .......................................................

6-24

Figure 6.12 Example of Equipment Utilization Schedule ......................................

6-25

Figure 6.13 Example of Straight Line Diagram .....................................................

6-27

Figure 6.14 Maintenance Period...........................................................................

6-29

Figure 6.15 Contractors Maintenance Activities ...................................................

6-30

Figure 6.16 Catch-up Program .............................................................................

6-32

Figure 6.17 Cost and Financial Management .......................................................

6-40

Figure 6.18 Project Logbook Format ....................................................................

6-61

Figure 6.19 Progress Photographs .......................................................................

6-63

Figure 7.1

Quality Management .........................................................................

7-1

Figure 7.2

Statistical Quality Control (X-R Control Chart) ...................................

7-2

Figure 7.3

Quality Control Procedures ...............................................................

7-5

Figure 7.4

Material Testing Equipment/Apparatus ..............................................

7-9

Figure 7.5

Flowchart for Batching Plant Accreditation ........................................

7-11

Figure 7.6

Assessment of Batching Plant for Accreditation ..............................

7-12

Figure 7.7

Asphalt and Portland Cement Concrete Batching Plants ..................

7-13

Figure 7.8

Common Problems in Aggregate Production (Case of River Gravel)

7-21

Figure 7.9

Flowchart for Approval of Concrete Pouring Permit ...........................

7-22

Figure 7.10 Concrete Pouring Permit Format .......................................................

7-23

Figure 7.11 Materials Quality Control Log Book ...................................................

7-24

Figure 7.12 Flowchart for Preparatory Work to Concrete Paving .........................

7-25

Figure 7.13 Trial Mix for Portland Cement Concrete ............................................

7-25

Figure 7.14 Trial Construction for PCCP ..............................................................

7-26

Figure 7.15 Marshall Stability Testing Equipment .................................................

7-28

Figure 7.16 Determination of Design Asphalt Content ..........................................

7-29

Figure 7.17 PCCP Reinforced with Welded Wire Mesh........................................

7-33

Figure 7.18 Recycling of Concrete Materials ........................................................

7-33

Figure 7.19 Equipment for RCCP .........................................................................

7-34

Figure 7.20 Typical Composition of RCCP ...........................................................

7-34

Figure 8.1

Site Instruction ...................................................................................

8-3

Figure 8.2

Hierarchy of Field Inspection .............................................................

8-6

Figure 8.3

Classification of Pavement by Work Category...................................

8-6

Figure 8.4

Flowchart for Field Inspection ............................................................

8-7

Figure 8.5

Example of Inspection Check Sheet ..................................................

8-9

Road Project Management and Supervision Manual Vol.1 Main Text

xii

Figure 8.6

Flowchart for Inspection Request and Approval ................................

8-10

Figure 8.7

Example of Work/Inspection Request................................................

8-11

Figure 9.1

Activities undertaken during completion stage ..................................

9-3

Figure 9.2

Flowchart of Activities Relative to the Issuances of


Certificates of Completion and Acceptance .......................................

9-5

Figure 10.1 Defects Liability and Warranty Periods ..............................................

10-2

Figure 11.1 Asset Management............................................................................

11-1

Figure 11.2 Maintenance Activities on Pavement .................................................

11-3

Figure 11.3 Programming Process (Asset Management System) ........................

11-4

Figure 11.4 Flow of Routine Maintenance Work ...................................................

11-5

Figure 11.5 Budget Allocation Flow ......................................................................

11-8

Figure 11.6 Effects of Overloading on Pavement .................................................

11-11

xiii

Road Project Management and Supervision Manual Vol.1 Main Text

ACKNOWLEDGEMENT
In behalf of the CWG on Road Manuals Improvement, The Group Leader would like to
thank the TWG members and the regional project managers of pilot regions for their
patience, guidance, words of encouragement and useful critiques which really helped us a lot
in accomplishing this undertaking.
TWG Members:
Dr. Judy F. SESE, Chairperson, OIC-Director, Bureau of Research and Standards
Ms. Carolina S. CANUEL, Fmr. Vice Chairperson, Fmr. Div. Chief, DPD, P/S
Mr. Adriano M. DOROY, Asst. Director, Bureau of Design
Mr. Aristarco M. DOROY, OIC-Asst. Director, Bureau of Construction
Ms. Edna F. MEEZ, OIC-DE, Negros Occidental 4th DEO, DPWH-Region VII
Mr. Felipe S. RAMOS, Fmr. Chief, Technical Services and Evaluation Div., BRS
Mr. Nestor B. CAOILE, OIC-Division Chief, Materials Testing Division, BRS

Regional Project Managers:


Ms. Elsa T. NABOYE, Regional Project Manager, Asst. Chief, QAD, DPWH-CAR
Ms. Ramie B. DOROY, Regional Project Manager, DE, Negros Oriental 1st DEO,
DPWH-Region VII
Ms. Rowena P. JAMITO, Regional Project Manager, Engr. V, MD, RO-XI
Thank you also to the CWG Members for their efforts and collaborations.
CWG Members:
MR. Jay Jenner R. BIARES, Engr. III, CAR; Group Leader
Mr. Elmer R. FIGUEROA, Engr. III, BOC
Mr. Ernante S. ANTONIO, Engr. III, BOM
Ms. Carina B. DIAZ, Engr. III, BOD
Ms. Nenita R. VALENCIA, Former Engr. III, BRS
Mr. Vicente R. VALLE, JR., Engr. IV, DPWH-Region VII
Ms. Aurora M. LACASANDILE, Engr. III, CD, DPWH-Region XI
Finally, we wish to thank our Expert, Mr. Ryoichi Yamasaki, Co-Team Leader, JICA TCP II
and his Asst. Engineer, Mr. Feliciano P. Carpio, for their support and encouragement
throughout this activity.

Road Project Management and Supervision Manual Vol.1 Main Text

xiv

ACRONYMS
A
AADT

Annual Average Daily Traffic

AASHTO

American Association of State Highway and Transportation Official

ABC

Approved Budget for the Contract

AC

Asphalt Concrete

ACI

American Concrete Institute

ADB

Asian Development Bank

AIP

Annual Investment Program

AMWP

Annual Maintenance Working Program

ASTM

American Society for Testing and Materials

AWP

Annual Working Program

B
BAC

Bids and Awards Committee

BMS

Bridge Management System

BOC

Bureau of Construction

BOD

Bureau of Design

BOM

Bureau of Maintenance

BOQ

Bill of Quantities

BOT

Built-Operate-Transfer

BQS

Bureau of Quality and Safety

BRS

Bureau of Research and Standards, DPWH

xv

CARBDP

Cotabato Agusan River Basin Development Project

CARP

Comprehensive Agrarian Road Program

CAD

Computer-Aided Design

CARI

Contractors All Risk Insurance

CBR

California Bearing Ratio

CDA

Cooperative Development Authority

CMS

Contract Management System

CNC

Certificate of Non-Coverage

CO

Central Office

COA

Commission on Audit

CPES

Contractors' Performance Evaluation System

Road Project Management and Supervision Manual Vol.1 Main Text

CPM

Critical Path Method

CV

Curriculum Vitae

CWG

Counterpart Working Group

D
DAO

DENR Administrative Order

DB

Design-Build

DBB

Design-Bid-Build

DE

District Engineer

DENR

Department of Environment and Natural Resources

DEO

District Engineering Office

DILG

Department of Interior and Local Government

DLP

Defects Liability Period

DO

Department Order

DOTC

Department of Transportation and Communications

DoTS

Documents Tracking System

DPD

Development Planning Division

DPM

DPWH Procurement Manual

DPWH

Department of Public Works and Highways

DTI

Department of Trade and Industry

E
EA

Executing Agency

ECC

Environmental Compliance Certificate

EIA

Environmental Impact Assessment

EMB

Environmental Management Bureau

EMK

Equivalent Maintenance Kilometer

EMP

Environmental Management Plan

eNGAS

Electronic New Government Accounting System

ESAL

Equivalent Single Axle Load

ESIA

Environmental and Social Impact Analysis

ESS

Environmental and Social Screening/Scoping

ESSO

Environmental and Social Safeguards Office

F
FABP

Foreign-Assisted Bridge Program

FCSEC

Flood Control and Sabo Engineering Center

Road Project Management and Supervision Manual Vol.1 Main Text

xvi

FDT

Field Density Test

FHWA

Federal Highway Administration

FIDIC

Fdration Internationale Des Ingnieurs-Conseils


(International Federation of Consulting Engineers)

G
GAA

General Appropriations Act

GCC

General Conditions of Contract

GOP

Government of the Philippines

GPPB

Government Procurement Policy Board

GPRA

Government Procurement Reform Act

GVW

Gross Vehicle Weight

H
HDM-4

Highway Development and Management Version 4

HMA

Hot Mix Asphalt

I
ICB

International Competitive Bidding

IEE

Initial Environment Examination

IN

International Expert

IO

Implementing Office

IRI

International Roughness Index

IROW

Infrastructure Right-of-Way

IRR-A

Implementing Rules and Regulations Part A (for locally-funded projects)

ISO

International Organization for Standardization

J
JICA

Japan International Cooperation Agency

JMF

Job Mix Formula

JCC

Joint Coordinating Committee

K
KAMANAVA

Kalookan Malabon Navotas Valenzuela

KEDCF

Korean Economic Development Cooperative Fund

xvii

Road Project Management and Supervision Manual Vol.1 Main Text

L
LCB

Local Competitive Bidding

LGU

Local Government Unit

LTO

Land Transportation Office

LTPBM

Long Term Performance-Based Maintenance

LTPBME

Long Term Performance Based Maintenance-cum-Enhancement

M
MBA

Maintenance by Administration (force account)

MBC

Maintenance by Contract-put

MC

Memorandum Circular

MCC

Millennium Challenge Corporation

ME

Materials Engineer

MFCDP

Major Flood Control development Project

MIS

Monitoring and Information Service

MOA

Memorandum of Agreement

MPE

Mount Pinatubo Emergency

MVUC

Motor Vehicle Users Charge/Cost

MYPSS

Multi-Year Programming and Scheduling System

N
N

National Expert

NEDA

National Economic and Development Authority

NGO

Non-Governmental Organization

NRIMP

National Roads Improvement and Management Program

NTP

Notice To Proceed

P
PAGASA

Philippine Atmospheric, Geophysical and Astronomical Services Administration

PAMS

Project Advisory and Management System

PBDs

Philippine Bid Documents

PCAB

Philippine Constructors Accreditation Board

PCC

Portland Cement Concrete

PCCP

Portland Cement Concrete Pavement

PE

Project Engineer

Pert/CPM

Program Evaluation and Review Technique / Critical Path Method

PI

Project Inspector

Road Project Management and Supervision Manual Vol.1 Main Text

xviii

PID

Public Information Division

PM

Project Manager

PM/O

Preventive Maintenance/Overlay

PMO

Project Management Office

PNP

Philippine National Police

PPP

Public-Private Partnership

PS

Planning Service

Q
QAD

Quality Assurance Division

QAS

Quality Assurance Section

QAU

Quality Assurance Unit

QCP

Quality Control Program

R
RA

Republic Act

RA 9184

Government Procurement Reform Act of 2003

RATPLAN

Rationalization Plan

RB

Road Board

RBIA

Road and Bridge Information Application

RE

Resident Engineer

REAPMP

Road Enhancement and Asset Preservation Management Program

RH

Rehabilitation

RM

Routine Maintenance

RMMS

Routine Maintenance Management System

RMP

Routine Maintenance Program

RO

Regional Office

ROCOND

Visual Road Condition Rating System

ROW

Right-of-Way

RRNDP

Rural Road Network Development Project

RUPP

Road Upgrading Preservation Project

RWS

Rural Water System

S
SB

Special Buildings

SBD

Standard Bidding Documents

SBP

Special Bridge Project

xix

Road Project Management and Supervision Manual Vol.1 Main Text

SCC

Special Conditions of Contract

SEC

Securities and Exchange Commission

SFD

Saudi Fund for Development

SMS

Short Messaging System

T
TARAS

Traffic Accident Recording and Analysis System

TCP

Technical Cooperation Project

TEAM

Traffic Engineering and Management

TOR

Terms of Reference

TWG

Technical Working Group

U
URPO

Urban Roads Project Office

USA

United States of America

V
VDF

Vehicle Damage Factor

VO

Variation Order

W
WB

World Bank

Road Project Management and Supervision Manual Vol.1 Main Text

xx

DEFINITIONS AND TERMS


Contract Words
(By) Administration
The procedure by which the implementation of an infrastructure project
is carried out under the administration and supervision of the DPWH
through its own personnel.
Approved Budget for the Contract (ABC)
The budget for the contract duly approved by the Head of the Procuring
Entity.
BAC
The Bids and Awards Committee established in accordance with Article V
of R.A.9184.
Bidding Documents
The documents issued by the DPWH as the basis for Bids, furnishing all
information necessary for a prospective bidder to prepare a bid for the
Goods, Infrastructure Projects, and Consulting Services to be provided.
Bill of Quantities
A list of the specific items of Work and their corresponding quantities,
unit prices, lump sums, and/or provisional sums.
Change Order
A written order issued by the Director to the Contractor, covering changes
in the plans or quantities or both, within or beyond the scope of the
contract and establishing the basis of payment for the work affected by
the changes.
Contract
The contract between the DPWH and the Contractor to execute,
completes, and maintain the Works. It consists of the documents listed
in the GCC and the SCC.
Contract Time Extension
The allowable period for the Contractor to complete the Works in addition
to the original Completion Date stated in this Contract.
Contractor
The juridical entity whose proposal has been accepted by the DPWH and
to whom the Contract to execute the Work was awarded.

xxi

Road Project Management and Supervision Manual Vol.1 Main Text

Corrupt, Fraudulent, and Coercive Practices


"Corrupt Practice" means behavior on the part of officials in the public or
private sectors by which they improperly and unlawfully enrich
themselves, others, or induce others to do so, by misusing the position in
which they are placed, and includes the offering, giving, receiving, or
soliciting of anything of value to influence the action of any such official in
the procurement process or in contract execution; entering, on behalf of
the Government, into any contract or transaction manifestly and grossly
disadvantageous to the same, whether or not the public officer profited
or will profit thereby, and similar acts as provided in Republic Act 3019.
"Fraudulent Practice" means a misrepresentation of facts in order to influence a
procurement process or the execution of a contract to the detriment of
the PROCURING ENTITY, and includes collusive practices among Bidders
(prior to or after bid submission) designed to establish bid prices at
artificial, non-competitive levels and to deprive the PROCURING ENTITY
of the benefits of free and open competition.
Collusive Practices means a scheme or arrangement between two or more Bidders, with
or without the knowledge of the PROCURING ENTITY, designed to
establish bid prices at artificial, non-competitive levels.
Coercive Practices means harming or threatening to harm, directly or indirectly, persons,
or their property to influence their participation in a procurement process,
or affect the execution of a contract.
Consulting Services
The services for Infrastructure Projects and other types of projects or
activities of the DPWH requiring adequate external technical and
professional expertise to undertake such as, but not limited to: (i)
advisory and review services; (ii) pre-investment or feasibility studies; (iii)
design; (iv) construction supervision; (v) management and related
services; and (vi) other technical services or special studies.
Day
Calendar days; months are calendar months.
Dayworks
Varied work inputs subject to payment on a time basis for the
Contractors Employees and Equipment, in addition to payments for
associated Materials and Plant.

Road Project Management and Supervision Manual Vol.1 Main Text

xxii

Defects Liability Certificate


The certificate issued by the DPWHs Representative upon correction of
defects by the Contractor.
Defects Liability Period
The one year period between project completion and final acceptance
within which the Contractor assumes the responsibility to undertake the
repair of any damage to the Works at his own expenses, aside from his
responsibility under warranty of the Civil Code which is 5 years for
horizontal, and 15 years for vertical.
Drawings (Plans)
The plans, profiles, typical cross sections, working drawings and
supplemental drawings, approved by the Engineer / the PE, or exact
reproductions thereof, which show the location, character, dimensions,
and details of the work. They include all supplementary details, shop
drawings, calculations, and other information provided or approved for
the execution of this Contract.
Engineer
In this Manual, Engineer means a qualified professional appointed or
designated by the Employer (DPWH) to render technical and/or
administrative decision for the purposes of supervising a project. In
DPWH, the hierarchy of command based on delegated authority of
officials/officers is being observed, hence the title Engineer most likely
changes in person of authority depending on the subject matter and its
cost limit from the omnibus levels of authority of DPWH officers and
officials.
Likewise, person appointed by the Contractor to act as Engineer for the
purposes of supervising the project and named in the Special Conditions
of Contract is also known as Engineer of the Contractor.
Environment
Surrounding air, water (both ground and surface), land, flora, fauna,
humans and their interrelations.
Environmental Compliance Certificate
A certificate of Environmental Compliance Commitment to which the
Proponent conforms with, after DENR-EMB explains the ECC conditions,
by

signing

the

sworn

undertaking

of

full

responsibility

over

implementation of specified measures which are necessary to comply


with existing environmental regulations or to operate within best

xxiii

Road Project Management and Supervision Manual Vol.1 Main Text

environmental practices that are not currently covered by existing laws. It


is a document issued by the DENR/EMB after a positive review of an ECC
application, certifying that the Proponent has complied with all the
requirements of the EIS System and has committed to implement its
approved Environmental Management Plan. The ECC also provides
guidance to other agencies and to LGUs on EIA findings and
recommendations, which need to be considered in their respective
decision-making process.
Environmentally Critical Area
An environmentally sensitive area declared through Proclamation 2146
wherein significant environmental impacts are expected if certain
types/thresholds of proposed projects are located, developed or
implemented in it. Updating of technical descriptions of ECAs is vested on
the DENR-EMB through Section 2-D of AO 42 (2002).
Environmentally Critical Project
Projects belonging to project types declared through Proclamation No.
2146 and Proclamation No. 803 which may pose significant negative
environmental impact at certain thresholds of operation regardless of
location. Updating of technical descriptions of ECPs is vested on the
DENR-EMB through Section 2-D of AO 42 (2002), in coordination with the
DTI as provided for in Section 3-A of AO 42.
Environmental Impact Assessment
Process that involves evaluating and predicting the likely impacts of a
project (including cumulative impacts) on the environment during
construction, commissioning, operation and abandonment. It also
includes designing appropriate preventive, mitigating and enhancement
measures addressing these consequences to protect the environment
and the communitys welfare.
Environmental Impact Statement
Document, prepared and submitted by the project Proponent and/or EIA
Consultant that serves as an application for an ECC. It is a comprehensive
study of the significant impacts of a project on the environment. It
includes an Environmental

Management

Plan/Program

that

the

Proponent will fund and implement to protect the environment.


Environmental Management Plan/Program
Section in the EIS that details the prevention, mitigation, compensation,
contingency and monitoring measures to enhance positive impacts and

Road Project Management and Supervision Manual Vol.1 Main Text

xxiv

minimize negative impacts and risks of a proposed project or undertaking.


For operating projects, the EMP can also be derived from an EMS.
Environmental Management Systems
Refers to the EMB PEPP EMS as provided for under DAO 2003-14, which
is a part of the overall management system of a project or organization
that includes environmental policy, organizational structure, planning
activities,

responsibilities,

practices,

procedures,

processes

and

resources for developing, implementing, achieving, reviewing and


maintaining an improved overall environmental performance.
Environmental Monitoring Fund
Fund that a Proponent shall set up after an ECC is issued for its project or
undertaking, to be used to support the activities of the multi-partite
monitoring team. It shall be immediately accessible and easily
disbursable.
Government Procurement Policy Board
The Government Procurement Policy Board established in accordance
with R.A.9184.
Head of the Procuring Entity
The head of the agency or his duly authorized official, for national
government agencies, or the local chief executive, for local government
units stated in the SCC. Provided that in a department, office or agency
where the procurement is decentralized, the head of each decentralized
unit shall be considered as the Head of the Procuring Entity subject to the
limitations and authority delegated by the head of the department, office
or agency.
IRR
The implementing rules and regulations to be promulgated in accordance
with Section 75 of R.A.9184.
IRR-A
"IRR-A" is promulgated pursuant to Section 74 of Republic Act No. 9184
(R.A. 9184), otherwise known as the Government Procurement Reform
Act (GPRA), for the purpose of prescribing the necessary rules and
regulations for the modernization, standardization, and regulation of the
procurement activities of the government. IRR-A shall cover all fully
domestically funded procurement activities from procurement planning
up to contract implementation and termination.
Negative Slippage

xxv

Road Project Management and Supervision Manual Vol.1 Main Text

A delay in work execution occurring when actual accomplishment falls


below the target as measured by the difference between the scheduled
and actual accomplishment of the Work by the Contractor as established
from the work schedule. This is actually described as a percentage of the
whole Works.
Notice to Proceed
Written notice issued by the DPWH to the Contractor requiring the latter
to begin the commencement of the work not later than the specified of
determinable date.
Permanent Works
All permanent structures and all other project features and facilities
required to be constructed and completed in accordance with this
Contract which shall be delivered to the DPWH and which shall remain at
the Site after the removal of all Temporary Works.
Project Engineer
In this Manual, Project Engineer means an Engineer appointed or
designated by the Employer (DPWH) to be responsible for the technical
operation and administrative supervision well-being of one or more
projects assisted by Resident Engineer in each project. The Project
Engineer serves as the link person between project field offices and
Employer (DPWH) Implementing Offices (IOs) or PMOs.
Special Provisions
The specifications prepared for specific terms of work or methods of
construction, measurement and payment under each contract, which are
not covered by the DPWH Standard Specifications.
Specifications
The description of Works to be done and the qualities of materials to be
used, the equipment to be installed and a method of construction.
Subcontractor
Any person or organization Who has subcontracted a part of the works of
the Contractor, as allowed by the DPWH, but not an assignee of such
person/organization.
Temporary Works
Works designed, constructed, installed, and removed by the Contractor
that are needed for construction or installation of the Permanent Works.
Tolerance
The allowable limits of variation from a specified measurement.

Road Project Management and Supervision Manual Vol.1 Main Text

xxvi

Unit Prices
These shall be prepared for each contract using costs based on
reasonable approved current prices as projected over the proposed
construction period, divided into local and foreign exchange costs, as the
case may be.
Work(s)
The Permanent Works and Temporary Works to be executed by the
Contractor in accordance with this Contract, including (i) the furnishing of
all labor, materials, equipment and others incidental, necessary or
convenient to the complete execution of the Works; (ii) the passing of
any tests before acceptance by the DPWHs Representative; (iii) and the
carrying out of all duties and obligations of the Contractor imposed in the
Contract.
Engineering Words -- Portland Cement Concrete Pavement
Admixture
A substance other than cement, water or aggregate added to a batch of
fresh concrete to alter one of the normal properties of concrete.
Batching Plant
The plant either on or off the work site where the materials are
assembled by batches for the mixer. Water and admixtures usually are
added as the batch is introduced into the mixer.
Coarse Aggregate
Aggregate which is retained on the No.4 (4.75 mm) sieve.
Contraction Joint
A joint which controls the location of a transverse crack and permits the
slab to contract and expand with changes in temperature.
Dowel or Dowel Bar
A smooth steel bar extending across a concrete joint to transfer the
applied load, prevent future misalignment of the slab and permit
movement at the joint.
Dowel Assembly
A cage or basket used to hold dowels in position during placement of
concrete.
Expansion Joint
A joint adjacent to a bridge or intersection to absorb expansion of
concrete pavement and prevent expansive pressure on the bridge or
intersecting pavement.

xxvii

Road Project Management and Supervision Manual Vol.1 Main Text

Joint Sealer
A compound for preventing entrance of water and solid particles into a
joint. The sealer may either be performed or liquid.
Longitudinal Joint
A joint which extends lengthwise in the roadway, parallel to the
centerline.
Segregation
The unintentional separation of the larger pieces of aggregate from the
smaller pieces within one size of aggregate or within a mixture of sizes of
fresh concrete.
Slip-Form Paving
Concrete paving by use of a machine carrying its own forms between
which low slump concrete is compacted sufficiently to retain its shape
after the machine has progressed onward.
Tie Bar
A deformed dowel or hook-bolt placed across longitudinal joints of
concrete pavement near middle depth to tie the slabs together and hold
the joint closed.
Engineering Words -- Asphalt Concrete Pavement Aggregate
Mineral material, such as sand, gravel, crushed stone, slag, or
combinations thereof.
Asphalt Concrete
A mixture of aggregate and asphalt binder (Bitumen).
Asphalt Binder (Bitumen)
A thermoplastic binding material obtained as a residue in the distillation
of petroleum, which may contain additives to enhance performance.
Coarse Aggregate
Aggregate which is retained on the No.4 (4.75 mm) sieve.
Cut Back Asphalt
Asphalt binder which has been rendered fluid by fluxing it with a light
volatile petroleum distillate. Upon exposure to atmospheric conditions,
the volatile distillate evaporates, leaving only the asphalt cement which
reverts to its original semi-solid condition. Cut back asphalts are classified
as rapid curing (RC), medium curing (MC), or slow curing (SC).
Emulsion (Asphalt)
A suspension of extremely small droplets of asphalt in water in the

Road Project Management and Supervision Manual Vol.1 Main Text

xxviii

presence of an emulsifying agent, which usually is a type of soap. Upon


exposure to atmospheric conditions, the water evaporates, leaving only
the asphalt cement which has been modified by the emulsifying agent.
Emulsions are classified as rapid setting (RS or CRS), medium setting (MS
or CMS), or slow setting (SS or CSS).
Job Mix Formula (JMF)
The mix composition of an asphalt concrete approved by the Laboratory.
The job mix formula (JMF) of a mix can be generally obtained from
Marshal Stability Test.
Marshall Mix Design
Volumetric mix design procedure used to establish the optimum Asphalt
binder content for an asphalt concrete.
Prime Coat
An application of asphalt material made on the surface of a pavement
layer for the purpose of binding the surface particles together.
Tack Coat
An application of asphalt material made on a pavement surface for the
purpose of bonding the existing course to the overlying course.

xxix

Road Project Management and Supervision Manual Vol.1 Main Text

Chapter 1 Introduction
1.1 Background
The Department of Public Works and Highway, hereinafter referred to as "DPWH" and
Japan International Cooperation Agency, hereinafter referred to as "JICA", agreed in 2006 to
implement the project for Improvement of Quality Management for Highway and Bridge
Construction and Maintenance, hereinafter called as " Phase I", aiming to enhance the
engineering knowledge of the Engineers of DPWH.
For the implementation of the said project, DPWH organized the Joint Coordinating
Committee, hereinafter called as "JCC", Technical Working Group, hereinafter called as
"TWG" and Counterpart Working group, hereinafter called as "CWG". On its part, JICA
dispatched the JICA Technical Cooperation Project Team, hereinafter referred to as "JICA
TCP Team" from February 2007 to February 2010.
Under Phase I, the following manuals/guidelines were prepared and issued for road
construction and maintenance through the CWG's activities.
*

Guidebook for Road Construction and Maintenance Management in the Republic of


the Philippines,

Road Project Management and Supervision Manual, Volume I: Main Text and

Road Project Management and Supervision Manual, Volume II: Appendices (Standard
Form, Examples and References)

From October 2011 to September 2014, the DPWH and JICA TCP Team -newly
dispatched by JICA - implemented the project for Improvement of Quality Management for
Highway and Bridge Construction and Maintenance, Phase II, hereinafter called as " Phase II"
to aim further enhancement.
This manual, Road Project Management and Supervision Manual, Volume I: Main Text,
Second Edition, was prepared under Phase II through the revision work done by CWG based
on the Road Project Management and Supervision Manual, Volume I: Main Text, 1st Edition
mentioned above.
The Volume I 1st Edition was a revision of the Road Construction Manual which was
published in 1990 and subject to be updated every 5 to 10 years. Thus, it was reviewed and
updated in Phase II.

1.2 Purpose
Engineers of the DPWH concerned with road construction and management are the main
targets of this Manual. The CWG made efforts to make this Manual 2nd Edition easy to

Road Project Management and Supervision Manual Vol.1 Main Text

1-1

understand by the Engineers, hence, it would be an effective tool related to the above areas.

1.3 Outline
This Manual serves as reference in order to achieve quality projects within the scheduled
time and budget as specified in the Contract. It includes project management and road
construction supervision information and techniques applicable to both development projects
and maintenance programs as illustrated below. It covers both locally-funded and
foreign-funded projects and programs undertaken by contract and is also useful for
maintenance activities undertaken by Administration - Maintenance by Administration
(MBA), Design-Bid-Build (DBB) and Design-Build (DB) contracts.
Table 1.1

Classifications of Projects and Programs


DPWH Implementing Office

Funding

Foreign-Funded
Projects
(WB, ADB, JICA,
etc.)

Locally-Funded
Projects
(GAA, MVUC, etc.)

Category

Central Office

Development Projects
(New Construction/ Upgrading/
Rehabilitation)

PMOs

BOM

ICB
Projects

ICB
Projects

Maintenance Programs
(Preventive & Routine)

BOC

LCB
Projects

Development Projects
(New Construction/ Upgrading/
Rehabilitation)

LCB
Projects

Maintenance Programs
(Preventive & Routine)

Legend: ICB: International Competitive Bidding,

ROs

DEOs

LCB
Projects
LCB
Projects

LCB
Projects

LCB
Projects

LCB
Projects

LCB: Local Competitive Bidding

The Manual is composed of two (2) volumes: a) Volume I - Main Text and b) Volume II
- Sample Forms and Documents.

1-2

Road Project Management and Supervision Manual Vol.1 Main Text

Chapter 2 Contracts and


Guidelines
2.1 Locally-funded Contract
The DPWH conducts the project design thru Force Account or employ Consultants and
procures civil works through bidding. The Contractor executes the project in accordance with
the Contract. This type of contract is called as Design-Bid-Build (DBB) Contract.

2.2 Foreign-funded Contract


The Japan International Cooperation Agency (JICA), World Bank (WB) and Asian
Development Bank (ADB) are the major partners of the DPWH in its road sector
development projects. Likewise, with the assistance of the World Bank, the DPWH has
initiated the National Roads Improvement and Management Program (NRIMP) and plans to
further enhance/improve the implementation of said program with the assistance and
cooperation of JICA and ADB . The following are being adopted in the implementation of the
NRIMP:
-

Asset Management Approaches

Long-Term Performance Based Maintenance (LTPBM)

Design-Build (DB) Contract

Value Engineering

2.2.1 Asset Management Approach


The asset management approach is effective for sustainability of road facilities and
services. Asset management can be defined as a comprehensive and structured approach to
the long term management of assets as tools for the efficient and effective delivery of
community benefits or systematic process of effectively maintaining, upgrading and
operating assets, combining engineering principles with sound business practice and
economic rationale. The priority is given to maintenance (preventive and routine
maintenance) of the existing facilities rather than new construction as illustrated in the
following figure:

Road Project Management and Supervision Manual Vol.1 Main Text

2-1

Figure 2.1

Asset Management Approach

2.2.2 Long-Term Performance Based Maintenance


The ongoing LTPBM under NRIMP is a contract implementation method applying
performance based specifications. The contractor is responsible for keeping road function and
quality through maintenance for multiple years after construction. Performance characteristics
may include end-result elements such as product strength, bearing capacity, stability, visibility,
and crack-free, as well as more functional requirements such as smoothness, friction, noise
reduction, chip retention, splash, and spray.
Under NRIMP, the contracts will be predominantly of the hybrid type including
rehabilitation and structural overlays with the standard routine and preventive maintenance
(both backlog and performance-based) interventions. Shoulder re-grading, side-slope
maintenance, side and cross drainage structure cleaning and maintenance, and maintenance of
road marking and roadside signs will be part of the performance-based phase. The
rehabilitation, structural overlays and other backlog maintenance items to be undertaken in the
first year of the contract will be paid on an item-rate basis, and the performance-based
component will be paid on a periodic lump-sum basis in relation to specified performance
standards and rectification.
(1)

Scope of LTPBM Contract


The LTPBM projects under the Road Enhancement and Asset Preservation
Management Program (REAPMP) are of a hybrid type, which includes a combination of
rehabilitation, preventive maintenance, backlog maintenance, routine maintenance and
road safety. Scopes of contract are as follows:

2-2

Road Project Management and Supervision Manual Vol.1 Main Text

Table 2.1
Rehabilitation

Scope of LTPBM Contract

Reconstruction will be applied to paved road sections which are


assessed to be in bad condition. It also involves restoring them to their
original condition as designed and constructed.
The major works include partial reconstruction, replacement of
shattered concrete pavement slabs and Asphalt Concrete (AC) overlay
(single or 2 layers) on the existing pavement. The works also include
drainage, improvement and slope and scour protection works.

Preventive

Asphalt overlay on paved road sections in fair and poor condition to

Maintenance

improve surface condition and/or strengthening the existing pavement


structures. Thickness of AC overlay will also be planned for roads in
good condition as it is expected to deteriorate and subject to fair
condition during 5-year contract period.

Backlog Maintenance

Restoration of shoulders, reconditioning or provision of new drainage,


and minor improvements such as localized slope protection.

Routine Maintenance

Maintaining the road condition through routine repairs including


pothole patching, sealing of cracks on pavement, shoulder grading,
drainage cleaning, vegetation control, road markings maintenance and
bridge maintenance.

Road Safety

Road safety works include installation of road safety facilities (guard


rails, guide posts, warning and information signs), road marking and
public information.

(2)

Performance Indicators of LTPBM


Performance standards/requirements represent the desired level of performance or
output of the of Long Term Performance-Based Maintenace Enhancement (LTPBME)
road link, in terms of quality, quantity, timeliness and other aspects of the output and
service, against which the actual output will be measured and compared. The objectives
of performance standards/requirements are (a) to satisfy the road users in terms of
accessibility, comfort, travel speed and safety; (b) to minimize the total road system cost,
including cost to road users and the DPWH over the life cycle cost of the assets; and (c)
to minimize environmental impacts. The LTPBME roads should aim to achieve good to
fair conditions only. The following table indicates road condition categories to be
adopted for the LTPBM.

Road Project Management and Supervision Manual Vol.1 Main Text

2-3

Table 2.2
Road

Road Condition Category

General condition

Condition

Treatment Measure

New pavement or with slight minor Little or no maintenance required.


defects (pop-outs, map cracking, partial
loss of joint

Good

First signs of cracks (all tight); First utility Needs joint and cracking sealing (routine
patch; moderate scaling in some locations. maintenance).
Moderate to severe scaling/raveling, Needs some partial/full depth repairs
spalling or rutting over 25% of the surface. grinding and/or asphalt overlay to correct

Fair

Moderate settlement, several narrow surface defects.


cracks
Many cracks, open and severely spalled. Needs extensive full depth patching plus
Severe faulting, spalling or rutting. some full slab replacement (for concrete).

Poor

Extensive patching in fair to poor


condition, Moderate settlement
Extensive cracking severely spalled and Needs

Bad

to

rebuild

pavement/total

patched (in poor condition). Severe and reconstruction.


extensive settlements/potholes

Table 2.3

International Roughness Index and Road Condition Category


Surface

Road
Condition

Asphalt Concrete

VIC

Cement Concrete

Gravel

Ranges in

Category

Range

Rep. Value

Range

Rep. Value

Range

Rep. Value

ROCOND

Good

3.0 or less

2.5

4.0 or less

3.5

6.0 or less

5.0

1 to 20

Fair

3.1 to 5.0

4.0

4.1 to 6.0

5.0

6.1 to 9.0

7.5

20.1 to 40

Poor

5.1 to 7.0

6.0

6.1 to 8.0

7.0

9.1 to 12.0

10.0

40.1 to 70

Bad

> 7.0

8.0

> 8.0

9.0

> 12.0

14.0

70.1 to 100

Source: PMS, DPWH

The intervention IRI for the overlay should be defined based on a pavement
deterioration curve reflecting the existing pavement strength and soundness, traffic level
and function of the road. Even if the current road condition is good, it would require PM
if it accommodates heavy truck traffic. The following table shows typical intervention
pattern on LTPBM Road.

2-4

Road Project Management and Supervision Manual Vol.1 Main Text

Table 2.4

Typical Intervention Pattern on LTPBM

Year
1
2
3
4
1
Fair
Good
Good
Fair*
RM*2
PM
RM
RM
Fair
Fair
Fair
Good
Good
RM
RM
PM
RM
Good
Fair
Fair
Fair
RM
RM
RM
PM
Fair
Good
Good
Good
Fair
PM
RM
RM
RM
Poor
Good
Good
Good
Poor
RH
RM
RM
RM
Bad
Good
Good
Good
Bad
RH
RM
RM
RM
1
* : Road Condition Category, Good, Fair, Poor and Bad
*2: Corresponding Rehabilitation and Maintenance Work
(RH: Rehabilitation, PM/O: Preventive Maintenance/Overlay,
RM: Routine Maintenance)

Road
Condition

(3)

5
Good
RM
Good
RM
Good
RM
Fair
RM
Fair
RM
Fair
RM

Design-Build (DB) Contract


The DPWH has recently introduced DB contract under the WB-financed NRIMP-I and II

and will be enhanced under the road sector projects financed by JICA and ADB. The above
LTPBM is a new project implementation scheme combined with the DB method as it is able
to give the design and construction responsibility to the Design-Build Contractor. The
preliminary design is still required for defining the project concept and cost for the DB
contract bidding.
Many highway agencies have been experimenting with a wide variety of innovative
project delivery strategies aimed at lowering the costs and time to produce highway
construction and rehabilitation projects while maintaining or improving project quality. One
of these strategies is the DB project delivery. DB is a method of project delivery in which the
design and construction phases of a project are combined into one contract, usually awarded
on either a low bid or best-value basis. This is in contrast to the more traditional
Design-Bid-Build (DBB)1 approach having been used in the DPWH that outsourced project
design work, or conducted it by own administrative force. The two different contracting
efforts must be undertaken in sequence to procure architecture/engineering services.

1 Design-Bid-Build: The DPWH conducts design of road project by Force Account or employing Consultant at
first and procures civil works contractor through bidding. After that, the Contractor executes the project in
accordance with the contract.

Road Project Management and Supervision Manual Vol.1 Main Text

2-5

Section 17.6 of the Implementing Rules and Regulations - Part A (IRR-A) of Republic
Act 9184 recognizes the use of design and build scheme in the procurement of infrastructure
projects. The following table shows the general advantages and disadvantages of
Design-Build Contract.
Table 2.5

Advantages and Disadvantages of Design-Built Contract


Advantages

Disadvantages

One Contractor bears all risks and -

Too much discretion given to Contractor

responsibilities

Difficulty in predicting the final cost

Reduced design and construction periods -

The end result may not exactly be in

and final project cost

accordance with what the procuring

Assured quality of the structure

entity required

Source: Government Procurement Policy Board (GPPB)

The following figure shows sequence of project delivery activity by Contract Approaches,
DBB and DB. It is generally said that the DB approach could save overall project
implementation time compared with conventional DBB approach.
Design-Build Scheme
Concept Preliminary Select
Planning
DesignDesign
Builder

Final Project Design


& Clearances

Construction

Extensive Contractor
Input

Minimal to Extensive
Contractor Input

Design-Build Associated
Time Savings

Design-Bid-Build Scheme
Concept Select
Preliminary
Planning Designer
Design

Final Project Design


& Clearances

Select
Contractor

Minimal Contractor
Input

Construction

Extensive Contractor
Input

Source: GPPB
Figure 2.2
(4)

2-6

Sequence of Project Delivery

Value Engineering

Road Project Management and Supervision Manual Vol.1 Main Text

Value Engineering is defined as the systematic application of recognized techniques by a


multi-disciplined team to identify the function of a product or service, establish a worth for
that function, generate alternatives through the use of creative thinking, and provide the
needed functions to accomplish the original purpose of the project, reliably, and at the lowest
life-cycle cost without sacrificing safety, necessary quality, and environmental attributes of the
project.
More simply, it is defined as

Value = Function / Cost

Value Engineering is a tool applicable in various stages of project development such as


functional analysis, feasibility study and evaluation matrix (multi-criteria matrix). This is
more effective in large and/or complicated projects but not for simple and small projects.

2.3 Guidelines, Manuals and Practices


2.3.1 Basic Guidelines and Manuals
The relations of basic guidelines for procurement and project implementation for the
road infrastructures under the DPWH are illustrated in the following figure:

Handbook on Philippine
Government
Procurement (R.A.9184
and Amended IRR-A of
R.A.9184 )_Y2007

Republic Act (R.A.) 9184_Y2003

Implementing Rule
and Regulations
Part A (IRR-A) of
R.A.9184 for
Locally-funded
Projects_Y2004

Implementing Rule
and Regulations
Part B (IRR-B) of
R.A.9184 for
Foreign-funded
Proejcts

Philippine Bidding Documents (PBDs)


Part II_Y2005
DPWH Procurement
Manual (DPM) for
Locally-funded projects,
Volume III _Y2006

Locally-funded Projects

Figure 2.3

Loan Agreement
and Procurement
Guide Lines of
Funding Bank or
Agency

FIDIC Harmonized
Edition for the
Multilateral
Development
Banks
(MDB)_Y2006

Foreign-funded Projects

Procurement and Contract Guidelines

The category, name of the documents, version (year issued) and issuing
agency/organization, to be used for the road and bridge projects of DPWH in this manual are

Road Project Management and Supervision Manual Vol.1 Main Text

2-7

shown in the following table:


Table 2.6
Category
Procurement

Construction
Contract

Design
Guidelines
and Drawings

Reference Guidelines and Manuals

Name of Documents

Issued by

Year Issued

Remarks

Handbook on Philippine
Government Procurement (R.A.9184
and Amended IRR-A of R.A.9184)

GPPB

Sep. 2007

IRR-A is for domesticallyfunded procurement.


IRR-B is for foreign- funded
procurement but still under draft
Included Standard Bidding
Forms and Bidding Documents

DPWH Procurement Manual for


Locally- Funded Infrastructure
Projects through Public Bidding
Conditions of Contract for
Construction for Building and
Engineering Works designed by the
Employer (The MDB Construction
Contract)
Conditions of Contract for Design,
Build and Operate Projects
GCC-Philippine Bid Documents
(PBDs)
Standard Specifications 2013,
Volume II, Highways, Bridges and
Airports (Blue Book)
Volume I&II, Design Guidelines,
Criteria and Standards (Red Book).
Part 1: Survey and Investigation, Part
2: Hydraulic Design, Part 3:Highway
Design and Part 4: Bridge Design
Technical Standard and Guidelines
for Planning and Design, Volume
1-Flood Control, Volume 3-Erosion
& Sediments Control, Volume
4-Natural Slope Failure
Countermeasures
Guide I - Risk Management, Guide
II Inventory Survey and Risk
Assessment and Guide III Road
Slope Protection
Standard Drawings for Roads and
Bridges

DPWH

Jan. 2006

FIDIC

Mar. 2007

World Bank and ADB still use


1987/1992 or 1999 edition
Construction Contract (Red
Book)

FIDIC

2007 Edition

GPPB

May 2005

Revision to 1999 Design-Build


Conditions of Contract
Part II, Section III-GCC

DPWH

2013

DPWH

1989

PMO-FCSEC
& JICA

2003

JICA

2007

DPWH

1989

Under review by BOD/DPWH

Under Review by BOD/DPWH

2.3.2 Standard Procurement and Implementation Guidelines


Republic Act 9184 and the following guidelines shall govern the procurement and
implementing contracts for government procurements:

2-8

Road Project Management and Supervision Manual Vol.1 Main Text

Table 2.7
Guidelines
1.

DPWH Procurement Manuals

Content

Remarks

Handbook on Philippine

Includes amended IRR-A of R.A. 9184 Subject to

Government Procurement (4th

and Latest GPPB3 issuances

updating.
Concerned

Edition)

Office: *BAC
2.

Philippine Bid Documents(PBDs), Bid procedures and practices of R.A.

Subject to

Procurement of Works, 2nd

updating

9184, harmonized with ADB, JICA

Edition

and WB

Concerned
Office: *BAC

3.

4.

DPWH Procurement Manual for

Procurement Guidelines, Manuals,

Subject to

Locally-funded Infrastructure

Standard Forms, Standard Bid

updating

Project through Public Bidding

Documents in compliance with IRR-A

Concerned

of R.A.9184

Office: *BAC

DPWH Procurement Manual for

Procurement Guidelines for Goods in

Subject to

Goods through Public Bidding

compliance with IRR-A of R.A. 9184

updating
Concerned
Office: *BAC

*DPWH Bids and Awards Committee (BAC)

Input
for Procurement of Goods
(Volume II)

Figure 2.4

DPWH Procurement Manuals Cover Pages

The above Philippine Bid Documents (PBDs) include unchanged provisions in Section II
- Eligibility Documents of Part I; and Section I - Instructions to Bidders and Section III General Conditions of Contract of Part II. Data and provisions specific to each procurement

2 As defined by Federal Highway Administration (FHA), USA


3 GPPB: Government Procurement Policy Board
4 In case of International Competitive Bidding (ICB) funded by ADB, JICA or WB, the use of the respective
standard bid documents of these banks shall be required.

Road Project Management and Supervision Manual Vol.1 Main Text

2-9

and contract should be included in the Section III - Eligibility Data Sheet of Part I, Section II Bid Data Sheet, and Section IV - Special Conditions of Contract of Part II.
The DPWH Procurement Manual is the specific manual complying with IRR-A of
R.A.9184 but suit the particular needs of the DPWH. The Manual shall be applied to the
entire DPWH organizations, including Central, Regional, District Engineering and other
offices. Volume 2 shall be used for goods, Volume 3 for infrastructure projects and Volume 4
for consulting services.

2.3.3 International Standard Practices


The Construction Contract of International Federation of Consulting Engineers (FIDIC) also known as Red Book - has been adopted as standard contract documents for building and
engineering works designed by the Employer or by his representative (the Engineer) for
international contracts.
The Federation produced the Harmonized Edition for the Multilateral Development
Banks (MDB) 5, including Word Bank and Asian Development Bank, in 1999 of which the
latest edition was released in March 2006. This MDB Harmonized Edition also includes
sample forms for Contract Data, Securities, Bonds, Guarantees and Dispute Board
agreements.
In general, this harmonized document follows earlier FIDIC risk sharing principles for
the type of contract for which they were prepared. In most cases, the amendments which have
been made to produce the MDB Harmonized Edition of the FIDIC General Conditions of
Contract for Construction are those arising from the requirements of the MDB.
For projects, including JICA-financed projects, that are not participating in the MDB,
FIDIC Conditions of Contact for Works of Civil Engineering Construction (4th Edition of
1987, reprinted 1992) or FIDIC Conditions of Contract for Construction 1999 (1st Edition)
should be used for construction of such works where tenders are invited on an international
basis. The 1999 version is based on more equal right and risk sharing between the Employer
and the Contractor.
The Conditions, subject to minor modifications with the Special Conditions, may also be
applicable for domestic contracts financed by WB, ADB and JICA. The FIDIC documents are
comprised of Part I - General Conditions with forms and agreement and Part II Condition of
Particular Applications with guidelines for the preparation of Part II clauses.
5 FIDIC Harmonized Edition for the MDB (2006) is downloadable from the Home Page of FIDIC and the
World Bank. The MDB members are WB, ADB, African Development Bank, Black Sea Trade and Development
Bank, Caribbean Development Bank, European Bank for Reconstruction and Development, Inter-American
Development Bank, Islamic Bank for Development Bank and Nordic Development Fund.

2 - 10

Road Project Management and Supervision Manual Vol.1 Main Text

It should be noted that either FIDIC Conditions of Contract for Design, Build and
Operate Projects 2007 or MDB Harmonized Edition Conditions for Construction is applicable
to design-build contracts.

FIDIC MDB Harmonized Edition Conditions of


Contract

Figure 2.5

FIDIC 1987/1992 Conditions of Contract

FIDIC Conditions of Contract Cover Pages

2.3.4 Standard Practices of DPWH


(1)

Foreign-funded Projects
Procurement methods of Contractors for foreign-funded projects and programs are
specified in the Loan Agreement and/or in the Minutes of Discussion between these
development partners and DPWH, or in the procurement guideline of each bank or
agency.
Procurement methods are as follows:
*

Procurement through International Competitive Bidding

Procurement through Local Competitive Bidding

Negotiated contracts

Conditions of Contract for the ICB projects funded by these international banks
shall follow FIDIC Contract Conditions as agreed by funding agencies. The General
Conditions (GC) of projects is recopying of Clauses in the FIDIC GC but adjustments or
modifications shall be made to meet the requirements in R.A.9184 as far as it is not
contradicting with the agreement of the funding banks. The GCs is comprised of 20
clauses, sub-clauses and appendices. Disputed Board in the case of MDB Harmonized
Edition March, 2006.
Under foreign-funded projects, the Employer is the DPWH represented by the
Secretary or Undersecretary (signatory of the subject Contract) in general. The Engineer
is the Consultant employed by DPWH and notified in the Contract Data of civil works in

Road Project Management and Supervision Manual Vol.1 Main Text

2 - 11

the bid documents.


In general practice of the DPWH, the Employers representative is the Director of
Project Management Office (PMO) or the Project Manager appointed by the PMO and
stationed at site. The Engineers representative is the Project Manager (or Resident
Engineer) assigned by the Consultant and approved by the Employer. The Contractors
representative is the Project Manager (or Superintendent) nominated by the Contractor
and approved by the Engineer and/or the Employers representative.
In the FIDIC General Conditions of Contract (GCC), Subcontractor means any
person named in the Contract as a subcontractor, or any person appointed as a
subcontractor, for a part of the Works, and the legal successors of the authorized
Contractor.
The Conditions of Contract for LCB projects funded by these international banks
will be the same or similar to locally-funded projects as long as these are not
contradicting loan agreement and procurement guidelines.
(2)

Locally-funded Projects
All Government procurement shall be governed by principles of transparency,
competitiveness, streamlined procurement process, accountability and public monitoring
in accordance with R.A.9184 and its Implementing Rules and Regulations - Part A.
The IRR-A is promulgated pursuant to Section 75 of R.A. 9184 for the purpose of
prescribing the necessary rules and regulations for the modernization, standardization,
and regulation of the procurement activities of the government. This IRR-A shall cover
all locally funded procurement activities from procurement, planning up to contract
implementation and termination.
The DPWH Procurement Manual (DPM) for locally-funded infrastructure projects
through public bidding was approved by GPPB in January 2006and comprised of:
Volume I:

Guidelines on the Establishment of Procurement System and


Organizations in the DPWH

Volume II:

Guidelines on Goods

Volume III:

DPWH Manual of Procedures for the Procurement of Locally-funded


Infrastructure Projects through Public Bidding

Annex A

Standard Forms

Annex B

Standard Bid Documents

The following table shows a comparison of the General Conditions of Contract


between FIDIC and Section III,Part II of Philippine Bid Documents from which the GCC
of DPWH has originated.

2 - 12

Road Project Management and Supervision Manual Vol.1 Main Text

Table 2.8 Comparison of GCC between FIDIC and DPWH Conditions of Contract
FIDIC General Conditions
(MDB Harmonized Edition 2006)
Clause
No

Clause Title

General Provisions

The Employer

3
4

The Engineer
The Contractor

5
6
7

Nominated Subcontractors
Staff and Labour
Plant, Materials and
Workmanship
Commencement, Delays and
Suspension

9
10
11

Tests on Completion
Employers Taking Over
Defects Liability

12
13

Measurement and Evaluation


Variation and Adjustments

14

Contract Price and Payment

15

Termination by Employer

16

Suspension and Termination by


Contractor
Risk and Responsibility
Insurance
Force Majeure
Claims, Disputes and Arbitration

17
18
19
20

Philippine Bid Documents ,


Section III/Part II, GCC* and DPWH GCC*
Section No. and Section Title
1. Definitions
4. Communications
2. Interpretation
5. Possession of Site
3. Governing Language and Law
10. Site Investigation Reports
11. Site Investigation Reports
13. PROCURING ENTITYs Risk 6
22. PROCURING ENTITYs Representatives Decisions
23. Approval of Drawings and Temporary Works by the PROCURING
ENTITYs Representative
33. Instructions, Inspections and Audits
6. The Contractors Obligations
7. Performance Security
12. Contractors Risk and Warranty Security
8. Sub-Contracting

9. Liquidated Damages
24. Acceleration and Delays
Ordered by the PROCURING
ENTITYs Representative
25. Extension of the Intended
Completion Date

29. Early Warning


30. Program of Work
31. Management Conferences
43. Contract Completion
44. Suspension of Work
46. Extension of Contract Time
48. Completion

49. Taking Over


34. Identifying Defects
35. Cost of Repairs
36. Correction of Defects
37. Uncorrected Defects
26. Right to Vary
28. Dayworks
42. Variation Orders
32. Bill of Quantities
40. Payment Certificates
38. Advance Payment
41. Retention
39. Progress Payments
47. Price Adjustment
16. Termination for Default of PROCURING ENTITY
18. Procedures for Termination of Contracts
45. Payment on Termination
15. Termination for Default of Contractor
17. Termination for Other Causes
14. Insurance
19. Force Majeure, Release from Performance
20. Resolution of Disputes
27. Right to Vary
21. Suspension of Loan, Credit, Grant, or Appropriation
50. Operating and Maintenance Manuals

* The same GCC in PBDs and DPM/DPWH.

6 PROCURING ENTITY is the DPWH in the DPWH contracts.

Road Project Management and Supervision Manual Vol.1 Main Text

2 - 13

(3)

Design-Build Projects
The DB Contract for infrastructure projects is a new scheme in the Philippines and
should be implemented in accordance with the Guidelines and Standards for the
Procurement and Implementation of Contracts for Design and Build Infrastructure
Projects under IRR-A of RA 9184.

2 - 14

Road Project Management and Supervision Manual Vol.1 Main Text

Chapter 3

Implementing
Organizations and
Role of Entities

3.1 Organization of Central Office


The DPWH is one of the three departments of the government undertaking major
infrastructure projects. The DPWH is mandated to undertake (a) the planning of infrastructure,
such as roads and bridges, flood control, water resources projects and other public works, and
(b) the design, construction, and maintenance of national roads and bridges, major flood
control systems and other infrastructure projects. The DPWH functions as the engineering and
construction arm of the Government and responsible for the planning, design, construction
and maintenance of infrastructure, especially the national highways, flood control and water
resources development system, and other public works in accordance with national
development objectives.
The DPWH has its Central Office (CO) at Manila and 16 Regional Offices (ROs) and
182 District Engineering Offices (DEOs) throughout the country. Figure 3.1 illustrates the
organizational chart of DPWH CO as of October, 2013.
The Bureaus and Offices which are directly administrating and implementing projects as
representative of the DPWH or which are providing major support services for the project
implementation are shown in Table 3.1.
The actual implementation of projects shall be done by the concerned DEO including the
projects that are bid out and contracted by the ROs in accordance with applicable approved
Department orders (DO 24, Series of 2007 Re: Amended Omnibus Levels of Authorities of
Official of the DPWH and further amendments).

Road Project Management and Supervision Manual Vol.1 Main Text

3-1

3-2

Road Project Management and Supervision Manual Vol.1 Main Text

Design Management
Division

Building Division

Bridge Division

Highways Division

Surveys and
Investigation Division
Water Project Division

Bureau of Design

Supply and Property


Management Division
Facilities Maintenance
Division

Human Resource
Management Division
Capacity Development
Division
Cash Division

Human Resource and


Administrative
Service

Construction Support
Services Division
Project Monitoring
Division

Pre-Construction
Division
Claims Review Division

Bureau of
Construction

Management Division

Accounting Division

Budget Division

Financial and
Management Servise

Figure 3.1

Road Condition
Monitoring and
Evaluation Division
Policies and Standards
Division
National Building
Services Division
Safety and Disaster
Management
Coordination Division

Bureau of
Maintenance

Environmental and
Social Safeguards
Division
Statistic Division

Development Planning
Division
Project Preparation
Division
Programming Division

Planning Service

Stakeholders Affairs
Division
Public Informations
Division

Equipment Planning
Division
Equipment Operation
and Maintenance
Division
Floating Equipment
Division

Bureau of
Equipment

Internal Audit Service


Operations Audit Division
Management Audit Division

Research and
Development Division
Standards
Development Division
Materials Testing
Division
Technical Services
Division

Bureau of
Research and
Standards

Project Development
Division
Project Implementation
Supervision Division
Project Operation and
Maintenance
Management Division

Public-Private
Partnership Service

Consultancy Services
Division
Goods and Services
Division

Civil Works Division

Procurement
Service

Quality Systems
Analyst Division
Quality Compliance
Division
Road Safety Program
Division
Traffic Engineering
Division

Bureau of
Quality and Safety

Project Managers' Pool


Road Management Division (Multilateral)
Road Management Division (Bilateral)
Bridge Management Division
Flood Control Management Division
Building and Special Projects
Management Division

Unified Project Management Office

Stakeholders
Relations Service

Organizational Chart of DPWH CO

District
Engineering
Offices (182)

Application Support
Division
Technology Support
Division
Business Innovation
Division
User Support Division

Information
Management Service

Regional
Offices (16)

Legislative Affairs and


Research Division
Right-of-Way
Acquisition and
Enforcement Division
Contract Letting and
Litigation Division

Internal Affairs Division

Legal Service

Office of the Secretary

Table 3.1
Project

Bureaus' Roles and Functions

Bureau/Office

Role / Function

Bureau of Construction

Technical Service on Development projects (New

Implementation

Construction, Up-grading and Rehabilitation)


and Implementation
Bureau of Maintenance

Technical Service on Maintenance


projects/programs
(Preventive Maintenance, Backlog Maintenance,
Routine Maintenance and Emergency
Maintenance)

Project Management

Implementation of Foreign-funded development

Office

projects (New Construction, Up-grading and


Rehabilitation)*

Bureau of Quality and

Implements policies for the purpose of ensuring

Safety

the safety of all infrastructure facilities, securing


the highest quality in construction.

Implementation

Planning Service

Technical services relating to public works and

Support

highways infrastructure, planning, programming

Services

and project development.


Bureau of Research and

Identification of the appropriate standards to be

Standards

used and provision of guidelines and standards.

Bureau of Design

Supervises and review the results of field surveys.


Review and evaluate the preparation of schemes,
designs, specifications, estimates, tender contract
documents.

*PMO is currently undertaking some locally-funded projects.

3.1.1 Bureau of Construction (BOC)


The BOC reviews, evaluate programs, estimates, contracts, progress reports of the
DPWH projects, as well as inspects, checks and monitor construction projects of the DPWH
implementing offices and other agencies. The BOC has four (4) divisions per approved
RATPLAN, namely: 1) Pre-construction, 2) Claims Review, 3) Construction Support Services,
and 4) Project Monitoring. The BOC also implements projects beyond the limit of authority of
the Regional Director with prior approval of the Secretary of DPWH.

Road Project Management and Supervision Manual Vol.1 Main Text

3-3

Figure 3.2

Organizational Chart of BOC

The BOC provides technical services on construction works in accordance with DO No.
95, Series of 20031 Re: Responsibilities of BOC and BOM, as follows:
*

Formulate policies relating to construction and contract management;

Review and evaluate construction programs, estimates and other contract documents;

Inspect, check and monitor construction works supervision activities of field


implementing offices to ensure that such activities are conducted in accordance with
the DPWH standards and guidelines; and

Provide special support to implementing field offices on construction management and


contract administration.

Latest issuance shall prevail.

3-4

Road Project Management and Supervision Manual Vol.1 Main Text

3.1.2 Bureau of Maintenance (BOM)


The BOM is primarily tasked with the maintenance of the nation's infrastructures and
also engaged in the continuous upgrading of the technical skill of its personnel through the
conduct of relevant technical courses and seminars. Field inspections are also conducted to
effectively monitor maintenance activities of the Regional and District offices.

Figure 3.3

Organizational Chart of BOM

The BOM provides technical services on the maintenance and repair of infrastructure
and facilities in accordance with DO No. 95 Series of 2003 Re: Responsibilities of BOC and
BOM, as follows:
*

Formulate policies relating to maintenance of infrastructure and facilities;

Review and evaluate maintenance programs, estimate and other contract documents;

Inspect, check and monitor maintenance activities of field implementing offices to


ensure that such activities are conducted in accordance with the DPWH standards and

Road Project Management and Supervision Manual Vol.1 Main Text

3-5

guidelines; and
*

Provide special support to implementing field offices on maintenance management


and contract administration.

3.1.3 Project Management Office (PMO)*


The five (5) specialized clusters and the PMOs to be absorbed by each cluster are as
follows:
(1)

Bridges Management Cluster


-

Foreign-Assisted Bridge Program (FABP-PMO)

Special Bridge Project (SBP-PMO)

(2)

Flood Control Management Custer


-

Kalookan Malabon Navotas Valenzuela (KAMANAVA-PMO)

Major Flood Control Development Project 1 (MFCDP 1-PMO)

Major Flood Control Development Project 2 (MFCDP 2-PMO to include Laoag &
Agno)

Cotabato Agusan River Basin Development Project (CARBDP-PMO)

Mt. Pinatubo Emergency (MPE-PMO)

Flood Control Sabo and Engineering Center (FCSEC-PMO)

(3)

Roads Management Cluster 1 (Bilateral)


-

Road

Upgrading

Preservation

Project

-Philippine

Japan

Highway

Loan

(RUPP/PJHL-PMO
-

Saudi Fund for Development (SFD-PMO)

Rural Road Network Development Project (RRNDP-PMO)

(4)

Roads Management Cluster 2 (Bilateral)


-

Asian Development Bank (ADB-PMO)

National Road Improvement and Management (NRIM-PMO)

Millenium Challenge Corporation(MCC-PMO)

Korean Economic Development Cooperation Fund (KEDCF-PMO)

Urban Road Project Office (URPO-PMO)

(5)

Buildings and Special Projects Management Cluster (with National Building


Code Development Component)
-

Special Buildings (SB-PMO)

Comprehensive Agrarian Road Program/Rural Water System (CARP/RWS-PMO)

* As per DO No. 87, Series of 2013.

3-6

Road Project Management and Supervision Manual Vol.1 Main Text

Other PMOs not included in the above clustering are as follows:


1.

The PMO for Build-Operate and Transfer (BOT) is elevated into the Public-Private
Partnership (PPP) under the approved RATPLAN.

2.

The functions of the PMO for Traffic Engineering and Management (TEAM) are
transferred to the newly created Bureau of Quality and Safety (BQS).

3.

The functions of the PMO for Feasibility Studies are being subsumed under the Project
Preparation Division, Planning Service.

3.1.4 Planning Service (PS)


The PS provides technical services relating to public works and highways infrastructure,
planning, programming and project development. Also provides technical assistance, support
and coordination with other offices/agencies on matters relating to public works and highways,
planning, programming and project development. The PS has four (4) divisions namely, 1)
Programming Division (PD) ;2) Development Planning Division (DPD); 3) Infrastructure,
Planning, Research and Statistics Division(IPRSD); and 4) Environmental, Social and
Safeguard Office (ESSO).

Road Project Management and Supervision Manual Vol.1 Main Text

3-7

Figure 3.4

3-8

Organizational Chart of PS

Road Project Management and Supervision Manual Vol.1 Main Text

3.1.5 Bureau of Research and Standards (BRS)


The BRS functions as follows:
*

Conduct or sponsor technical research on conventional and marginal construction


materials for roads, bridges, water resources and buildings to advance technology;

Coordinate and establish linkages with academe and other institutions on research and
development;

Generate and souce funds for research and development activities;

Evaluate new construction materials/products/technologies introduced to government


infranstructure projects including construction of pilot trials;

Promote, publish and disseminate technical publications and sponsor technical


symposia;

Assist all DPWH testing laboratories on their materials testing requirements including
assessment and development of their capabilities and laboratory facilities;

Formulate and recommend guidelines, standards, criteria and systems on new


technologies for construction, rehabilitation, maintenance and improvement of all
public works and highways;

Provide DPWH and its implementing office with technical assistance related to
geotechnical engineering, field test requirements and other related technical services;

Accredit DPWH professionals, private testing laboratories, and other private firms and
facilities engaged in DPWH projects and monitor compliance with accreditation
requirements of Department; and

Coordinate with other government agencies relative to the conduct of geologic hazard
mapping activities.

Road Project Management and Supervision Manual Vol.1 Main Text

3-9

Figure 3.5

Organizational Chart of BRS

3.1.6 Bureau of Design (BOD)


The BOD conducts and supervises and/or review the results of field surveys for
highways, bridges, flood control and water resources development systems, and other public
works projects, including aerial, hydrographic, topographic, geotechnical and other
investigations. It also conducts, supervises and/or reviews and evaluates the preparation of
schemes, designs, specifications, estimates, tender contract documents covering architectural,
structural, mechanical, electrical and other technical design aspects of highways, bridges,
flood control and other public works projects of the DPWH and other agencies in accordance
with current design standards, guidelines and specifications.
The BOD provides technical assistance in the procurement and selection of firms or
entities that shall undertake consultancy services for the conduct of detailed design of public
works projects through participation in the technical evaluation aspects of the bidding/award
process.

3 - 10

Road Project Management and Supervision Manual Vol.1 Main Text

Road Project Management and Supervision Manual Vol.1 Main Text

3 - 11

Hydrology
Section

Flood Control
& Urban
Drainage
Section
Water Supply
& Coastal
Facilities
Section

Geotechnical
Section

Geology
Section

Water Project
Division

Engineering
Surveys
Section

Surveys and
Investigation
Division

Figure 3.6

Substructure
Section

Superstructure
Section

Bridge
Hydraulics
Section

Bridges
Division

Organizational Chart of BOD

Pavement
Section

Highway
Drainage &
Slope Protection
Section

Geometric
Section

Highways
Division

Office of the Director

Office of the Director

Mechanical &
Electrical
Section

Structural
Section

Architectural
& Sanitary
Plumbing
Section

Buildings
Division

Design
Policies &
Standards
Development
Section

Design
Compliance
Monitoring
& Evaluation
Section

Design
Management
Division

3.1.7 Bureau of Quality and Safety (BQS)


To formulate and implement policies for the purpose of ensuring the safety of all
infrastructure facilities, securing the highest efficiency and quality in construction through
checking of compliance with approved plans and specifications, and establish and implement
traffic engineering policies through analysis and evaluation of traffic data.

Figure 3.7

3 - 12

Organizational Chart of BQS

Road Project Management and Supervision Manual Vol.1 Main Text

3.2 Organizations of RO and DEO


Sixteen (16) ROs and 182 DEOs under four (4) Undersecretaries administrate and
manage infrastructure projects of the DPWH throughout the country
These ROs and DEOs are responsible for the management, construction supervision and
maintenance of the national roads under their administration. The RO is headed by the
Regional Director while the DEO by the District Engineer. The RO and the DEO shall be
responsible for planning and implementation of the project within the following limit in
accordance with DO No. 24, Series of 2007.

Table 3.2

Limits of Authority

Office
Regional Director

Limit
Approval of program of works and agency estimate,
conduct public bidding, approve contracts costing up to
P200M*

District Engineer

Approval of program of works and agency estimate,


conduct public bidding, approve contracts costing up to
P50M*

*As per Memorandum Order dated January 26, 2009

Moreover, the ROs can implement a project exceeding the above limit if there are no
appropriate PMOs with prior approval of authority by the Secretary.
Figures 3.8 and 3.9 show typical organizational charts of RO and DEO, respectively.

Road Project Management and Supervision Manual Vol.1 Main Text

3 - 13

Organizational Chart of RO
Figure 3.8
3 - 14

Road Project Management and Supervision Manual Vol.1 Main Text

Figure 3.9

Organizational Chart of DEO

Road Project Management and Supervision Manual Vol.1 Main Text

3 - 15

3.3 Organizations for Construction Supervisions


3.3.1 For Foreign-funded Projects through International Competitive Bidding
(ICB)
(1)

Employment of Consultants for Construction Supervision


The DPWH shall employ Consultants for construction supervision in accordance
with the Terms of Reference (TOR) and in consonance with the project appraisal
mission of development partners. The DPWH awards contract for consultancy services,
including staff assignment, in accordance with the proposal submitted by the Consultant
and evaluated by the DPWH.
The typical staff assignment schedule and organizational chart for the construction
supervision of a a foreign-funded project are shown in Figures 3.9 and 3.10, respectively.
POSITION

NAME

FIRM

Man-Months
2005
2006
for
A S O N D J F MAM J J A S O N D J F MAM J J A S O
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Construction
Construction Period 720 days (24 months)

Final
Acceptance

Supervision
Stage

A. International (Key Staff)


1. Project Manager

25.00

2. Sr. Highway Engineer

e
pl

am
Ex

3. Sr. Structural Engineer


4.

Geotechnical Engineer for Slope


Protection Works
Sub-Total

11.00
8.00
1.00
45.00

B. National (Key Staff)


1. Deputy Project Manager

25.00

2. Sr. Highway Engineer

10.00

3. Quantity / Sr. Cost Engineer

24.00

4. Materials Engineer

20.00

Sub-Total

79.00

C. National (Support Staff)


Civil Engineer / Inspector A
(road)
Civil Engineer / Inspector B
2.
(structures)
Civil Engineer / Quantity
3.
Surveyor
1.

24.00
16.00
24.00

4. CAD Operator

6.00

5. Secretary

25.00

6. Encoder

12.00

7. Utility-man / Messenger

25.00
132.00
256.00

Sub-Total
Total
Pre-construction Stage
Supervision Stage
Assignment of International Consultants
Assignment of National Consultants
Issuance of Notice to Proceed

LEGEND:

Source: PJHL/DPWH

Figure 3.10

Typical Assignment Schedules of Consultants

The Consultant shall employ technical support staff (Inspectors, Laboratory


Technicians, CAD Operators) and administrative staff (Secretary, Encoder and Office

3 - 16

Road Project Management and Supervision Manual Vol.1 Main Text

Road Project Management and Supervision Manual Vol.1 Main Text

Source: PJHL/DPWH

Figure 3.11

- Material Engineer
- Laboratory Technician A
- Laboratory Technician B
- Laboratory Aides ( x 4)
- Clerk Typist / Encoder ( x 1)
- Labor / Utility Man (x 3)

LABORATORY OPERATION TEAM

For: - All materials


- Quality control
- Field subsoil
investigations

Materials Engineer

- Secretary
- Encoder
- CAD Operator
- Utility-man / Messenger

ADMINISTRATIVE SUPPORTING STAFF

JICA

For:
Drawings
& design check
assistance

- Civil Engineer Aide A


- CAD Operator

e
pl

- Civil Engineer Aide B

SURVEY STAFF / AIDE

Civil Engineer /
Quantity Surveyor

Sr. Quantity /Cost Eng.

am
Ex

Sr. Structural Engineer

For: - All cost and quantities


- PCCP Construction
- Miscellaneous
and Minor Structures

SURVEY STAFF / AIDE

Civil Engineer / Inspector B

For:
- All bridges
- Major Damaged Areas

For: PCCP, ACP


For: Bridges
Note: Short-term experts

Sr. Highway Engineer

Sr.Engineer In Charge of
Bridges/Major Structures

For:
- Overall construction
supervision
- Project safety & EMP

For overall project management

DPWH Regional Office


(Region VII)

LEGEND
DPWH / PMO
Foreign Consultant
Local Consultant
Local Consultant
From Contractor
For: Major duties and
works in charge
(
) Name to be filled

Typical Organizational Chart of Consultants for Construction Supervision

- Geodetic Engineer
- Instrument Man A
- Instrument Man B
- Survey Aides ( x 4)
- Rodman ( x 2)
- Labor (x 2)

SURVEY TEAM

Civil Engineer / Inspector A

For: - Alignment
- Drainages
- PCCP, ACP
- All formation levels
& dimensions check

Sr. Highway Engineer

Deputy Project
Manager
/ Resident Engineer

Project Manager

PM/PE

PJHL-PMO
(Director)

DPWH Head Office

Assistant) for the construction supervision and office operation in accordance with the

contract with the Employer. The Consultant will control and utilize survey and laboratory

supplies in accordance with civil works contract.

3 - 17

(2)

Duties and Responsibilities of Consultants


The duties and responsibilities Consultants are, but not limited to, the following:
Table 3.3

Position

Category

Project

IN

Manager (PM)

Deputy Project

Manager
(Dep.PM)/
Resident
Engineer (RE)

Supervision

IN and/or

Engineer

(Highway)

Duties and Responsibilities of Consultants (1/2)


Duties and Responsibilities
-

Overall project implementation management (cost, progress, quality


and safety/environment)
- Overall management of construction supervision to ensure that works
are implemented in accordance with the Contract and specified
quality.
- Issue certification, approval, recommendations, instructions and
acceptance of works, payment and valuation of claims (time, cost,
etc)
- Maintain good coordination and harmonious relationship with the
DPWH, local authorities and funding institutions.
- Monitor and review the schedule as required and prepare guidance
for the key staffs and Contractors
- Supervise the preparation of required reports for their timely
submission
- Preparation of disbursement schedule for both foreign and local
currencies
- Assist the PM in the overall project management
- Construction supervision including work progress, quality, quantity,
cost and safety
- Check and approve Contractors work plan and schedule.
- Maintain good coordination harmonious relationship with local
authorities
- Monitor Environmental Management Plan (EMP), public relations
and traffic control
- Assist the RE in the construction supervision including monitoring of
work progress, quality, quantity, cost and safety control
- Supervise As-stakesurvey and As-staked Plan preparation
- Conduct full-time inspection of road and pavement works
- Ensure that the works are in accordance with the plans and
Specifications
- Assist the RE in the review of Contractors working drawings and
documents relating to road, pavement, drainage and other works
- Review and evaluate Contractor's payment certificates pertaining to
road construction
- Assist the RE in the evaluation of any claim or variation order
relating to road construction
- Assist the RE in the preparation of progress and other needed reports

Legend: IN: International Expert, N: National Expert, IN and/or N: International and/or National Expert.

3 - 18

Road Project Management and Supervision Manual Vol.1 Main Text

Table 3.3

Duties and Responsibilities of Consultants (2/2)

Position

Category

Duties and Responsibilities

Supervision

IN and/or

Engineer

(Bridge/

Structures)

Quantity

Engineer

Accredited

Materials

Engineer
-

Inspector

Assist the RE in the construction supervision including monitoring


ofwork progress, quality, quantity, cost and safety control
Conduct full-time inspection of structural works
Assist the RE in the review of Contractors working drawings
(shop-drawings) and documents relating to structures
Ensure that the works are in accordance with the plans and
Specifications
Review and evaluate Contractor's payment certificates pertaining to
structural works
Assist the RE in the evaluation of any claim or variation order
relating to structural construction
Assist the RE in the preparation of progress and other needed reports
Conduct quantity measurements for acceptable work
Check and review monthly statements to validate actual quantities of
acceptable work for payment
Check record and evaluate claims (time, cost, etc) and make
recommendations
Assist the PM and the RE in the review of all payment certificates,
claims for extra works and variation orders.
Assist the RE in the preparation of progress reports and other reports
Assist the PM and the RE for final quantity and payment
Supervise the Contractors in setting-up the field laboratory and
testing facilities
Understand and familiarize with the guidelines and procedures for
material testing and quality control guidance
Ascertain that all materials incorporated into the work passes the
requirements
Supervise all samplings and tests at site and laboratory
Advise the PM on the acceptance or rejection of construction
materials based on test results
Recommend corrective measures for unsatisfactory condition of
materials
Check and certify design mixes prepared by Contractors for concrete
and bitumen mixtures
Responsible for the proper operation of field laboratory
Keep daily record of quality control activities
Submit required test and other pertinent reports
Assist the RE and other engineers in the construction supervision
including monitoring of work progress, quality, quantity, cost and
safety control
Conduct full-time inspection of construction activities
Ensure that the works are in accordance with the plans and
Specifications
Inform the concerned supervisor in case there are deviations from
approved plans and specifications
Conduct and monitor daily activities including weather conditions
and maintain a dailyrecord of construction activities

Legend: IN: International Expert, N: National Expert, IN and/or N: International and/or National Expert.

Road Project Management and Supervision Manual Vol.1 Main Text

3 - 19

The Consultant shall employ accredited Materials Engineer (ME) as per D.O. No.42,
Series of 2006 subject to the limits of assignment described in Table 3.7.
The Contractor may assign a non-accredited ME to every DPWH project costing below
P1Million.
Renewal of Certificate of Accreditation is required for Contractors and Consultants
MEs after three (3) years from the date of issue.
The concerned ME shall not be connected with any government office. A certification
signed by the Head or Administrative Officer that the concerned ME is no longer connected
with the government office is necessary.

3.3.2 For Locally and Foreign-funded Projects through Local Competitive


Bidding (LCB)
The construction supervision for locally and foreign-funded projects is mostly conducted
thru Force Account ( By Administration). The Head of the Implementing Office shall organize
the construction supervision team before or upon approval of the Contract and the issuance of
Notice to Proceed. The composition of the team will vary depending on the type of
construction and size of the project. A typical organizational chart of the team is shown below.
DISTRICT ENGINEER

ASSISTANT DISTRICT ENGINEER

CHIEF, CONSTRUCTION

CHIEF MATERIALS QUALITY

SECTION

CONTROL SECTION

PROJECT ENGINEER

M ATERIALS ENGINEER

RESIDENT ENGINEER/PROJECT
INSPECTOR

M LT/LAB AIDE
UTILITY M AN
ENCOER/CLERK

GEOMETRIC CONTROL

UTILITY MAN
DRIVER
CLERK

Figure 3.12

Typical Organizational Chart for Construction Supervision of


Project conducted thru Force Account

3 - 20

Road Project Management and Supervision Manual Vol.1 Main Text

(1) Limits of Assignments of DPWH Engineers


Only accredited Project Engineer (PE) and Project Inspector (PI) (as per DO. No. 73,
Series of 1998) and Materials Engineer (as per DO 42, Series of 2006) shall be assigned
to supervise the project in accordance with the following limitations:
Table 3.4

*Limits of assignment of Project Engineer and Project Inspector

Classification

Limit of Assignment

Project Engineer III:

- No limit.

Project Engineer II:

- Projects being implemented simultaneously do not exceed P50.0 M


in cost

Project Engineer I:

- Projects being implemented simultaneously do not exceed P20.0 M


in cost

Project Inspector II:

- Assist the Project Engineer III or II in the implementation of assigned


project

Project Inspector I:

- Assist the Project Engineer I in the implementation of assigned


project

*Per DO no.73, Series of 1998

Table 3.5
Classification
Materials Engineer II:

*Limits of Assignment of Materials Engineer


Limit of Assignment
One (1) project, no cost limit, or
Two (2) projects located within the same province with an aggregate
cost of P10Million, but not more than P30Million

Materials Engineer I:

One (1) project costing not more than P100Million, or


Three (3) projects located within the same province with an aggregate
cost of P1Million, but not more than P3Million

*Per DO No. 42, Series of 2006

(2)

Duties and Responsibilities of Project Engineer, Materials Engineer and


Project Inspector
Their duties and responsibilities are as follows:

Road Project Management and Supervision Manual Vol.1 Main Text

3 - 21

Table 3.6

*Duties and Responsibilities of Project Engineer

Classification
Project Engineer

Duties and Responsibilities


a. In charge of the overall planning and control of the project.
b. Ensure that materials and workmanship are at all times in accordance with
plans and specifications.
c. Ensure that inspections and tests are carried out promptly and timely.
d. Witnesses critical activities of the project.
e. Check and verify physical and financial status of the project.
f. Check and verify statement of work accomplished.
g. Approve concrete pouring permit.
h. Issue work suspension orders and other site instructions.
i. Prepare proposed Change Order, Extra Work Order or Supplemental Work
Agreement, when necessary.
j. Maintain and/or update field documentation such as log book, plans and
programs of work, schedules, S-curve, laboratory test results, etc.
k. Resolve problems encountered in the implementation of the project
l. Coordinate with the Project Directors/District Officer/Local Government
Units/ NGOs and other coordinating officers in the project
implementation.
m. Submit monthly physical and financial report.

*Per DO No. 73, Series of 1998

Table 3.7

*Duties and Responsibilities of Project Inspector

Classification

Duties and Responsibilities

Project Inspector

a. Assist the PE in the overall direction and supervision of the field operation.
b. Ensure that the works being inspected are in accordance with the plans and
specifications.
c. Witness critical activities of the project.
d. Notify the Project Engineer in case there are deviations from the approved
plans and specifications.
e. Conduct and monitor daily activities including weather conditions and
maintain a logbook to record such activities.
f. Prepares and submit statement of work accomplished
g. Prepare and submit physical/financial status to the Project Engineer.
h. Carry out instructions/orders of the Project Engineer.

*Per DO No. 73, Series of 1998

3 - 22

Road Project Management and Supervision Manual Vol.1 Main Text

Table 3.8

*Duties and Responsibilities of Materials Engineer

Classification

Duties and Responsibilities

Materials Engineer

a. Ascertain that all materials incorporated into the work pass the requirements
of the DPWH Standard Specifications for Highways, Bridges and Airports
Vol. II and to strictly comply with the schedule of Minimum Testing
Requirements.
b. Advice the Project Engineer on the acceptance or rejection of construction
materials intended for use in the project based on test results.
c. Responsible for the sampling, testing, inspection and submission of data
and to fully acquaint himself with the standard procedures of the same.
d. Recommend to the Project Engineer remedial measures for the correction
of unsatisfactory conditions of materials.
e. Prepare design mixes for concrete and bituminous mixtures.
f. Ensure that the field laboratory is adequately equipped so that the progress
of the work will not be impeded to laboratory testing and that
non-performance of tests should not be a cause of delay in the prosecution
of the work.
g. Keep record of the daily activities ready for inspection anytime.
h. Submit within the required time frame test reports and other pertinent
papers to the Regional/District Engineering Office concerned.
i. Recommend corrective measures to improve the quality of completed
works.
j. Recommend acceptance of completed works.

*As per DO No. 42, Series of 2006

3.4 Administrative Penalties/Sanctions


In accordance with DO No. 193, Series of 1992 regarding Liability of Contractors and
Sub-Contractors including Public Officials for violations of Presidential Decree (PD) No.
1759, any public official who, by reason of the duties of his office, shall consent, or through
abandonment or negligence, permit the Contractor or Sub-Contractor to violate any material
provisions of contracts involving public works projects, either as to materials, quality and
quantity of work, resulting to the prejudice of the government, shall suffer the penalty of from
twelve (12) years to life imprisonment and perpetual disqualification to hold office.
In accordance with the Department Memorandum dated January 19, 2004 regarding
Additional Guidelines on the Imposition of Administrative Sanctions on Erring DPWH
Officials and Employees Involved in Project Implementation and Processing of Project

Road Project Management and Supervision Manual Vol.1 Main Text

3 - 23

Documents, sanction shall be imposed on the PE and PI if in any of the given reporting
period:
(a) He fails to initiate calibrated actions (in accordance with DO 102, Series of 1988)
on a project/projects under his supervision with a negative slippage; and
(b) He gets ten (10) points or greater based on the values shown below.
Table 3.9

Points against Negative Slippage

Slippage

Points
1 Project

2 Projects

3 Projects

5%-10%

10

11% - 15%

10

15

>15%

10

15

20

The calibrated actions shall be as follows:


1st Offense:

Reprimand

2nd Offense:

Suspension for six (6) months

3rd Offense:

Suspension for one (1) year

3.5 Authorities of DPWH Officials


It is the Governments policy that the exercise of authorities with corresponding
accountabilities in the DPWH shall be decentralized to the extent possible, especially in the
implementation of infrastructure projects and the delivery of frontline services.
The levels of authorities are grouped based on the DPWH project cycle and functions
and services of the offices in DO No.24, Series of 2007 Amended Omnibus Levels of
Authorities of Official of the DPWH, as follows:
i)

Planning

ii)

Environmental and Social Aspects

iii) Design
iv) Land Acquisition and Infrastructure Right of-Way
v)

Procurement

vi) Contract Management


vii) Infrastructure Maintenance
viii) Quality Control
ix) Human Resources

3 - 24

Road Project Management and Supervision Manual Vol.1 Main Text

x)

Financial Resources

xi) Equipment and Properties (Other than Real Estate).


The authorities being delegated to the DEO engineers shall also apply to Heads of
Sub-District Engineering Offices who have been designated as such by the Secretary.

3.7 Reforms in DPWH


The DPWH has faced institutional challenges in carrying out its mission on good
governance supported by high moral and ethical standards. In line with this, the DPWH has
implemented Anti-Corruption Program to address corruption and institutionalize reforms as
follows:
(1)

Quality Assurance
1.

Quarterly assessment or quality audit by the Quality Assurance Unit (QAU) of


on-going and completed construction and maintenance projects to check compliance
with the approved plans and specifications.

2.

Quarterly assessment by the Performance Evaluators accredited by Construction


Industry Authority of the Philippines (CIAP) to evaluate performance of a contractors
specific kind of projects using the Constructors Performance Evaluation System
(CPES) guidelines.

3.

The DPWH through the Bureau of Research and Standards (BRS) is continuously
undertaking the accreditation of DPWH Project Engineers and Inspectors including the
Materials Engineers of Contractors and Consultants in order to ensure that only
competent engineers will be assigned to DPWH projects.

4.

The BRS-DPWH is continuously undertaking the accreditation of private testing


laboratories to augment the testing capability of its Regional and District Offices.

5.

Accreditation of concrete and asphalt batching plants by the BRS/DPWH to ensure


that only concrete and asphalt mixes of the highest quality will be used in the DPWH
project.

6.

Compliance to the provisions of pertinent Department Orders and Administrative


Issuances by all implementing offices of the DPWH relative to materials and
construction quality control.

7.

A sanction mechanism was put in place to penalize the project implementors noted
with unsatisfactory performance; and the contractors were encouraged to report to the
DPWH Integrity Board any corrupt practices in project implementation.

Road Project Management and Supervision Manual Vol.1 Main Text

3 - 25

(2)

Project Implementation
1.

Project monitoring system to track slippages of project accomplishment was


strengthened.

2.

Project Advisory and Management System (PAMS), an inter-agency group to ensure


the immediate resolution of problems and issues in project implementation was
created.

3.

Documents Tracking System (DoTS) to track status of all contract related documents
was put in place.

4.

Executive Information System to provide instant information that needs urgent


attention by top management was put in place.

5.

Guidelines to check the performance of implementing offices and the corresponding


sanction mechanism for unacceptable performance was developed.

6.

Payment System through the use of the electronic New Government Accounting
System (eNGAS) was adopted.

7.

Job rotation of personnel to avoid camaraderie with Contractors shall be a continuing


process.

(3)

Document Tracking System (DoTS)


In line with the Departments thrust to fast track the completion of projects and to be
transparent in its operation, all offices involved in the processing of documents on the
procurement and implementation of local anf foreign-assisted civil works undertaken
shall utilize the DoTS (per DO No. 273, Series of 2003, DO No. 32, Series of 2004 and
DO No. 159, Series of 20042.

Latest issuance shall prevail

3 - 26

Road Project Management and Supervision Manual Vol.1 Main Text

Chapter 4 Procurement
4.1 Bids
The bid documents are documents issued by the DPWH to provide the prospective
bidders all necessary information to prepare their bids. These bid documents are prepared in
accordance with Volume III-DPWH Manual of Procedures for the Procurement of
Locally-funded Infrastructure Projects through public bid of DPWH Procurement Manual
(DPM) together with procurement guidelines of the funding institutions in case of
foreign-funded projects.
The bid documents shall consist of the following:
Table 4.1
Part
Part I:

Part II:

Bid Documents

Section

Section Title

Section I

Invitation to Apply Eligibility and to Bid

Section II

Eligibility Requirements

Section I

Instruction to Bidders including documents comprising the Bid

Section II

Bid Data Sheets

Section III

General Conditions of Contract

Section IV

Special Conditions of Contract

Section V

Specifications (Standard Specifications and Special Provisions)

Section VI

Plans and Drawings

Section VII

Bill of Quantities and Unit Price Analysis

Section VIII

Forms

The bid documents become part of the contract documents. As such, these should be well
kept and handed over to the Engineer. A checklist of bid documents is shown below:

Road Project Management and Supervision Manual Vol.1 Main Text

4-1

Checklist of Bid Documents (1/3)

4-2

Road Project Management and Supervision Manual Vol.1 Main Text

Checklist of Bid Documents (2/3)

Road Project Management and Supervision Manual Vol.1 Main Text

4-3

Checklist of Bid Documents (3/3)

Note:
Entries on appropriate spaces provided, e.g. costs, percentages and other
information that may be required are subject to change in the light of official issuances such
as Department Orders, Office Orders etc.

4-4

Road Project Management and Supervision Manual Vol.1 Main Text

4.2 Contract
4.2.1

Contract Documents

The contract documents are legal documents on which the project management and
construction supervision are relied. The Contract is the agreement between the DPWH and the
Contractor to execute, complete, and maintain the Works. It consists of the Agreement itself
and all documents that form part as written in the GCC. Among others are the following:
Table 4.2

List of Contract Documents

Category
A. The Contract:

Title of Documents
1) Contract Agreement
2) Documents forming part of Contract Agreement
a) Bidding

1. General Conditions of Contract

Documents for

2. Special Conditions of Contract

the Contract

3. Drawings/Plans
4. Specifications
5. Invitation for Apply Eligibility and to Bid
6. Instruction to Bidders
7. Bid Data Sheet
8. Bid Bulletins (Addenda)

b) CONTRACTORs Calculated Bid in the Form of Bid including its


Technical and Financial Proposals
c) CONTRACTORs Letter of Intent for Eligibility and Contractors
Information from the DPWH Registry
d) Notice of Award of Contract and the CONTRACTORs Conforme
e) Performance Security
f) Credit Line or Cash Deposit Certificate
g) PERT/CPM diagram and bar chart with S-curve
B. Supporting

1) Approved Program of Work

Documents for the

2) Obligation Slip

Contract

3) Certificate of Availability of Fund


4) Abstract to Bid as Calculated
5) Approved BAC Resolution declaring the LCRB and Recommending
Award

The documents in items (1) and (2)-a) to (2)-c) above shall be provided by the DPWH
and those in items (2)-d to (2)-g shall be submitted by the winning bidder within ten (10)
calendar days from the date of its receipt of the Notice of Award.

Road Project Management and Supervision Manual Vol.1 Main Text

4-5

The documents forming the Contract are to be taken as mutually explanatory of one
another. For the purpose of interpretation, the Contract documents shall be interpreted in the
following order of priority:
(a) Contract Agreement (if any)
(b) The Letter of Acceptance
(c) The Tender
(d) The Particular Conditions
(e) The General Conditions
(f)

Specifications1

(g) Drawings
(h) Any other document listed in the SCC as forming part of this Contract.
There are many other documents which are part of Contract documents as listed in the
next page and those documents should be compiled in a file or book to avoid lost or
misplacement.
If an ambiguity or discrepancy is found in the documents, the Engineer shall issue any
clarification or instruction.

The Specification means the DPWH Standard Specifications for Highways, Bridges and Airports Vol. II 2013
Edition. Modifications to Standard Specifications shall be in the form of Special Specifications to be mentioned
in the Special Provisions which is part of the Bid Documents.

4-6

Road Project Management and Supervision Manual Vol.1 Main Text

Checklist of Contract Documents and Supporting Documents

Road Project Management and Supervision Manual Vol.1 Main Text

4-7

4.2.2

Subcontract/Sublease

A Subcontractor is any person or organization who has subcontracted a part of the work
from the main Contractor as approved by the Employer.
No Contractor shall subcontract any portion of work without prior approval of the
Secretary in accordance with DO No. 70, Series of 2004 2. In no case, shall subcontracting be
allowed for more than fifty percent (50%) of the value of project.
Subcontracting of any portion of the Works does not relieve the Contractor of any
liability or obligation under the Contract. The Contractor shall be responsible for the acts,
defaults, and negligence of any subcontractor, its agents, servants or workmen as fully as if
these were the Contractors own acts, defaults, or negligence, or those of its agents, servants
or workmen.

4.3 Facilities and Land Acquisition


4.3.1
(1)

Facilities for the Engineer


Field Office and Laboratory
In general, the Contractor shall provide facilities for the Engineer as specified in

the Special Provisions Part A of the Special Specifications.


Facilities shall include:
*

Temporary Field Office, Laboratory, Living Quarter

Combined Field Office, Living Quarters and Laboratory Building

Furniture, Fixtures and Appliance for these facilities

The Implementing Office shall identify a site intended for the construction of
buildings and facilities such as combined field office, laboratory, living quarter buildings
and other facilities in accordance with DO No. 08, Series of 20063.
The construction of buildings on a property other than DPWH-owned should be
covered by a Memorandum of Agreement (MOA) to be approved by the DPWH
Secretary or Undersecretary for Administration. The MOA shall provide a provision
allowing the DPWH the use their property free of charge until the completion of the
project and shall be turned over to the lot owner without cost after completion of the
project.
If it is more economical and reasonable, the Contract would provide the Engineers
office on a rental basis. The Contractor shall rent, operate and maintain one (1) unit of
combined field office building and materials testing laboratory and a separate building
2
3

Latest issuance shall prevail.


Latest issuance shall prevail

4-8

Road Project Management and Supervision Manual Vol.1 Main Text

for the living quarter, including all necessary electricity, water, drainage, sanitary
facilities and telephone services for the use of the Engineer and his staff.
(2)

Vehicles and Other Equipment


The Contractor shall provide, operate and maintain the following:
-

Service Vehicles

Communication Equipment and Cellular Phones

Laboratory Testing Equipment, Apparatus and Publications

Progress Photographs

Survey Equipment and Apparatus

Office Computers

Survey and Laboratory Operation Aids.

The specified facilities provided by the Contractor and paid by the Government
shall be turned over to the Government upon completion of the project.

4.3.2

Right-of-Way Acquisition

Acquisition of real property shall be governed by Republic Act (RA) No. 8974, entitled
"An Act to Facilitate the Acquisition of Right-of-Way Site or Location for National
Government Infrastructure Projects and for Other Purposes".
"Right-Of-Way (ROW)" refers to the overall width along the road alignment of proposed
works with regard to the area of land that must be cleared before the works are commenced.
Parcellary survey will be conducted to identify the specified area, land title, land owners and
cost required for ROW acquisition and resettlement.
The Implementing Office is responsible for ROW acquisition before commencement of
the Works.
Unless otherwise specified in the Contract, the Implementing Office shall provide access
to and possession of the site including special and/or temporary right-of-way which are
necessary for the Works. The Contractor shall obtain, at his own risk and cost, any additional
rights of way or facilities outside the site which he may require for the purposes of the Works.

4.3.3

Possession of Site

Prior to commencement of works, the implementing Office shall issue the Contractor in
writing the possession of site, specifying the relevant stations of the project as maybe required
to enable him to proceed with the execution of the works.
If the Contractor suffers delays or incurs delay or incurs cost from failures on the part of
the Implementing Office to give possession of such site, it shall give the Contractor a contract

Road Project Management and Supervision Manual Vol.1 Main Text

4-9

time extension and certify such reasonable sum to cover the cost incurred.

4.3.4

Relocation of Utilities

Though the Contractor is responsible for identifying utilities affected by the Works, the
Engineer should confirm the locations of these utilities, if such are not shown in the contract
documents.
These include:
*

Electricity Authority (power lines, cables, pylons, etc.)

Water (pipes, irrigation channels, etc.)

Sanitation and

Telecommunication.

The Engineer shall coordinate and assist the Contractor and the concerned agencies in
the relocation of these utilities prior to commencement of any works.

4.4 Performance Security and Insurance


4.4.1

Performance Security

The Contractor shall obtain at his own cost a Performance Security to guarantee his
faithful performance performance to complete the project on time. This shall be submitted to
the Implementing Office not later than the date specified in the Letter of Acceptance and shall
be issued in an amount and form as specified in the Special Conditions of Contract, and
denominated in the currency in which the contract price is payable. The Performance Security
shall be valid up to the date of acceptance of the project.
The validity of the Performance Security shall be from the date of Contract signing up to
the final acceptance of the project wherein the warranty period shall have commenced.
At the Contractors option, the Performance Security is to be in any of the following
forms:
*

Cash, Cashiers Check, Bank Draft or Irrevocable Letter of Credit in the amount
equivalent to five percent (5%) of the contract price

Bank guarantee in the amount equivalent to ten percent (10%) of the contract price.

Surety bond in the amount equivalent to thirty percent (30%) of the contract price
callable upon demand issued by any reputable Surety or Insurance company; and

Any combination of the above

The Performance Security shall be released by the Implementing Office after issuance
of the Certificate of Acceptance, provided that there are no claims for labor and materials filed
against the Contractor or the Surety company and provided further that the Contractor should
have submitted the warranty security.

4 - 10

Road Project Management and Supervision Manual Vol.1 Main Text

The Performance Security shall bear the provision:


The right to institute action on the penal bond pursuant to RA No. 3688 of any
individual firm, partnership, corporation and association supplying the contract with
labor and materials for the prosecution of the work is hereby acknowledged and
confirmed.

4.4.2

Contractor's All Risk Insurance (CARI)

The Contractor shall, under DPWH name and at his own expense, obtain and maintain
for the duration of the Contract.
The Contractor shall provide evidences to the Engineer that the insurance required under
the Contract has been effected and shall, within a reasonable time, provide copies of the
insurance policies to the Engineer.
The Contractor shall notify the Insurers of changes in the nature, extent, or program for
the execution of the Works and ensure the adequacy of the insurance at all times in accordance
with the terms of the Contract and shall submit to the Implementing Office the insurance
policy in-force including receipts for payment of current premiums.
If the Contractor fails to obtain and keep in-force any insurance and pay such premiums
as maybe necessary for the purpose, the Implementing Office shall obtain and keep in-force
the same and shall be deductable from the Contractors collection(including extra expenses in
securing insurance coverage).

4.5 Notice to Proceed (NTP)


The Implementing Office shall issue the NTP together with a copy or copies of the
approved Contract to the successful bidder within three (3) calendar days from the date of
approval of the Contract by the appropriate government approving authority. However, for
infrastructure projects with an Approved Budget for the Contract (ABC) of fifty (50) million
and below, the maximum period is two (2) calendar days. All notices called for by the terms
of the Contract shall be effective only at the time of receipt thereof by the successful bidder. If
the effectivity date is provided in the Notice to Proceed by the Implementing Office
concerned, such date shall not be later than seven (7) calendar days from issuance thereof4.

As per amended GPPB Resolution No. 014-2006 dated 20 July 2006.

Road Project Management and Supervision Manual Vol.1 Main Text

4 - 11

Chapter 5 Public Information, Road


Safety and
Environmental
Management
5.1 Public Information System
Since 2007, the DPWH has launched the "Bantay Lansangan" (Roadwatch), a
partnership that seeks to mobilize a multi-sectoral group composed of private stakeholders,
non-government organizations and development partners to work with the DPWH and other
government stakeholder agencies. This is aimed at enhancing the delivery of quality national
road services responsive to user's needs and satisfaction, through more efficient and
transparent use of public resources.
For excellent service delivery and total public satisfaction, the Public Information
Division (PID) of DPWH responds to queries, complaints, concerns, and other needs of
external stakeholders to include road users, civil society groups, non-governmental
organizations, development partners, the academe, other government agencies, etc. The PID is
mandated to develop and implement the DPWH development communication program to
ensure that policies, plans, programs, and activities be known to the public. Likewise, it is the
office responsible in providing information and quick-response action to the issues, concerns,
problems, and queries regarding the DPWH.
The major functions of Public Information Officer in relation with project
implementation are:
*

Develop a communications program to ensure that policies, plans and activities of


the DPWH be known to the public;

Supervise the preparation of information materials, reports, briefing materials,


photo exhibits in line with the communication program;

Act or provide answers to issues/problems brought about by the media;

Receive public complaints, problems, and queries and provides direct and
quick-response to the general public needs;

Establish a data bank for all the relevant data and information to the media,
researchers, non-governmental organizations and the general public about the
plans / on-going activities and accomplishments; and

Provides information on projects, road infrastructure, travel conditions,


administration.

Road Project Management and Supervision Manual Vol.1 Main Text

5-1

The DPWH has been improving its continuing feedback monitoring system on matters
concerning the DPWH projects and others through its webpage and the Short Messaging
System (SMS) technology in reaching out to citizens and communities for feedback and
resources mobilization.

5.2 Relations with Local Communities and Road Users


The Engineer shall monitor the Contractors relations with local communities and road
users. In setting up and during operation of his plant and facilities, the Contractor shall at all
times bear in mind and to the extent practicable minimize the impact of his activities on the
existing communities. Where communities are likely to be affected by major activities such as
road widening or the establishment of a camp, quarry, extensive road closure or detour, he
shall liaise closely with the concerned communities and their representatives. The Contractor
should organize periodic or at-required basis meetings to provide project information, resolve
issues and claims and minimize impacts on local communities. The Engineer should enhance
communication capacity with local communities and public.
For the safety and convenience of the public and road users, the Contractor shall erect
and maintain as required by conditions prevailing at the site and progress of the works, all
reasonable safeguards for safety and protection. It shall include all danger signs and other
warnings against hazards.
The Contractor shall install and maintain
traffic

control

information

boards

bearing

location of detours and one-way control, type of


work, period of traffic control at several strategic
points as approved by the Engineer for public
and road users.
Figure 5.1

Figure 5.2

5-2

Project Information

Traffic Control Information

Road Project Management and Supervision Manual Vol.1 Main Text

5.3 Road Safety


5.3.1 Road Safety Program
Road safety is one of the primary concerns of the government. The DPWH implements
road safety program to develop technical standard, policies and procedures for the safety of
road users and minimize traffic accident.
Table 5.1

Safety Programs

Safety Output
1.

Safety Projects

Activities
Installation and operation of traffic signals, advanced traffic
management systems, surveillance devices and vehicle weighing
devices, etc.

2.

Road Safety Education Public information dissemination.


and Training

3.

Road
Management

Safety Professional services necessary to undertake accident reduction


studies design and implement remedial treatments including design
of traffic safety devices.

The DPWH has developed a computerized accident data system called as the Traffic
Accident Recording and Analysis System (TARAS). It incorporates the collection, storage,
retrieval and analysis of traffic accident data.
TARAS is a text and graphic data entry and statistical query system that provides access
to accumulated traffic accident information occurring on national roads throughout the
country.
TARAS Reporting and Analysis Module are used to query and report on traffic accident
information stored within the TARAS database. Reporting and Analysis is the core module
that makes TARAS a powerful tool in Traffic Accident Analysis.

Figure 5.3

Traffic Accident Recording and Analysis System (TARAS)

Road Project Management and Supervision Manual Vol.1 Main Text

5-3

TARAS identifies blackspots and the concerned office conducts Accident Blackspot
Investigation and recommends treatment or proposals. The Engineer should obtain this
information and utilize it for the safety in the project.

5.3.2 Road Safety Manual


The DPWH has four (4) technical manuals and two (2) handbooks 1 on road
infrastructure safety as listed below:
Table 5.2

Road Safety Manual and Handbook

1. Road Safety Audit Manual


2. Road Works Safety Manual
Road Safety
Manual

3. Highway Safety Design Standards Manual - Part 1: Road Safety Design


Manual
4. Highway Safety Design Standards Manual - Part 2: Road Signs and
Pavement Marking Manual

Road Safety
Handbook

Figure 5.4

1. Accident Blackspot Investigation Handbook


2. Project Evaluation Handbook

Road Safety Manual and Highway Safety Design Standards Cover


Pages

The Road Works Safety Manual shall be used as a reference for defining temporary
signage, traffic devices and traffic management for maintenance and construction works on
roads and bridges. The manual also defines the circumstance under which the devices should
be arranged to provide warning for various types of works and environments.
The Accident Blackspot Investigation Handbook contains information on the use of
1 These manuals and handbooks were prepared under Road Infrastructure Safety Project (Capacity Building
Component of the 6th ADB Road Project) and covered by DO No.09, Series of 2006.

5-4

Road Project Management and Supervision Manual Vol.1 Main Text

accident data, reports and maps from the Traffic Accident and Analysis System (TARAS) to
identify hazardous locations and assist with the analysis of accident patterns and casual factors
at particular sites. The Handbooks provide guidance on the critical steps required to
investigate and develop a project comprising engineering countermeasures that will have a
high probability of improving road safety at an accident blackspot location.

5.3.3 Provision of Road Safety Devices


To enhance road safety and guide motorists, road safety devices such as guardrails or
protective barriers including warning or directional signs shall be installed along critical
sections of all DPWH projects in accordance with DO No. 36,Series of 2007.
The safety and convenience of the road users and the public in general public are of
prime importance in the project implementation. At all times during the Works, the Contractor
shall ensure smooth flow of traffic, safe condition at temporary approaches, intersections and
private entrances.
The Contractor shall provide, erect and maintain at all times suitable barricades, fences,
signs, and watchmen as necessary or as directed by the Engineer.

Example

Installation of concrete barriers


Figure 5.5

Provision of precautionary signages

Road Safety Devices and Signages

This provision on road safety shall be considered in the detailed engineering design and
in the preparation of program of work. To preclude excessive provision on road safety devices,
the total cost shall not be more than 10% of the total project cost. All works under this item
shall be in accordance with Items 603 Guardrail and 605 Road Sign of the DPWH Standard
Specifications for Highways, Bridges and Airports, Vol. II 2013 Edition.

Road Project Management and Supervision Manual Vol.1 Main Text

5-5

5.3.4 Traffic Management


(1)

Closure of Road
The Contractor shall submit a traffic management and control plan at least two (2)
weeks before commencement of any work for approval of the Engineer.
No road shall be closed by the Contractor to the public except when permitted by
the Engineer in writing. When the road under construction is to be used, special attention
shall be exercised such that the public can safely travel without undue delay.

(2)

Detour
The Contractor shall provide, construct and maintain detours wherever the work
interferes with traffic on existing roads, footways or other ways within a road
right-of-way. No detours shall be constructed and no traffic diverted until the
Contractors proposal thereof has been approved by the Engineer.
Prior to the commencement of the construction and of the use of detours, the
Contractor shall provide the Engineer with a full photographic record of the existing
roads, pathways, etc. The Contractor shall furnish and erect all detour and traffic control
signs required in the Plans and Specifications and at the direction of the Engineer.
All detour roads shall be maintained in good condition at all times by the Contractor.
All detours shall be kept graded, compacted and sprinkled with water for dust
control.Where public or private roads are used as detours, such roads shall be restored
back to its original state.

5.3.5 Safety Officer


The Contractor shall designate a competent Safety Officer who will be responsible for
maintaining safety in the site.

5.4 Safety and Health Programs


5.4.1 Obligation of the Contractor
The Contractor shall prepare a program covering all items on safety, health and traffic
management for approval of the Engineer. The Engineer and the Contractor shall conduct
joint periodic inspection based on the approved program. The Contractor shall submit the
required report indicating, among others, the findings and respective actions to be undertaken.
The Contractor shall:
*

5-6

comply with all applicable safety regulations;

Road Project Management and Supervision Manual Vol.1 Main Text

take care of the safety of all persons entitled to be on the Site;

use reasonable efforts to keep the Site and Works clear of unnecessary obstruction
so as to avoid danger to these persons;

provide fencing, lighting, guards and watchers of the Works until completion and
turning over; and

provide any Temporary Works which may be necessary, because of the execution
of the Works, for the use and protection of the public and of owners and occupants
of land and properties adjacent to the project/works site.

The Contractor shall take all reasonable precautions to maintain the health and safety of
his personnel. In collaboration with local health authorities, the Contractor shall ensure that
medical staff, first aid facilities, sick bay and ambulance service are available at all times at
the site. The Contractor shall maintain records and make reports concerning health, safety and
welfare of personnel and damage to property as the Engineer may reasonably require.
The Contractor shall be responsible for keeping unauthorized persons off the site.
Authorized persons shall be limited to the Engineers and Contractors personnel and any
other personnel notified to the Contractor by the Engineer.

5.4.2 Load Restriction


The Contractor shall comply with the legal load restrictions in the transportation of
contruction materials on public roads and shall use every reasonable means to prevent the
road from being damaged.
The Contractor shall bear all the responsibility and liability for damages or injuries
resulting from his failure to abide by relevant provisions.

5.4.3 Coordination during Emergency


The Contractor shall establish and maintain at all time emergency communication lines
with the Engineer and all concerned authorities including government agencies and facilities.
The Contractor shall inform the Engineer details of any accident as soon as practicable.

Road Project Management and Supervision Manual Vol.1 Main Text

5-7

5.5 Environmental Management


Revised Procedural Manual for DENR Administrative Order No. 30, Series of 2003
(DAO 03-30) was issued on August, 2007.

5.5.1

Legal Framework and Process

The basic national policy governing environmental functions of DPWH is stated in


Presidential Decree 1586 also known as the Philippine Environmental Impact Assessment
Law, which requires the DPWH to undertake environmental impact assessments for all its
major projects.
Since international and bilateral donor agencies have their own guidelines on
environmental and social considerations, the projects funded by these agencies should be
referred to the respective guidelines.

5.5.2 Environmental Impact Assessment (EIA)


An EIA is a process that involves predicting and evaluating the likely impacts of a
project (including cumulative impacts) on the environment during construction,
commissioning, operation and abandonment. It also includes designing appropriate preventive,
mitigating and enhancement measures addressing these consequences to protect the
environment and the communitys welfare.
The objectives are:
*

To present a clear assessment of potential impacts on environment;

To apply appropriate methodology which assesses and predicts impacts and


provides a) means for impact prevention and mitigation, b) the enhancement of
project benefits, and c) the minimization of long-term impacts; and

To provide specific forum for consultation for allowing stakeholders to have


direct input to the environmental management process.

EIA is used to enhance planning and guide decision-making. It is primarily presented in


the context of a requirement to integrate environmental concerns in the planning process of
projects at the feasibility stage. Through the EIA process, adverse environmental impacts of
proposed actions are considerably reduced through a reiterative review process of project
siting, design and other alternatives, and the subsequent formulation of environmental
management and monitoring plans. A positive determination by the Department of
Environment and Natural Resources-Environment Management Bureau (DENR-EMB) results
to the issuance of an Environmental Compliance Commitment (ECC) document, to be
conformed to by the Proponent and represents the projects Environmental Compliance
Certificate. The release of the ECC allows the project to proceed to the next stage of project

5-8

Road Project Management and Supervision Manual Vol.1 Main Text

planning, which is the acquisition of approvals from other government agencies and LGUs,
after which the project can start implementation. A summary flowchart of the complete
process is presented in Figure 5.5 while a descriptive overview is provided in Figure 5.6. The
Philippine EIA Process has six (6) sequential stages Screening, Scoping, EIA Study
andReport Preparation, EIA Review and Evaluation, Decision Making, and Post-ECC
Monitoring, Validation and Evaluation/Audit stage. Stages 1, 2, 3 and 6a are all
Proponent-driven while Stages 4, 5 and 6b are DENR-EMB driven stages. The first five (5)
stages are those involved when a Proponent applies for ECC or CNC.

Figure 5.6

Summary Flowchart of EIA Process

Road Project Management and Supervision Manual Vol.1 Main Text

5-9

Figure 5.7

Overview of Stages of the Philippine EIA Process

5.5.3 Environmental Compliance Certificate (ECC)


No person, partnership or corporation shall undertake or operate any in part such
declared Environmentally Critical Projects or project in Environmentally Critical Areas
without first securing ECC. Table 5.3 and 5.4 show the matrix for determination of EIA report
type - New Single and Co-located Projects.
The Engineer shall make a thorough study on the conditions given in the ECC including
the following:
1)

All applicable requirements/ permits from other concerned agencies should be


complied before the project implementation;

2)

Careful construction planning and work scheduling/ phasing should be made to avoid
nuisance and public inconvenience;

5 - 10

Road Project Management and Supervision Manual Vol.1 Main Text

3)

Systematic traffic management and operation should be implemented to maintain


smooth flow of public traffic;

4)

Site should be kept free from obstructions like spoiled materials, construction debris/
materials and scattered stones to prevent any untoward accidents;

5)

Water sprinkling on exposed soil for dust control;

6)

Overburden and/or excess materials should be disposed of at designated areas and


should not block a natural drainage;

7)

Construction camps should be provided with adequately designed and maintained


sanitary systems;

8)

Supply of aggregates for the project should be legalized by an ECC;

9)

Trees to be cut should be covered by cutting permit and replaced with appropriate
species;

10) Proper disturbance compensation affected by the road right of way should be effected;
and
11) Philippine Occupational Safety and Health Standards requirements applicable during
construction phase of the project should be properly observed.
Once a project is implemented, the ECC remains valid and active for the lifetime of the
project. ECC conditions and commitments are permanently relieved from compliance by the
Proponent only upon validation by EMB of the successful implementation of the
environmental

aspects/component

of

the

Proponents

Abandonment/Rehabilitation/

Decommissioning Plan. This pre-condition for ECC validity applies to all projects including
those wherein ECC expiry dates have been specified in the ECC. However, the ECC
automatically expires if a project has not been implemented within five (5) years from ECC
issuance, or if the ECC was not requested for extension within three (3) months from the
expiration of its validity. If the baseline characteristics have significantly changed to the extent
that the impact assessment as embodied in the Environmental Management Plan (EMP) is no
longer appropriate, the EMB office concerned shall require the Proponent to submit a new
application. The EIA Report on the new application shall focus only on the assessment of the
environmental component, which significantly changed.
ECCs may be suspended for violation of Proponents to comply with ECC conditions. It
is noted that ECC suspension does not necessarily mean the Proponent is absolved of its
responsibility in implementing its approved EMP. PD 1586 does not preclude the fact that
DENR may require the Proponent to institute environmental safeguards/measures to prevent
further threat or actual damage to the environment.

Road Project Management and Supervision Manual Vol.1 Main Text

5 - 11

5 - 12

Road Project Management and Supervision Manual Vol.1 Main Text

D.4.a.

MAJOR POWER PLANTS (Proc. No. 2146 declared types: fossil-fueled, nuclear fueled, hydroelectric or geothermal)

D.4.

33.

Tunnels and sub-grade roads and railways

D.3.d.

32.

Fuel Cell

(including RO-RO facilities)

100 MW

1.0 km

10.0 km

Source: Revised Procedural Manual for DENR Administrative Order No. 30, Series of 2003 (DAO 03-30) Annex 2-1b

total power production capacity

length

critical slope

20.0 km OR

length with no critical slope OR length with

Roads, new construction, widening

D.3.c.

Regardless of length and width

On-grade railway system, new

31.

10.0 km

D.3.b.

length

50 hectares

30.

Bridges and viaducts, new construction

D.3.

area reclaimed

20 million m3

25 hectares OR

Environmental Impact Statement (EIS) / ECC

D.3.a.

MAJOR ROADS AND BRIDGES

D.2.

28.

capacity

Reservoir flooded area OR water storage

Parameter

Document

EIA Report Type Required / Decision

29.

MJOR RECLAMATION PROJECTS

D.1.

MAJOR DAMS

INSFRASTRUCTURE PROJECTS

27.

D.

Project Type

Project Size

Proclamation No. 803 (1996) for Gold Courses, and Presidential Proclamation No. 2146 (1981) for Heavy and Resource Extractive Industries & Infrastructure Projects

Project Grouping Matrix for Determination of EIA Report Type - New Single and Co-located Projects (Group I)

Group I: ENVIRONMENTALLY CRITICAL PROJECTS (ECPs)2 in both Environmentally Critical Areas (ECAs) and Non-ECAs, as declared in and Presidential

Table 5.3

Road Project Management and Supervision Manual Vol.1 Main Text

5 - 13

C.4.c.

C.4.b.

78.

79.

C.4.a.

C.4.

77.

MINOR ROADS & BRIDGES

C.3.

76.

Regardless of length and width

< 10.0 km

OR length with
critical slope

2 km but < 20.0 km. OR 2km but

80 m but < 10.0 km

< 50 hectares

5.0 MW but < 30.0 MW

/ ECC

(IEE Report: IEER Checklist: IEEC)

Initial Environment Examination3

critical slope,

length with no

length

area reclaimed

capacity

production

total power

Parameter

Report12 / CNC

Project Description

< 2 km

other bridges

foot bridges <80 m for

Regardless of length for

< 5.0 MW

Decision Document

Source: Revised Procedural Manual for DENR Administrative Order No. 30, Series of 2003 (DAO 03-30) Annex 2-1b

Elevated roads, flyover/cloverleaf/interchanges

Roads, new construction, widening (including RO-RO facilities)

Bridges and viaduct, new construction

PROJECTS

MINOR RECLAMATION

C.2.f.

75.

Other thermal power plants (e.g., diesel, bunker, coal, etc.)

Project Type

Projects Size

First Set of Group II Projects under similar Project Types as declared in Presidential Proclamation No. 2146
EIA Report Type for Corresponding Projects Size/Threshold

Project Grouping Matrix for Determination of EIA Report Type - New Single and Co-located Projects (Group II)

Group II Non-ECPs in Environmentally Critical Areas (ECAs)

Table 5.4

5.5.4 Environmental Management Plan (EMP)


EMP is a framework comprised of environmental commitments outlined in the EIA
report, environmental mitigation measures, standards and plans, and monitoring requirements
throughout the project implementation. It is the project specific activity plan designed to
minimize the negative impacts identified in the EIA process.
The objectives are:
*

To provide a detailed action plan for the implementation of the recommendations made
in the impact assessment report;

To provide goals and targets for environmental control that are measurable and
auditable;

To provide a basis on which the prospective contractor can accurately price for
environmental management in his tender document;

To specify particular roles, responsibilities and time scales;

To provide a basis for monitoring compliance;

To provide a site management tool;

To form part of the construction specifications;

To go beyond the construction phase and cover the whole project cycle including
operation;

To develop the detailed design in an interacted process to form a coherent and


consistent operational tool; and

To see to it that a dynamic plan will be able to incorporate and interpret new and
improved measures.

The Contractor shall take all reasonable steps to protect the environment on and off the
site and to avoid damage or nuisance to persons or properties. The Contractor shall comply
with the measures given in the ECC issued by the Environmental Management Bureau (EMB)
and shall take all reasonable precautions to avoid harm to the living and work environment in
accordance with the Environmental Management Plan prepared based on the EIA.
The Contractor shall strictly comply with the conditions stipulated in the ECC issued to
the project. The Contractor shall submit an overall EMP to meet those conditions within
fourteen (14) days after the receipt of Notice to Proceed for approval of the Engineer taking
those conditions into account. The Contractor shall also submit monthly EMP status report to
the Engineer.
Categories of Environmentally Critical Areas Sanctuaries:
1.

5 - 14

Areas declared as parks, watershed and wildlife reserves

Road Project Management and Supervision Manual Vol.1 Main Text

2.

Areas set aside as aesthetic, potential tourist spot

3.

Areas which contributes habitat for any endangered or threatened species of


indigenous Philippine wildlife (flora or fauna)

4.

Areas of unique historic, archeological, geological and scientific interest

5.

Areas which are traditionally occupied by cultural communities or tribes

6.

Areas frequently visited or hard hit by natural calamities

7.

Areas with critical slope

8.

Areas classified as prime agricultural lands

9.

Water bodies

10. Mangrove areas


11. Coral reefs
12. Recharged areas of aquifers

5.5.5 Environmental and Social Considerations


Projects financed by foreign funding agencies must comply with their general guidelines
on social and environmental enhancement.
(1)

Japan International Cooperation Agency


The agency requires the following:
*

Compliance with environmental pollution standards;

The natural environment in regard to conservation of endangered species and


biodiversity;

Plans for involuntary resettlement must restore living income for project affected
people;

The costs to conserve the environment must be included in the project cost;

Pollution control equipment and financial monitoring must be covered in


operations and maintenance; and

A third party other than the executing agency is desirable in the interests of
objectivity, in the evaluation and monitoring of project-related environmental
measures.

(2)

World Bank
Environmental Assessment (EA) is to ensure its environmental soundness and
sustainability and it;
*

evaluates a project's potential environmental risks and impacts in its area of


influence;

Road Project Management and Supervision Manual Vol.1 Main Text

5 - 15

examines project alternatives;

identifies ways of improving project selection, siting, planning, design. and


implementation by preventing, minimizing, mitigating, or compensating for
adverse environmental impacts and enhancing positive impacts; and

includes the process of mitigating and managing adverse environmental impacts


throughout the project implementation.

The EA takes into account the natural environment (air, water and land), human
health and safety, social aspects (involuntary resettlement, indigenous people and cultural
property) and transboundary and global environmental aspects. The EA should be
initiated as early as possible in project planning and is integrated closely with the
economic, financial, institutional, social and technical analyses of a proposed project.

(3)

Asian Development Bank


It sets environmental assessment requirements and review procedures to ensure that
appropriate environmental considerations are properly integrated into and monitored in
each stage of the project cycle. Initial Environmental Examinations (lEEs) and
Environmental Impact Assessments (EIAs) are among the main tools for complying with
its requirements.

5 - 16

Road Project Management and Supervision Manual Vol.1 Main Text

5.6 Risk Management


There are many potential risks, such as financial, contractual, weather (heavy rain),
floods, environmental/safeguard, etc, which may endanger viability of the project or cause
substantial cost and time increase though the degrees of their impacts differ. A risk
management approach should be adopted for a large and/or complicated project to mitigate or
reduce fatal incidents.
All risks should be identified at the beginning of construction stage and the Engineer
shall analyze the nature and probability of risks and prepare measures as illustrated in the
following figure employing the latest risk management methodology.

Major Risks antipated in Road Projects


Financial Capacity of GOP

(Typhoon, Floods, etc.)


Source: JICA TCP Team

Figure 5.8

Risk Management Diagram

The Engineer should adopt appropriate actions to reduce or mitigate the risks, especially
those which may endanger the project or cause serious adverse impacts on the residents at the
earliest possible time.
The risks are monitored continuously during implementation and respective report
(including risk status, assessment and recommendations) should be prepared at quarterly
basis.

Road Project Management and Supervision Manual Vol.1 Main Text

5 - 17

Chapter 6

Construction
Management and
Supervision

6.1 Preliminary Activities


The activities to be undertaken by the Implementing Office are, but not limited to, the
following as illustrated in Figure 6.1.

Figure 6.1

6.1.1

Stages of Implementation

Study of Design Reports, Design Drawings, Specifications and


Contract Documents

The Engineer shall undertake a comprehensive review of the design reports, original
plans and contract documents in order for him to be familiar with the basic information of the
project.
(1)

Design Reports and Drawings


Important points to be studied are summarized below.

Road Project Management and Supervision Manual Vol.1 Main Text

6-1

Table 6.1
Report
Design

Geotechnical and
Materials

Earthworks
Pavement

Bridge

Drainage

Slope and scouring


protection

Miscellaneous structure
and road facilities
Type of soil

Original Plan

Checklist of Reports for Review

Category
Geometric

Bridge Site Boring


Data
Slope stability and/or
weak ground
Construction Materials
Plan and Profile

Quantity / Cost
Estimate Report
Environmental
Report
ROW

Others
(Road Safety
Audit Report)

6-2

Typical Roadway
Sections
Detailed Cross Sections

Bridge and structures

Drainage Schedule

Other Structures
Summary of Quantity
Quantity Calculation
Cost Estimate
Environmental Impact
Assessment
Parcellary Survey
Land Acquisition and
Resettlement
Traffic Control
Road Safety Structures,
Road Signage,
Markings

Points to study
Design speed, standard roadway width (cross section, carriageway,
shoulder), horizontal and vertical alignment, design grade, sight
distance, etc.
Slope and extent of cut and fill; soil classification/type
AADT (Current and future vehicle types)
Design Parameters (ESAL, CESAL, Design Methods, Design CBR,
Materials, Structural Layer Thickness, Sc, fc, etc.)
Design parameters (design load, dimensions, bearing system, etc)
Flood elevation and scouring depth
Structural analysis and reinforcing design
Discharge and flow analysis
Location and sizes of drainage structures (RC Box culverts and
pipes) and road side drains
Slope stability analysis, countermeasure design, retaining wall
design
Scouring analysis and protection design
Location and type
Dimensions (length, height, etc)
Sub-soil classifications, CBR, PI
Soft ground, rock
Boring log (soil classification, SPT, depth of bearing layer)
Location, topographic and geotechnical condition, countermeasure
design and/or structures
Specifications, availability and sustainability, sources
Location of control points and coordinates, bench marks and
elevation
Location of curves, structures and road facilities (existing and
proposed)
Elevation of existing ground and finished grade
Extent of cut and fill
Location of cross pipes, ditches
Road width and pavement thickness
Location of cut and fill (especially high cut or fill), extent of cut and
fill slopes
Position of earth retaining structures/ slope protections
Plan, profile, elevation, structural details
Reinforcement schedule
Type, dimensions and locations
Reinforcement schedule
Road signs, guard rails, guide posts, Km posts, ROW posts, etc.
Bills of Quantity with quantity estimation reports
Any calculation errors
Project cost and unit price analysis
Environmental Management Plan(EMP)
Environmental Compliance Certificate (ECC)
Parcellary Survey Drawings
Status of Land Acquisition and Resettlement
Existence of traffic diversion road and its capability
Villages and shops near ROW
Verify accident prone areas and sections that require additional road
signs and alignment improvement, etc.

Road Project Management and Supervision Manual Vol.1 Main Text

(2)

Specifications
The DPWH Standard Specifications for Highways, Bridges and Airports, Vol. II,
2013 Edition and other special provisions shall be used.

(3)

Contract Documents
This shall include the following:
(a)

Contract Agreement
-

Contract ID Number, Contract Name and Location of the Contract

Description of the Project, Limits, Scope of Work and Quantities

Contract Amount and Duration

(b)

(c)

Conditions of the Contract


-

Advance and Progress Payments

Liquidated Damages, Retention, Price Escalation


Others
If an ambiguity or discrepancy is found in the documents, the implementing

official shall issue any clarification or instruction.

6.1.2

Study on Meteorological Condition

The meteorological condition influences not only the work progress but also quality and
cost. The Engineer should collect climate records including rainfall, typhoon, floods and other
hydrology conditions from the nearest PAGASA office and incorporate such conditions in the
implementation management plan.
2,400
2,200
2,000
1,800
1,600
1,400
1,200

Rainfall (mm

1,000
800
600
400
200
1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004

Monthly Rainfall Variation (1992-2005)

Figure 6.2

6.1.3

Yearly Rainfall Variation (1992-2004)

Example of Rainfall Record

Pre-construction Survey

The Engineer shall conduct detailed pre-construction survey to verify the following:

Road Project Management and Supervision Manual Vol.1 Main Text

6-3

The location and limits of the project;

Current road conditions;

Towns and villages situated within the project including public facilities such as
schools, hospitals, churches etc.;

6.1.4

Progress of ROW acquisition and resettlement;

Proposed disposal areas and quarry sites;

Possible access and detour roads; and

Others

Joint Site Inspection

A joint site inspection shall be conducted in order to be familiar with the project site.
Project briefing shall also be made during the inspection.
The participants and the scope of inspection are tabulated in Tables 6.2 and 6.3,
respectively.
Table 6.2
Entity
The Implementing Office

Participants for Site Inspection


Foreign-funded Project

Locally-funded Project

Consultants:

Project Engineer

Project Manager(PM)

Project Inspector

Other key staffs

Materials Engineer

Employer:

Other key staffs

Project Manager
Project Engineer
Other key staffs
The Contractor

6-4

Project Manager

Project Manager

Other key staffs

Other key staffs

Road Project Management and Supervision Manual Vol.1 Main Text

Table 6.3

Scope of Inspection

Category
The Project itself

Scope
-

Start and end points(Limits)

Towns, villages and public facilities

Access road to the project site

Major items of work involved such as earthworks, pavement,


bridge etc.

Quarry sites and

Locations

Proposed locations

ROW Acquisition and

ROW status (land acquisition and resettlement)

Utility Relocation

Lot for Contractors temporary facilities

Environmental

Major Environmental issues stated in the ECC/EMP

Traffic Control

Existing traffic condition and road safety measures

Possible detour road

disposal areas
Planned Camp Site and
Plant Yard

6.1.5

Conduct of Pre-construction Meeting

The Engineershall conduct a pre-construction meeting with the Contractor to discuss,


among others, the following:

Road Project Management and Supervision Manual Vol.1 Main Text

6-5

Table 6.4

Agenda for Pre-construction Meeting

Agenda
1

Officials and Personnel involved and


their respective
assignments/functions, duties and
responsibilities.
A)

Matters for Discussion


-

Information about the personnel involved namely:


Heads of Implementing Office and Contractors representatives.
Project Engineers, Quantity Engineers, Materials Engineers, Project
Inspectors and Administrative staffs
Functions/responsilbilities shall be clearly defined such as: preparation
of letters/memoranda, quantification of work accomplished,
preparation/submission of construction drawings and others.
Facilities for the Engineer including vehicles, office equipment,
supplies, furniture etc. as stipulated in the Contract
Set up operational and maintenance rules
Bar Chart/S-Curve and PERT/CPM
Payment (disbursement) schedule
Equipment and material schedule
Weekly and monthly schedule and progress monitoring
Confirm the required manpower/equipment to be provided

Work and inspection request and approval


Work days and working hours
Instruction and recording
Measurement and billing preparation
Contractor will explain any proposed deviations

Proposed sources
Quality tests and approval
Project laboratory and testing equipment
Preparation of Quality Control Program
Accredited Materials Engineer and testing laboratories
Proposed locations of Engineers and Contractors offices and project
laboratory
Batching Plant yards
Borrow and disposal sites
Supply of contract drawings
Control points and as-stake survey
Shop drawings preparation and approval
Maintenance and traffic management plans
Coordination with concerned agencies
Re-routing plan (if necessary)
Provision of suitable safety and health program in accordance with the
Department of Labor and Employment rules and regulations.
ROW acquisition including resettlement

Monthly Progress Report Preparation


Monthly Materials Quality Control Report preparation
To be submitted by the Contractor prior to mobilization

Coordination meetings with ROs and DEOs


Preparation of minutes of meeting
Project Bill Board
Labour Welfare and Safety
Utility Relocation

Approval of Contractors

Organizational Chart
2

Program of Work

Weekly/Monthly schedules and


progress meeting B)

Equipment and Manpower

Utilization
5

Work procedures

Methodologies

Material sources and borrow areas

Quality Control

Base camp, plant yard and disposal


areas

10

Preparatory Works

11

Existing road maintenance and traffic


control

12

Environmental Compliance

Certificate ,Environmental
Management and Safety Plans
13

Reports

14

Contractors All Risk Insurance


(CARI)

15

6-6

Others

Road Project Management and Supervision Manual Vol.1 Main Text

(A)

Approval of Contractor's Organizational Chart


The Contractor shall submit his organizational chart for approval of the Engineer. The

organizational chart shall include the names of the PM, PE, Highway Engineer, Bridge
Engineer, ME and other key staffs.
The Contractor shall likewise submit their respective Curricula Vitae for approval of
the Engineer.
(a)

For Foreign-Funded Projects:


The PM shall be the head of the project and the delegated authority by his
Head office for the management of the project. A typical organizational chart is
shown in Figure 6.3.

(b)

For Locally-Funded Projects


The Contractors organization will vary depending on the contract size and
complexity. If large, it will be similar to the foreign-funded projects. The PM shall
be the head of the project and delegated the authority by his head office for
operation and management of the project. A typical organizational chart for medium
size contract is shown in Figure 6.4.

Road Project Management and Supervision Manual Vol.1 Main Text

6-7

6-8

Road Project Management and Supervision Manual Vol.1 Main Text

** BRIDGE ENGINEER

SUPPORT STAFF:
JR. ENGINEER
LABORERS

5.
** HIGHWAY ENGINEER

PROJECT MANAGER TO BE ASSIGNED SHALL BE THE SAME


PERSON AS INDICATED IN THE PQ DOCUMENT.

SUPPORT STAFF:
JR. ENGINEER
LABORERS

4. DRAINAGE & SLOPE


ENGINEER

Source: PJHL/DPWH

Figure 6.3

6.

1
2
3
4
5
6
7
8
9
10
11
12
13

NO

SITE ENGINEERS/
FOREMAN

7. ** CONSTRUCTION
SUPERINTENDENT

NAME OF KEY STAFF

LABORATORY TECH.
LABORATORY AIDES
CLERK / TYPIST

** MATERIALS &
QUALITY
CONTROL ENGINEER
SAFETY
SUPERINTENDENT

ENVIRONMENTAL
SUPERVISOR

SAFETY SUPERVISOR

8.

NATIONALITY

PROJECT ENGINEER

* PROJECT MANAGER

14
15
16
17
18
19
20
21
22
23

NO

11.

FINANCE OFFICER

Example

NATIONALITY

SUPPORT STAFF

10. ADMINISTRATIVE
OFFICER

NAME OF KEY STAFF

SUPPORT PERSONNEL

9. PLANT / EQUIPMENT
MANAGER

Typical Organizational Chart of Contractor for Foreign-Funded Project

(2) ** THE POSITION NAME OF KEY PERSONNEL SHALL BE


DEEMED TO BE SAME AS INDICATED IN
PQ DOCUMENT

(1) *

NOTES:

SUPPORT STAFF:
JR. ENGINEER
LABORERS

3.

2.

1.

CONTRACTOR'S ORGANIZATIONAL CHART

Case 1

Proprietress
Liaison Officer
Construction Safety and Health
Personnel
Project Manager

Project Engineer

Material Quality
Control Engineer

Foreman

Laboratory Head

Labors, Masons, Steelmen,


Welders, Carpenters

Laboratory Technicians/Aids

Case 2

Head Office
Purchasing / Accounting
Project Manager
Project Engineer

Quality
Control Engineer (ME)

Civil Engineer

Mechanical Engineer

- Surveyor
- Foreman
- Leadman
- Steelman
- Mason

- Mechanic
- H.E.Operator
- Rigger
- Driver
- Helper

- Laboratory Technician
- Aid
- Laboratory Head

Safety Engineer
- Company Nurse
- Electrician
- Skilled Personnel

- Carpenter
- Labourer

Source: DPW H

Case1: Single Proprietorship,

Figure 6.4

Case 2: Corporation

Typical Organizational Chart of Contractor for Locally-Funded


Project

(B)

Weekly/Monthly Schedules and Progress Meetings


The Engineer shall be the organizer and the chairperson for these meetings. The
attendees shall be as shown in Table 5.4 and matters to be discussed are, but not limited
to, the following:
*

Appoval of the Minutes;

Work schedules and progresses (physical and financial);

Road Project Management and Supervision Manual Vol.1 Main Text

6-9

Discussion on various problems and issues to draw action plans;

Guidance on project implementation and/or technical clarification; and

Other matters

In special circumstances, invitations may be extended to other parties such as the


local government units, utility companies, ROW committee and other concerned.
The secretary, who will be from the Implementing Office, Consultant or the
Contractor, shall be responsible for the preparation of the Minutes. The Minutes shall
contain points of interest and importance only.
The following shall be clearly stated:
*

Time and place of meeting;

Names of participants and who they represent;

Issues raised by whom;

What decisions were taken; and

Actions to be taken by whom and when.

The Minutes is a formal record and therefore, it must be duly signed.


Table 6.5
Entity
The

Attendees for Meeting

Foreign-funded Projects
Implementing Consultants:

Office

Locally-funded Projects
Project Engineer*

Project Manager*

Project Inspector

Resident Engineer

Materials Engineer

Site Engineers

Other key staffs

Quantity Engineer
Materials Engineers
Other key staffs
Employer:
Project Manager
Project Engineer
Other key staffs
The Contractor

Project Manager

Project Manager

Deputy Project Manager / PE

Deputy Project Manager / PE

Site Engineer

Site Engineer

Materials Engineer

Materials Engineer

Plant Engineer

Plant Engineer

Safety Officer

Safety Officer

Other key staffs

Other key staffs

* Chairperson

6 - 10

Road Project Management and Supervision Manual Vol.1 Main Text

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 11

Aggregate Base Course

201

Steel Sheet Pile Type II

Stone Masonry

Structural Excavation

Foundation fill

Reinforcing steel

Concrete Class A

Lean Concrete

1702(2)

1702(2)

1712(1)

1712(2)

1712(4)

D.A.No.4

D.A.No.5

27.35
27.35

594.72
594.72
671.40
671.40

985.08
985.70

m2
2

m3
m3
3

m
m3

m2
m2

Sta.4+200 - 5+200
Sta.12+800 - 13+200
Sta.4+200 - 5+200
Sta.12+800 - 13+200

(Sta.1+980-2+184)

No.7-10,
No.2, 4,

Sta.1+120-1+210(L)

Sta.1+120-1+210(L)

Sta.12+470 - 12+527

Sta.12+800 - 13+200

Sta.4+500 - 5+500

Source: PJHL / DPWH

Figure 6.5

(Name)
Contractor

Plant modification/improvement
Fabrication of reinforcement

Concrete Plant at Magdugo


Asphalt Plant at Magdugo
RCP at Base Camp

Prepared by

Pavement concrete for PCC t=200mm

Concrete Plant at Talisay

(Sta.16+140-16+540)

PRODUCTION

Aggregate Subbase

Foundation Conc.

Foundation Conc.

Foundation Conc.

(Sta.4+476-4+514)

(Sta.3+348-3+388)

(Sta.3+010-3+045)

Adjustment of Plant

200

207.66

m2

Sta.13+700 - 14+070

Crushing Plant at Magdugo

D.A.No.11

SPL105(4) Subgrade Improvement

Foundation fill

1711(1)

D.A.No.3

207.66

m2

Sta.8+000 - 8+800

771.00

m3
kg
3901.03
456.00
594.72

m3
m3

l.m.

To be Filled

(Peso)

AMOUNT

To be Filled

ESTIMATED
QUANTITY
9
MON

11
WED

MAY
12
THU
13
FRI

(Name)
Project Manager, Contractor

Submitted by

10
TUE

Typical Weekly Work Schedule

7095.00

m3

56.55

10350.00

771.00
2690.20

m3

4148.78

m3

l.m.

231.01
13475.62

5091.10

m3
m
l.m.
each

562.11
3865.96

m3

196.74

Sta.5+200 - 6+500

Sta.5+200 - 6+500
205.92

UNIT
PRICE
(Peso)

UNIT

m3

LOCATION

Steel sheet piling preparation (Sta.2+620-2+940)


works

1717(1)

1702(2)

D.A.No.2

D.A.No.1

Cleaning RCPC
Cleaning RCBC

503(3)
503(3)

Concrete Class B

405(2)

Drainage

Foundation Fill

Lean Concrete

103(2)

PCC Supporting Blocks

PCCP t=200mm

Aggregate Subbase

200

Removal of PCCP

101(3)

Subgrade Preparation

Surplus Unclassified Exc.

102(4)

105

Surplus Common Exc.

102(2)

Drainage & Slope Protection


Slope Protection
103(1)

Surface Course

Subbase / Base

Earth Works

DESCRIPTION

ITEM
NO.

MATERIALS

FLOOD
CONTROL

ROADWAY

CATEGORY

WEEKLY WORK SCHEDULPERIOD MAY 9TH - 15TH, 2005

(NAME OF CONTRACTOR)
(PROJECT NAME)

14
SAT

15
SUN

(Date)

(Foreman)

To be Filled

To be Filled

(Engineer)

Supervisor in Charge

6.1.6

Conduct of Joint As-stake Survey and Preparation of As-staked Plan

The Engineer shall monitor the conduct of joint as-stake survey in accordance with the
original plan. The Contractor shall then prepare and submit as-staked plans based on the
as-stake survey for review of the Engineer and approval of the implementing official. The
as-staked plans and the corresponding back-up quantity calculations must be completed
within a reasonable period from the commencement of the project. These shall reflect the
modifications, including changes in road alignment, types or main components of structures,
introduction of new work items and others.
The Contractor shall promptly notify the Engineer of any error, omission or defects such
that these are reported to and decided by the implementing official on whether a Variation
Order is necessary.
The Engineer shall furnish the Contractor the horizontal and vertical control points and
other reference data for each element of the work.
The Contractor shall be responsible for the true setting of the works or improvements,
correctness of positions, levels, dimensions, alignments and preservation of all stakes and
marks.
Established control points shall be within the tolerances as prescribed in the DPWH
Standard Design Guidelines, Criteria and Standards and DPWH Standard Specifications for
Highways, Bridges and Airports, Vol. II 2013 Edition. For supplemental reference, refer to
Table 6.6.

6 - 12

Road Project Management and Supervision Manual Vol.1 Main Text

Table 6.6

Control Points and Tolerances


Tolerance

Control Point
Existing Government network
Local supplemental control points set from exisiting
Government network points
(4)
Centerline points -(PC), (PT), (POT), and (POC) including
references
Other centerline points
(5)
Cross section points and slope stakes
(5)
Slope stakes references
Culverts, diches and minor drainage structures
Retaining walls, curb and gutter
Bridge substructures
Bridge superstructures
Cleaning and grubbing limits
(7)
Roadway subgrade finish stakes
(7)
Roadway finish grade stakes

Horizontal
10 mm
10 mm

Vertical
(2)
8 mm K
3 mm N

10 mm

10 mm

50 mm
50 mm
50 mm
50 mm
20 mm
10 mm
10 mm
500 mm
50 mm
50 mm

50 mm
50 mm
50 mm
20 mm
10 mm
10 mm
10 mm
-- 50 mm
50 mm

(3)

(1) At 95% confidence level, tolerances are relative to existing Government network control points.
(2) K is the distance in kilometers.
(3) N is the number of instrument setups.
(4) Centerline points: PC - point of curve, PT - point of tangent, POT - point on tangent, POC - point on curve.
(5) Take the cross-sections normal to the centerline + 1 degree.
(6) Bridge control is established as a local network and the tolerances are relative to that network.
(7) Include paved ditches.
Source: Japan Standard

The approval of the As-staked plan does not relieve the Contractor of responsibility for
correcting errors discovered during the work and for bearing all additional costs associated
with the error, unless such error is based on incorrect data supplied in writing by the Engineer.
If there will be changes in the survey, the Contractor shall coordinate with the Engineer to
facilitate prompt reestablishment of field controls.
Shown below is a sample flowchart of activities for as-stake survey and as-staked plan.

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 13

As-stake Survey and As-staked Plan Preparation


Period:May 1 June, 30,20___

Location: Sta.___________ Sta.____________

(2 months)

Schedule

The Contractor

The Project Engineer


(One Survey Team)

(Two Survey Teams)


Start
May 1,
Control Points
Survey

May 5

Road Centerline
Survey

Inventory / PCCP Condition Survey


including Sta. of each panels

Road Cross Section


Survey

May 20

Inventory of Cross
and Roadside
Drainages

May 25

Measurement of
Quantities for PCCP
Replacement

As-staked Plan
Preparation

June 15

Quantity and Cost


Comparison

Review and evaluation


of the Project Engineer

June 15

Clarification
Approval for
Implementation

June 30

Figure 6.6

Flowchart of activities for As-stake Survey and Approval of


As-staked Plan

6.1.7

Preparation and Processing of Variation Order (VO)

Variations may be initiated by the Engineer either by an instruction or by a request for


the Contractor to submit a proposal. The Contractor shall execute and be bound by each
Variation, unless he promptly gives notice to the Engineer stating that (i) He cannot readily
obtain the goods required for the Variation, or (ii) Variation triggers a substantial change in the
sequence or progress of the Works. Upon receiving the notice, the Engineer shall cancel,
confirm or vary the instruction.

6 - 14

Road Project Management and Supervision Manual Vol.1 Main Text

Each Variation may include:


(a) Changes in the quantities of any item of work included in the Contract;
(b) Changes in the quality and other characteristics of any item of work;
(c) Changes in the elevations, positions and/or dimensions of any part of the Works;
(d) Omission of any work unless it is to be carried out by others;
(e) Any additional work, plant, materials or services necessary for the Permanent
Works, including any associated tests on completion, boreholes and other testing
and exploratory work; and
(f)

Changes in the sequence or timing of the execution of the Works.

The Contractor shall not make any alteration and/or modification of the Permanent
Works, unless and until the Engineer instructs or approves a Variation. The cumulative
amount of the VO should not exceed ten percent (10%) of the original project cost. The
addition or deletion of works should be within the general scope of the project as bid and
awarded.
A VO may either be in the form of a Change Order or Extra Work Order. A Change
Order is issued by the Engineer to cover any increase or decrease in quantities of original
work items in the contract. An Extra Work Order is issued by the Engineer to cover the
introduction of new work necessary for the completion, improvement or protection of the
project which were not included as items of work in the original contract
Any cumulative VO beyond ten percent (10%) shall be subject of another contract to be
bid out if the works are separable from the original contract in principle. In exceptional cases
where it is urgently necessary to complete the original scope of work, the Implementing
Office may authorize the Variation Order beyond ten percent (10%) but not more than twenty
percent (20%) subject to the guidelines to be determined by the Government Procurement
Policy Board (GPPB).
In claiming for any VO, the Contractor shall, within seven (7) calendar days after such
work has been commenced or after the circumstances leading to the extra cost, and within
twenty-eight (28) calendar days, deliver a written notice to the Engineer. The notice should
include full and detailed particulars of any extra cost. Failure to provide either of such notices
in the time stipulated shall constitute a waiver by the Contractor for any claim.
The preparation and submission of VOs are as follows:
(a) If the Engineer believes that a Change Order or Extra Work Order should be
issued, he shall immediately instruct his technical staff to conduct an on-the-spot
investigation to verify the need for the work;

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 15

(b) The Engineer, after being satisfied that such Change Order or Extra Work Order is
justified and necessary, shall review the estimated quantities and prices and
forward the proposal with the supporting documentation to the Implementing
Office for consideration; and
(c) After review of the plans, quantities and estimated unit cost of the items of work
involved, the DPWH will review and evaluate Change Orders or Extra Work
Orders for approval.
Prior clearance is required to provide for efficient implementation and management.
All requests for Prior Clearance to Issue Variation Order on Civil Works and/or
Consultancy Services Contracts shall be submitted by the Implementing Office(IO)
directly to the Office of the Assistant Secretary for Operations concerned, for review and
recommendation in accordance with DO No. 12, Series of 2009.
Prior clearance to issue variation order should not be taken as an outright approval
for the variation order itself. A "request for prior clearance" should only be for the
approving official to establish the need for additional works/variations. As such, the
request need not be supported by voluminous supporting documents normally required
for the review/evaluation of plans and proposed variation orders. Only the basic
documents required under the Memorandum of the Secretary dated 25 August 2003 shall
be submitted. To facilitate the review process, the IO shall provide a corresponding
Executive Summary using the standard format as shown in Figure 6.7. A routine slip
which includes a checklist of required supporting documents shall likewise be prepared
by the IO.

6 - 16

Road Project Management and Supervision Manual Vol.1 Main Text

Figure 6.7

Executive Summary

After the review of the request by the concerned Assistant Secretary for Operations, the
same shall be forwarded to the Office of the Undersecretary for Operations concerned, prior to

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 17

the approval/disapproval of the Secretary. If the request involves additional funding, then it
shall be referred to the Planning Service for evaluation and recommendation.
DO No.03, Series of 2005 must be noted in line with DO No. 17, Series of 2007 that:
*

No work shall be commenced covering any Variation Order (Change Order/ Extra
Work Order) of foreign or locally funded projects without the Request for Prior
Clearance being first approved by the Secretary;

No Services pertaining to any Addendum/ Re-alignment/ Supplemental Agreement of


foreign or local consultant shall be commenced without first securing approval of the
Request for Prior Clearance to Issue Addendum / Realignment/ Supplemental
Agreement;

Works undertaken by the Contractor or Services performed by the Consultant in


violation of the above shall not be paid by the DPWH (Implementing Office) and shall
be deemed personal liability of the person who authorized the commencement of the
work; and

All officials and employees who allowed the commencement of such work shall be
liable administratively after hearing, pursuant to existing Civil Service Laws, Rules
and Regulations.

6.2 Project Management


Project Management is a control system designed to accomplish a project within the
prescribed quality, cost and duration. It is one of the advanced approaches for project
implementation in order to attain minimum life cycle cost and maximum benefit for the public
on long-term aspects. It is comprised of time (schedule), cost (finance), quality assurance and
safety/environment management as illustrated in the following figure.
PLAN
(Design)

REVIEW
(Evaluation)

Minimum Life
Cycle Cost &
Maximum
Benefit for
Public

Time
(Schedule)

DO
(Construction)

Cost
(Finance)

Quality
Project
Management Assurance

Safety
& EMP
OPERATION
(Maintenance)

Project Cycle Management Approach

Figure 6.8

6 - 18

Components of Project Management

Project Management

Road Project Management and Supervision Manual Vol.1 Main Text

In pursuing not only a road project, effective control of resources and proper time
management without compromising the quality is of utmost concern. DPWH has its existing
policies/requirements/acceptable practices taken from different management approaches that
could be used by the Engineer to manage projects and discover their own approach later on.
The Engineer should learn to organize a group that can function productively with
optimum resources under minimum supervision. A thorough study of the project needs must
be done so that the framework of workforce could be set in diagram or chart to analyze and
realize a good organization set up.

6.2.1

Mobilization/Demobilization

The Contractor shall mobilize the required minimum plants, equipment, temporary
facilities and personnel for implementation of the project as stipulated in the Contract.
The work and activities shall include the following:
*

The purchase and/or rental of all land required for the Contractors base camps and
construction activities. The location of base camps shall be subject to the approval of
the Engineer. The Contractor shall provide sufficient area required for scheduled
operations of rock/gravel crushing plant, asphalt and concrete production plants, and
other requirements for the completion of the Works;

Mobilization and installation of construction plant from existing locations or port of


unloading to the project sites;

The construction and maintenance of the Contractors base camps including offices,
living quarters, workshops, stores, etc.;

Mobilization and demobilization of the Contractors Equipment and work forces; and

Demobilization of the sites occupied by the Contractor at the end of the Contract
including the removal of all installations, construction plants and equipment.

Only the equipment and plants appropriate to produce the required quality of work and
materials shall be permitted to operate on the project. The Contractor shall provide
appropriate equipment and plants to meet the construction requirements, and when ordered by
the Engineer, shall remove unsuitable equipment from the work or stop the operation.
The Contractor shall not demobilize and/or use the mobilized equipment for other
projects without prior written approval of the Engineer.

6.2.2

Provision of Project Billboard

The Contractor shall install Project Billboards at least one (1) at the beginning and
another one (1) at the end of the project at locations designated by the Engineer prior or upon

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 19

commencement of the Works. It shall be fabricated in conformity with the DO No.83, Series
of 2005 Installation of Revised Project Billboard Requirements.

6.2.3

Work Program

The Contractor shall, within ten (10) calendar days from receipt of the Notice of Award,
submit to the Implementing Office, for approval, complete documentary requirements to
include work program that contains the following:
(1)

Construction Schedule
The Contractor shall submit to the Engineer an approved construction schedule
indicating the sequences of works to be implemented, the planned rates of progress and
the estimated periods of time for execution andcompletion as well as the corresponding
cash flow.
(a)

Pert/CPM
Is a network diagram showing all activities or events for the completion of the
project within the contract period. It gives emphasis on the activities along the
critical path. The Engineer shall review and provide comments as follows:
*

Whether the quantities of the works to be executed agree with the construction
period, construction plant/equipment, materials and manpower schedule.

Whether the basic sequence of works meets the requirements of the Contract.

Whether the program makes opportunities available for other Contractors and the
requirements of other authorities such as utility owners in relation to service lines
relocation.

Whether the program is realistic in relation to the seasons and other constraints,
including financial capacity of the Contractor.

6 - 20

Road Project Management and Supervision Manual Vol.1 Main Text

(b) Bar Chart with S-curve

A time-sequenced Bar Chart based on the Pert/CPM diagram with the progress

S-curve, indicating the monthly progress estimates of accomplishments in every major

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 21

Source: PJHL/DPWH

2.5 Separate Landslide


Movement Observation in
Activity 4->14 from others
since this shall be a
continuous activity up to the
end of construction period.

2.4 Do not connect Activity 3>15, Activity 15->25 (bridge)


and Activity 25-> 39 since
those are not related each

Add a separate activity


for Seal Coat for
Damaged PCCP, etc. for
a duration of 3-months.

2.7 Earliest Start and Latest


Start Date computation in some
activities are wrong, please
calculate again and correct
accordingly

2.2

1
0

2.5

2.4

01

6 0 C.D.

M ove -in

02

60

60

60

60

60

60

04

120

9 0 C.D.

120

120

150
150

10

12

13

14

15

16
17

2.6

1 5 0 C.D.

7 2 0 C.D.

300

17

19

3 0 0 C.D.

480

22

1 5 0 C.D.

Gab io n Bo x & Ga bion Mattress

1 5 0 C.D.

14
200 210

230

240

15

1 8 0 C.D.

F LOOD C ONT R OL & DRAINAGE


S te el S he et Piles

330

4 8 0 C.D.

Gab io n Bo x & Ga bion Mattress

3 0 0 C.D.

R EP AI R OF S IX ( 6) BRIDGES

2 1 0 C.D.

Example of Pert/CPM

320

20

21

F LOOD C ONT R OL & DRAINAGE


S tr uctu ra l Co ncre te , Gr outed Riprap
& S to ne M asonry

440 450

1 8 0 C.D.

3 3 0 C.D.

530 540

25

530 540

24

1 8 0 C.D.

6 0 C.D.

32

590

590

600

28

600

27

690

30

630

31

29

24

Example
23

9 0 C.D.

I nsta lat io n of
R oad Signs

660

33

3 0 C.D.

C omp lete
S ubbase
( Sho uld er)

660 660

34

37

38

1 5 0 C.D.

680

690

40

680 690

39

680 690

3 0 C.D.

M ove -out

690 690

35

680 690

36

680 690

41
720

720

Note:
Comments in red color

630

630 660

9 0 C.D.

P avem en t Ma rkings
& R ef le ct or ized
P ave men t S tuds

1 2 0 C.D.

630

620

630

I nsta lat o
i n of M et al Guardrail

S od ding &
T ree Plant ing

F LOOD C ONT R OL & DRAINAGE


S eed -Mu d S pra yo n S lopes

620

22

2.6 Activity 19->30


Cleaning/Reconditioning of
Pipe Culvert & Box Culvert
should be completed before the
next rainy season (June July
2005) as much as practical

21

2.3 Activity 18->34, Start AC


Pavement & Continue PCC
C oncret e C urb , R igh t-o f-Way Mon ume nt,
Pavement (200mm & 300mm)
M ain t. Dra ina ge Mar ker Po st & K M P ost
be separated to two (2) activities

20

C om plet e Ma so nr y Lined Canal

S ta rt A C Pa ve me nt & C on tinu e PC C Pa ve me nt ( 200 mm & 300 mm thick)

16

F LOOD C ONT R OL & DRAINAGE


Dre dg in g of R iverbed
& E mb an kment

330 330

18

260 270

1 5 0 C.D.

S ta rt P CC P avem en t (2 00 m m & 300 mm thick)

4 5 0 C.D.

C ont inu e Laying of Agg reg ate Su bba se & B ase Co urse

4 8 0 C.D.

S tar t E xca vat ion , E mba nkm ent , S ubg rad e P rep ara tio n & Su bgr ade Im provement

2.3 AC Pavement (Binder, Wearing Course, Crack Relief Layer)

3 6 0 C.D.

C on tinu e Re mo va l of E xist in g PC CP , ACP & RCPC

330 330

470

C le an in g / Re co nd ti o
i ning o f Pipe C ulve rt & BoxCulvert

1 8 0 C.D.

Grou ted Ripra p, Sto ne Masonry


& Ru bble C oncrete

23
470 480

19

26

290

3 0 0 C.D.

C on cr et e Line d Ca na l & Ma so nr y Ln
i ed Canal

18

560 570

Figure 6.9

1 5 0 C.D.

Obser va tion & I nvestiga tion

T op og ra ph ic , Ge olog ic al, Su bsoilStrata


S ur ve y, Lan dslide M ovement

11

13

C le ar in g & Gr ub bing , Removalof


T re es & E xcavation

1 8 0 C.D.

10

200 210

2 1 0 C.D.

F LOOD C ONT R OL & DRAINAGE

180 180

120 120

6 0 C.D.

11

S ta rt Laying of
S ubba se &
B ase Co urse

1 8 0 C.D.

C on tinu e La ying of RCPC

180

09

R CP C Co ncre te C at ch B asin & M ason ryCatch Basin

180

12

08

P ro vide , Op er at e an d Ma in ta in F acilit ie s fo r th e En gine er , Ge ne ra l Ro ad M aint en an ce , Co nt in ue s De live ry o f Construction Materials, Stake-out Survey

07

S ta rt R em oval o f Existing
P CCP , A CP & R CPC
C on tinu e Clea ring & Grubbing
& R em oval o f Trees

06

120 120

120 120

110

05

Deto ur Roa d f or Dam age d A rea s Nos. 11 , 1 2, 13 & 14 and


R em oval & S to ck o f Exis ting T em po ra ry S teelBridge

6 0 C.D.

Gru bb in g & Re moval


o f T rees

S tar t C lea rin g &

E AR THWORKS

6 0 C.D.

S ta rt Laying
o f R CPC
( In it ia l De l. of
R CP C Ma te rials)

03

PERT / CPM OF NAGA - TOLEDO ROAD PROJECT


Assume that the
UNDER ARTERIAL ROAD LINKS DEVELOPMENT PROJECT,
PHASE
IV1st month will
2.1 be October 2004 and show
rainy seasons of the project
PROVINCE OF CEBU

6.797

5 4,750, 354.64

R em oval o f Exis ting P CC P, A C Pa ve me nt & R C Pipe Culvert

E xcavat o
i n (Unsuita ble, C om mo n, Har d Ro ck, Un classified, etc.)

2.802

2.637

2 2,571, 859.24
2 1,242, 563.16

C on cr et e Line d Canal

M ason ry Lin ed Canal

0.105

8 43,954.25

T ota l f or Par t J

S eed -Mu d S pra yo n S lopes

Dra in ag e & Re mo va l & St ock of E xist in g Te mp or ar ySteelBridge

T OT AL

S CHEDULED C AS H FLOW

P ROGR ES S SC HE DULE

Daywo rk / P ro vision al S um

Source: PJHL/DPWH

P AR T K

0 .0 36

0 .3 13

0 .1 84

0 .2 89
0 .1 64

0 .2 81
0 .1 10

0 .2 31
0 .0 56

0 .3 87

0 .6 48

0 .3 78

0 .4 67

0 .3 60

0 .0 35

5 .0 99
9 3 .8 16

Figure 6.10

C UM ULAT IVE

M ONTHLY

1 6 .7 11

8 8 .7 17

8 3 .3 13

7 7 .1 05
2 1 .0 87

7 0 .0 57
6 3 .0 39

5 6 .0 18
1 7 .9 17

5 0 .0 21

4 4 .0 35

3 8 .1 01

QUA RT ER LY

1 7 .6 38

3 2 .1 92
2 6 .3 20

2 0 .4 63
1 5 .1 40

1 0 .5 08

6 .3 66

4 .1 48

2 .5 64

1 .8 00

1 .2 78

0 .6 39

C UM ULAT IVE

1 00.00

1 4 .0 97

5 .4 04

6 .2 08

7 .0 48

7 .0 18
7 .0 21

5 .9 97
5 .9 86

5 .9 34

5 .9 09

5 .8 72
5 .8 57

5 .3 23
4 .6 32

4 .1 42

2 .2 18

1 .5 84

0 .7 64

0 .5 22

0 .6 39

0 .6 39

M ONTHLY

8 05,600 ,004.69

4 .5 66

0 .0 88

0 .0 88

0 .0 88

0 .0 88

0 .0 88

0 .0 88

1 .8 00

0 .0 32

0 .0 40

0 .0 43

0 .0 41

0 .0 39

0 .0 35

0 .0 88

0 .0 88

0 .0 88

0 .0 88
0 .0 88

0 .0 88
0 .0 88

0 .0 88

0 .0 88

2.110

1 2.207
0 .0 88

1 7,000, 000.00

9 8,339, 611.03
0 .0 88

0 .5 33

0 .0 88

0 .0 61

0 .0 69

0 .0 81

0 .0 70

0 .0 55

0 .1 12

0 .1 35
0 .1 55

0 .2 26
0 .2 19

0 .2 25

0 .3 11

0 .3 67

0 .3 43
0 .2 72

0 .2 60

0 .3 55
0 .4 02

0 .0 53

0 .0 52

0 .0 88

0 .0 50

0 .0 53

0 .0 66

0 .0 56

0 .4 15

0 .5 61

0 .6 25

0 .6 98

0 .1 02

0 .1 47

0 .2 20

0 .2 10

0 .3 01

0 .2 50

0 .1 62

0 .1 82

0 .1 44

0 .1 86

0 .1 06

0 .1 42

0 .1 34

0 .3 31

0 .3 48

0 .5 09

0 .0 99

0 .1 26

0 .0 81

0 .3 95

0 .1 20

0 .0 98

0 .1 50

0 .1 87
0 .2 32

0 .2 39

0 .2 78

0 .2 01

0 .2 19

0 .2 20

0 .2 18

0 .2 14

0 .2 06

0 .0 06

0 .2 34

1 .6 99

1 .1 81

0 .1 95

0 .0 11

1 .9 51

1 .6 46

0 .2 18

0 .0 06

0 .2 28

2 .1 75

2 .0 30

0 .1 15

21
0 .1 07

0 .0 17

0 .2 43

0 .2 81

0 .4 05

0 .3 39

0 .0 97

0 .2 46

0 .0 06

Example

0 .1 14

0 .3 22

0 .2 11

0 .0 06

20
0 .1 07

0 .1 40

0 .4 61

1 .9 83

2 .3 25

0 .1 08

0 .1 42

0 .5 76

0 .2 26

0 .0 06

19
0 .1 07

0 .0 23

0 .4 78

1 .9 40

2 .0 93

0 .1 55

0 .1 48

0 .6 47

0 .2 31

0 .0 06

18
0 .1 07

0 .1 36

0 .2 80

17
0 .1 07

0 .0 26

0 .0 24

0 .4 87

1 .6 51

1 .6 46

0 .3 04

0 .1 72

0 .9 40

0 .2 40

0 .0 06

0 .3 45

0 .5 08

1 .0 08

0 .9 99

0 .5 63

0 .1 88

0 .7 29

0 .2 48

0 .0 06

16
0 .1 07

0 .0 21

0 .5 47

0 .8 64

0 .9 90

0 .4 61

0 .1 72

0 .1 73

0 .6 47

0 .2 54

0 .0 06

15
0 .1 07

0 .3 87

0 .2 88

14
0 .1 07

0 .0 18

0 .0 12

0 .1 04

0 .0 54

0 .4 79

1 .0 27

1 .2 88

0 .4 19

0 .1 68

0 .1 97

0 .4 04

0 .2 66

0 .0 06

0 .1 08

0 .2 65

0 .3 71

0 .0 52

0 .5 04

0 .8 98

1 .2 48

0 .3 79

0 .1 76

0 .2 62

0 .3 94

0 .3 08

0 .0 07

0 .1 08

(month)

0 .0 11

0 .4 56

1.3(2)

1.3(2)

0 .0 53

0 .0 43

0 .0 48

0 .4 65

1 .6 01

1 .1 20

0 .1 68

0 .3 41

0 .3 53

0 .2 96

0 .0 07

0 .1 08

13

1.3 Avoid some major


works in the mid-rainy
season

0 .0 81

0 .1 17

0 .1 54
0 .0 35

0 .0 34

1.4
0 .1 80

0 .4 31

1 .7 42

0 .9 98

0 .1 72

0 .2 96

0 .3 32

0 .2 88

0 .0 07

0 .0 27

0 .3 59

1 .1 09

1.3(1)

0 .9 31

0 .1 60

0 .2 38

0 .0 28

0 .3 12

0 .2 76

0 .0 07

0 .1 08

0 .1 60

1 .0 66

0 .7 45

0 .1 47

0 .0 48

0 .3 00

0 .2 59

0 .0 07

0 .1 08

12

D U R A T I O N

0 .0 88

0.230

0.386

0.281

0 .1 25

1 .0 42

0 .5 02

0 .1 10

0 .0 61

0 .2 55

0 .2 26

0 .1 18

0 .0 07

0 .1 08

11

0 .0 87

1 ,848, 552.50

3 ,111, 166.39

Deto ur Roa d f or Dam age d A rea s No. 11, 12 , 1 3 & 14 , Late ral Underground

Obser va tion & S ub so il I nvestigation

2 ,262, 540.02

3.414

2 7,506, 411.40

S te el S he et Piles

T op og ra hic, Geo lo gica l & Su bsoil St ra ta S ur ve y, Lan dslide Movement

2.772

2 2,332, 795.85

0.843

1.952

Gab io n Bo x & Ga bion Mattress

6 ,788, 280.10
2.329

1 5,723, 749.87

1 8,766, 114.90

Dre dg in g of R v
i er be d, F ou nd at io n Fill& Embankment

4 .957

S tr uctu ra l Co ncre te , Gr ou te d Ripr ap C la ss A & Stone Masonry

C le ar in g & Gr ub bing , Re mo va l of T re es & Excavation

F loo d C ont rol an d Drainage

T ota l f or Par t H

3 9,936, 007.28

1.460

1 1,763, 819.25

P avem en t Ma rkin gs & R ef le to rize d Pavement Studs

S odd ing & Tre e P a


l n ting

1.649

1 1,228, 883.12

1.394

0.349

2 ,813, 069.16
1 3,286, 281.50

War ning , Re gu la to ry & P ro je ct I nformation Sign

9 .219

M et al Gua rdrail

C on cr et e Cu rb , Righ t- of -Way M on um en t, M aint . Dr ain Marker Post & KM Post

M is ce lan eo us S tr uctures

T ota l f or Par t G

7 4,268, 962.84

0.858

6 ,915, 151.80

Gab io n Bo x & Ga bion Mattress

Note:
Comments in red color

P AR T J

P AR T H

1.565

1 2,611, 013.24

Gro ut ed R ip ra p Class A, S to ne M ason ry & Rubble Concrete

0.169

1 ,359, 056.06

C le an in g / Re co nd ti io ning o f Pipe C ulve rt & BoxCulvert

0 .0 60

1.4 Work to be
completed by the
coming rainy season

0.258

2 ,081, 445.47

R CP C Co ncre te C at ch B asin & M ason ryCatch Basin

0.930

7 ,487, 873.87

Layin g of P ip e Cu lver t & Un de rd ra in P erforated PVC Pipe

Dra in ag e & Slop e Pr ot ection Structures

4 .719

Example of Bar Chart with S-Curve

5 ,1 4 7 ,7 8 4.03
5 ,1 4 7 ,7 8 4.03

P AR T G

3 8,016, 454.23

5 ,1 4 7 ,7 8 4.03
1 0 ,2 9 5 ,5 6 8.06

B ridg e Co nstr uction

2 3.381
3 9.882

4 ,2 0 5 ,2 3 2.02
1 4 ,5 0 0 ,8 0 0.08

P ART F

1 88,354 ,461.35
3 21,287 ,716.15

P CC P avem en t (2 00 m m & 300 mm thick)

1 6.501

0 .1 44

0 .0 65

6 ,1 5 4 ,7 8 4.04
2 0 ,6 5 5 ,5 8 4.12

T ota l f or Par t E

1 32,933 ,254.80

A sp ha lt P avem en t (B in de r, Wea ring C ou rse & Cr ackRelief Layer)

0 .1 38

0 .0 53

1 2 ,7 6 0 ,7 0 4.07
3 3 ,4 1 6 ,2 8 8.19

S urf ace Co urse

7 .495

1 5.230

0 .0 52

1 7 ,8 6 8 ,2 0 8.10
5 1 ,2 8 4 ,4 9 6.30

P ART E

6 0,376, 294.44

0 .0 44

0 .2 11

0 .2 17

0 .1 32

0 .0 07

0 .1 08

3 3 ,3 6 7 ,9 5 2.19
8 4 ,6 5 2 ,4 4 8.49

S ubb ase & Base C ourse

2.252

1 8,144, 589.50

S ubg rad e P rep ara tio n & Su bgr ade Im provement

0 .0 38

0 .1 29

0 .1 55

0 .1 56

0 .0 29

0 .1 08

10

3 7 ,3 1 5 ,3 9 2.22
1 2 1 ,9 6 7 ,8 40.71

P AR T D

1 22,691 ,788.80

1.507

1 2,144, 013.99

E mb an km en t (f ro m Ro ad wa y Exca va tion & S elected Borrow)

0 .0 32

0 .1 41

0 .1 40

0 .1 08

09

1 6 4 ,8 4 9 ,9 28.96

T ota l f or Par t C

0.303

2 ,443, 010.10

0 .1 21

0 .0 06

0 .1 08

08

2 1 2 ,0 3 3 ,9 21.23

F ou nd at io n Fill, Sh or in g of P an gd an B ridg e & Pipe Culvert & Drain Exc.

0.668
3.703

5 ,379, 838.54
2 9,829, 982.03

C le ar in g & Gr ub bing , Re mo va l of T re es/E xist in g Structures

0 .0 06

0 .4 37

0 .1 08

07

4 7 ,3 0 4 ,8 3 2.28
2 5 9 ,3 3 8 ,7 53.51

E ar th wo rks

0 .0 06

0 .4 36

0 .1 08

06

4 7 ,6 0 2 ,9 0 4.28
3 0 6 ,9 4 1 ,6 57.79

P AR T C

1.094
0.506

4 ,076, 068.55
1 .600

8 ,815, 000.00

1 2,891, 068.55

Gene ral Ro ad Mainte nan ce, Se al Coa t f or Dam age d P CCP, etc.

0 .1 08

05

4 7 ,8 0 4 ,3 0 4.28
3 5 4 ,7 4 5 ,9 62.07

T ota l f or Par t B

M ob iliz at io n an d De mo bilization

1 .689

04

4 8 ,2 2 3 ,2 1 6.28
4 0 2 ,9 6 9 ,1 78.35

1.2

2 0,792, 101.37

03

4 8 ,3 1 1 ,8 3 2.28
4 5 1 ,2 8 1 ,0 10.63

F acilit ie s fo r th e Engineer

02

5 6 ,5 6 1 ,1 7 6.33
5 0 7 ,8 4 2 ,1 86.96

Oth er Gen er al R eq uirements

01

5 6 ,5 3 7 ,0 0 8.33
5 6 4 ,3 7 9 ,1 95.29

P AR T A

OK
% WT.

5 6 ,7 7 8 ,6 8 8.33
6 2 1 ,1 5 7 ,8 83.62

P AR T B

AMOUNT

5 0 ,0 1 1 ,6 4 8.29
6 7 1 ,1 6 9 ,5 31.91

D E S C R I P TI O N

4 2 ,8 8 2 ,0 8 8.25

4 3 ,5 3 4 ,6 2 4.25
7 1 4 ,7 0 4 ,1 56.16

ITEM NO.

Assume that the 1st month will

UNDER ARTERIAL ROAD LINKS DEVELOPMENT PROJECT,


PHASE
be October
2004 IV
and the rainy
season is from June to
PROVINCE OF CEBU

1.1
CONSTRUCTION SCHEDULE OF NAGA - TOLEDO ROAD PROJECT

4 7 ,1 8 3 ,9 9 2.27

4 1 ,0 7 7 ,5 4 4.24

6 - 22
7 5 5 ,7 8 1 ,7 00.40

1.2 Divide General Road Maintenance, Seal Coat


for Damaged PCCP,etc. to two sub-items by pay
item

pay item in terms of percentages or quantities.It is used to determine whether the

project is ahead or behind schedule.

Road Project Management and Supervision Manual Vol.1 Main Text

(c)

Construction Methodology
This shall embody a narrative description of the order of procedure in which
the Contractor proposes to carry out each main item of work. This shall conform to
the approved Pert/CPM.

(d)

Contractor's Organizational Chart


This is a structural chart showing the hierarchical order of personnel the
Contractor shall assign for superintendence on the execution of the Works and the
respective duties, roles, etc., of every component of the chart.

(e)

Manpower and Equipment Utilization Schedules


The Engineer shall ensure that the Contractor complies with the number of
manpower at site based on the submitted Manpower Schedule. Likewise, he shall
ensure that the Contractor is maintaining the required number, good working
condition equipment until completion of the project.

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 23

6 - 24

Road Project Management and Supervision Manual Vol.1 Main Text

Aurora Fabro
Jasmin Salandanan
Jose Leonides David
Salvador Meriel
Eugene Torralba
Santos Lucila
Rolando Jimenez
Bernabe Quitoriano

Sr. Struct Engr (2)

Sr. Struct Engr (3)

Sr. Struct Engr (4)

Sr. Highway Engr

Struc/Br Insp (1)

Struc/Br Insp (2)

Struc/Br Insp (3)

Struc/Br Insp (4)

Eugene Torralba
Marianne Molina
Liza Gonzales
Glory Grace Quebral
Jonas Marasigan
Pablo Joya
Janet Ferrer
Josie Adame
Alexander Villafuerte
Nancy Catapusan
Violeta Mallorca
Josephine Angeles
Maricel Mendoza
Sammy Kamad
Joselito Arciaga

Jr. Struct Engr (2)

Jr. Struct Engr (3)

Jr. Struct Engr (4)

Jr. Highway Engr

Jr. Geotech Engr

Jr. Drainage Engr

Jr. Cost Engr

Jr. Specs Doc Writer

Draftsman/CADD (1)

Draftsman/CADD (2)

Admin/Secretary

Typist/Encoder (1)

Typist/Encoder (2)

Utility/Janitor

Driver

1999

2000

2001

Example of Manpower Schedule

J AS OND J FMAM J ND J FMAMOND J FMAM J J AS OND

1998

Figure 6.11

Rhonda Amores

Jr. Struct Engr (1)

SCHEDULE
ACTUAL
ACTUAL (ON-CALL)

Dionisio Tandingan

Sr. Survey Engr

LEGEND:

Helen Difuntorum

Cost/Doc Engr

Hydro/Drain Engr

Venancio Buenconsejo

Melodina Tuao

Geotech/Found Engr

Benjamin A. Domingo, Jr.

Sr. Struct Engr (1)

NAME

Chief Engineer

POSITION

37.00

33.00

24.00

30.50

36.00

32.50

32.50

27.00

12.00

6.00

12.00

19.00

29.50

31.00

24.00

15.50

6.00

33.50

15.00

9.00

8.00

8.00

9.50

6.50

6.00

24.00

28.50

35.00

37.00

MAN
MOS.

45.00

40.19

32.27

40.58

28.11

38.75

41.01

34.79

16.10

10.53

10.50

30.20

36.94

39.49

20.45

26.28

3.77

41.84

26.54

8.77

8.73

10.50

7.16

5.53

16.77

36.94

37.45

40.61

36.77

MM
USED
(CUMM)

-8.00

-7.19

-8.27

-10.08

7.89

-6.25

-8.51

-7.79

-4.10

-4.53

1.50

-11.20

-7.44

-8.49

3.55

-10.78

2.23

-8.34

-11.54

-0.77

-0.73

-1.00

-0.66

0.47

7.23

-36.94

-8.95

-5.61

0.23

MM
REMAINING

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 25

Source: CAR/DPWH

Figure 6.12

Example of Equipment Utilization Schedule

Example

(f)

Cash Flow and Payment Schedule


This shall show a cash flow estimate, in monthly and quarterly periods, of all
payments the Contractor will be entitled to receive under the Contract.
The Engineer shall have the right to reject any part of the original programs
submitted with the Bid even if the Bid is accepted and to require the Contractor to
revise the original programs to the satisfaction of the Engineer prior to the award
and signing of the Contract Agreement. The Contractor shall not commence the
execution of the Works without such requirements.
The construction schedule shall be revised and resubmitted at intervals as
required by the Engineer. In addition, the Contractor shall immediately advise the
PE any proposed changes in the construction schedule. Any changes in the
construction schedule shall show construction operations for each item of work
from the time of Notice to Proceed to the anticipated completion date, thereby
indicating the periods where works were delayed as well as estimated future periods
of construction operations to negate the delay. Each revised construction schedule
shall be related to the original construction schedule and shall show months ahead
or behind the schedule for both completed activities and future activities.

6.2.4

Straight Line Diagram

A straight line diagram is a visual monitoring method showing the work plan and
accomplishment on a diagram as shown in Figure 6.13. It will give information on where
work is planned, ongoing and completed.

6.2.5

Value Engineering

The Contractor may, at any time, submit to the Engineer a written proposal which in the
Contractors opinion, if adopted, will i) accelerate completion, ii) reduce the cost to the
Employer in executing, maintaining or operating the Works, iii) improve the efficiency or
value to the Employer of the completed Works, or iv) otherwise be of benefit to the Employer.
The proposal shall be prepared at the cost of the Contractor, if a proposal, which is approved
by the Engineer, includes a change in the design of part of the Permanent Works.

6 - 26

Road Project Management and Supervision Manual Vol.1 Main Text

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 27

2.0m

6.7m

2.0m

Source: PJHL/DPWH

L = 40.00m.

L = 237.00m.

Damaged No.3
Sta.3+010.00 Sta.3+050.00

L = 40.00m.

L=17.649km

Lutak Bridge

Sta.12+302.216

12

L = 39.00m.

Damaged No.5
Sta.4+475.00 Sta.4+514.00

L = 50.00m.

Sta.5+520.00

Sta.5+470.00 -

ACP
T=200m m

L=3.965km

L=1.501km

Uling 1 Bridge

L= 27.00m.

ACP

Overlay

AC

Sta.17+640.000

PAVEMENT WORKS

L = 84.00m.

L = 400.00m.

11
Damaged No.11
Sta.16+080.00 Sta.16+480.00

12

L=1.923km

T=150m m

Sta.19+070.00 -

L = 300.00m.

14

L = 230.00m.

Sta.19+300.00

21

L=0.124km

Section 3

Example of Straight Line Diagram

32

33

34

& Drainage

Shoulder Pavement

Section 4

Slope Protection Works

35 km

City Hall

Toledo

Toledo
City Hall

Toledo
City Hall

2.0m

6.1m

2.0m

Toledo City Hall

Sta.34+440.000

Shoulder Pavement (ACP)


(Town Area)

L=2.374km

Section 4

Drainage Improvement

Scouring Protection Works

LEGEND

Jct.Sangi

Sta.32+066.000

31

LEGEND
Work completed by Last Month
Work Accomplished in this Month
Work under construction

Sta.25+076.628-25+103.628
L= 27.00m.

Sub Base
(T=250mm)

Balud Bridge

L=11.562km

Section 3

Base (T=200mm)

T=60m m

ACP

22
Miscellaneous Works

AC Overlay
on Existing AC

Jct.Poog

Damaged No.14

13
Damaged No.13
Sta.17+280.00 Sta.17+580.00

L = 220.00m.

Sta.16+940.00

Sta.16+720.00 -

Damaged No.12

BRIDGE REHABILITATION WORKS

L=0.821km

20

Sta.20+504.000

ACP

AC Const.

Section 2

ACP

L=3.229km

T=150m m T=200m m

ACP

AC Const.

Sta.16+140.000

19

Section 2

18

Jct.Lutopan

Sta.17+280.000

17

PROFILE (SECTION A-A)

Damaged No.10
Sta.10+926.00 Sta.11+010.00

10

PLAN

ACP

AC Overlay on Exsit.PCCP

Sta.12+252.761-12+302.761
L= 50.00m.

10

16

SLOPE AND SCOURING PROTECTION WORKS FOR MAJOR DAMAGED AREAS

L = 120.00m.

Sta.10+380.00 Sta.10+500.00

9
4
Damaged No.9

Figure 6.13

L = 35.00m.

Damaged
No.7
4
Sta.6+825.00 Sta.6+860.00

Damaged No.6

Sta.8+841.590-8+868.590
L= 27.00m.

15

Project Road L=34.814km

14

Replacement of Damaged
PCCP

13

Uling 2 Bridge

Section 1

11

Sta.12+753.873-12+780.873

L= 27.00m.

Sta.5+637.219-5+702.219
L= 65.00m.

Sta.3+390.00

10

Jaguimit Bridge

Pangdan Bridge

Sta.3+350.00 -

Major Works

Section 1

STRAIGHT LINE DIAGRAM FOR _WORK ACCOMPLISHMENT OF JUNE 2005 (Example)


7

Sta.5+965.308-5+992.308

BASE T=200m m

Damaged No.4

Shoulder pavement (ACP), Slope > 4% OR Se>7%

PCCP T=300m m

L= 12.543km

Sta.2+890.00

L=290.00M

Reconstruction by PCCP

PCCP

Sta.2+600.00 -

Damaged No.2

Damaged No.1
Sta.1+953.00 Sta.2+190.00

Jct.Naga

Jct.Naga

Jct.Naga

Sta.0+056.000

Jct.Naga

Sta.0+056.000

Km

6.2.6

Construction Drawings

This shall form part of the contract documents, any revision shall be duly approved prior
to implementation of work. In case of discrepancy or ambiguity on the plans, specifications
and special provisions, the following rules shall govern:
a)

Supplemental specifications shall govern over original specifications;

b)

Plans shall govern over specifications;

c)

Special provisions shall govern over plans and specifications;

d)

Figure dimension, unless obviously incorrect, shall govern in case of any discrepancy
between figured dimensions and scaled dimension.

6.2.7

Shop Drawings

The Contractor shall prepare shop drawings if required by the Engineer. Shop drawings
are prepared to supplement the construction drawings and where there is a need of more
details of the works to be implemented. These shall be deemed to include design drawings,
fabrication drawings, catalogue, brochures, illustrations, materials lists, design calculations,
reference standards and performance data which may be required by the Specifications for the
proper execution of the Work.
The Contractor shall submit shop drawings in sufficient lead time to prevent delays in
delivery of materials or in the progress or completion of the work. The shop drawings shall be
complete in all respects and shall show clear compliance with the Specifications. The
Engineer will review these drawings within a reasonable time and return them with comments.
The Contractor shall resubmit the revised shop drawings, if required, for further review and
approval.

6.2.8

Establishment of Communication Network

The Engineer shall furnish the Implementing Office of his contact numbers (landline and
mobile), facsimile, mail and e-mail addresses. He shall establish a communication network for
all concerned entities such as the Contractor (Head and Site Offices), the Consultants, Police,
Hospital, Fire Department, Public Utility Companies and others.
In addition, the Engineer should also establish an emergency hotline.

6.2.9

Conduct of Coordination Meetings

The Engineer shall hold a coordination meeting at least once a month to discuss the
following:

6 - 28

Road Project Management and Supervision Manual Vol.1 Main Text

Table 6.7

Agenda for Coordination Meeting

Meeting/Venue

Agenda

Monthly Coordination

Meeting/Implementing

Monthly project

acccomplishment(phy

Office
-

The Head of Implementing


Office*

sical and financial

The PEs

progress)

Consultants

Monthly work plan

Contractor

and schedule

Other key staffs

Problems and Action


Plan

Construction methods

Environmental and
traffic managements

Other matters

*Chairperson

6.2.10 Maintenance Work during Contract Period


The Contractor shall be responsible for the maintenance of the accomplished items of
work during construction and until acceptance of the project.

General Maintenance
during the Contract Period

Maintenance by
DEO/DPWH

Maintenance by

CONTRACTOR

CONTRACTOR

Construction
Period

Maintenance
Liability Period

Possession of
Site

Figure 6.14

Completion of
Works

DEO/DPWH
Maintenance

Final Taking
Over

Maintenance Period

The Contractor shall maintain the pavement, shoulders, drainage systems, structures and
road fixture provided in the Special Specifications and paid as General Maintenance, as
follows:
Pavement:
*

Repair of potholes by bituminous mixtures

Grading and compaction of gravel surface

Crack sealing

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 29

Watering on the existing road surface for dust control

Other work

Drainage:
*

Removal of silted soil and debris from RC pipes and Box culverts

Removal of silted soil and debris from road side ditches and catch pits

Other works

Shoulder:
*

Repair of potholes and grading

Vegetation control (grass cutting)

Road fixture
*

Temporary installation or repair of sign boards (warning and information)

Guard rails and blocks

Other fixtures

A road maintenance work, in general, should be performed for the comfort and safety of
road users and minimizing further deterioration of the present road and/or keeping the road in
good condition until acceptance of the project. TheMaintenance Engineer shall instruct,
inspect and record the Contractor's maintenance activities.
The Contractor shall also be obliged to maintain the project road during the maintenance
liability period, which is one (1) year in general 1. For this purpose, the Maintenance Engineer
or his representative shall conduct a joint periodic inspection with the Contractor.

Installation of Guide Blocks at Accident- Grading and Watering on the Existing


Prone Section by Slope failure
Project Road for Dust Control

Figure 6.15

Removal of A Overturned Truck from


the Project Road for Public Safety

Contractors Maintenance Activities

6.2.11 Delay of Work and Action Plans


(1)

Delay of Work
The Contractor shall promptly give notice to the Engineer of probable future events

The Contractor has multi year maintenance responsibility in the case of Long-Term Performance Based
Maintenance (LTPBM).

6 - 30

Road Project Management and Supervision Manual Vol.1 Main Text

or circumstances which may adversely affect or delay the Works.


The Engineer shall give notice to the Contractor to submit a revised program if;
*

The actual progress is too slow to be completed within the time of completion,
and/or

The progress has fallen (or will fall) behind the current program/schedule.

The revised program and supporting report shall include the revised methods which
the Contractor proposes to adopt to increase work progress and complete within the time
of completion. The Contractor shall adopt these revised methods, which may require the
increased working hours and/or mobilization of additional resources including manpower,
equipment and/or goods at his own risk and expense.

(2)

Slow Progress
When there is a slow progress at a given point of time, the Contractor is to be
reminded of DO No.102, Series of 1988 regarding the courses of actions to be taken by
the Engineer whenever the Contract reaches a level of negative slippage as described
below.
Table 6.8
Stage

a.

Early
Earning

Condition

The Contractor shall be given a warning and submit a


catch-up program to eliminate the negative slippage.
The Engineer shall provide close supervision and
monitoring.
The Contractor shall be given a second warning and
submit detailed action program on two weeks basis to
accelerate the execution of the Works. Furthermore, the
Contractor shall be instructed to mobilize the additional
inputs. The Engineer shall exercise closer supervision at
every other week.
The Contractor shall be issued a final warning. He shall
provide a more detailed program of activities with weekly
physical targets together with additional inputs. The
Engineer shall intensity and evaluate the project
performance at least once a week.
The Employer shall initiate termination/rescission of the
Contract or take-over of the remaining Works by
administration
or
assignment
to
another
Contractor/appropriate agency.

b.

ICU Stage

For negative
slippage of ten
(10%) percent

c.

Make or

For negative
slippage of
fifteen (15%)
percent

Stage
d.

Terminal
Stage

Required Actions

For negative
slippage of five
(5%) percent

Stage

Break

Stages of Negative Slippage

For negative
slippage beyond
fifteen (15%)
percent

The Engineer shall instruct the Contractor to submit a Catch-up program at the early
warning stage. The catch up program must be supported by additional working hours
(Sunday work, holiday work, night work, two shift work, etc), equipment and cash flows.

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 31

6 - 32

Station 5+000 - 12+275, Sta 12+302 - 16+140

Base Course

Sta 12+302 - 16+140

Sta 0+056 - 10+000

Sta 12+302 - 16+140

Sta 12+302 - 16+140

Bit. Binder Course

PCCP, t = 300 mm thick

PCCP, t = 200 mm thick

Supporting Blocks

RCBC (17 Locations)

RCBC (17 Locations)

RCBC (17 Locations)

Reinforcing Steel, Grade 40

Structural Conc. Class A for Minor Structures

Lean Concrete

RCPC - 910mm diameter

Section 1

Section 1

Section 1

Section 1

Section 1

Section 1

Section 1

Catch Basin

Cleaning RCPC

Cleaning RCBC

Grouted Riprap - Minor Damaged & Roadway

Stone Masonry - Minor Damage & Roadway

Underdrain

Geotextile Filter Fabric

Masonry Lined Canal (Reblocking Area)

Dredging of Riverbed

Earthworks at Damaged Area No.1 & No.2 and Lutak Bridge

Source : PJHL / DPWH

250

150

7000

500

10000

200

4000

25,691,301.62

336,275.00

594,606.00

403,530.00

131,819.80

363,177.00

1,866,951.00

538,040.00

354,750.00

3,484,975.20

1,494,507.63

103,300.00

569,030.00

2,028,562.50

435,170.75

1,051,098.36

69,303.00

215,073.24

523,354.50

32,860.66

602,572.65

623,662.00

719,875.02

1,064,556.00

2,376,012.96

1,409,940.00

666,086.40

341,419.17

156,668.69

146,354.70

25,827.30

983,700.00

1,029,600.00

50,838.80

897,803.30

JUN

19.867%
5.625%

5.225%
-4.581%

PROJECTED WORK SLIPPAGE (%)

Catch-up Program

-2.883%

22.750%

12.544%
17.125%

SCHEDULED MONTHLY ACCOMPLISHMENT (%)

7.323%

58,994,280.99

776,323.33

336,275.00

1,101,040.00

672,550.00

329,549.50

242,118.00

336,275.00

425,700.00

1,866,951.00

538,040.00

354,750.00

1,494,507.63

103,300.00

569,030.00

2,028,562.50

435,170.75

215,073.24

523,354.50

32,860.66

602,572.65

623,662.00

1,079,812.54

2,129,112.00

4,752,025.92

21,984,710.00

4,190,400.00

2,357,680.00

1,409,940.00

666,086.40

341,419.17

156,668.69

146,354.70

25,827.30

1,967,400.00

1,029,600.00

2,200,936.43

50,838.80

897,803.30

JUL

SCHEDULED CUMULATIVE ACCOMPLISHMENT (%)

*PROJECTED CUMULATIVE ACCOMPLISHMENT (%)

300,107,851.92

2,328,970.00

1,345,100.00

4,529,600.00

594,606.00

1,101,040.00

672,550.00

403,530.00

659,099.00

605,295.00

1,345,100.00

851,400.00

12,446,340.00

2,152,160.00

709,500.00

11,616,584.00

5,978,030.50

206,600.00

1,138,060.00

8,114,250.00

1,740,683.00

1,051,098.36

69,303.00

860,292.96

2,093,418.00

131,442.64

2,410,290.60

2,494,648.00

1,799,687.56

5,322,780.00

11,880,064.80

109,923,550.00

41,904,000.00

23,576,800.00

7,049,700.00

3,330,432.00

2,048,515.00

626,674.75

585,418.80

51,654.60

4,918,500.00

10,296,000.00

4,401,872.85

254,194.00

4,489,016.50

( Ph. Peso )

ESTIMATED AMOUNT

3.189%

Figure 6.16

m3

m3

m3

m3

m3

245

225

500

120

3000

800

100

2800

3965

1000

2000

3000

700

78

300

24

600

34

340

44200

388

5400

12060

67000

80000

40000

10500

5600

74900

2665

2040

180

25000

50000

21197.5

QUANTITY

PROJECTED MONTHLY ACCOMPLISHMENT (%)

TOTAL ESTIMATED AMOUNT

Stone Masonry, Riprap & Gabions

Gabions, Masonry & Underdrain

Embankment from Borrow

Crushed Agg. Base Course

Damaged Area No. 11

Other Damaged Areas

m3

Stone Masonry, Riprap & Gabions

Damaged Area No. 6

Damaged Area No.12

m3

Stone Masonry, Riprap & Gabions

Damaged Area No. 5

m3

m3

Stone Masonry, Riprap & Gabions

m3

Stone Masonry, Riprap & Gabions

Stone Masonry, Riprap & Gabions

Damaged Area No. 4

m3

Conc. Class A

m3

Stone Masonry, Riprap & Gabions


l.m.

m3

Conc. Class A

Sheet Piles

l.m.

Sheet Piles

l.m.

m2

l.m.

m3

m3

ea.

l.m.

ea.

l.m.

m3

m3

kg

l.m

m2

m2

m2

m2

m2

m3

m3

m2

m3

Damaged Area No. 3

Damaged Area No. 2

Damaged Area No. 1

FLOOD CONTROL AND DRAINAGE

RCPC - 910mm diameter (26 Locations)

RCPC

DRAINAGE & SLOPE PROTECTION

Lutak Bridge

Steel Sheet Piles

BRIDGE CONSTRUCTION

Sta 12+302 - 16+140

Bit. Crack Relief Layer

SURFACE COURSES

Station 5+000 - 12+275, Sta 12+302 - 16+140

Subbase Course

SUBBASE AND BASE COURSE

Station 5+000 - 10+000, Sta 12+302 - 16+140

m3

RCBC (17 Locations)

Subgrade Preparation

m3

Station 1+100 - 1+220 (Riprap)

Structure Excavation - Roadway

RCPC - 910mm diameter (26 Locations)

m3

Pipe & Drain Excavation

m2

Station 5+000 - 8+800,Sta 8+800-12+275, DA 9


m3

Station 8+800 - 12+275

Station 5+000 - 8+800,Sta 8+800 - 12+275

mo.

mo.

UNIT

ESTIMATED QUANTITY

PROGRESS CATCH-UP PROGRAM, JUNE - OCTOBER 2007 (EXAMPLE)

Surplus Common Excavation - Roadway & DA 9

Removal of Existing Pavement

STATION LOCATION

Surplus Unclassified Excavat Surplus Unclassified

EARTHWORKS

General Road Maintenance

GENERAL REQUIREMENTS

Facilities for the Engineer

FACILITIES FOR THE ENGINEER

DESCRIPTION

Note: Computation based on major items only.

PART J

PART G

PART F

PART E

PART D

PART C

PART B

PART A

ITEM

-0.225%

28.646%

5.896%

28.421%

8.554%

68,908,362.36

776,323.33

336,275.00

905,920.00

197,729.70

336,275.00

425,700.00

538,040.00

1,494,507.63

2,028,562.50

435,170.75

215,073.24

523,354.50

32,860.66

602,572.65

623,662.00

2,129,112.00

4,752,025.92

21,984,710.00

12,571,200.00

7,073,040.00

1,409,940.00

666,086.40

341,419.17

156,668.69

146,354.70

1,967,400.00

3,088,800.00

2,200,936.43

50,838.80

897,803.30

AUG

2007

2.138%

33.500%

4.854%

35.638%

7.217%

58,141,378.31

776,323.33

336,275.00

1,811,840.00

336,275.00

538,040.00

1,494,507.63

2,028,562.50

435,170.75

215,073.24

523,354.50

32,860.66

602,572.65

623,662.00

21,984,710.00

12,571,200.00

7,073,040.00

1,409,940.00

666,086.40

341,419.17

156,668.69

146,354.70

3,088,800.00

50,838.80

897,803.30

SEPT

Most Critical Activity

37.25%

REMARKS

3.192%

38.553%

5.053%

Normal

Semi-critical

Critical

6.108% Legend:
*
Base on Actual Accomplishment
41.745%

49,202,352.67

1,811,840.00

336,275.00

21,984,710.00 Most Critical Activity

12,571,200.00 Most Critical Activity

7,073,040.00 Most Critical Activity

1,409,940.00

666,086.40

341,419.17

Most Critical Activity

2,059,200.00 Most Critical Activity

50,838.80

897,803.30

OCT

The Engineer shall assess the Contractors proposal and provide further advice and

instructions to assure that such program works well. The Engineer needs to establish a

closer inspection and quality control system for the catch-up program. Any extra cost for

the construction supervision, including overtime and holiday work allowances, shall be
charged to the Contractor.

Road Project Management and Supervision Manual Vol.1 Main Text

(3)

Liquidated Damages
If the Contractor fails to comply with the time for completion, he shall pay
liquidated damages to the Implementing Office for this default. These damages shall not
relieve the Contractor from his obligation to complete the Works, or from any other
duties, obligations or responsibilities which he may have under the Contract.
The Contractor shall pay liquidated damages to the Implementing Office at the rate
stated in the Special Conditions of Contract for each day of delay. The total amount shall
not exceed the amount defined in the SCC and this may be deducted from payments due
to the Contractor. Once the cumulative amount reaches ten percent (10%) of the contract
amount, the Implementing Office shall rescind the Contract, without prejudice to other
courses of action and remedies open to it.
(a)

For locally-funded project


A liquidated damage is equivalent to an amount to be determined in
accordance with the following formula until the work is completed and accepted or
taken over by the Employer:
n

TLD
=
VUUP =
where:
TLD
VUUP

VUUP x [ (1+ OCC) - 1] x K


TCP VCUP
=
=

TCP
VCUP

=
=

OCC

=
=

Total Liquidated Damages, in pesos


value of the uncompleted and unusable portions of the
contract work, as of the expiry date of the contract, in
pesos
Total Contract Price, in pesos
value of the completed and usable portion of the contract
work, as of the expiry date of the contract, in pesos
prevailing opportunity cost of capital for government
projects set by NEDA, which is currently pegged at 15%
total number of days that the contract work is delayed
after the expiry date of the contract
adjustment factor to cover additional losses
1 + C + ( i x n)

where:
C

cost of construction supervision as a percentage,


not exceeding 10%, of construction cost
annual inflation rate as defined by NEDA

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 33

To be entitled to such liquidated damages, the Implementing Office does not


have to prove that it has incurred actual damages. Such amount shall be deducted
from any money due or which may become due the contractor under the contract
and/or collect such liquidated damages from the retention money or other securities
posted by the Contractor whichever is convenient to the Implementing Office.
In case that the delay in the completion of the work exceeds a time duration
equivalent to ten percent (10%) of the specified contract time plus any time
extension duly granted to the Contractor, the Implementing Office may rescind the
Contract, forfeit the Performance Security and takeover the prosecution of the
project or award the same to a qualified Contractor through negotiated contract.
In no case however, shall the total sum of liquidated damages exceed ten
percent (10%) of the total contract price, in which event the Contract shall
automatically be taken over by the DPWH or award the same to a qualified
contractor through negotiation and the erring Contractors Performance Security
shall be forfeited.
(b)

For foreign-funded project


The applicable liquidated damages is at least one tenth (1/10) of a percent of
the cost of the unperformed portion for every day of delay in accordance with the
GCC and the SCC.
The maximum deduction shall be ten percent (10%) of the amount of the
contract and the Implementing Office shall rescind the contract, without prejudice to
other courses of action and remedies open to it.

6.2.12 Suspension of Works


The Implementing Office shall have the authority to suspend the work wholly or partly
by written order for such period as may be deemed necessary due to force majeure or any
fortuitous events or for failure on the part of the Contractor to correct bad conditions which
are unsafe for workers or for the general public, to carry out valid orders given by the
Implementing Office or to perform any provisions of the Contract, or due to adjustment of
plans to suit field conditions as found necessary during construction. The Contractor shall
immediately comply with such order to suspend the work wholly or partly.
The Contractor or its duly authorized representative shall have the right to suspend work
operation on any or all projects/activities along the critical path of activities after fifteen (15)
calendar days from date of receipt of written notice from the Engineer or equivalent officials,
due to the following:

6 - 34

Road Project Management and Supervision Manual Vol.1 Main Text

1)

There exist right-of-way problems which prohibit the Contractor from performing
work in accordance with the approved construction schedule;

2)

Requisite construction plans which must be owner-furnished are not issued to the
contractor precluding any work called for by such plans;

3)

Peace and order conditions make it extremely dangerous, if not possible, to work.
However, this condition must be certified in writing by the Philippine National Police
(PNP) station which has responsibility over the affected area and confirmed by the
Department of Interior and Local Government (DILG) Regional Director;

4)

There is failure on the part of the Employer to deliver government-furnished materials


and equipment as stipulated in the contract; and

5)

Delay in the payment of Contractors claim for progress billing beyond forty-five (45)
calendar days from the time the Contractors claim has been certified to by Employers
Representative.

6.2.13 Extension of Contract Time


(1)

For Foreign-funded Projects through ICB


Contract Time Extension is the allowable period for the Contractor to complete the
Works in addition to the original completion date stated in the Contract. The Contractor
shall be entitled subject to Contractors Claims, to an extension of the time for
completion if that completion is or will be delayed by any of the following causes:
(a) A variation or other substantial change in the quantity of an item of work included
in the Contract;
(b) A cause of delay giving an entitlement to extension of time;
(c) Exceptionally adverse climatic conditions;
(d) Unforeseeable shortages in the availability of personnel or goods caused by
epidemic or governmental actions; and
(e) Any delay, impediment or prevention caused by or attributable to the
Implementing Office, its personnel or other Contractors.
Delays caused by authorities will be applied in case of the following conditions:
(a) The Contractor has diligently followed the procedures laid down by the relevant
legally constituted public authorities in the country;
(b) These authorities delay or disrupt the Contractors work; and
(c) The delay or disruption was unforeseeable.

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 35

If the Contractor considers himself to be entitled to an extension of the time for


completion, he shall give notice to the Engineer in accordance with the Contractors
Claims. When determining each extension of time under Contractors Claims, the
Engineer shall review previous determinations and may increase, but shall not decrease,
the total extension of time.
(2)

For Locally-funded project thru LCB


Should the amount of additional work of any kind or other special circumstances of
any kind whatsoever occur to fairly entitle the Contractor to an extension of contract time,
the Engineer shall evaluate and determine the amount of such extension on the
Contractors claim. Upon receipt of full and detailed particulars, the Engineer shall
examine the facts and extent of the delay and shall extend the contract time of
completing the contract work when, in the Engineers opinion, the findings of facts
justify an extension.
No extension of contract time shall be granted the Contractor due to (a) ordinary
unfavorable weather conditions and (b) inexcusable failure or negligence of the
Contractor to provide the required equipment, supplies or materials.
Extension of contract time may be granted only when the affected activities fall on
the critical path of the Pert/CPM network. No extension of contract time shall be granted
when the reason given to support the request for extension was already considered in the
original contract time.
Extension of contract time shall be granted for:
*

rainy/unworkable days considered unfavorable for the prosecution of the works at


the site based on the actual conditions obtained at the site, in excess of the number
of rainy/unworkable days pre-determined by the Engineer in relation to the
original contract time;

equivalent period of delay due to major calamities such as exceptionally


destructive typhoons, floods,earthquakes and epidemics;

causes such as non-delivery on time of materials, working drawings, or written


information to be furnished by the Engineer;

non-acquisition of permit to enter private properties within the right-of-way


resulting in complete construction activities; and

other meritorious causes as determined by the Engineer and approved by the


Implementing Office.

6 - 36

Road Project Management and Supervision Manual Vol.1 Main Text

Shortage of construction materials, general labor strikes, and peace and order
problems that disrupt construction operations through no fault of the Contractor may be
considered as additional grounds for extension of contract time provided they are
publicly felt and certified by appropriate government agencies.

6.2.14 Termination of Contract


(1)

Termination for Default of Contractor


The Employer shall terminate the Contract for default when any of the following
conditions attend its implementation:
*

Due to the Contractors fault and while the project is on-going, it has incurred negative
slippage of fifteen percent (15%) or more in accordance with Presidential Decree 1870
regardless of whether or not previous warnings and notices have been issued for the
Contractor to improve his performance;

Due to his own fault and after the Contract time has expired, the Contractor incurs
delay of ten percent (10%) or more in the completion of the Work after the Contract
has expired; and

The Contractor:
1)

abandons the contract Works, refuses or fails to comply with a valid instruction of
the Engineer or fails to proceed expeditiously and without delay despite a
written notice by the Engineer;

2)

does not actually have on the project site the minimum essential equipment listed
on the Bid necessary to prosecute the Works in accordance with the approved
Program of Work and equipment deployment schedule as required for the project;

3)

does not execute the Works in accordance with the Contract or persistently or
flagrantly neglects to carry out its obligations under the Contract;

4)

neglects or refuses to remove materials or to perform a new work that has been
rejected as defective or unsuitable; and

5)

sublets any part of the Contract without approval by the authorized DPWH
officials.

All materials on site, plant, equipment and works shall be deemed to be the property
of the Implementing Office if the Contract is rescinded because of the Contractors
default.
(2)

Termination for Default of the Employer


The Contractor may terminate the Contract with the Implementing Office (IO) if the
works are completely stopped for a continuous period of at least sixty (60) calendar

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 37

days ,through no fault of his own, due to any of the following reasons:
1)

Failure of the IO to deliver, within a reasonable time, supplies materials,


right-of-way, or other items it is obligated to furnish under the terms of the
Contract; and

2)

The prosecution of the Work is disrupted by adverse peace and order situation as
certified by the Armed Forces of the Philippines Provincial Commander and
approved by the Secretary of National Defense.

(3)

Termination for Other Causes


The IO may terminate the Contract, in whole or in part, at any time for its
convenience. The Implementing Office or the Contractor may terminate the Contract if
the other party causes a fundamental breach of Contract, including:
1)

The Contractor stops work for twenty eight (28) days when no stoppage of work is
shown on the Program of Work and the stoppage has not been authorized by the ;

2)

The Engineer instructs the Contractor to delay the progress of the Works and the
instruction is not withdrawn within twenty eight (28) days;

3)

The IO shall terminate the Contract if the Contractor is declared bankrupt or insolvent
as determined with finality by a court of competent jurisdiction;

4)

A payment certified by the Engineer is not paid to the Contractor within eighty four
(84) days from the date of the certificate;

5)

The Engineer gives notice that failure to correct a particular defect is a fundamental
breach of Contract and the Contractor fails to correct it within a reasonable period of
time determined;

6)

The Contractor does not maintain a Security, which is required;

7)

The Contractor has delayed the completion of the Works by the number of days for
which the maximum amount of liquidated damages can be paid; and

8)

In case it is determined prima facie by the IO that the Contractor has engaged, before or
during the implementation of the contract, in unlawful deeds and behaviors relative to
contract acquisition and implementation, such as, but not limited to, the following:
*

corrupt, fraudulent, collusive and coercive practices

drawing up or using forged documents

using adulterated materials, means or methods, or engaging in production


contrary to rules of science or the trade

*
(4)

any other act analogous to the foregoing.

Termination for Convenience (RA 9184 Section 3.1)


The funding source or the IO, as appropriate, will seek to impose the maximum
civil, administrative and/or criminal penalties available under the applicable law on

6 - 38

Road Project Management and Supervision Manual Vol.1 Main Text

individuals and organizations deemed to be involved with corrupt, fraudulent, or


coercive practices.
If the Contract is terminated, the Contractor shall stop work immediately, make the
site safe, secure and leave as soon as reasonably possible.

6.3 Cost Management


(1)

Outline
Cost management is the management process and efforts of the Engineer for
increasing the values (quality) of the works and completion of the project within the
budget. Cost management, as one of the key elements for the project management, is a
series of activities through planning, detailed engineering, bidding and implementation
(See Figure 5.7).
As cost overrun is very common, every effort should be made through good project
implementation. The cost management is a non-compromised routine work carried out
on a daily, weekly and monthly basis with the cooperation of all involved in the project.
The Engineer shall carry out the following activities:
*

Control or see to it that works are executed in accordance with the plans and
specifications;

Check interim (monthly) statement on financial aspects (budget);

Monitor scope of work, quantities and cost which may increase by item,
especially for major pay items;

Take appropriate precautions and actions to avoid cost overrun;

Conduct value engineering techniques to reduce the cost; and

Evaluate the Contractors Claims at earliest time and identify effect on the project
cost.

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 39

C
1.50m
0.50m
0.50m

0.50m

6.70m
6.10m
(Existing Road Width)

0.30m
Widening

3.0%

2.0%

0.30m
Widening
2.0%

2.00m

3.0%

MFWL

1.0
5.00m

1.5

1.00m
0.60m

W=6.0-7.0m

2.00 3.00m

2.00m

Selected Embankment
(River Gravel)

Grouted Riprap T=300mm

RC Class A

Stone Masonry

River Bed
2.00m
Gabion
0.5 x 1.0 x 3.0m

Steel Sheet Pile L=6m


Type II

Geotextile Fabric

N o C o s t O ve rru n

Planning & Budgeting

Quantity & Finance Management

Bidding

Detailed Engineering Design

Establishment of Approved
Budget for Contract

Work Volume
(Bills of Quantities)
Price Negotiation & Contract

Establishment of Unit Prices

C o m p le tio n w ith in th e B u d g e t
or
Le a s t C o s t O ve rru n

Cost, Price
&
Productivity
Database

P
Currency Factor
(FC & LC)

Equipment

Materials

Labor

Project Implementation
(Cost Management)

Figure 6.17
(2)

Project Completion

Cost and Financial Management

Types of Payment
Payments are classified as follows:
*

Advance Payment;

Monthly Progress Payment;

Final Payment;

Release of Retention; and

Others.

The Contractor shall submit a statement of payment in accordance with the


conditions of the Contract. The Implementing Office shall verify and pay the Contractor
within the specified time.

6 - 40

Road Project Management and Supervision Manual Vol.1 Main Text

Table 6.9

Types of Payments

FIDIC GCC (MDG Edition)


Clause

DPWH GCC (Annex B, Volume 3)

Title

Clause

Title

14

Contract Price and Payment

38

Advance payment

14.2

Advance Payment

39

Progress Payment (Monthly


Payment)

14.3

Application for Interim Payment

40

Payment Certificate

14.4

Schedule of Payment

41

Retention

14.5

Plant and Materials for the Works

45

Payment on Termination

14.6

Issue of Interim Payment


Certificate

14.7

Payment

14.8

Delayed Payment

14.9

Payment of Retention Money

14.10

Statement of Completion

14.11

Application for Final Payment


Certificate

14.12

Discharge

14.13

Issue of Final Payment


Certificate

14.14

Cessation of Employers
Liability

14.15
(3)

Currencies of Payment

Guidelines for Payments


The following guidelines shall be referred to for verification and processing of
claim and payment of civil works.
Table 6.10

Payment Guidelines

Title
- Guidelines to Implementing Office for Processing Claims for

Date Issued
January 5, 2001

Payment (District and Regional Offices) for Civil Works Contract


- Guidelines to Implementing Office for Processing Claims for

January 5, 2001

Payment (Project Management Offices) for Civil Works Contract

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 41

(4)

Financing Schedule
The Engineer shall request the Contractor to submit a payment schedule at quarterly
basis for disbursement estimate by funding source and currency. The payment schedule
shall correspond to the work schedule and taking into account payment for advance
mobilization and retention deduction. The financing schedule shall be reviewed at every
quarter taking the latest progress into account.

6.3.1

Advance Payment

At the request of the Contractor, the Implementing Office will make an interest-free
advance payment and to the Contractor in a lump sum amount not exceeding 15% of the total
contract price, or as stipulated in the Conditions of Contract.
The Engineer will issue an Interim Payment Certificate for advance payment or its first
installment after receiving:
*

Performance Security;

A bank guarantee or surety bond, acceptable to the Implementing Office in amounts


and currencies equal to the advance payment; and

Such guarantee remains effective until the advance payment has been completely
repaid by the Contractor.

In DPWHs practice, advance payment is divided into two installments; the first 7.5% as
mentioned above and the remaining 7.5% at the completion of mobilization of minimum
required equipment. The advance mobilization payment shall be repaid by way of deduction
from the interim payments in consonance with the method stipulated in the Contract.
Table 6.12 illustrates the necessary actions and supporting documents for advance
payment.

6 - 42

Road Project Management and Supervision Manual Vol.1 Main Text

Table 6.11

Actions and Supporting Documents for Advance Payment


(Regional and District Offices)

Step

Necessary Actions and Supporting Documents


First Release

Second Release

Check the following:


1.
Background Information / Executive
Summary
2.
Billing Summary
3.
Letter-Request of Contractor
4.
Disbursement Voucher
5.
Irrevocable standby letter of credit, bank
guarantee or a surety bond plus verification from
SAC
6.
Copy of approved contract
7.
Notice to Proceed
8.
Resolution of Award
9.
Transmittal of contract documents to
COA
10.
Certificate of Availability of Fund

Check the following:


1.
Pictures
2.
List of Minimum
Required Equipment
3
Certification of Full
Mobilization of Required
Minimum Equipment

Verify Letter-Request of Contractor

If the above documents are incomplete and/or inaccurate, return the billing to the
Contractor for correction
If all documents are complete and accurate, the Implementing Office recommends
for the processing of the payment
Implementing Office provide Certified True Copy of the following documents:
Special Action Committee Verification of List of Minimum
Advance Payment Security or Performance
Required Equipment
Security
Resolution of Award
Transmittal of contract documents to
COA
Certificate of Availability of Fund
Copy of Approved Contract
Copy of Notice to Proceed

4
5

The billing documents must have appropriate approvals before submitting them to
Accounting for processing of payment

Source: Guidelines to Implementing Office for Processing Claims for Payment (District and Regional Offices)
for Civil Works Contract.

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 43

6.3.2

Interim Payment

The Contractor shall submit a monthly request for payment for work accomplished. The
request for payment shall be verified and certified by the Engineer.
The procedure, necessary actions and supporting documents are described below.
Table 6.12

Payment Procedure

Foreign-funded Projects
-

Locally-funded Projects

The Contractor shall submit each month

to the Engineer a billing statement

submit a request for payment for Work

supported with documents.

accomplished

The Statement shall include the

estimated value of the accomplished


Work, Plant and materials on site ( if
-

Once a month, the Contractor may

The Implementing Office shall verify


and certify it.

Materials and equipment delivered on the

stipulated in the SCC).

site but not completely put in place shall

The Engineer shall verify and submit to

not be included for payment, except as

the Implementing Office for payment

otherwise stipulated in the SCC.

within 28 days from receipt.


-

The payment shall be made within 56


days from receipt of the Engineer.

In the event of the failure of the


Employer to make payment within the
said period, the Employer needs to pay
interest to the Contractor.
Table 6.14 illustrates the necessary actions and supporting documents for interim

payment.

6 - 44

Road Project Management and Supervision Manual Vol.1 Main Text

Table 6.13

Actions and Supporting Documents Required for Interim Payment


(Regional and District Offices)

Step
1

3
4
5

Action and Support Documents for Progress Payment


Check the following submitted billing and documents:
1. Background Information / Executive Summary
2. Billing Summary
3. Letter-Request of Contractor
4. Certification
5. Disbursement Voucher
6. Monthly Certification of Payment
7. Statement of Work Accomplished
8. Statement of Time Elapsed
9. Contractors Affidavit
10. Certificate of Clearance on Labour and Materials Payment
11. Certification of Clearance for Equipment Rentals and/or Lease
12. Support Pictures
13. Request of Payment of Contractors (Material on Site)
14. Certification of Materials Quality Test (Materials on Site)
15. Manufactures Certificate (Materials on Site)
16. Official Receipts
17. Change Order/Supplemental Agreement/Time Extensions/Suspension and Resume
Orders, if applicable
18. Back-up Computations
19. Statement of Materials on Site
20. Security to cover the Release of Materials on Hand in the Form of Letter of Credit/Bank
Guarantee (Materials on Site) plus verification from SAC
21. Performance Security in the form of Letter of Credit, Bank Guarantee or Surety Bond
(Materials on Site) plus verification from SAC
22. BIR Form No. 2550 M VAT Declaration
23. BIR Form No. 750-V-1 (Certificate of VAT withheld on Government Payment (RA 7649)
24. BIR Form No. 1743 - 750 (Certificate of Creditable Taxes withheld at Source)
Verify the following documents for accuracy
Statement of Materials on Site
Request for Payment of Contractor
Back-up Computation
Statement of Work Accomplished
Monthly Certificate of Payment
Statement of Time Elapsed
Contractors Affidavit
If the above documents are incomplete and/or inaccurate, return the billing to the Contractor
for correction
If all documents are complete and accurate, the Implementing Office prepares forms for
processing forward
Implementing Office provide Certified True Copy of the following documents:
Special Action Committee Verification of Surety Bond (Materials on Site)
Special Action Committee Verification of Security to cover the Release of Materials on
Site
Special Action Committee Verification of Performance Bond
Special Action Committee Verification of All Risk Insurance
Comment of DBM Re; purchase of vehicles and equipment

The billing documents must have appropriate approvals before submitting them to the
Accounting for processing of payment
Source: Guidelines to Implementing Office for Processing Claims for Payment (District and Regional Offices)
for Civil Works Contract

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 45

The details of procedures and required documents together with examples are given in
the DPWH payment guidelines.

6.3.3

Payment of Materials on Site

Materials delivered on site but not completely put in place can be paid so as to help the
financial condition of the Contractor. However, payment of such can only be made if this is
specified in the Contract.
The Contractor shall request in writing for the evaluation and approval of the
Implementing Office. The materials shall have satisfactorily passed the required quality tests.
The payment shall be up to a maximum of seventy percent (70%) of the invoiced cost of
materials or seventy percent (70%) of the Bid price of the work item which these materials
shall be incorporated, whichever is lower, and the quantity shall not exceed the requirements
of the Contract. The Contractor shall post an Irrevocable Letter of Credit in favor of the
Implementing Office or Bank Guarantee from a reputable bank acceptable to the
Implementing Office in the amount equivalent to the partial payment applied for. The partial
payment shall be fully deducted from the Contractors next interim payment without prejudice
to his submitting another written request for partial payment with similar conditions
mentioned above.

6.3.4

Disbursement Estimate and Monitoring of Payment

The Engineer shall make disbursement schedule for the whole contract period which
shall include advance payment, progress payment and release of retention. The schedule
should be reviewed every quarter.
The progress of the payment shall be monitored in order that the Contractor can receive
such payment within the specified time since any delay in the payment will cause cash flow
problems and delay of works especially for small and medium category Contractors. The
Contractor shall be entitled to receive interest on the unpaid amount in accordance with the
Contract.

6.3.5

Cost Reduction

For PCCP not meeting the criteria for acceptance for strength and/or thickness (Taken
from the DPWH Standard Specifications for Highways, Bridges and Airports, Vol. II 2013
Edtion)
(1)

Strength Deficiency
The PCCP is considered to have met the minimum strength requirements if the
flexural strength obtained after fourteen (14) days is not less than 3.58 MPa (550psi)
when tested by third point method or 4.5 MPa (650 psi) when tested by mid-point

6 - 46

Road Project Management and Supervision Manual Vol.1 Main Text

method in accordance with AASHTO T97 and T177, respectively; or a compressive


strength of 24.1MPa (3500psi) for cores taken at fourteen (14) days and tested in
accordance with AASHTO T24.
The strength level of the concrete will be considered satisfactory if the averages of
all sets of three (3) consecutive test results equal or exceed the specified strength, f'c and
no individual test result is deficient by more than 15% of the specified strength, f'c.
Concrete deemed to be not acceptable using the above criteria maybe rejected
unless the Contractor can provide evidence, by means of core tests, that the quality of
concrete represented by failed test results is acceptable in place. At least three (3)
representative cores shall be taken from each member or area of concrete in place that is
considered deficient. The location of core shall be determined by the Engineer so that
there will be a least impairment of strength of the structure. The obtaining and testing of
drilled cores shall be in accordance with AASHTO T24.
Concrete in the area represented by the cores will be considered adequate if the
average strength of the cores is equal to at least 85% of, and if no single core is less than
75%, the specified strength, fc.
If the strength of control specimens does not meet the requirement of this subsection,
and it not feasible or not advisable to obtain cores from the structure due to structural
considerations, payment of the concrete will be made at an adjusted price due to strength
deficiency of concrete specimens as specified hereunder:
Table 6.14

(2)

Cost Reduction due to Deficiency in Strength

Deficiency in strength of concrete

Percent (%) of Contract

specimens, Percent (%)

Price Allowed

Less than 5

100

5 to less than 10

80

10 to less than 15

70

15 to less than 20

60

20 to less than 25

50

25 or more

Thickness Deficiency
The thickness of the pavement will be determined by measurement of cores from
the completed pavement in accordance with AASHTO T 148.
The completed pavement shall be accepted on a lot basis. A lot shall be considered
as 1000 linear meters of pavement when a single traffic lane is poured or 500 linear

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 47

meters when two (2) lanes are poured concurrently. The last unit in each slab constitutes
a lot in itself when its length is at least of the normal lot length. If the length of the last
unit is shorter than of the normal lot length, it shall be included in the previous lot.
Other areas such as intersections, entrances, crossovers, ramps, etc., will be grouped
together to form a lot. Small irregular areas may be included with other unit area to form
a lot.
Each lot will be divided into five (5) equal segments and one, core will be obtained
from each segment in accordance with AASHTO T 24.

It is the intent of the Specification that the pavement has a uniform thickness as
called for in the Plans for the average of each lot as defined. After the pavement has met
all surface smoothness requirements, cores for thickness measurements will be taken.
In calculating the average thickness of the pavement, individual measurements
which are in excess of the specified thickness by more than 5 mm will be considered as
the specified thickness plus 5 mm and measurement which are less than the specified
thickness by more than 25 mm shall not be included in the average. When the average
thickness for the lot is deficient, the contract unit price will be adjusted for thickness.
Individual areas within a segment found deficient in thickness by more than 25 mm
shall be evaluated by the Engineer, and if in his judgment, the deficient areas warrant
removal, they shall be removed and replaced by the contractor with payment of the
specified thickness at his entire expense. However, if the evaluation of the Engineer is
that the deficient area should not be removed and replaced such area will not be paid.
When the measurement of any core is less than the specified thickness by more than
25 mm, the actual thickness of the pavement in this area will be determined by taking
additional cores at no less than 5m intervals parallel to the center line in each direction
from the affected location until a core is found in each direction, which is not deficient in
thickness by more than 25 mm. The area of slab for which no pavement will be made
shall be the product of the paving width multiplied by the distant along the center of the
road between transverse sections found not deficient in thickness by more than25 mm.
The thickness of the remainder of the segment to be used to get the average thickness of
each lot shall be determined by taking the average thickness of additional cores which
are not deficient by more than 25 mm.

When the average thickness of the pavement per lot is deficient, payment for the lot

6 - 48

Road Project Management and Supervision Manual Vol.1 Main Text

shall be adjusted as follows:


Table 6.15

6.3.6
(1)

Cost Reduction due to Deficiency in Thickness

Deficiency in Average

Percent (%) of Contract

Thickness per Lot (mm)

Price per Lot

0 to 5

100% payment

6 to 10

95% payment

11 to 15

85% payment

16 to 20

70% payment

21 to 25

50% payment

More than 25

Remove and replace/no payment

Price Adjustments
Locally-funded Projects
Except for extraordinary circumstances as determined by National Economic and

Development Authority (NEDA) and approved by the GPPB, no price adjustment shall
be allowed unless otherwise specified in the SCC.
(2)

Foreign-funded Projects
"Adjustments for Changes in Cost" of the GCC shall be applied, if provided in the
Contract, with its details as indicated in the SCC. The amounts payable to the Contractor
shall be adjusted per rise or fall in the cost of labour, goods and other inputs to the Works,
by the addition or deduction of the amounts determined by the hereunder listed formula
as prescribed in the Contract.

where,
Pn

is the adjustment multiplier to be applied to the estimated contract value


in the relevant currency of the work carried out in period n, this
period being a month unless otherwise stated in the SCC.

is a fixed coefficient, stated in the relevant table of adjustment data,


representing the non-adjustable portion in contractual payments.

b, c, d

are coefficients representing the estimated proportion of each cost


element related to the execution of the Works, as stated in the relevant
table of adjustment data; such tabulated cost elements may be
indicative of resources such as labour, equipment and materials.

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 49

Ln, En, Mn are the current cost indices or reference prices for period n,
expressed in the relevant currency of payment, each of which is
applicable to the relevant tabulated cost element on the date 49
days prior to the last day of the period (to which the particular
Payment Certificate relates).
Lo, Eo, Mo are the base cost indices or reference prices, expressed in the relevant
currency of payment, each of which is applicable to the relevant
tabulated cost element on the Base Date.
If the Contractor fails to complete the Works within the Time for Completion,
adjustment of prices thereafter shall be made using either (i) each index or price
applicable on the date 49 days prior to the expiry of the Time for Completion of the
Works, or (ii) the current index or price: whichever is more favorable to the Employer.
The Contract Price shall be adjusted to take account of any increase or decrease in
Cost resulting from a change in the Laws of the Country (including the introduction of
new Laws and the repeal or modification of existing Laws) or in the judicial or official
governmental interpretation of such Laws, made after the Base Date, which affect the
Contractor in the performance of obligations under the Contract.
The Implementing Office shall adjust the Contract Price if taxes, duties, and other
levies are changed within the period between twenty eight (28) days before the
submission of Bids for the Contract and the date of the last Completion certificate. The
adjustment shall be the change in the amount of tax payable by the Contractor, provided
such changes are not already reflected in the Contract Price.

6.3.7
(1)

Provisional Sum and Daywork


Provisional Sum
Provisional Sum means a sum included in the Contract and so designated in the

BOQ for the execution of any part of the Works or for the supply of goods, materials,
plant or services. Each Provisional Sum shall only be used, in whole or in part, in
accordance with the Engineers instructions and the Contract Price shall be adjusted
accordingly. The total sum paid to the Contractor shall include only such amounts, for
the work, supplies or services to which the Provisional Sum relates, as the Engineer shall
have instructed.
Provisional Sum may be used to facilitate budgetary approval of Variation Orders
without need to seek additional budget. Provisional Sum shall not exceed 3% of the
project cost in general. The Provisional Sum may be also used for the execution of
additional works beyond the limit of Dayworks.

6 - 50

Road Project Management and Supervision Manual Vol.1 Main Text

Works executed under the Provisional Sum shall be valued at the rates or prices set
out at the BOQ or as determined by the Engineer. The Contractor shall submit, when
required by the Engineer, produce quotations, invoices, vouchers and accounts or
receipts in substantiation.
(2)

Daywork
For work of a minor or incidental nature, The Engineer may instruct that a Variation
shall be executed on a daywork basis. The work shall then be valued in accordance with
the Daywork Schedule (unit price of labour by classification, material and equipment)
included in the Contract.
Before ordering goods for the work, the Contractor shall submit quotations to the
Engineer. When applying for payment, the Contractor shall submit invoices, vouchers
and accounts or receipts for any goods.
The Contractor shall deliver each day to the Engineer accurate statements in
duplicate which shall include the following details of the resources used in executing the
previous days work:
(a) The names, occupations and time of Contractors personnel;
(b) The identification, type and time of Contractors equipment and temporary
Works; and
(c) The quantities and types of plant and materials used.
One copy of each statement will be signed by the Engineer and returned to the
Contractor. The Contractor shall then submit priced statements of these resources to the
Engineer, prior to their inclusion in the next statement.
Daywork shall not be executed without written order of the Engineer.

The

Contractor will be paid for daywork at the rates set down in the schedule. All profits,
overheads and other costs must be included in the rates as incidental to the performance
of daywork.

6.3.8

Claims

The word Claim is defined in the context of FIDIC Conditions of Contract as the
Contractor makes formal demands for his due in writing. The demands are either claim for
additional payment or time extension.
Some situations which may give rise to claims are as follows:
*

disputes over quantities

applicability of items in the Bill Of Quantities (BOQ)

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 51

new items

actions of a nominated sub-contractor

Specification interpretation

remedies

delay of issue of drawings or instructions

delay in approval

suspension of work

variation and valuation of variations

delay in payment

acceleration

failure to give possession of site due to delay of ROW acquisition

adverse physical obstructions or condition

adverse weather condition (rain, flood)

If the Contractor considers himself to be entitled to any extension of time for


completion and/or any additional payment, under any Clause of the GCC, the SCC or
otherwise in connection with the Contract, the Contractor shall give notice to the Engineer
describing the event or circumstance giving rise to the claim. The notice shall be given as
soon practicable as and not later than 28 days after the Contractor became aware, or should
have become aware, of the event or circumstance.
The Contractor shall keep such contemporary records as may be necessary to
substantiate any claim acceptable to the Engineer. Without admitting the Implementing Office
liability, the Engineer may, after receiving any notice for claim, monitor the record-keeping
and/or instruct the Contractor to keep further contemporary records. The Contractor shall
permit the Engineer to inspect all these records, and shall (if instructed) submit copies to the
Engineer.
The Contractor shall send to the Engineer a fully detailed claim which includes full
supporting particulars of the basis of the claim and of the extension of time and/or additional
payment claimed.
If the event or circumstance giving rise to the claim has a continuing effect:
(a) This fully detailed claim shall be considered as interim;
(b) The Contractor shall send further interim claims at monthly intervals, giving the
accumulated delay and/or amount claimed, and such further particulars as the Engineer
may reasonably require; and
(c) The Contractor shall send a final claim within 28 days after the end of the effects
resulting from the event or circumstance.

6 - 52

Road Project Management and Supervision Manual Vol.1 Main Text

The Engineer shall respond with approval or with disapproval and detailed comments
based on his evaluation. He may also request any necessary further particulars, but shall
nevertheless give his response on the principles of the claim. The Engineer shall proceed to
agree or determine (i) the extension of the Time for Completion and/or (ii) the additional
payment to which the Contractor is entitled under the Contract. The unit price analysis
submitted by the Contractor at his bid will be one of the most important data for cost claim
evaluation.
Table 6.15 illustrates Contractors Claim for Time Extension due to delayed payment.
Table 6.16

Contractors Claim for Time Extension


Date of Full Payment (Evaluation):

19-Aug-05

Computation of Time Extension due to Delayed Payment


Progress Billing No.1:

Billing Period: From


Date of Certification:
Date of Payment:

Feb.

Mar.

Apr.

11-Nov-04
1-Apr-05
FC ($): 60%

FC (P): 40%

YEAR 2005
May

Jun.

- 25-Feb-05
11-Nov-04
Billing Period)

25-Feb-05

To

GOP: 10%

(Not yet paid)

Jul.

Aug.

End of R.P./
Start of Time Extension
13-Jun-05

* Date of Certification
1-Apr-05
TDPP
0 c.days

Date of Evaluation
19-Aug-05

Proposed TE
54 c.days

TDPS
13 c.days

Time Extension (TE)


67 c.days

Reglamentary Period (RP)

73 c.days

Total Time Duration (TTD) = 140 c.days

1.
2.
3.

TTD
=
From
Reglamentary Period (RP)
TE
=

1-Apr-05
=
TTD-RP =

Note: Period covered by TE: From

To
45 + 28
140

19-Aug-05
=
73

13-Jun-05

To

140

c.days

73 c.days
=

67 c.days

19-Aug-05 (as of the evaluation date)

Reduction of Time Extension (TE)


A.

TDPP - Time Duration due to Partial Payment (Billing No.19


a).
Contract Breakdown
Foreign Component (JBIC)
: FC (US$)
: FC (P)
GOP
: LC (P)
b).
Date of Partial Payment received:
As of
Foreign Component (JBIC)
: FC (US$)
: FC (P)
GOP
:
TDPP
a.
b.

B.

=
=
=
=

50%
40%
10%
19-Aug-05
0%
0%
0%

TE x % of partila payment
67
days x
67
days x
67
days x

0%
0%
0%

Not yet received.


Not yet received.
Not yet received.
=
=
=
Total =
TDPP =

cal.days
cal.days
cal.days
cal.days
cal.days

TDPS : Time Duration during where the Contractor slowed down the rate of work due to delay in payment
Month

Workable Days

Slow-Down Rate
a) Actual Accomplishment
(during partial suspension)

Equivalent
Workable
Days

b) Sched. Accomplishment

(1)
Jun.'05
Jul.'05
Aug.'05

Notes:

TDPS

(2)
18

(3)
(4)
1.173%
4.04
5.225%
19
1.153%
3.89
5.625%
21
0.868%
5.04
3.614% <-------------------------------------Total:
12.98
a) Actual accomplishment (refer to Attachment 3)
b) Scheduled accomplishment based on the approved Bar Chart/S-curve
(4) =
(3)a x (2)
(3)b
=
13 cal. Days

5.896% x19days/31days

Net Time Extension


TE (net)

=
TE (computed)
=
67
=
54 c.d.
where,
TDPP =
TDPS =

Possible Overlap (PO)

with previous billings

(TDPP + TDPS)
0
+
(Positive Net Time Extension)
- c.d.
13 c.d.
=

13 )

(None)

Proposed Time Extension


TE (NET) = TE - possible overlap
=
54 c.days

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 53

6.4 Quantity Control


6.4.1

Objectives

Most of DPWH contract is a unit price and quantity contract. The quantity control is
one of the most important elements for project management as it directly relates with the
project cost. The documents to be referred to for quantity control are GCC, SCC,
Specifications, BOQ and Drawings.
The Engineer, in cooperation with the Project Inspector, should work to:
*

Ensure that the methods used in the measurement of quantities meet the contract
requirements and Specifications;

Verify that the correct quantities of completed work are reported for progress payments.
Note that large quantities are not forgotten in the billings;

Ensure that a new overall estimate is made for each progress estimate. If computed
monthly work quantities are merely added on the previous period, it may result in
cumulative errors;

Check the quantity calculation back-up data submitted by the Contractor for monthly
billings. Compare with the quantity estimate data of the detailed design stage;

Ensure double payment will be avoided by checking field measurement notes


(logbook) and drawings;

Monitor the planned quantity and work progress. If there is any big difference, instruct
the Contractor to identify the causes;

Where appropriate, do additional checking to assure the sufficiency of the validation.


Do not wait until the final stage of construction as correction of over-quantity,
especially for major items, would become impossible; and

At the final statement stage, review all final quantities in details on all items.

No payment shall be made to any defective work until the Contractor meets the
requirements, either by removal, replacement or reconstruction, and accepted by the Engineer.

6.4.2

Duties of Quantity Engineer

The Quantity Engineer (or the Project Inspector) is responsible for all quantity
measurement and estimate. He should monitor all works executed by the Contractor and treat
variations instructed by the Engineer.
His duties include:
*

verify the quantities in the Contract BOQ through a check of quantity estimate data of
the design stage;

6 - 54

Road Project Management and Supervision Manual Vol.1 Main Text

carry out quantity measurement at the field;

keep up-to-date quantity records including field measurements;

assist the Engineer in the review of shop drawings for quantity estimate;

assist the Engineer in preparing weekly and monthly reports;

evaluate variation orders and costs proposed by the Contractor;

evaluate monthly statement and claims; and

prepare forecast final quantity and construction cost and revise it from time to time.

6.4.3

Inspection Techniques

The following is a summary of recommended inspection techniques to be applied for


quantity control:
*

Verify that the items reviewed were measured in the units called for in the BOQ and
that the methods of measurement prescribed in the contract were followed;

Examine project records to ensure that all materials for payment were delivered and
incorporated into the project or stockpiled for future incorporation;

When payment is based on weight or mass, verify the accuracy of the measurements,
including calibration of scales;

Where payment is based on loads delivered to the project, either on a weight or volume
basis, verify the procedures for assuring validity in receipt of haul tickets;

For area or volume measurement, clarify whether measurement is based on actual


dimensional checks to the extent necessary to verify the actual work performed
(on-site measurement) or by dimensions in the approved drawings/plans; and

Ensure that measurements were made at the proper time and prior to the subsequent
placement (cover) of other courses of materials.

6.4.4

Bill of Quantities (BOQ)

The BOQ is an estimated quantity. It is subject to change in accordance with the


measurement at the site or the shop drawings submitted by the Contractor reflecting the
current site conditions. The quantity for earthworks in particular, has a risk of substantial
change compared with the contract design drawings (plans) as a result of As-stake survey.
The BOQ provides information on the quantities of Works to be performed by the
Contractor and a priced BOQ for use in the periodic valuation of Works executed for payment.
Works are itemized in the BOQ in detail to identify the different classes of Works, or between
Works

of

the

same

nature

carried

out

in

different

locations

or

in

other

circumstances/conditions which may lead to different considerations of cost.


*

The BOQ contains items of work for the construction, installation, testing, and
commissioning of work to be done by the Contractor.

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 55

The BOQ is used to calculate the Contract Price. The Contractor is paid for the
quantity of the work at the rate in the BOQ for each item.

If the final quantity of any work differs from the quantity in the BOQ for the particular
item and is not more than twenty five percent (25%) of the original quantity, provided
the aggregate changes for all items do not exceed ten percent (10%) of the Contract
price, The Engineer shall make the necessary adjustments to allow the changes subject
to applicable laws, rules, and regulations.

The Contractor must provide the Engineer with a detailed cost breakdown of any rate
in the BOQ.

6.4.5

Measurement and Evaluation

The Works shall be measured and valued for payment. The Contractor shall show in
application of his statement for Interim Payment and Completion the quantities and other
particulars detailing the amounts which he considers to be entitled under the Contract.
Whenever the Engineer requires any part of the Works to be measured, reasonable notice
shall be given to the Contractor who shall:
(a) Promptly either attend or send another qualified representative to assist the Engineer in
making the measurement; and
(b) Supply any particulars requested by the Engineer.
If the Contractor fails to attend or send a representative, the measurement made by the
Engineer shall be accepted as correct.
Except as otherwise stated in the Contract and notwithstanding local practice,
(a) Measurement shall be made of the net actual quantity of each item of the Permanent
Works in accordance with the Specifications; and
(b) The method of measurement shall be in accordance with the BOQ or other applicable
schedules.
Quantity Control should also take into account any variations approved by the Engineer
during the project implementation for quantity monitoring, including:

6 - 56

increase or decrease the quantity of any work included in the Contract,

omit any such work;

change the character or quality or kind of any such work;

change the levels, lines, position and dimensions of any part of the Works;

execute additional work of any kind necessary for the completion of the Works; and

change any specified sequence or timing of construction of any part of the Works.

Road Project Management and Supervision Manual Vol.1 Main Text

The Engineer shall evaluate each item of work, applying the measurement agreed or
determined in the above and the appropriate rate or price for the item in the Contract.. Any
item of work included in the BOQ for which no rate or price was specified shall be considered
as included in other rates and prices in the BOQ and will not be paid for separately, in
principle.

6.4.6

Monitoring and Estimate of Final Quantity

The Engineer shall monitor work quantities provided in the BOQ, especially in the
As-staked plan, shop-drawings and monthly billings. The Engineer shall monitor the progress
of work item, especially major items and earth works, against the BOQ and forecast the final
quantity. If any items are seemed to exceed the planned quantity in the BOQ, he must evaluate
and take appropriate actions to correct and/or propose measures to control the project cost
within the budget.

6.5 Documentation
The project implementation requires many types of reports and records. The objectives
of recording and reporting are to keep the project information and data as evidence of proper
project implementation, correct processing of payment, report the project status to CO, RO,
DEO and funding agencies (local/foreign).
The Engineer shall keep and maintain the following project data during the
implementation (construction and maintenance period) and handover them to the concerned
RO and DEO after the final taking over of project for maintenance by DPWH.

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 57

Table 6.17

Checklist of Project Documents


Data Type
Hard Copy
Electronic
Data
Data

Classification of Data at the


Engineers Office during
Implementation

Hand-over to
Administration

Maintenance

Office

Office

(DPWH)

(DPWH)

Contract Documents

Yes

Yes

Correspondence (Letters)

Yes

Yes

Progress Report (monthly, quarterly)

Yes

Yes

Yes

Billing and Payment

Yes

Yes

Yes

Completion Report

Yes

Shop Drawings

Yes

As-built Drawings

Yes

Minutes of Meetings

Yes

Inspection Sheet / Instruction Sheets

Yes

Quality Control Data

Yes

Quantity Measurements

Yes

EMP Data

Yes

Other Miscellaneous Data

Yes

Yes

Yes

Yes

Yes
Yes

Yes
Yes

Yes

The Administration and Maintenance Office of DPWH shall take over important
documents which are required for administration and maintenance. These offices shall keep
them for a certain period in accordance with regulations and requirements.

6.5.1

Progress Reports

The Engineer shall accomplish a monthly progress report for submission to the
Implementing Office, funding institutions and other concerned agencies.
The report shall contain the following:

6 - 58

Road Project Management and Supervision Manual Vol.1 Main Text

Table 6.18

Progress Report
Foreign-Funded

Locally-Funded

Project with

Project w/o

Consultant

Consultant

Need

Need

- Project Information and Impact

Need

Need

- Construction Progress and Status

Need

Need

- Construction Status (Progress)

Need

Need

- Project Activities and Accomplishment of Quantity

Need

Need

- Material Testing and QC Activities

Need

Need

- Contractors Resources

Need

Need

Need

Need

- Bar Chart and S-Curve

Need

Need

- Status of Construction Equipment

Need

Need

- Status of Contractors Personnel

Need

Need

- Weather Report

Need

Need

- Progress Photographs

Need

Need

- Letters (List)*

Need

Need

- Overall Implementation

Need

- Manning Schedule

Need

Content

Executive Summary
Main Report

- Issue and Problems, and Recommendations and


Actions
Attachments

Consultancy Services for Construction Supervision

- Organization Set-up

The Office of the


Need
Engineer

Note: Attach letters if they are very important, such as claim or action plans for recovery of delay.

6.5.2

Project Logbook

The Engineer shall accomplish the Project Logbook to keep a complete record of daily
entries. The logbook shall be duly signed by the Engineer and concurred by the Contractor in
accordance with DO No. 216, Series of 2000.
The logbook provides the following:
*

Permanent file evidence that inspections are being made as required by the Contract

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 59

and Specifications;
*

Basis for acceptance of completed work;

Record of field conditions and contractors performance;

Record of daily project activities, equipment, manpower and resources at site; and

Record of daily management and supervision activity, observations, findings,


resolution of identified problems, claims, and any other topics of interest.

The logbook should be clear and concise with facts. The record should be accurate and
specific since the content may be used in evaluating contract claims. If no work was
performed at all, a daily report shall be stated No Work and reasons. The daily record of
personnel and equipment is particularly important in view of the possibility of Contractors
claims for stand-by cost of the idled personnel and equipment. Verify that discussions with the
Contractor are confirmed in writing and are made a part of the official project file.
The record contains the following:
1)

Date and weather conditions;

2)

Work of staking party;

3)

Work of inspectors;

4)

Work of office staff;

5)

Construction work in progress;

6)

Contractors crew, equipment and materials on each item;

7)

Inspections, decisions, and details discussed with inspectors;

8)

Instruction to Contractors;

9)

The substance of important communications and discussions with the Contractors,


concerning activity, progress, change, interpretation of specifications, etc.; and

10) Any information not covered in other records, which might have bearing in case of
future disagreement, such as difficulties encountered in construction and their causes,
delays caused by breakdown of equipment, etc.
If the operation is on a shift basis, the entries should be signed and properly endorsed.
The Materials Engineer is also required to keep a Log Book on Material Quality Control
(per Memorandum dated 28 October 2004 on Revised Format Submitting Monthly Materials
Control Report) recording quality control activities and other information and observation
relevant to materials quality control in addition to the above.
After completion of the project, the logbook shall be turned over to the Implementing
Office.

6 - 60

Road Project Management and Supervision Manual Vol.1 Main Text

CONTRACT I.D. NO.


: ___________________________________
PROJECT NAME
: ___________________________________
LOCATION
: ___________________________________
CONTRACTOR : ___________________________________
DATE
: ___________________________________
WEATHER
(AM)
: ___________________________________
(PM)
: ___________________________________
ACTIVITIES:
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
EQUIPMENT ON SITE:
Payloader

Road Grader

Vibratory Roller

Water Truck

Dump Truck

Bulldozer

Backhoe

Backhoe

One Bagger Mixer

Transit Mixer

Concrete Vibrator

Welding Machine

Plate Compactor

Concrete Screeder

MANPOWER ON SITE:
Project Manager

Warehouseman

Project Engineer

Driver Operator

Materials Engineer

Carpenter/Mason

Foreman

Laborer

Survey Team

Watchman

Timekeeper

LEGEND:
/

OPERATIONAL/PRESENT

IDLE/ABSENT/BREAKDOWN

ACCOMPLISHMENT:
Scheduled

________________________

Actual:

________________________

Slippage:

________________________

Time Elapsed:

________________________

VISITORS:
______________________________
______________________________
______________________________
______________________________
REMARKS:
___________________________________________________________________________________
___________________________________________________________________________________

Prepared by:

Concurred by:

______________________________

______________________________

Project Inspector (DPWH)

Project Engineer (Contractor)

Noted by:

Noted by:

______________________________

______________________________

Materials Enginer (DPWH)

Project Engineer (DPWH)

Figure 6.18

Project Logbook Format

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 61

6.5.3

Correspondence

Letters are official communication between the Engineer and the Contractor2.
It is very common that the Engineer gives verbal instructions so these should be
officially confirmed in writing.
The letters are filed in order and kept at the office as follows:

Table 6.19

Out-Going

In-Coming

6.5.4

Responsible Office for Securing the Documents


Foreign-Funded Project with

Locally-Funded Project without

Consultant

Consultant

Employer (DPWH)

DPWH (CO, RO, DEO, etc)

Contractor

Contractor

Others

Others

Employer (DPWH)

DPWH (CO, RO, DEO, etc)

Contractor

Contractor

Others

Others

Progress Photographs

Photographs shall be taken for:


*

Periodic record of work progress (weekly or monthly);

Construction record of important work activities, including concreting, laying of


Asphalt Concrete pavement, etc.;

Construction record of the Works which will be covered after construction such as
reinforcement, foundation, back fill, drainage pipes, base, subbase, etc.;

Construction record of the Works which are removed after construction, such as
excavation, demolition of obstacles, tree cutting, etc.;

Material and quality control tests such as field density, CBR, compression, etc.;

Defects, wrong workmanship, damage by flood, wrong traffic safety control;

Mobilization of equipment and materials; and

Any other specific issues and incidents, including visit of very important persons.

The use of digital camera is recommendable since digital files are easily transferred and
stored.
Figure 6.13 illustrates progress photographs.

2 Communication thru E-mail is one of the efficient communication means and the record (print-out) should be
kept in letter files for reference.

6 - 62

Road Project Management and Supervision Manual Vol.1 Main Text

Apr. 2005

Jun. 2002
Damage of Outlet & Apron of Box Culvert by Scouring

Steel Sheet Piling for Foundation

Dec. 2005

Jul. 2005

Completion of Repair (Scouring Protection Works)

Steel Sheet Piling for Foundation

Progress Record for Scouring Protection Works


Gabion
Retaining Wall
Removal of Head of
Slide-Mass

Sub-soil / Road
Side Drainage

Typical
Section
A-A
SECTION

Mar 2003

Jun. 2002
Damage of Roadway by Landslide

Landslide Countermeasure Design

Mar. 2006

Jun. 2005

Completion of Countermeasure Works

Completion of Earthworks

Dec. 2004
Start of Removal of Head of Slide-Mass

Progress Record for Landslide Countermeasure Works

Mar. 2006
Flood by Heavy Rain

Rejection of Stone Masonry Work because of Insufficient Mortar Fill

Figure 6.19

Progress Photographs

Road Project Management and Supervision Manual Vol.1 Main Text

6 - 63

Chapter 7

Quality Control

7.1 General
Quality Control, as applied to the various stages of project implementation, is viewed
and considered as the Contractors responsibility while quality assurance refers to the
responsibility/obligation of the Implementing Office (IO) to ensure strict compliance to
existing standards/specifications and other pertinent issuances relative to project
implementation. However, the concept that quality control is solely the Contractors
responsibility is wrong. Quality control is the responsibility of everyone involved in the
project and as such, it is not a separate function but rather is one of the core elements of
quality assurance.
Quality Assurance is defined as planned systematic actions to ensure that the quality of a
product satisfactorily meets the requirements of the governing Specifications. It is an
all-encompassing term that includes quality control by the Contractor, the conduct of
assessment/inspection by an independent inspectorate team such as the DPWH Quality
Assurance Units (QAUs), the employment of qualified laboratory and technical personnel by
both parties (the Contractor and the IO) and the acceptance of the project by the IO. Quality
Assurance is a total system attained as a result of the combined efforts and resources of the
entities involved in the project. It is a cycle of management in terms of planning,
implementation, review and evaluation as illustrated in the following figure.

Figure 7.1

Quality Management

Statistical quality control method is not yet being used by DPWH for infrastructure
projects. Statistically-based methods are effective means of ensuring a quality product and
would be a fundamental component in the quality management. It is a challenge to be
introduced for the DPWH projects especially for portland cement and asphalt concrete
production and construction.
Quality control charts combined with statistical analysis will help identify problems and

Road Project Management and Supervision Manual Vol.1 Main Text

7-1

suggest solutions or improvement. A Control Chart is a tool which graphically depicts the
average value and the upper and lower control limits. It helps to distinguish between normal
and unusual variation in a process. The most popular chart is the Average and Range Control
Chart (X-R Chart) as shown in the following figure.
*

If the data fluctuates within the limits, it is the result of common causes within the
process and can only be affected if the system is improved or changed;

If the data falls outside of the limits, it is the result of special causes; and

If the data show incremental or declining trends, earliest action should be taken for
correction before it become out of control.
Asphalt Temperature

150.0

Spot Problem

148.0

al
e nt
re m
Inc oble m
r
P

146.0

Upper Limit 145oC

Ave-X ( C)

144.0
142.0

Average 141oC

140.0
138.0
136.0
Lower Limit 135oC

134.0
132.0
130.0
1

10

11

12

13

14

15

Lot No

Temperature Range Deviation

Range (oC)

Spot Problem
10
9
8
7
6
5
4
3
2
1
0

al
e nt
re m m
Inc
ble
o
r
P

Average 4.1oC

Source: JICA TCP Team

Figure 7.2

7-2

10

11

12

13

14

15

Lot No

Statistical Quality Control (X-R Control Chart)

Road Project Management and Supervision Manual Vol.1 Main Text

7.2 Quality Control Program


The Contractor has the prime responsibility to produce the product (i.e., construction
materials) to satisfy the quality requirements in accordance with the Specifications prior to
incorporating them into the project. The Engineer, on the other hand, has the responsibility to
verify ands ensure that the Contractor produces the product in accordance with the Contract
and Specifications.
Sub-Clause 4.9 of the FIDIC GC stipulates the following conditions where the
Contractor shall satisfy and comply with:
*

The Contractor shall institute a quality assurance system to demonstrate compliance


with the requirements of the Contract. The Engineer is entitled to audit any aspect of
the system;

Details of all procedures and compliance documents shall be submitted to the Engineer
for information before each design and execution stage will be commenced; and

Compliance with the quality assurance system shall not relieve the Contractor of any
of his duties, obligations or responsibilities under the Contract.

The Quality Control Program (QCP) is a program/schedule of quality control works in a


certain project which involves inspection and testing of construction materials to be
incorporated into the work in accordance with the Contract, Specifications and other related
policies.
The Contractor shall submit a quality control plan for delivering quality production as part
of the construction methods. It is imperative that the preparation of the plan should be a detailed
one, taking into account and shall include the following:
1)

Site Condition;

2)

Laboratory Plan in accordance with the Contract;

3)

Process of control testing ;

4)

The schedule of activities to be undertaken/performed;

5)

Materials resources, list of materials to be tested and type of tests to be conducted;

6)

Frequency of tests, taking into account the project quantity by item; and

7)

Laboratory equipment/apparatus and technical staffs to be employed.

The table hereunder describes the quality control activities to be undertaken by the
Materials Engineer in each phase of construction.

Road Project Management and Supervision Manual Vol.1 Main Text

7-3

Table 7.1
Phase
Preparatory
Phase

Startup
Phase

Production
Phase

Quality Control Activities

Activities
Review all contract requirements
Ensure compliance of component material to the contract
requirements
Coordinate all submittals including certifications
Ensure establishment of laboratory and equipment, tools and
personnel to comply with the contract requirements
Ensure preliminary testing is accomplished
Review the contract requirements with personnel who will
perform the work
Inspect startup of work
Establish standards of workmanship
Provide training as necessary
Establish detailed testing schedule based on the production
schedule
Conduct intermittent or continuous inspection during construction
to identify and correct deficiencies
Take samples and test them at site and laboratory to verify the
specified quality
Inspect completed phases before scheduled Government
acceptance
Provide feedback and system changes to prevent repeated
deficiencies
Description of records and documents. List the records and data to
be submitted and maintained

The Materials Engineer shall prepare a Quality Control Procedures Flow Chart (for
instance for Concrete Works, refer to Figure 7.3) on the major quality control and testing of
construction materials in accordance with the Specifications and Standard Test Procedures set
by AASHTO and/or ASTM. The said procedures/flow chart shall include the tests to be
performed, the applicable test methods, frequency of tests and requirement.

7-4

Road Project Management and Supervision Manual Vol.1 Main Text

Figure 7.3

Quality Control Procedures

7.3 Quality Control Specifications


The term Specification as used in the DPWH Standard Specifications applies to the
written contract documents which includes material and workmanship requirements,
inspection and testing procedures, and procedures for measurement and payment of work, all

Road Project Management and Supervision Manual Vol.1 Main Text

7-5

of which are mostly based on AASHTO and ASTM.


The functions of the Specifications are categorized into two (2) areas, depending on the
perspective/viewpoint of the person/s utilizing it:
1)

2)

With respect to the Owner and his Engineer


-

obligation to define material and workmanship requirements

inspection and testing during the period of project implementation

to indicate how the work will be measured and paid for

With respect to the Contractor


-

obligation of complying with the contract requirements during the construction


period

The Specification is the starting point of quality control, without this, there can be no
quality control.
Hereunder are Specifications/Standards that are usually referred to in the project
implementation and conduct of materials testing.
Table 7.2
1.

Specifications/Standards

DPWH Standard Specifications for Highways, Bridges and Airport Vol. II


2013 Edition

2.

AASHTO Standards
Part I, Specifications, Part II, Methods of Sampling and Testing

3.

Annual Book of ASTM Standards


Volume 4.02 - Concrete and Aggregates
Volume 4.03 - Roads and Paving Materials, Traveled Surface Characteristics
Volume 4.04 - Roofing, Water Proofing, Bituminous Materials
Volume 4.08 - Soil and Rock, Building Stone, Geotextile

4.

Other Standards and Special Specifications including relevant DPWH


Department Orders.

The above Specifications or a copy thereof should be made available at the project site at
all times for guidance and ready reference.

7.4 Project Laboratory


In order to ensure the quality of materials to be incorporated into the works, the
Contractor is required to provide competent quality control personnel and fully equipped
laboratory. In consonance with PD 1594, the provision of minimum testing equipment is

7-6

Road Project Management and Supervision Manual Vol.1 Main Text

included in the pre-qualification of Contractors to ascertain their technical capability and


financial capacity to undertake the project. The Engineer shall have necessary quality control
supervisory personnel to oversee the Contractors work.
Listed hereunder are conditions set for the provision and use of project laboratory.
The Engineers

Laboratory

some of the locally-funded projects where the Consultant is


employed as the Engineer

Refer to Part A of
Specifications

This is applicable on most of the foreign-funded projects and

The Contractor is obliged to provide the Engineers laboratory


in accordance with the Contract. The Engineer (Consultant)

(Special

will operate the laboratory with apparatus and testing

Specifications) as

equipment, assistant and consumables furnished or supplied

to the details.

by the Contractor.
-

This laboratory may be also used by the Contractor upon


approval of the Engineer. The Special Specification must
define whether the Contractor is allowed to use the Engineers
laboratory or he should provide separate laboratory for his
own use to avoid duplicated laboratory cost in the Bid.

Use of RO and/or

DEO Laboratory

This is applicable on most of the locally-funded projects


where the Consultant is not employed as the Engineer.

The Engineer uses the laboratory of the RO and the DEO or


the laboratory established by the Contractor at site.

The Materials Engineer shall ensure that the testing laboratory provided by the
Contractor satisfactorily meets the contract requirements and that the scales/weighing devices
are calibrated by a duly accredited calibration center/company.
The Contractor may avail the services of private testing laboratories1 that are accredited
by the Bureau of Research and Standards (BRS) to conduct materials testing for and in behalf
of the Implementing Office. However, it is required that the samples must first be submitted to
the BRS or the Regional/ District laboratory for the conduct of testing thereof. If and when the
said laboratories do not have the capability to conduct the required tests (either due to lack of
necessary equipment or that the samples could no longer be accommodated due to the
voluminous samples that have to be tested) and after having issued the waiver/certification
stating either of the reasons as stated above, only then can the Contractor avail the services of
the accredited private testing laboratories.

1Updated list is posted at the DPWH website

Road Project Management and Supervision Manual Vol.1 Main Text

7-7

The typical equipment/apparatus required for the conduct of tests on materials in various
road construction operations are shown in Table 7.3.
The laboratory testing equipment/apparatus used in the implementation of local and
foreign assisted projects shall be transferred/turned-over in line with the proposed
standardization of the DPWH District laboratories pursuant to DO Nos. 07, Series of 2006
and 13, Series of 2007 regarding the Guidelines in the Purchase, Use and Transfer/Turn-over
of Non-Expendable Properties for the Implementation of Local and Foreign-assisted Projects.
Table 7.3

Material Testing Equipment/Apparatus

Tests
Soils

Required Equipment and Apparatus*


sieves, scales, liquid limit devices, compaction test equipment, FDT
apparatus, hot plates or field stove, oven, sampling equipment, sample
containers, drying pans and CBR apparatus, etc.

Soil Aggregates

sieves, sample splitters, scales, hot plates, devices for determination of


moisture content and liquid limit, drying pans, and apparatus for
conducting laboratory compaction and field density tests , CBR
apparatus, etc.

Hot Mix Asphalt

thermometers, sieves, sample splitters, scales, stove, oven, equipment

(HMA)

for taking samples from the pavement, and apparatus for determining
density and stability of the HMA mixture.

Portland Cement

slump cone or other specified equipment for determining consistency

Concrete

of the mix, air meter, concrete cylinder or beam molds, sieves, sample
splitters, scales, pans, stove or hot plate, and containers for
determining unit weights

7-8

Road Project Management and Supervision Manual Vol.1 Main Text

Gradation
AASHTO T88-93

Atterberg Limit (LL, PL)


T89-93, T90-92

Laboratory Compaction
T99-93

Los Angeles Abrasion


T96

CBR Test
AASHTO T193 &
AASHTO T180, Method

Field Density
T191-93

Marshal Stability
AASHTO T 245

Bitumen Extraction
AASHTO MT 307-04
(Modified AASHTO T164 Method A)

Slump Test
T119

Temperature of Concrete
and Asphalt Mixture
(Digital)

Figure 7.4

Core Sampling
AASHTO T24

Flexural Strength &


Compressive Strength
AASHTO T23 & T97

Material Testing Equipment/Apparatus

7.5 Accreditation of AC and PCC Batching Plants


Portland cement and asphalt concrete batching plants are required for most of the DPWH
road construction or preventive maintenance projects.
Under DO No. 253, Series of 2003, the BRS is authorized to accredit asphalt and
portland cement concrete batching plants for the supply of concrete mixes to DPWH projects.
Accreditation refers to the procedure by which an Agency (DPWH-BRS in this case)
gives formal recognition, under duly established rules and regulations, that a private company
is capable of and competent to operate a batching plant to concrete mixes to the project.
One of the major requirements to be submitted to the BRS by an applicant is his/her
companys Quality Manual which contains the following information:
a.

Company Policy (Mission/Vision/Objectives)

b.

Information on Physical Plant Layout

c.

Vicinity Map of the Plant

Schematic Flow Diagram

Batching Procedures/Flow Chart

Road Project Management and Supervision Manual Vol.1 Main Text

7-9

d.

Organizational and Manpower Chart, Including Production Staff

e.

Curriculum Vitae and Job Description of Key Production and Quality Control
Personnel

f.

System of Quality Control, Quality Assurance and Standards being adopted

g.

Calibration Report of all Measuring Devices/Testing Equipment

h.

Safety Program/Requirement or Commitment to Safety or Safety Policy

i.

Sources of Raw Materials (for cement, aggregates, water and admixtures)

j.

List of Available Laboratory Testing Equipment

The said manual shall be in accordance with and conform to the accepted standards of
quality performance, technical expertise and competence which should be made available for
use by the companys quality control personnel. Likewise, the plant laboratory shall have
adequate catalogue and instruction manuals on the use and operation of all relevant equipment,
on the handling and preparation of test items, and on the standard testing techniques, where
the absence of such instructions could jeopardize the effectiveness of the whole testing
procedure/process.
Upon receiving all the requirements from the applicants, the BRS personnel/accreditors
shall inspect the batching plant, evaluate the capabilities of the technical personnel, observe
the actual production operations and assess the quality control system. The BRS then issues a
Certificate of Accreditation to the applicant who meets the requirements for said accreditation
in accordance with the work flow in Figure 7.4.

7 - 10

Road Project Management and Supervision Manual Vol.1 Main Text

APPLICANTS FILE
APPLICATION BRS FORM NO.2
WITH SUPPORTING DOCUMENTS
(Quality Manual, Mayor's Permit, DENR
Permit to Operate (Optional), Articles of
Incorporation, Accreditation Fee)

APPLICANT SUBMITS
CORRECTED DOCUMENTS

TSED EVALUATES DOCUMENTS

NO

COMPLETE
AND
IN ORDER

INFORMS APPLICANT

ARRANGE SCHEDULE
OF ASSESSMENT

APPLICANT COMPLIES
WITH REQUIREMENTS

TSED CONDUCTS ASSESSMENT

NO
COMPLY

INFORMS APPLICANTS

YES
TSED CONDUCTS
FINAL EVALUATION

ISSUES CERTIFICATE
OF ACCREDITATION

Figure 7.5

BRS MONITORS
COMPLIANCE WITH RULES
AND REGULATIONS

Flowchart for Batching Plant Accreditation

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 11

Under DO No. 253, Series of 2003, the BRS Certificate of Accreditation shall be issued
specifically to an assembly of mechanical and/or digital/electronic type of batching plant.
However, there are some private companies and Contractors supplying concrete mixes to
DPWH projects that use conventional/volumetric type of batching plant. Inasmuch as the said
type of batching plant is technically not within the scope of the said Department Order, they
seldom undergo the accreditation procedure of the BRS, unless in few cases where the owners
request for the inspection/assessment of the same.
The said type of batching plant is issued BRS permit to supply mixes to DPWH projects
for a period of one (1) year only and may be utilized by the Implementing Office on small
projects in accordance with Subsection 311.3.7, Mixing Concrete, paragraph 7 of the DPWH
Standard Specifications for Highways, Bridges and Airports, Vol. II 2013 Edition which states
that: In exceptional cases and when volumetric measurements are authorized for small
projects requiring less than 75 cu.m. of concrete per day of pouring, the weight proportions
shall be converted to equivalent volumetric proportions. In such cases, suitable allowance
shall be made for variation of the moisture condition of the aggregates, including the bulking
effect in the fine aggregate. Batching and mixing shall be in accordance with ASTM C 685,
Sections 6 through 9.

Checking of Plant

Figure 7.6

Calibration of Weighing Materials

Checking of Control Machines

Assessment of Batching Plant for Accreditation

The BRS shall monitor the operation to ensure their continuous compliance with its
terms and conditions. The guidelines cover both stationary and portable asphalt and portland
cement concrete batching plants to supply quality concrete mixes to DPWH projects.
The plant shall have a quality control and assurance system manual that complies with
accepted standards of quality performance, technical expertise and competence and available
for use by the quality control personnel. The laboratory shall ensure that all incoming
materials/products are not used or processed until it has been inspected or otherwise verified
as conforming to specification requirements. For example, one Quality Test shall be
performed on Portland Cement per bulk delivery or for every 2,000 bags.

7 - 12

Road Project Management and Supervision Manual Vol.1 Main Text

Aggregate
Graduation
Control Unit

Drier

Oversize
Removal

Cold Bin with Wet Aggregate


3/4"

3/8"

Screenings

Hot Bin

Fine
Sand

Weight
Measuring

Filler
Belt Conveyer

Bitumen
Mixer

Aggregate Elevator

Aggregate Weighing System of Standard Asphalt Batch Mix Plant

Aggregate Graduation Control


/ Hot Bin
Mixer
Measuring Unit
Cold Bin

Drier

FRONT VIEW
ASPHALT BATCHING PLANT

CONCRETE BATCHING PLANT


Figure 7.7

Asphalt and Portland Cement Concrete Batching Plants

7.6 Quality Control Activities


7.6.1 Category of Activities and Frequency of Tests
Quality Control activities consist of the following three (3) major areas of responsibility:

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 13

Table 7.4
Category

Quality Control Categories


Area of Responsibility

Materials Quality - Ensure that only accredited Asphalt and Portland


Cement Concrete Batching Plants are used for AC
and PCC production
- Ensure that the types, properties, and procedures for
production and storing of materials meet the
Specifications
- Only materials that passed the Specifications and
approved by the Engineer are used for the
construction
- Test results are submitted to the Engineer for
approval before the materials are incorporated
into the Works
- Good skill, art and/or technique are used for quality
Workmanship
products in accordance with appropriate
construction methodology.
- Check/verify in compliance with specified geometry
(lines and grades), dimensions, strength, etc.
- Test results on finished product of the Contractors
Product Quality
Works meet the specified strength and quality.
- Compliance
with specified geometry (line and
grades), dimensions, strength, tolerances in length,
weight, height, camber, evenness, etc. in the
approved plans and specifications

Staff
- ME
- Quality Control
Inspectors
- Laboratory
Technicians

- Project Inspectors
- Technicians

- ME
- Quality Control
Inspectors
- Project Inspectors

The Materials Engineer and his staff in cooperation with the Project Inspectors shall
carry out the following Quality Control activities:
*

Supervise continuously the Contractors technicians/foremen in carrying out specified


sampling, testing and reporting works;

Instruct

the Contractor

where to take representative samples and ensure frequency

of sampling and testing as required in the Specifications;


*

Ensure

that all

tests on

materials and field operations are correctly recorded by

the Contractors technicians daily and submitted to the Engineer without delay;
*

Ensure that the Contractors technicians submit the results of all tests using the
standardized

laboratory

forms;

Submit a monthly summary of all test results to the Engineer, together with the
recommendations regarding approval or rejection of materials and work,
based on the test data and observation; and

7 - 14

Carry out independently from the Contractors technicians, any

sampling

Road Project Management and Supervision Manual Vol.1 Main Text

and testing for the purpose of confirming

the test results submitted by the

Contractor, if required. The Engineer should also conduct a random or surprise


sampling and testing.
The Engineer needs to work not only with his own staff but also with the other Inspectors
and Surveyors as most of the works are correlated. Acceptance on the quality shall be based
on the results of sampling and testing along with visual inspection.
Frequencies of testing are specified in the Specifications, depending on the
characteristics of the overall process. The conduct of these tests on construction materials are
intended to be used for quality assurance and acceptance of the work.
Table 7.5 illustrates the minimum test requirements for roadworks.

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 15

Table 7.5
Item
No.

Description

102 Excavation
&
104 Embankment

105
200

201
&
202

Item of Test*

Minimum Test Requirements


Test or Control
(AASHTO)

Frequency

1. Gradation
T88-93
2. Atterberg Limit (LL, PL, PI)
T89-93, T90-92
3. Laboratory Compaction
T99-93
4. CBR Test
T193-92
5. Field Density
T191-93
Subgrade
Same as Item 104
Preparation
Spot weakness
Proof Rolling Test
Aggregate Sub- 1. Gradation
T27-93
base Course
2. Atterberg Limit (LL, PL, PI)
T89-93, T90-92
3. Laboratory Compaction
T180-93
4. Field Density
T191-93
5. CBR Test
T193-92
Aggregate
1. Gradation
T27-93
Base Course
2. Atterberg Limit (LL, PL, PI)
T89-93, T90-92
Crushed
3. Fractured face
BS 8-12
Aggregate Base 4. Laboratory Compaction
T180-93
Course
5. Field Density
T191-93

For every 1,500 cu.m. or fraction thereof


For every 1,500 cu.m. or fraction thereof
For every 1,500 cu.m. or fraction thereof
For every 500 sq.m. of each layer or fraction thereof
For every 500 sq.m. of each layer or fraction thereof
Same frequency as in Item 104
Both lanes for full length
For every 300 cu.m. or fraction thereof
For every 300 cu.m. or fraction thereof
For every 1,500 cu.m. or fraction thereof
For every 500 sq.m. for every layer or fraction thereof
For every 2,500 cu.m. or fraction thereof
For every 300 cu.m. or fraction thereof
For every 300 cu.m. or fraction thereof
For every 1,500 cu.m. or fraction thereof
For every 1,500 cu.m. or fraction thereof
For every 500 sq. m. for every layer of
150 mm of compacted depth at 3 in-situ thereof
T193-92
For every 2,500 cu.m. or fraction thereof
Proof Rolling Test
Both lanes for full length
For every 1,500 cu.m. or fraction thereof
M82
For every 40 metric tons
Quality Test (set), Grading For every 1, 500 cu.m., for every 75 cu.m. or fraction thereof
Quality Test (set), Grading For every 1,500 cu.m., for every 75 cu.m. or fraction thereof
Quality Test (set)
For every 100 metric tons
(LL, PL, PI Grading Test) For every 75 cu.m. or fraction thereof
For every 130 metric tons or
75 cu.m. of mix or fraction thereof

6. CBR
7. Spot weakness
8. Quality Test
310 AC Surfacing
A. Bituminous Materials
Course (WC,
B. Fine Aggregates
BC)
C. Coarse Aggregates
D. Mineral Filler
E. Hot Mix
1. Extraction (Bitumen
Content & Graduation)
2. Stability Test
3. Grading Test
4. Laboratory Compaction
F. Compacted Pavement
1. Core sampling &
Density, Bitumen Content For every 100 linear meter or one (1) but not more
Lab.Tests
& Thickness
than three(3) samples shall be taken for each
full days operation
311 Portland Cement A. Cement
M85
For every 2,000 bags or fraction thereof
Concrete
B. Fine Aggregates
Quality Test (set)
For every 1,500 cu.m. or fraction thereof
Pavement
1. Grading Test
T27-93
For every 75 cu.m. or fraction thereof
2. Quality Test
M6
For every 1,500 cu.m. or fraction thereof
C. Coarse Aggregates
1. Grading Test
T27 - 93
For every 75 cu.m. or fraction thereof
2. Quality Test
M80
For every 1,500 cu.m. or fraction thereof
D. Concrete
1. Slump Test
Per batch
2. Temperature
Per batch
3. Flexural Strength
Per 330 sq.m. of pavement, 230 mm
(on 1 set of 3 beam
depth or fraction thereof placed each day
samples)
or 75 cu.m. of conc.
E. Completed Pavement
1. Thickness
Core sampling
Five (5) holes per km. per lane
404 Reinforcing
Quality Test for Bending,
For every 10 ton or
Per size of bars
Steel
Tension and Chemical
10,000 kgs or
Analysis
fraction thereof
Note: Principal tests only

For small quantities of cement, steel bars and other materials not intended to be used in
critical structures, simplified tests conducted by available test facilities in the region and
district shall be allowed as basis of acceptance and payment of these materials in accordance
with Memorandum Circular 138-A dated 1st September 1980. The term small quantity
means ten (10) percent or less of the maximum quantity that can be covered by one test in the
above table. For example, ten (10%) of 2,000 bags is 200 bags or less.
In order to ensure proper and effective materials control in the implementation of

7 - 16

Road Project Management and Supervision Manual Vol.1 Main Text

maintenance projects, all construction materials for regular maintenance projects shall be
subjected to the revised Schedule of Minimum Testing Requirements in the Standard
Specifications regardless of quantity. In no case should the materials be allowed to be
incorporated in the works without prior tests in accordance with DO No.63, Series of 1994.

7.6.2 Quality Control on Construction Materials


Materials used for road construction are categorized as follows:
Table 7.6
Category
Category I:
Prefabricated

Category II:
Manufactured,
Processed or
Natural Products

Categories of Materials
Requirements

1. Imported Materials
- Bureau of Customs Certificate of Importation
- Mill Test Certificate and Shop Inspection
Certificate/Report
- Certificate of Inspection at point of delivery by DPWH
representative/s
2. Locally Prefabricated Material
- Mill Test Certificate and Shop Inspection
Certificate/Report
- Sampling of materials at the factory by DPWH
representative/s
- Certificate of Inspection at point of delivery by DPWH
representative/s
- Must have a representative sample each for testing
1. Acceptance Test
2. Retest or Referee Test, if the 1st test failed
3. Pretesting
- Applicable to materials manufactured in bulk such as
cement, asphalt, steel bars, etc.
- Pre-tests shall be undertaken by the DPWH laboratories
in principle
- Sampling shall be attended by the DPWH
representatives (ME/Laboratory Technician)
4. Testing shall be attended by the DPWH representatives
(ME/Laboratory Technician)

Representative
Materials
Structural Steel,
Metal Culvert
Pipe,
Accessories,
etc.

Cement,
Asphalt, Steel
Bars, Concrete
Mix, Aggregate

Note: Refer to Memorandum Circular (MC) No.73, Series of 1973 and Part I of Standard Specification of DPWH
as to details.

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 17

7.6.3 Production of Aggregates


The most common materials produced at the site or sourced out from quarries are coarse
and fine aggregates for Portland cement and asphalt concrete production.
The following should be taken into consideration in order to obtain a good quality
material:
*

Contamination of gravel by too much soil or soft stones

Lack or insufficient fine components (Note: This often happens at the quarry stationed
at up-stream of river. Insufficient fine material may cause Flexural Strength failure for
PCCP even though it satisfies compression strength)

Too much flat shapes after crushing

Insufficient fractured surfaces if crushed from river gravel

Utilize clean water in cleaning aggregates. Proper disposal of used water is necessary
to avoid polluting the environment.

Aggregates production should be stored on lean concrete base or on the appropriate


base and shaded to avoid contamination of foreign materials and high temperature.

The grain size, its distribution and specific characteristics of aggregate differ depending
on their incorporation to products such as subbase course, base course, asphalt concrete,
Portland cement concrete and structural concrete as shown in Table 7.8. Generally, the
Contractor mobilizes only one set of crushing plant and produces the required products
arranging a combination of vibrations screens and blending of different size of screened
materials. Therefore, the operation of the crushing plant should be carefully planned in line
with the construction schedule.

7 - 18

Road Project Management and Supervision Manual Vol.1 Main Text

Table 7.7

Types of Aggregates Required for Road Projects

Material / Aggregate Crushed


Type
Subbase Aggregate
Base

Max.Size

Asphalt Concrete
PC Concrete
Wearing
Binder
PCCP
Class A
Class A* Class A**
t=50mm t=50mm - Grading C
(Reinf.
(Slab)
(RCPC)
60mm
Concrete)

Grading A
1 1/2"

2"

Class A
3/4"

Class A
3/4"

LA
=<50%
=<45%
=<40%
=<40%
CBR
>=25%
>=80%
PI
<12
<6
0
0
Note: Refer to Technical Specifications as to details.

1 1/2"

1"

3/4"
(1/2")

2"

=<40%
0

#16

#50

#4

#8

3/8" 1/2"

1"

Grading B

US Standard Sieve No.

2"

#200

#16

#50

#8

Grading A
#4

3/8" 1/2"

1"

2"

100.0

100.0

100.0

90.0

90.0

90.0

90.0

80.0

80.0

80.0

80.0

70.0

70.0

60.0

60.0

50.0

50.0

40.0

40.0

Percent Finer by Weight

100.0

70.0

70.0

60.0

60.0

50.0

50.0

40.0

40.0

50.0

100.0

20.0

5.0

10.0

2.0

1.0

0.5

0.1

0.2

0.05

0.01

0.02

0.005

50.0

100.0

10.0

0.2

0.1

0.05

0.02

0.005

0.002

0.001

10.0

0.002

10.0

20.0

10.0

5.0

10.0

2.0

30.0
20.0

1.0

30.0
20.0

0.5

30.0
20.0

0.01

30.0
20.0

0.001

Percent Finer by Weight

#200

2"

Aggregate
Subbase

US Standard Sieve No.

Class B
Unreinf.
Concrete

Grain Size in Millimeters

Grain Size in Millimeters

Coase Agg. Grading C

Grading D
US Standard Sieve No.

#16

#50

#8

3/8" 1/2"

1"

Fine Aggregate

US Standard Sieve No.

Grading B
#4

2"

#200

#16

#50

#8

#4

3/8" 1/2"

1"

2"

100.0

100.0

100.0

90.0

90.0

90.0

90.0

80.0

80.0

80.0

80.0

70.0

70.0

60.0

60.0

50.0

50.0

40.0

40.0

Percent Finer by Weight

100.0

70.0

70.0

60.0

60.0

50.0

50.0

40.0

40.0

50.0

100.0

20.0

10.0

5.0

2.0

1.0

0.5

0.2

0.1

0.05

0.02

0.01

Grain Size in Millimeters

Grain Size in Millimeters

Grain-size Distribution Curves for Hot Plant Mix Bituminous Pavement

0.005

0.001

0.002

100.0

50.0

20.0

10.0

5.0

2.0

1.0

0.5

10.0

0.2

10.0

0.1

10.0

0.05

10.0

0.02

30.0
20.0

0.01

30.0
20.0

0.005

30.0
20.0

0.002

30.0
20.0

0.001

Percent Finer by Weight

#200

Grading C

Grading E

Grain-size Distribution Curves for Portland Cement Concrete Pavement


(Coarse Aggregate)

Aggregate production crusher plant is a combination of the crushers and vibration


screens, belt conveyors and washing system as an option, depending on the raw materials and
grading requirement of products, as shown in Table 7.8.

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 19

Table 7.8
Process

Type

Types of Crushers
Photograph

Product

Jaw Crusher
(Primary)
Jaw Crusher
(Secondary)

Rodmill

SCHEMATIC DIAGRAM

The following figure shows common problems in the production of aggregates.

7 - 20

Road Project Management and Supervision Manual Vol.1 Main Text

Vibration Screens
Joe Crusher
(Primary)

Cone Crusher
(Secondary)

River Quarry

Crushing Plant

Contaminated water from washing

Figure 7.8

Coarse-Aggragates coated with clay due to


insufficient washing

Common Problems in Aggregate Production


(Case of River Gravel)

The following actions shall be taken for non-specification compliance materials


encountered at the source and production facility:
*

If excess contaminated materials or out-of-specification materials are encountered, the


Engineer should reject these materials in writing; and

If a change in material type is encountered within a source, additional sampling and


testing shall be performed to characterize the material. If the material meets
specification requirements for another material type, then the material will be approved
for use. If the material does not meet specification requirements, the material shall not
be permitted for use on the Project.

The apparent omission of a detailed description or definition concerning the quality of


materials from the plans and specifications shall be regarded to mean that materials of
first class quality are to be used.

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 21

7.6.4 Submission and Approval of Concrete Pouring Permit


The Contractor shall apply for the issuance of Concrete Pouring Permit before the
scheduled date of concrete pouring, that is - two (2) days in case the approving officer is the
Chief of the Quality Assurance Division/Section and one (1) day if the approving officer is the
Engineer.
The permit shall clearly state the portion of the structure/station limits, the specification
number of the concrete to be poured and all other information required in the checklist for
Concrete Pouring Permit.
The portion/part of the project poured with concrete without the necessary approved
permit shall be subjected to alternative test, compression test for in-situ concrete, if it failed
to meet the requirements or if its location does not warrant the extraction of core specimen,
the affected/represented area shall be removed and replaced with new concrete mix.
Flow of circulation and approval is as shown in the following figures.

The Contractor

The Consultant/Engineer

The Employer' Representative

c.c.

Submission of
Concrete Pouring
Permit

Original

Noted by
PMO/DPWH (PM/PE)
at Site

RE
Approval of Concrete
Pouring Permit

File
Informing reasons

Disapproved

Original

File

File

Approved
Original

Foreign-funded Projects with Consultant's Supervision


Contractor

DPWH (RO or DEO)


Project Inspector
and
Materials Engineer

Submission of
Pouring Permit

Project Engineer
File

File

Inform reason of disapproval

Disapproved

Approved
with
Condition

Approved

Inform what are the conditions


Inform approval

Locally-funded Projects supervised by RO/DEO


Figure 7.9

7 - 22

Flowchart for Approval of Concrete Pouring Permit

Road Project Management and Supervision Manual Vol.1 Main Text

Republic of the Philippines

Department of Public Works and Highways


( Office Name)
Date:
Ref.No.:

CONCRETE POURING PERMIT


Name of
Project/Location
Contractor
Part of Structure
to be poured

Estimated Volume
m3

Station Limits/Section
Date of Pouring

Time of Pouring
Requested by:

Contractor:
(Name & Signature)

CHECKLIST
Concrete Vibrator

Field Density Test

Protective Covering Materials

Beam/Cylinder Molds

Warning Signs/Barricades/Flagmen

Curing materials

Concrete Saw

Slump Cone

Concrete Block Spacers


Finishing Tools/Equipment (Screeder,
broom, etc.)

Plumbness
Quality of Materials Used (Result of Design/Trial
Mix, Test Reports, etc.)

Line and Grade alignment (form setting,


elevations, etc.)
Required construction equipment

Air meter (if requried)


Lighting system
Electrical Layout (Roughing-ins/embedment)

Rebars sizes, spacing and number

Plumbing Layout (Roughing-ins/embedment)

Rebars installation requirements

Falsework/formworks adequacy

Checked by:
Materials Engineer
(Name and Signature)

Date

REMARKS/
RECOMMENDATIONS
Project Inspector
(Name and Signature)

Date

REMARKS/
RECOMMENDATIONS
Request: [ ] Approved

[ ] Disapproved

REMARKS/CONDITION /
RECOMMENDATIONS
Approved by*:

Noted by*:

Project Engineer
Resident Engineer
(The Engineer)

(Name and Signature)


Accreditation No.

Note: Approval shall be by the Engineer in the case of foreign-funded projects.


Approval shall be by the Project Engineer/DPWH for the locally-funded projects.

Figure 7.10

Concrete Pouring Permit Format

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 23

7.6.5 Quality Control Logbook


Pursuant to DPWH MC #80, Series of 1978, the ME is required to accomplish a Log
Book on Materials Quality Control wherein the daily project activities as well as quality
control activities with appropriate/necessary comments/observations are recorded. Said
Quality Control Log Book shall be used to verify the following conditions:
*

All materials are covered by adequate quality control and acceptance tests, and the
frequency of sampling and testing is in accordance with the requirements of the
Specifications;

The project has been assessed by the Buareau of Quality and Safety.

Compare the test results with those conducted by an independent Third Party for
calibration.

Figure 7.11

Materials Quality Control Log Book

The ME shall verify and certify the Contractors quality control report as back up data
for monthly billings. The ME shall prepare and submit Monthly Quality Control Report on
field tests performed on construction materials used in the project in accordance with DO
No.55, Series of 1989.
In order to ensure uniformity, the standard form prescribed under Memorandum dated 28
October 2004 regarding Revised Format for Monthly Materials Control Report, shall be used.

7.7 Design Mix and Trial Construction


7.7.1 Design Mix and Trial Construction for PCC Pavement
The Contractor is obliged to formulate a design mix, conduct trial mix and trial
construction before the commencement of pavement construction for approval of the Engineer
as illustrated below.

7 - 24

Road Project Management and Supervision Manual Vol.1 Main Text

Design Mix
and Trial Mix

Material Test

Figure 7.12
(1)

Trial Paving

Approval of
Design Mix and
Methodology

Start
Paving

Flowchart for Preparatory Work to Concrete Paving

Design Mix and Trial Mix


In compliance to Section 311.2 of Standard Specifications, the Contractor shall
prepare design mix for Portland Cement Concrete (PCC) Pavement for approval of the
Engineer. The design mix shall be based on the absolute volume method as outlined in
the American Concrete Institute (ACI) Standard 211.1, Recommended Practice for
Selecting Proportions for Normal and Heavyweight Concrete.
The Design Mix shall be based on the approved materials of aggregate, sand, water,
additive, and cement that meet the Specification requirements and the appropriate design
parameters indicated in Standard Specifications (or its Special Provisions).
The Specification requires at least 364 kg (9 bags) of cement per cubic meter of
concrete to meet the minimum strength requirements. The Engineer shall determine the
cement content and the proportions of aggregate and water that will produce workable
concrete having a slump of between 40 and 75 mm if not vibrated or between 10 and 40
mm if vibrated, and a flexural strength of not less than 3.8 MPa (550 psi) when tested by
the third-point method or 4.5 MPa (650 psi) when tested by the mid-point method at
fourteen (14) days in accordance with AASHTO T97 and T177, respectively; or a
compressive strength of 24.1 MPa (3500 psi) for cores taken at fourteen (14) days and
tested in accordance with AASHTO T24.

Note: The modulus of rupture (Flexural strength, AASHTO T97) shall be given preference over other tests and
must be satisfied at all times.

The Design Mix shall be verified through trial mix, sampling and testing. The following
photographs show a typical trial mix operation for PCC.

Trial Mix
Preparation

Weighing
Materials

Figure 7.13

Mixing Materials

Sampling &
Slump Test

Flexural Strength
Test of Concrete

Trial Mix for Portland Cement Concrete

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 25

(2)

Trial Construction
At least 30 days before the start of paving operations, the

Contractor shall

construct a test section using the trial mix design. This test pavement will allow the
Engineer to evaluate the strength of PCCP, methods of construction, and surface
conditions of the test pavement.
Prior to commencement of PCC production, the Contractor shall carry out a
complete and comprehensive calibration of the plant in accordance with the
manufacturer's recommended practice.
Concrete may be mixed at a central plant, including purchase of concrete mix
products produced by nearby concrete mixing plant, a drum mixer at site and/or a truck
mixer conforming to the requirements of AASHTO M157. The central-mixed concrete
shall be hauled to site by truck agitators or other appropriate trucks. The trial
construction should be conducted for the concrete production mixed at the central plant
and the truck mixer. It might be omitted for the mix by drum mixer.
The PCC pavement test section shall be at least 9.0 m long (2 slabs). It shall be
located either on an outside area or on actual construction lane site. The equipment,
materials and techniques used to construct the test section shall be that which will be
used to construct the main pavement. The Contractor must demonstrate the ability to
achieve a smooth, hard, uniform surface free of excessive tears, ridges, spall and loose
material.
The following photographs show a typical trial construction operation for PCC
Pavement.

Slip Form Paver


& PCC Mixing
Plant Check

Placing PCC and


Sampling

Figure 7.14

Dowel Bar
Setting by SemiManual Dowel

Finishing,
Grooving &
Curing Compound

Dowel Bar
Position Check &
Coring

Trial Construction for PCCP

If the 1st trial is unsatisfactory, the Contractor should conduct the 2nd trial. When
the Engineer is satisfied of the test results and the trial construction, he will approve the
design mix. Once a design mix is approved, the Contractor shall not modify proportions

7 - 26

Road Project Management and Supervision Manual Vol.1 Main Text

of the various materials without the prior approval of the Engineer.

7.7.2 Job-Mix Formula and Trial Construction for AC Pavement


(1)

Job-Mix Formula
In compliance to Section 307.2.1 of Standard Specifications, the Contractor shall
design and submit a Job-Mix Formula for each Hot Mix Asphalt (HMA) for approval of
the Engineer. The bituminous mixture shall be based on the approved materials of
aggregate, mineral filler, hydrated lime, and bitumen that meet the applicable material
requirements and the appropriate design parameters indicated in Section 307.2.1 of
Standard Specifications (or its Special Provisions) and are capable of being placed and
compacted as specified.
Each job-mix submitted shall propose definite single values for:

(2)

1)

The percentage of aggregate passing each specified sieve size;

2)

The percentage of bituminous material to be added;

3)

The temperature of the mixture delivered on the road;

4)

The kind and percentage of additive to be used; and

5)

The kind and percentage of mineral filler to be used.

Marshall Mix Design Method


The Marshall Mix Design Method (ASTM D 1559, AASHTO T 245) shall be used
for the job-mix establishment and its procedures shall be as follows:
1)

Marshall specimens shall be obtained from each of the binder and wearing course
materials supplied for trial construction. The Marshall specimens shall be formed and
compacted in moulds in accordance with the procedure specified in ASTM D 1559;

2)

The loss in Marshall Stability for submerged specimens in water at 60C for 24 hours
shall not be more than 25 percent of the stability of the design-mix;

3)

To determine the Marshall Specimen Density from each set of six (6) specimens, the
highest and lowest densities shall be discarded and the Marshall Specimen Density
shall then be the mean density of the remaining four specimens; and

4)

Six (6) specimens per set of the trial binder and wearing course shall be made and
tested in accordance with ASTM D 1188 or ASTM D 2726.

The Marshall Method is very popular because of its relative simplicity, economical
equipment and proven record. The Marshall Method has been proven to produce quality
Hot Mix Asphalt (HMA) from which long-lasting pavements can be constructed. The
Marshall mix design method consists of three basic steps:

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 27

1)

Aggregate selection. Different agencies/owners specify different methods of aggregate


acceptance. For each mix design, gradation and size requirements are checked. Often,
aggregate from more than one source is required to meet the specified gradation
requirements;

2)

Asphalt binder selection; and

3)

Optimum asphalt binder content determination. In the Marshall method, this step can
be broken up into 5 sub-steps:
*

Prepare a series of initial samples, each at different asphalt binder content. For
instance, two to three samples be made up of 4.5, 5.0, 5.5, 6.0 and 6.5% asphalt
content by dry weight. There should be at least two samples above and two below
the estimated optimum asphalt content;

Compact these trial mixes using the Marshall drop hammer/Mechanical


Compactor which is specific to the Marshall mix design method;

Test the samples in the Marshall testing machine for stability and flow. Passing
values of stability and flow depend upon the mix class being evaluated;

Determine the density and other volumetric properties of the samples; and

Select the optimum asphalt binder content. The asphalt binder content
corresponding to 4 percent air voids is selected as long as this binder content
passes stability and flow requirements.

Marshall Hammer

Figure 7.15

7 - 28

Marshall Test Samples

Marshall Stability
and Flow Device

Marshall Stability Testing Equipment

Road Project Management and Supervision Manual Vol.1 Main Text

Density of
Specimen

Plot in
Graph

Select Asphalt
Content to
meet All
Criteria

Source: Japan Road Association

Figure 7.16
(4)

Determination of Design Asphalt Content

Trial Construction
At least 30 days before the start of paving operations, the Contractor shall construct
a test section using the trial mix design. This test pavement will allow the Engineer to
evaluate the strength of the HMA material, methods of construction, and surface
conditions of the test pavement.
The test section shall be at least 50 m long. It shall be located either on an actual
construction lane site or an outside area. The equipment, materials and techniques used
for the trial construction should be the same as those for the actual pavement
construction. The Contractor must demonstrate the ability to achieve a smooth, hard,
uniform surface free of excessive tears, ridges, ruts and loose material.
During construction of the test section, the Contractor will establish an optimum
rolling pattern and procedure for obtaining a density of not less than 98% of the
maximum wet density. Cores shall be taken for testing.
When the Engineer is satisfied of the test results and the trial construction, he will
approve the design-mix.

Once a design-mix is approved, the Contractor shall not

modify proportions of the various materials without the prior approval of the Engineer
and without carrying the necessary Marshall tests.

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 29

7.7.3 Design Mix and Trial Construction for Other Major Work Items
(1)

Structural Concrete
The Contractor shall prepare Design-Mix for each structural concrete used for
bridges, box culverts, RCPC and other concrete structures required for road construction
and maintenance by applying the same methods and procedures explained in the above
PCC Pavement.
Five classes of concrete are provided for structural concrete, namely: A, B, C, P and
Seal, in the Standard Specifications. The classes of concrete will generally be used as
follows:
Table 7.9

Class A:

Classes of Concrete

All superstructures and heavily reinforced substructures. The important parts of the
structure included are slabs, beams, girders, columns, arch ribs, box culverts,
reinforced abutments, retaining walls, and reinforced footings.

Class B:

Footings, pedestals, massive pier shafts, pipe bedding, and gravity walls,
unreinforced or with only a small amount of reinforcement.

Class C:

Thin reinforced sections, railings, Precast R.C. piles and cribbing and for filler in
steel grid floors.

Class P:
Seal:

Prestressed concrete structures and members.


Concrete deposited in water.

Gradation of coarse aggregate for these structural concrete shall conform to the
following table (Table 405.1 in the Standard Specifications).
Table 7.10
Sieve Designation
Standard
Alternate
Mm
US
Standard
63
2-1/2
50
2
37.5
1-1/2
25
1
19.0

12.5

9.5
3/8
4.75
No.4

Grading Requirement for Coarse Aggregate


Class
A

100
95 100
35 70
10 30
0-5

Mass Percent Passing


Class
Class
Class
B
C
P
100
95 100
35 70
10 30
0-5

100
90 100
40 70
0 15*

100
95 100
20 55
0 10*

Class
Seal

100
95 100
25 60
0 10*

The strength requirements for each class of concrete shall be as specified in the
following table (Table 405.2 in the Standard Specifications).

7 - 30

Road Project Management and Supervision Manual Vol.1 Main Text

Table 7.11

Table 7.12
Class of
Concrete

Strength Requirements for Cement Concrete

Composition and Strength of Concrete for Use in Structure

Minimum Cement
Maximum
Content
Water/Cement
Ratio
3
kg/kg
Kg/m (bag**)
360

0.53

(9 bags)
B

320
380
440
380
(9.5 bags)

(2)

Std. mm

50 100

37.5 4.75

20.7

(2 4)

(1-1/2 No. 4)

(3000)

50 4.75

16.5

(2 No. 4)

(2400)

0.55

50 100

12.5 4.75

20.7

(2 4)

(1/2 No. 4)

(3000)

0.49

100 max.

19.0 4.75

37.7

(4 max.)

(3/4 No. 4)

(5000)

100 200

25 - 4.75

20.7

(4 - 8)

(1 N o. 4)

(3000)

(11 bags)
Seal

mm (inch)

Minimum Compressive
Strength (150x300m
Cylinder) at 28 days
MN/m2 (psi)

(2 4)

(9.5 bags)
P

Designated Size of
Coarse Aggregate

50 100

0.58

(8 bags)
C

Consistency
Range in Slump

0.58

Trial Construction
Trial construction shall be conducted for other work items, including subbase, base,
prime coat, tack coat, foundation piling, to check suitability of materials, efficiency of
equipment, valuation on the construction methods proposed by contractors and
workmanship. Quality tests required in the Specifications shall be conducted during or
after the trial construction.
If a trial construction shows that the proposed materials, equipment or procedures in
the Engineers opinion are not appropriate, he should inform the Contractor of his
disapproval. The material shall be removed by the Contractor at his own expense. The
Contractor shall identify causes if such trial construction failed to pass the quality and
workmanship required in the Specifications. The Contractor shall propose a new trial

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 31

construction with revised methods or with appropriate measures. New trial construction
shall be conducted in accordance with the instruction of the Engineer.
If the basic conditions regarding the type or source of material or procedures change
during the execution of the work, new trial construction should be conducted.

7.8 Calibration of Testing Equipment


To ensure the accuracy of test results obtained from testing equipment used in various
DPWH projects, the testing equipment should be calibrated regularly as per DO No. 82 Series
of 1996.

7.9 Accreditation of New Product and Technology


The procedures for the accreditation of new products and technology evaluation under
the New Products Accreditation Scheme (NPAS) of the DPWH is also presented in the
succeeding pages as DO No. 189, Series of 2002.

7.9.1 PCCP Reinforced with Welded Wire Mesh


The DPWH is being challenged by the introduction of new technologies in seeking more
efficient, effective and economical engineering application for infrastructure development and
maintenance.
The DPWH issued DO No. 18, Series of 2006 - DPWH Standard Specifications for
Portland Cement Concrete Pavement with Wire Mesh (Item 312). This is one of the standard
PCCP being practiced in Japan.
The PCC shall be the same as the standard PCC pavement (Item 311). The diameter of
wire (wire mesh/ bar mat) shall not be less than 6mm for both lateral and longitudinal
directions. Tie wire shall be No.16 gauged annealed wire. The spacing of the lateral direction
is twice wider than that of the longitudinal direction. The weight of wire mesh shall not be
less than 3kg/m2 and it shall be fabricated by welding or binding at each crossing point and
shall meet the requirements of ASTM A185. After placement of slip bar placed at every 9.0 m
maximum interval, wire mesh shall be placed at a depth of 5.0 cm to 7.5 cm below the surface
of slab or at 2/3 thickness from the bottom of the pavement.
It should be noted that the objective of provision/introduction of wire mesh is to allow an
interval of transversal contract joints (weakened joints) from 4.5 m to 9.0 m. It shall not
replace the slip bars at contract joints.

7 - 32

Road Project Management and Supervision Manual Vol.1 Main Text

Figure 7.17

PCCP Reinforced with Welded Wire Mesh

7.10 Recycling of Pavement Materials


The pavement life can be extended either by repair or overlay. However, it may also
require reconstruction rather than overlay and recycling of the existing pavement material
shall be applied on both environmental and economical aspects.

Removal
After Crush

Re-use for Concrete

Crushing

Before Crush

Source: Komatsu / Japan and PJHL/DPWJ

Figure 7.18

Recycling of Concrete Materials

7.11 Roller Compacted Concrete Pavement (RCCP)


The roller compacted concrete pavement is a type of PCC pavement constructed without
contraction joints. The PCC requires less cement and mixed at zero-slump consistency. The
required construction equipment is a heavy duty asphalt finisher and rollers for compaction. It
can be opened to traffic earlier compared with the standard PCCP. However, its current
application is up to a PCC thickness of 25 cm (medium traffic).
The following table and figure show example and illustration of the RCCP construction.

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 33

Table 7.13

Comparison between PCCP and RCCP

Item
Fresh Concrete
Equipment
Standard Productivity
Joint Structures

Roller Compacted Concrete RCC T=25cm

Curing Period
AC T=5cm
Construction Aggregate
Cost Base

PCCP
RCCP
(Portland Cement Concrete
(Roller-compacted Cement
Pavement)
Concrete Pavement)
2.5 cm 1.0 cm
Zero Slump
More Cement
Less Cement
Slip-form Paver (or Fixed
Dump Truck, Ashphalt
form), Transit Mixer,
Finisher, Vibration Roller, Tyre
Concrete Vibrator, Screeder
Roller
20 to 30 m per hour
30 to 50 m per hour
Dowel bars, expansion joints
None
Roller Compacted Concrete RCC T=25cm
Roller
RCC T=25cm
and
soCompacted
on areConcrete
required.
14 days at least
2 to 3 days
SCB T=10cm
Soil Cement Base
Base
higher Aggregate
lower
T=25cm
Aggregate Base
T=20cm

T=20cm

Typical Structures of RCCP

Combination of Equipment

Dump Truck

Asphalt Finisher

Vibration Roller

Tyre Roller

Photo: Maeda/Japan
Photo: Maeda Road/Japan

Combination
Figure 7.19 of Construction
EquipmentEquipment
for RCCP for RCCP

Roller Compacted Concrete RCC T=25cm

Roller Compacted Concrete RCC T=25cm

AC T=5cm
Aggregate Base
T=25cm

Aggregate Base
T=20cm

Roller Compacted Concrete RCC T=25cm

Soil Cement Base

SCB T=10cm
Aggregate Base
T=20cm

Structures
of RCCPof RCCP
Figure 7.20 Typical
Typical
Composition

7.12 Electrical Density


Gauge
Combination
of Equipment
The Electrical Density Gauge (EDG) is a nuclear-free alternative for determining the
moisture and density of compacted soils used in road beds and foundations. The EDG is a
portable, battery-powered instrument capable of being used anywhere without the concerns
Dump Truck

Vibration Roller

Asphalt Finisher
and regulations associated
with nuclear safety. It can be used Tyre
as aRoller
construction
aidMaeda
to monitor
Photo:
Road/Japan

Photo: Maeda/Japan

Combination of Construction Equipment for RCCP

7 - 34

Road Project Management and Supervision Manual Vol.1 Main Text

day-to-day compaction operations by providing performance and measurement results highly


comparable to those achieved with traditional methods, including the nuclear gauge and/or a
sand-cone and oven moisture test combination. The EDG measures and displays the results
for wet and dry density, gravimetric moisture and percent compaction.
The advantages of using the EDG are:
-

it does not require a highly-trained or license technician

it does not require special handling for shipping or regulatory compliance for
hazardous materials materials

it is easy to learn and easy to use with its step-by-step menu

lightweight and easy transportable

it is accurate and repeatable with results that mirror known testing methods

The EDG measures the electrical dielectric properties and moisture levels of compacted
soil using high, radio frequency traveling between darts driven into the soil being tested. The
darts depth of penetration positively determines the depth of measurement. Darts are
available in 4, 6, 8 and 12 lengths. In addition, the darts have been designed with a taper,
which ensures a continual positive contact with the soil for accurate measurements.
Source: HUMBOLDT

7.13 ISO Accreditation of Large Contractors


Department Order No. 38 Series of 2008 requires Large B Contractors of DPWH
projects to seek ISO 9000 Certification.

Road Project Management and Supervision Manual Vol.1 Main Text

7 - 35

Chapter 8

Field Inspections

8.1 Objectives of Field Inspection


Inspections are being conducted to oversee construction projects and maintenance
activities. The objectives of field inspections are as follows:
1)

Assure that the project has been implemented in conformity with the plans and
specifications which shall provide as a basis for acceptance of the project and
reimbursement of project costs with public expenditures;

2)

Acquire information on problems and condition changes to provide opportunity for


timely remedial action to solve the problems;

3)

Assess the DPWHs capabilities and effectiveness in managing and controlling the
projects with respect to:
*

Administrative and technical supervision

Staffing, equipment and facilities

Performance

Project documentation, including inspection diaries, test reports, etc.

4)

Enhance quality management programs for project implementation;

5)

Offer technical and procedural advice and recommend improved construction


techniques and engineering supervision; and

6)

Come up with a report on special or innovative construction materials, methods,


procedures, new equipment, and other technological innovations.

Field inspection and control shall be based on Volume II of the DPWH Standard
Specifications for Highways, Bridges and Airports, Vol. II 2013 Edition, its special provisions
provided by project category/type and approved rawings (plans). The Standard Specifications
is comprised of nine (9) parts; Parts A to H provides specifications for certain item of work;
and Part I for materials details.
Part A: Facilities for the Engineer
Part B: Other General Requirements
Part C: Earthworks
Part D: Subbase and Base Courses
Part E:

Surface Courses

Part F:

Bridge Construction

Part G: Drainage and Slope Protection Structures


Part H: Miscellaneous Structures
Part I:

Materials Details

Road Project Management and Supervision Manual Vol.1 Main Text

8-1

The quality of construction relies on field inspections and this is achieved thru a
cooperative and coordinative effort of those involved in the implementation.
Various instructions are given to the Contractor for correct implementation or remedy of
works through daily field inspection. Such instructions should be officially done in writing
and properly filed. If verbal instructions are given at the site, these should be confirmed in
writing as soon as possible. The instructions should be clear, concise and conforming with the
particular provisions of the contract and specifications. Whenever a dispute or conflict arises,
the issued instructions shall be referred to.

8-2

Road Project Management and Supervision Manual Vol.1 Main Text

Republic of the Philippines


Department of Public Works and Highways
OFFICE OF THE PROJECT ENGINEER
Date: ________________
SITE INSTRUCTION NO. _____
Name of Project
Location
Contractor

: _____________________________________________
: ____________________________________________
: _____________________________________________

To

: ________________________________________
Project Engineer (Contractor)
: ________________________________________
Project Engineer (DPWH)

From

You are hereby instructed to:


____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
For compliance.

_______________________
Project Engineeer (DPWH)

Noted:
_______________________________________
Chief, _____________Division/Section

Received by:
_______________________________
Project Engineer (Contractor)

Figure 8.1

Site Instruction

Road Project Management and Supervision Manual Vol.1 Main Text

8-3

8.2 Categories of Field Inspection


The categories (depending on the required output on road construction) are as follows:
I.

PROGRESS INSPECTION
The Inspector focuses on the progress accomplishment to be paid for and should
take actual measurement and direct counting of work accomplished per work item. Only
quantities that conformed to the criteria for acceptance shall be reported.
Shown in Table 8.2 are some of the criteria for acceptance of a particular work item.
Table 8.1

Criteria for acceptance

Description

Criteria

Item 104 Embankment

Design elevation, compaction

Item 200 Subbase Course

Thickness, Quality Test

Item 201 Base Course

Thickness, Quality Test

Item 310 Bituminous Surface

Thickness,

Course(Hot-laid)

Density
Compaction

Item 311 Portland Cement

Thickness,

Concrete Pavement

Flexural Strength ,
Condition

of

the

weakened

plane/

longitudinal joints, surface and the applied


joint sealant.
II.

ASSESMENT INSPECTION
The Inspector conducting this category of inspection will make use of anyone or
combination of the applicable checking processes, physical and mechanical tests such as
test pitting, core boring, field density testing and laboratory procedures etc. to: (1)
Discover hidden defects or potential cause that will endanger the safety and/or service
life of the project; (2) Recover cost of money arising from deficiencies, miscalculations,
contract obligation, e.g. deficiencies in the average thickness and compressive strength of
PCCP, over-valuation of contract quantities, liquidated damages, etc.

III.

INVESTIGATIVE INSPECTION
The Inspector conducting this category of inspection will make use of any or a
combination of the applicable checking processes, physical and mechanical tests such as
test pitting, core boring, field density testing and laboratory procedures etc. to determine
the following:
a)

8-4

Whether the complaint is valid or not;

Road Project Management and Supervision Manual Vol.1 Main Text

b)

The implication of findings and observation to the quality, worthiness, cost and
service life of the road

c)

To be able to provide technical analysis of the actual situation and to present


solution to resolve the problem, if any.

IV.

ENGINEERING INSPECTION
The Inspector conducting this category of inspection will make use of anyone or
combination of the applicable checking processes, physical and mechanical tests such as
test pitting, core boring, field density testing and laboratory procedures etc. in
conjunction with the modern testing devices such as Nuclear Testing, Distance Meter,
DCP, etc to collect data to support further studies and speedy solutions to problems in
road construction and quality management.

V.

WORKMANSHIP INSPECTION
Quality products are attained as a result of good workmanship. Good workmanship
is a result of experience, skill, art and techniques of workers, plant and equipment
operators and supervisors incorporated in the process or procedures of production. The
in-situ and laboratory tests are for confirmation of the product quality while
workmanship is for work process and product control during production or
manufacturing. The workmanship inspection is most important daily duty of the
supervision engineers and inspectors. The workmanship inspection is conducted by both
visual observation and measurement.
Quality products are attained as a result of the Contractors appropriate quality
control and good workmanship. Either the tests or inspection by the Engineer does not
relieve the Contractors quality assurance obligations. The Contractor is obligated to
comply with the contract and specifications irrespective of the presence of the Inspectors.
The in-situ and laboratory tests reflect representative quality. As sampling could not
be taken from all sections or portions, the Engineer should inspect workmanship to
ensure that the standardized and consistent operations are carried out for production. The
inspection staff should provide immediate instruction and guidance if any trouble or
problems like rain, high concrete temperature, breakdown of equipment/tools, etc.
happen or he found any wrong practice or substandard materials.
It should be noted that Engineer and his staff are not only representatives of the
DPWH but also representatives of the public to witness the Contractors activities.
Easy compromise and acceptance on poor quality product are not allowed.

Road Project Management and Supervision Manual Vol.1 Main Text

8-5

8.3 Field Inspection Plan


Major field inspection activities cover 1) Materials Quality Control, 2) Workmanship, 3)
Alignment and Dimensions Check, 4) Quantity Measurement and 5) Work Progress
Monitoring in accordance with the Request for Inspection by the Contractor and/or by own
initiative of the Engineer. Field inspections also include checking of mobilization and
deployment of resources (manpower, equipment and materials), traffic safety, maintenance
and environmental management plan.
Construction Supervision
Work Description

Item
Quality Control

Part
A
B

Field Inspection

Workmanship

Alignment / Dimensions

Quantity Measurement

Facilities for the


Engineer
Other General
Requirements

Mobilization

B.2

Safety / Environment

B.3

Maintenance

B.4

Materials

Subbase and Base


Course

B.5

As-staked survey

Surface Courses

Bridge Construction

H
K

Equipment
Crusher Plant, Concrete
Batching Plant, Trucks,
Slipform Paver
Tool

Earthwork

Concrete Vibrator, Sprayer,


Joint Cutter, Air Compressor

Manpower

Drainage and Slope


Protection Structures
Miscellaneous
Structures
Dayworks

Item

Work Description

301

Bituminous Prime Coat

302

Bituminous Tack Coat

303
310

Compliance to Safety and


Environmental
Requirements

Note:

B.1

G
Work Progress

Work Category

311

Foreman, Plant Operator,


Driver, Paver Operator, Skilled
Workers, Labour, Security
Materials
Cement, Aggregate, Sand,
Water, Additive

Bituminous Seal Coat


Bituminous Concrete
Surface Course, Hot Laid
Portland Cement Concrete
Pavement

Quality Control Apparatus


and Materials
Insitu Test (Slump Cone),
Sampling and Laboratory
Equipment

Same or similar activities

Figure 8.2

Hierarchy of Field Inspection

The road works of the DPWH is categorized to Parts A K (see Fig. 8.2) The pavement
works is classified into new construction, upgrading/improvement/rehabilitation and
preventive (periodic) maintenance (Fig. 8.3) Field inspection plan should be established
according to work category and pavement type taking each characteristic into account.
Upgrading / Improvement
Rehabilitation

New Construction

Preventive Maintenance
(Periodic)

Overlay / (Selected Replacement)

Re-construction / Widening

Existing Pavement

Existing Pavement
Rigid Pavement
(Concrete
Pavement)

Rigid
Pavement
(Concrete
Pavement)

Flexible
Pavement
(Asphalt
Concrete
Pavement)

Rigid
Pavement
(Concrete
Pavement)

Figure 8.3

8-6

Flexible Pavement
(Asphalt Concrete
Pavement)

Flexible
Pavement
(Asphalt
Concrete
Pavement)

Rigid
Pavement
(Concrete
Pavement)

Flexible
Pavement
(Asphalt
Concrete
Pavement)

Rigid Pavement
(Concrete
Pavement)

Rigid
Pavement
(Concrete
Pavement)

Flexible
Pavement
(Asphalt
Concrete
Pavement)

Flexible Pavement
(Asphalt Concrete
Pavement)

Flexible Pavement
(Asphalt Concrete
Pavement)

Classification of Pavement by Work Category

Road Project Management and Supervision Manual Vol.1 Main Text

Standard Flow for Subgrade Preparation and Approval


for AC Overlay Section from Sta.__________ to Sta.___________
Contractor

The Engineer / The PE


Approved
As-staked Survey/As-staked Plan

Removal of Damaged
PCCP
LEGEND
Activity of Contractor

Common Excavation / or
Unclassified Excavation

Joint Activity

NOT OK
Activity of the Engineer/the PE

Excavation Width and


Elevation Check

I/R:

Inspection Request

OK

Subgrade Preparation
Works
NOT OK
NOT OK
Formation Check
(Width, Elevation and
Superelevation ,etc.)

OK
Inspection Request
(Level Book)

Contractor' Level Book


Check and Random
Subgrade Formation Level
Check

I/R
OK
Field Density

NOT OK

OK

Subgrade Recompaction / Grading

Proof Rolling

Inappropriate
Workmanship
Identify
Reasons/Cause
s (Jointly)
For Medium /
Large Areas/Length

NOT OK

NOT OK

Work Order
by the Engineer
(Location, Width,
Depth)
Unsuitable Material
Excavation / Subgrade
Improvement

OK
(Approval of
Subgrade
Preparation)

IR

NOT OK

For Small Areas


Materials, Dimensions,
Workmanship Check, Proof
Rolling (Jointly)

OK

Commencement of Aggregate Base


Construction

(Approval of
Subgrade Preparation)

Source : PJHL / DPWH

Figure 8.4

Flowchart for Field Inspection

Road Project Management and Supervision Manual Vol.1 Main Text

8-7

8.4 Standard Inspection Check Sheet


The field inspection and quality control shall be conducted in accordance with the
Specifications . The DPWH Standard Specifications for Highways, Bridges and Airports, Vol.
II 2013 Edition is comprehensive and therefore, quality road and bridges could be constructed
if followed to the Specifications. On this aspect, Standard Inspection Check Sheets are
necessary for major work items to ensure that all construction and maintenance works are
implemented strictly in accordance with the Specifications.
The Standard Inspection Check Sheet covers the following check points as per
Specifications:

8-8

Work Approval

Scope of Works

Materials Requirement

Construction Requirements, including equipment.

Remarks/Comments.

Road Project Management and Supervision Manual Vol.1 Main Text

Existing Surface

Figure 8.5

Example of Inspection Check Sheet

Road Project Management and Supervision Manual Vol.1 Main Text

8-9

8.5 Request for Inspection


The Contractor shall submit a request for inspection for approval of the Engineer as early
as practicable. All necessary resources to support the inspection are deemed ready upon
submission of the request.
The following figure illustrates the flow of activities for the processing of inspection
request.
The Contractor

The Engineer (Consultant)

The Employer' Representative

c.c.
Submission of Notice to
Work / Inspection
Request

PMO (PM/PE)
at Site Office
RE
Approval of Notice to
Work / Inspection
Request

Original

File
Informing
Reasons

Disapproved

Approved with
Condition*

Approved
c.c.

Informing Condition
Informing the PI / ME in charge for inspection
Note: * The Contractor shall not be allowed the works
if the conditions not fulfilled.
Informing the PI / ME in charge for inspection

Inspection /
Quality Tests
File
Approval of Works
Informing with Reasons

Figure 8.6

8 - 10

Disapproved

File
Noted by
PMO (PM/PE)

Approved

Flowchart for Inspection Request and Approval

Road Project Management and Supervision Manual Vol.1 Main Text

________________________________ PROJECT
WORK / INSPECTION REQUEST
DATE
NO.
CONTRACTOR
STATION LIMITS

:
: Sta.1+053.00 - Sta.1+138.00
left side

(LOCATION)

:
:

ITEM NO. :
QUANTITY :

2-Feb-07

105(1)
260 m2

DESCRIPTION OF WORKS/INSPECTION REQUESTED:


Subgrade Preparation/ Field Density Test

FOREMAN IN CHARGE:

EQUIPMENT TO BE USED:
Motor Grader: 1 Unit
Vibration Roller: 1 Unit
MAJOR MATERIALS TO BE USED:

3-Feb-07 / 8.00 A.M.

SCHEDULED START OF WORK:


REQUESTED DATE/TIME OF INSPECTION:

3-Feb-07 /

9.00 A.M.
REQUESTED BY:

PROJECT MANAGER
(Contractor)

APPROVAL OF / COMMENTS ON WORKS (TESTS)/ INSPECTION REQUESTS


INTENSION OF WORKS (TESTS) / INSPECTION REQUESTS
APPROVED WITH
CONDITION

APPROVED

NOT APPROVED

COMMENTS / NOTES / CONDITION

DATE:
BY:

ENGINEER / INSPECTOR
TO BE ASSIGNED:

RESIDENT ENGINEER
(The Engineer)

APPROVAL OF WORKS
CHECKED LINES & GRADES:

CHECKED MATERIALS, FORMS & REBARS:

CHECKED EQUIPMENT / PLANT:

RECOMMENDATIONS:

RECOMMENDED
FOR APPROVAL BY:

APPROVED BY:

INSPECTION ENGINEER/ ME/ INSPECTOR

RESIDENT ENGINEER

(The Engineer)

(The Engineer)

NOTED BY:

PROJECT ENGINEER
(
)

Source: PJHL / DPWH

Figure 8.7

Example of Work/Inspection Request

Road Project Management and Supervision Manual Vol.1 Main Text

8 - 11

Chapter 9 Project Completion


9.1 Pre-final Inspection for Completion
Once the project reaches an accomplishment of 95%, the Engineer and the Contractor
shallconduct a pre-final inspection. The Engineer shall prepare a punch-list of observed
defects and/or deficiencies and the necessary corrective measures. He shall direct the
Contractor to do the necessary rectification works and ensure that the Contractor has complied
with the requirements described in the punch-list prior to the conduct of Final Inspection for
Completion.

9.2 Final Inspection for Completion


9.2.1 Submission of Request for Final Inspection for Completion
The Contractor shall, upon rectification of the defects and/or deficiencies observed
during the pre-final inspection, submit to the Implementing Office through the Engineer a
written request for the conduct of final inspection.Together with the request for final
inspection, the Engineer shall furnish the Inspectorate Team copies of the following
documents.
1.

Pre-final Inspection Report statingthat the defects/deficiencies noted during the


pre-final inspection havebeen complied withby the Contractor;

2.

Original plans and specifications

3.

Approved As-Staked Plans

4.

Approved As-Built Plans

5.

Approved Contract Agreement and Bill of Quantities

6.

Approved Variation Order (if any)

7.

Approved Contract Time Suspension/Extension

8.

Monthly Progress Report indicating substantial completion (C > 95%)

9.

Approved Statement of Work Accomplished (latest)

10. Quality Control Logbook, Quality Contorl Assurance Certificate


11. Monthly Materials Report
12. Others as maybe required.

Road Project Management and Supervision Manual Vol.1 Main Text

9-1

9.2.2 Participants for the Final Inspection for Completion


The final inspection shall be participated in by representatives as shown in Table 9.1.
Table 9.1

Composition of Inspectorate Team

Project undertaken by
Central Office and PMO

Composition*
Quality Assurance Unit (QAU) Member

Bureau of Research and Standards (BRS)

Bureau of Design (BOD)

Bureau of Construction (BOC)

Bureau of Maintenance (BOM)

Non-QAU Member

Regional Office

Quality Assurance Unit (QAU) Member

Planning and Design Division

Construction Division

Maintenance Division

District Engineering Office

Implementing Unit

QualityAssurance Division
Implementing Unit

District Inspectorate Team

Planning and Design Section

Construction Section

Maintenance Section

Quality AssuranceSection
Implementing Unit

*One(1) representative from each office

The Inspectorate Team shall prepare and submit to the Implementing Office the Final
Inspection for Completion Report containing its findings and corresponding recommendations,
and the duration of rectification works. The Implementing Office shall notify and require the
Contractor, at his own expense, to do the rectification works within the prescribed duration
from the date of notification.

9-2

Road Project Management and Supervision Manual Vol.1 Main Text

The figure below illustrates activities undertaken specifically during completion stage.
Certificate of
Completion

Implementing Office - PMO


Defects Liability
Period

Construction Period
Substantial Completion
(95% of the Contract Amount)
Joint Preliminary
Inspection of I.O.
& Contractors
Rep.

Inspection by QAUCentral Office

Remedial Work by
Contractor

Maintenance by
Contractor
(365 days)

Remedial Work by
Contractor

Certificate of
Completion

Implementing Office - Regional Office


Defects Liability
Period

Construction Period
Substantial Completion
(95% of the Contract Amount)
Joint Preliminary
Inspection of QAUR.O. &
Contractors Rep.

Inspection by 4 - Division
Chiefs + 1 Implementing Unit
Representative

Remedial Work by
Contractor

Maintenance by
Contractor
(365 days)

Remedial Work by
Contractor

Certificate of
Completion

Implementing Office - District Engineering Office


Defects Liability
Period

Construction Period
Substantial Completion
(95% of the Contract Amount)
Joint Preliminary
Inspection of DEO
rep. &
Contractors Rep.

Figure 9.1

Inspection by 4 - Section
Chiefs + 1 Implementing Unit
Representative

Remedial Work by
Contractor

Maintenance by
Contractor
(365 days)

Remedial Work by
Contractor

Activities undertaken during completion stage

Road Project Management and Supervision Manual Vol.1 Main Text

9-3

9.2.3 Remedial Works


The remedial works by the Contractor shall be monitored and supervised by the Engineer
who shall certify the correctness of the applied methodologies and shall recommend issuance
of Certificate of Completion for the project. Remedial works shall be completed within the
approved contract time otherwise, provisions for liquidated damages shall be applied.

9.3 Issuance of Certificate of Completion


The Contractor shall request to the Implementing Office for the issuance of Certificate of
Completion. The certificate shall be issued if:
1)

All defects/deficiencies (as per Inspectorate Teams Final Inspection for Completion
Report) have been rectified by the Contractor to the satisfaction of the Engineer;

2)

There are no pending Third Party Claims against the Contractor.

The Implementing Office shall take over the project within seven (7) days from the date
of issuance of Certificate of Completion.

9-4

Road Project Management and Supervision Manual Vol.1 Main Text

Contract Period

Warranty Period
Defects Liability Period

Construction Period

Maintenance
by Contractor
Commencement
of Works

Certificate of

Certificate of
Acceptance

Completion

Contractor requests for final


acceptance to the Implementing Office
after defects liability period of the
Project.

Contractor requests for final inspection to


the Implementing Office upon completion of
the Project.

The Implementing Office endorses requests


of the Contractor to the designated
inspectorate team for a joint final inspection
of the project.

The Implementing Office informs /


coordinates with the Consultant for
final inspection of project.

D.O.No.53 & 81, Series of 1995

INSPECTORATE TEAM

Documentation
(Check & Evaluation)

Ocular
- Checking compliance of
materials quality and
quantity per approved plans
and specifications
- Checking workmanship
- Verification per As-built Plan

BRS
QAU

BOC
QAU

MQCH
Div.
MQCH
Sec.

Const.
Div.
Const.
Sec.

BOM
QAU

Imp.
Office

Planning Maint.
Des. Div. Div.
Planning Maint.
Sec.
Sec.

Imp.
Unit
Imp.
Unit

Checking / evaluation of the following project


documents:

Actual Inspection

Preparation and Submission of


Final Inspection Report of
completion (or Acceptance
Report ) to the Implementing
Office

Institution of Corrective
Measures on Defects and
Deficiencies

- Approved Contracts
- Approved Plans and Specifications
- Approved Change Orders, variation Orders,
Extra Work Orders and Supplemental
Agreements
- Approved Final Statement of Work
Accomplished
- Inspection Reports (Punch List of defects
/ deficiencies)
- Quality Control and Materials Reports
- Approved As-built Plan

- The report shall contain findings and


corresponding recommendations.
- The report shall be ubmitted to the
Implementing Office duly signed by the
Inspection Team.

The Implementing Office shall require the


contractor to institute corrective measures on the
noted effects / deficiencies as per
recommendation of the Inspection Team.

The Certificate of Project Completion shall be issued by the Head


of Implementing Office after all the defects / deficiencies have
been corrected at the contractor's own expense.

Issuance of Certificate
of Project Completion

BOD
QAU

Issuance of Certificate
of Acceptance

Source: BRS / DPWH, Dec.1995

Figure 9.2

Flowchart of Activities Relative to the Issuances of Certificates of


Completion and Acceptance

Road Project Management and Supervision Manual Vol.1 Main Text

9-5

9.4 Final Payment


Within 84 days upon receipt of the Taking-Over Certificate for the Works, the Contractor
shall submit to the Engineer a draft final billing statement with supporting documents
showing:
(a) The value of all work done in accordance with the Contract up to the date stated in the
Taking-Over Certificate for the Works;
(b) Any further sums which the Contractor considers to be due; and
(c) An estimate of any other amounts which the Contractor considers will become due to
him under the Contract.
If the Engineer disagrees with or cannot verify any part of the draft final statement, the
Contractor shall submit such further information as the Engineer may reasonably require
within 28 days from receipt of the said draft and shall make such changes in the draft as may
be necessary. The Contractor shall then prepare and submit to the Engineer the billing for
Final Payment.
Figure 9.2 illustrates the procedures and supporting documents for final payment.

9-6

Road Project Management and Supervision Manual Vol.1 Main Text

Table 9.2

Procedures and Supporting Documents for Final Payment


(Regional and District Offices)

Step
1

Action and Support Documents for Final Payment


Check the following submitted billing and documents:
1. Background Information / Executive Summary
2. Billing Summary
3. Letter-Request of Contractor
4. Certification (DO 55 1988)
5. Disbursement Voucher
6. Monthly Certification of Payment
7. Statement of Work Accomplished
8. Statement of Time Elapsed
9. Contractors Affidavit
10. Certificate of Clearance on Labour and Materials Payment
11. Certification of Clearance for Equipment Rentals and/or Lease
12. Proof of Completeness of Documents Duly Submitted to COA
13. As-Built Quantity/Final Change Order (if any)
14. Inventory of Office Equipment, Building, Surveying Instrument and Service Vehicle
(Turnover of Equipment Bought Out of Project Funds)
15. Turnover of Laboratory Equipments to BRS For Foreign Assisted Projects
16. Regional Equipment Clearance
17. Property Clearance
18. Certificate of Completion
19. DPWH Final Inspection Report
20. Request for COA Final Inspection Duly Received by COA
21. Pictures
22. Approved Time Extensions and/or Suspension and Resume Orders, if any
23. BIR Form 2555 (for contracts entered into prior to July 1, 1993)
24. Back-up Computation
25. BIR Form No. 2550M VAT Declaration
26. BIR Form No. 750-V-1 (Certificate of Value-Added Tax Withheld on Government
Payments (RA 7649)
27. BIR Form No. 1743 750 (Certificate of Creditable Taxes Withheld at Source)
28. Certification from QAU that defects for final inspection have already been corrected.
29. As Built-Plans/Drawings
2
Verify the following documents for accuracy
Back-up Computation
Statement of Time Elapsed
Monthly Certificate of Payment
Letter Request of Contractor
Statement of Work Accomplished
Contractors Affidavit
3
If the above documents are incomplete and/or inaccurate, return the billing to the Contractor
for correction
4
If all documents are complete and accurate, the Implementing Office prepares forms for
processing forward
5
Implementing Office provide Certified True Copy of Proof of completeness of documents
submitted to COA.
6
The billing documents must have appropriate approvals before submitting them to the
Accounting for processing of payment
Source: Guidelines to Implementing Office for Processing Claims for Payment (District and Regional Offices)
for Civil Works Contract

Road Project Management and Supervision Manual Vol.1 Main Text

9-7

Chapter 10 Defects Liability Period,


Final Acceptance and
Warranty Period
10.1 Defects Liability Period
The Contractor, after the issuance of the Certificate of Completion, is still responsible
for the maintenance of the project within a period of one (1) year - the Defects Liability
Period (DLP).
The Engineer shall conduct a joint inspection with the Contractors representatives at a
quarterly basis during the DLP and shall direct any remedial and maintenance works that may
be required for keeping the road in good condition such as:
(a) Vegetation Control
(b) Maintenance cleaning of canals and ditches
(c) Cracks/Joints Sealing
(d) Reshaping/recompacting of road shoulders
(e) Others as maybe required

10.2 Pre-final Inspection for Acceptance


After the DLP, the Contractor shall request for a joint Pre-Final Inspection for
Acceptance with the Engineer. Any defects that occurred during this period shall be rectified
by the Contractor at his own expense. Said defects shall be rectified within ninety (90)
calendar days upon receipt from the Engineer of the notice/instruction to undertake repair.

10.3 Final Inspection for Acceptance


The designated Inspectorate Team shall conduct Final Inspection for Acceptance and
submit to the Implementing Office the Final Inspection for Acceptance report containing its
findings and corresponding recommendations, if any. The Implementing Office shall notify
and require the Contractor, at his own expense, to do the rectification works within the
prescribed duration from the date of notification.

10.3.1 Remedial Works


Any remedial works by the Contractor shall be monitored and certified by the Engineer
for the subsequent recommendation for the issuance of Certificate of Acceptance.

10.4 Issuance of Certificate of Acceptance


The Contractor shall request to the Implementing Office for the issuance of Certificate of

Road Project Management and Supervision Manual Vol.1 Main Text

10 - 1

Acceptance.
The certificate shall be issued if:
1)

All defects/deficiencies (as per Inspectorate Teams Final Inspection for Acceptance
Report) have been rectified by the Contractor to the satisfaction of the Engineer;

2)

There are no pending Third Party Claims against the Contractor.


Certificate of

Certificate of
Completion

Completion

Release of
Warranty

Defects Liability Period (365 c.d.)

Request of Acceptance
I.O. representative
Joint Pre-Inspection
With the Contractor

Warranty Period (5 years)


Inspection by QAU

Remedial Work by
Contractor

Figure 10.1

Remedial Work by
Contractor

Defects Liability and Warranty Periods

10.5 Release of Remaining Retention Money


The remaining Retention Money or On demand Bank Guarantee shall be released
upon final acceptance of the Works.

10.6 Release of Performance Security


Upon submission of Warranty Security, the Contractor may request for the release of the
Performance Security.

10.7 Warranty Period


After final acceptance of the project, the Contractor shall be held liable for structural
defects and/or failure of the completed project within the warranty period prescribed in RA
9184 except those occasioned by force majeure and those caused by other parties.
The Warranty Security (see Table 10.1) shall remain effective for a period of five (5)
years and shall only be released if in the final round of inspection by the designated
Inspectorate Team, no structural/major defects were discovered.

10 - 2

Road Project Management and Supervision Manual Vol.1 Main Text

Table 10.1
Form of Warranty
1. Cash Deposit, Cash Bond or Letter of

Warranty Security
Minimum Amount in Percent of Total
Contract Price
Five (5) Percent

Credit
2. Bank Guarantee

Ten (10) Percent

3. Surety Bond

Thirty (30) Percent

Road Project Management and Supervision Manual Vol.1 Main Text

10 - 3

Chapter 11

Maintenance after
Final Acceptance

11.1 Maintenance by DPWH after Final Acceptance


(1)

Necessity of Maintenance
Sustainability of the road facilities after development, upgrading or rehabilitation is
the most important issue. New or rehabilitated roads will deteriorate through vehicle
loading, weathering and aging. Maintenance reduces the rate of pavement deterioration,
lowers vehicle operational costs, saves time and cost, and provides continuous service for
road users and communities. On the other hand, as overloaded vehicles will shorten
pavement life significantly, its strategic and systematic control should be established and
sustained.
Road maintenance is defined as a process that optimizes overall performance of the
roadway over time. Maintenance should be supported by a system of information (data),
planning, budgeting, organization/staff and thorough practices with sound techniques.

(2)

Asset Management Approach


Asset Management is defined as systematic process of effectively maintaining,
upgrading and operating assets, combining engineering principles with sound business
practice and economic rationale to achieve the reliable publics expectations. Sound
engineering, efficient administrative organization/staff and stable budgetary supports are
required for the road asset sustainability. Overloaded vehicle control is also important to
avoid early or premature damage of the pavement.
Time
(Schedule)

Cost
(Finance)

Quality
Project
Management Assurance

Safety
& EMP

Figure 11.1

Asset Management

Road Project Management and Supervision Manual Vol.1 Main Text

11 - 1

(3)

Classification of Maintenance
Road maintenance consists of routine maintenance, preventive (periodic)
maintenance and emergency works. Routine maintenance is an activity that should be
undertaken every year. It is mostly a labor intensive work compared with the preventive
maintenance that is equipment based. The design period for new or upgrading projects is
10 years for AC pavement and 20 years for PCC pavement. The first preventive
maintenance is required within 10 years after the opening of the road. In principle, since
the design life of preventive (periodic) maintenance is 5-10 years, it should be repeated
every 4-9 years depending on the level of traffic and road condition.
The main goals of preventive/periodic and routine maintenance are as follows:
Table 11.1

Main Goals of Preventive/Periodic and Routine Maintenance

Category

Unpaved Roads

Paved Roads

Periodic/

* Control of gravel thickness

* Control of roughness

Preventive

* Control of roughness (when

* Control of pavement distresses

Maintenance

re-gravelling)

(cracking, rutting, etc)


* Strengthen drainage structures
capacity
* Control of gravel thickness of
unpaved shoulders
* Control of the general
conditions for stability and safety

Routine

* Control of roughness through

Maintenance

* Delay of the needs for preventive/

grading and patching


* Control of road side conditions

periodic maintenance
* Control of road side conditions

through:
-

through:

Cleaning and minor repair of

drainage and major structures

drainage and major structures

Vegetation control

Vegetation control

Grading and patching of

Grading and patching of

shoulders

Emergency
Repair

Cleaning and minor repair of

shoulders

Minor repair of road signs

Minor repair of road signs

Spot repair of road marking

Spot repair of road marking

* Emergency works for user and


road safety

* Emergency works for user and


road safety

Source: Road & Bridge Routine Maintenance Procedures and Planning Manual, DPWH

11 - 2

Road Project Management and Supervision Manual Vol.1 Main Text

The required maintenance activities are classified in Table 11.2.


Table 11.2
Category

Required Maintenance Activities for Road Facilities

Classification

Road surface
(AC pavement)
Road surface
Roadway
(PCCP)
Shoulders and
approaches

Drainage

Culverts
Roadside
Drains
Embankments

Roadside
Cut slopes
Superstructure

Bridges

Traffic
control
device
Safety
devise

Preventive
(periodic)
Maintenance

Routine Maintenance

Crack sealing
Patching
Crack sealing

Emergency Maintenance

Overlay, partial
reconstruction
Overlay, partial
reconstruction

Damage or road cut-off by


slope failures, scouring, etc.
Damage or road cut-off by
slope failures, scouring, etc.

Material addition
and/or sealing
Capacity increase

Cleaning debris

Vegetation control
Spot failure repair
Cleaning/Desilting

Cleaning/Declogging Repair, addition


Vegetation control
Removal of fallen
rock/boulders
Drainage

Foundation

Slope
stabilization
Slope
stabilization
Repainting (steel)
Scouring
protection work
Approach slab
construction

Cleaning debris
Slope failure/settlement
Slope failure repair
(grouted riprap, rock net)
Joint repair
Scouring protection / repair

Others

Approach road crack


sealing

Informatoryand
regulatory
signs,
markings, etc.

Repair

Repainting of
markings,
addition

Replacement of
damaged/broken signs, etc.

Guard rails,
barriers, etc.

Repair

Repair and
addition

Replacement of
damaged/broken guard
rails, signs, barriers, etc.

Approach road settlement

The above mentioned maintenance activities need equipment, materials, tools,


personnel and budget. Most of the routine maintenance works shall be implemented by
administration and preventive maintenance shall be by contract.

Crack Sealing
Figure 11.2

Patching Work

Patching

Maintenance Activities on Pavement

Road Project Management and Supervision Manual Vol.1 Main Text

11 - 3

(4) Responsible Offices


The DPWH shall be responsible for road maintenance works after issuance of the
Certificate of Acceptance. The Planning Service is responsible for maintenance
programming and budgeting. The BOM is responsible for overall maintenance
management and the RO/DEO is responsible for implementation of the maintenance
works.
(5)

Planning and Programming


The programming and budget allocation for the maintenance works shall be made
by the Central Office with the integrated asset management system of the DPWH
illustrated in the following figure:
O n -g o in g
W o rk s

C o n tra c t
M anagem ent
S y s te m
(C M S )

TARAS

R T IA
Ongoing
T ra
ffic
Works

C o n tra c t
M anagem ent

R oad
S a fe ty
P ro je c t
R o ad
C o n d itio n

A cOngoing
c id e n t
Works

O n -g o in g
W o rk s

W o rk
P ro g ra m

R B IA

P ro c u re m e n t

C ost
E s tim a tio n

B rid g e
D a ta

R o a d N e tw o rk
In v e n to ry &
C o n d itio n

W o rk
P ro g ra m

M u lti-Y e a r
P ro g ra m m in g &
S c h e d u lin g
(M Y P S )
P ro g ra m
R e v ie w
M u ltiY ear
A n a l y s is
G e n e ra tio n

BMS
PM S

RMMS

R o u tin e M a in te n a n c e
N eeds

M u lti-Y e a r P ro g ra m

Source: PS/DPWH

Figure 11.3

Programming Process (Assets Management System)

The road and bridge condition collected by the DEO under the supervision of the
RO are stored by Planning Service in the Road and Bridge Information Application
(RBIA) as network level road and bridge base data. The purpose of RBIA is to make
comprehensive, appropriately accurate and up-to-date road and bridge information
available throughout the country. The information that is compiled within the RBIA is
only suitable for purposes of network level planning. It cannot be used for project level
design work.
The pavement management comprise of activities starting from planning and
programming, design, construction and maintenance of the pavement portion of the road
works program. Pavement Management System (PMS) means tools and procedures that

11 - 4

Road Project Management and Supervision Manual Vol.1 Main Text

assist decision makers in finding optimum strategies for planning and maintaining
pavements in a serviceable condition over a given period of time.
(6)

Routine Maintenance Management System (RMMS)


The RMMS is an integrated tool for planning, scheduling and monitoring the annual
basic maintenance activities in order to sustain a Level of Service for the national roads.
The DPWH has prepared the Road & Bridge Routine Maintenance Procedures and
Planning Manual1 (Volumes I, II and III) as guide and reference for personnel of the
DPWH CO, RO and DEO who are responsible for the routine maintenance of the
national road network. This manual is consistent with the capabilities of the Software
used for the support of the Maintenance Management.
The main objective of management system is to formulate a framework for making
well-informed decisions about highway maintenance. The specific objectives are to
provide the following:
*

Adequate levels of maintenance service throughout the country;

Means to use labor, equipment and material of Administration and Contractors;

Objective basis for planning and maintenance works programming; and

Comparison of planned work and actual performance (monitoring and


evaluation).

The major components of the RMMS manual are as shown in Table 11.3.

Plan and
Budget Routine AMWP/PB
AWP
Maitenance
Activities
DO, RO
BOM

Schedule
Routine
Maitenance
Works

DO, RO

Evaluate
Perfom/Monitor
Work
Work
Performance of
Routine
Schedule
Performance Routine Maitenance
Maitenance
for MBA &
Activities
Works
MBC

DO (MBA), RO
Contractors
(MBC), BOM

DO, RO
BOM

Source: Road & Bridge Routine Maintenance Procedures and Planning Manual, DPWH

Figure 11.4

Flow of Routine Maintenance Work

The DPWH revised the previous maintenance management system under the ADB 6th Road Sector Loan. The
Road & Bridge Routine Maintenance Procedures and Planning Manual was launched after pilot testing for
refining in ten (10) DEOs.

Road Project Management and Supervision Manual Vol.1 Main Text

11 - 5

Table 11.3

1.

2.
3.

4.

(7)

Component
Planning
(Chapter 4)
Scheduling
(Chapter 5)
Monitoring
(Chapter 6)

Evaluation
(Chapter 7)

Major Components of RMMS

Content
Development of Annual Work Program, including:
Revision of planning standards
Preparation of annual plans and budgets
Development of short term schedules by activity and location
Monitoring routine maintenance activities, including:
Recording/Reporting (collection of daily activity data for preparing
data/reports for local use and performance report for higher
management
Control of activities
Evaluation of maintenance activities, including:
Analysis of achieved RMMS-level of services, through data acquired by Annual
Visual Inspection (ROCOND) and BMS Type 3 condition inspection, and actual
work quantities for feedback to the planning.

Budget Allocation for Maintenance


The road asset preservation is comprised of routine maintenance and periodic
maintenance and rehabilitation. The sources of funding for asset preservation projects are
the General Appropriations Act (GAA) and Motor Vehicle Users Charge (MVUC). The
maintenance budget is allocated based on either PMS for preventive maintenance or
RMMS for Routine Maintenance. However, at present the RMMS is not yet in place.
The Bureau of Maintenance (BOM) is mandated, based on various data submitted by the
Regional/District Office and dominated in the RBIA, to calculate the maintenance share
of all national roads thru the Equivalent Maintenance Kilometer (EMK) method.
Currently, the maintenance allocation is being calculated manually using the EMK
method (see Table 11.4) where it is believed that there probably exist margins of error.
The calculation of EMK is made thus;

[Length of Road (km.)] X [Factor for Road width ] X [Factor for Surface Type]+
[Length of Bridge (l.m.)] X [Factor of Bridge]

The allocated budget is often insufficient because of a time gap between the data
collection by ROCOND and actual implementation.

11 - 6

Road Project Management and Supervision Manual Vol.1 Main Text

Road Project Management and Supervision Manual Vol.1 Main Text

11 - 7

1.00
1.15
1.30
1.45
1.60
1.75
1.90
2.05
2.20
2.35
2.50
2.65
2.80
2.95
3.10
3.25
3.40
3.55
3.70

EMK FACTOR
0.80
1.00
1.20
1.40
1.60
1.80

CORRECTION FACTOR

FROM ROAD INVENTORY

0.50

CONCRETE
>20 cm

0.80
0.80

0.70
0.70

0.60
0.60

0.95

0.85

0.70

0.50

1.20

1.55

1.25

1.00

<100 mm - 200

EXTRA STRENGHT

2.00

2.10

1.55

400

1.10

200

2.50

0.90

0.90

1.65

2.20

2.60

1.500

1.000

600

BITUMINOUS
LOW
10-30mm
MEDUIM
31-60mm
HIGH
61-100mm

1.45

1.00

0.60

0.40
0.85

100

1.90

75

1.40

0.40

0.35

0.50

30

0.90

25

UNPAVED
LOW
<100 mm
MEDUIM
100 mm - 200 mm
HIGH
>200 mm

TYPE/THICKNESS 1

1.00

1.00

1.85

2.30

2.75

2.000

1.90

2.20

150

5.000

3.000

1.10

1.10

1.95

1.20
1.20

1.15

2.20

2.60

10.000

2.50

2.60

400

1.15

2.10

2.50

2.30

2.10

2.40

2.50

300

2.40

200

AADT AND SURFACE FACTORS

FROM BRIDGE INVENTORY

1.25

1.25

1.68
1.68

1.48
1.33

3.15

1.48

2.75

2.33
2.33
1.93

4.45

1.93

3.65

30.000 50.000 70.000 100.000

EMK FACTOR
0.010
0.035
0.100

1.33

2.45

20.000

15.000

2.30

3.50

3.10

1000

2.90

2.80

600

TYPE
CONCRETE
STEEL
TEMPORARY
BAILEYN & TIMBER

BRIDGE FACTOR

(LENGTH OF ROADS IN KMS. X (EMK FACTOR FOR WIDTH) X (EMK FACTOR FOR SURFACE TYPE) + (LENGTH IF BRIDGE IN L.M.) (EMK FACTOR FOR BRIDGES) = TOTAL EMK

WIDTH
5m
7.5m
5.
10m
>7.5
Unpaved
12.5m
>10.0
15m
>12.5
>15m
Paved (Asphalt or Concrete)
7.5m
10m
>7.5
2.5m
>10
15m
>12.5
17.5m
>15
20m
>17.5
22.5m
>20
25.5m
>22.5
27.5m
>25.5
30m
>27.45
35.5m
>30
32.5m
>32.5
37.5m
>35
40m
>37.5
42.5m
>40
45m
>42.5
47.5m
>45
50m
>47.5
>50m

TYPE

Calculation of Maintenance Share

CALCULATION OF MAINTENANCE SHARE


EQUIVALENT MAINTENANCE KILOMETERS (EMK) METHOD

Table 11.4

Routine
Maintenance
(AMWP/AWP)

GAA

BOM

Preventive
Maintenance
(AWP)

GAA
MVUC

Rehabilitation/
Reconstruction
of Damaged
National Paved
Roads (AIP)

PS

Figure 11.5
(8)

MVUC

GAA

Budget Allocation Flow

Implementation and Monitoring of Maintenance Works


The preventive maintenance programs will be implemented like the development
projects in accordance with the DPWH Standard Specifications for Highways, Bridges
and Airports, Vol.II 2013 Edition.
The planned and scheduled routine maintenance activities will be performed in
accordance with the Specifications for Routine Maintenance in Chapter 2 of Road &
Bridge Routine Maintenance Procedures and Planning Manual (RMMS Manual). The
accomplishment will be monitored based on the following:
Table 11.5
MBA

Monitoring for Maintenance Works

- The actual use of assigned resources and the actual work quantities
- The quality of the works

MBC

- The actual work quantities


- The quality of the works

In accordance with Chapter 6 of RMMS Manual, these tasks require:


*

Recording/reporting (collection of daily activity data); and

Control activities (checking the reliability of the reports and the compliance of the
completed work with the Specifications).

11.2 Maintenance Inspection and Remedial Measure Design


PMS (HDM-4) based on RBIA are planning tools for allocation of resources with
priority but not for the design. The RO/DEO needs to conduct inspection and remedial
measure designs for the implementation of the preventive and routine maintenance works

11 - 8

Road Project Management and Supervision Manual Vol.1 Main Text

with the allocated budget.


Shown in Tables 11.5 and 11.6 are types of pavement distresses, major causes and
common repair methods for AC and PCC pavements, respectively.

Table 11.6

Pavement Distress, Major Causes and Common Repair Methods


for AC Pavement

Distress Type*

Major Causes

Common Repair Method

Consolidation and lateral movement of AC, base,


overload

Overlay, mill and


resurfacing

Lack of AC stability (too much asphalt, too much


fines, round aggregates, lack of aeration)

Remove and reconstruct


or patching, plane
surface and overlay

A.2 Edge Break

Insufficient compaction, loss of lateral support,


aging

Patching

A.3 Potholes

Weakness in pavement (little asphalt, spot


Remove, replace and
thickness defects, less fine or excess fines, poor patch
drainage

A.1 Rutting
(corrugation and shoving)

A.4 Surface Failures (deterioAging, weather, improper tack coat between PCC Overlay (after spot failure
ration, delamination, edge break) and AC overlay, construction on wet PCC
repair), Patching
A.5 Wearing Failures (Raveling,
flushing, polishing )

Insufficient compaction, construction during wet,


dirty aggregate, asphalt overheating, insufficient
asphalt

A.6 Cracking:

Seal coat, Thin overlay

Crack sealing, patching

A6.1 Edge cracks

Lack of lateral support, settlement (poor drainage


or weak foundation), lack of lateral support,

A6.2 Reflection cracks

Reflection of cracks from underneath (concrete


pavement joints, SCB cracks, AC cracks)

A6.3 Transverse and


Longitudinal cracks
A6.4 Cracks along ruts

Volume change of surface or base materials, low


asphalt penetration, aging etc.
Over loads, passing of heavy vehicles (see rutting)

A6.5 Crocodile cracks /


Fatigue Cracks

Excessive deflection over unstable base and


subgrade, overload, poor drainage, aging

A.7 Road Cut/Slip

Slope failure, landslide, scouring, slip

(depends on causes and


condition)

A.8 Shoulder (Erosion, pothole,


high gap, insufficient fill,
vegetation)

Steep slope, lack of maintenance, pass of traffic,


inadequate cross-fall, side drainage, lack of
surface protection, lack of shoulder materials

Add materials and


compaction, Sealing,
patching, grading, grass
cut

Road Project Management and Supervision Manual Vol.1 Main Text

11 - 9

Table 11.7

Pavement Distress, Major Causes and Common Repair Methods


for PCC Pavement

Distress Type*
C.1 Shattered Slabs

C.2 Scaling

Major Causes
Subgrade and/or base failure, lack of dowel bars
(load transfer problem), insufficient slab thickness,
foundation settlement, low concrete quality

Common Repair Method


Full depth repair (slab
replacement)

Over-finishing, improper curing, unsuitable


aggregates, chemical action

Slurry seal, a skid


resistance treatment, AC
overlay

C.3 Cracking:
C3.1 Corner cracks
C3.2 Diagonal cracks

Crack sealing, remove


and replace
Traffic loads on unsupported corners, spot weak
subgrade/base
Traffic loads on unsupported slab end, subgrade
settlement, pumping

C3.3 Longitudinal cracks Shrinkage of concrete, expansive base/subgrade


failure/settlement, loss of support from edge
i
C3.4 Transverse cracks Overllaods,
repeated bending on pumping slabs,
failure of foundation, shrinkage
C3.5 Crocodile cracks

Improper load transfer devise, base/subgrade


weakness, insufficient slab thickness, settlement

C.4 Road Cut/Slip

Slope failure, landslide, scouring, slip

(depends on causes and


condition)

C.5 Joint Faulting

Inadequate load transfer device, pumping

Raising of slabs

(+ Pumping)

Freewater on or in subgrade or base and deflection Drainage improvement,


of slab
joint resealing, dowel bar
introduction

C.6 Joint Spalling

Segregation of aggregate, improper load transfer


device, improper joint forming, joint sawing, joint
compression

Joint spall repair (Epoxy


patching), AC patching

C.7 Joint Sealant

Aging, low quality, pumping, cracking

Joint resealing

A.8 Shoulder (Erosion, pothole,


high gapa, insufficient fill,
vegetation)

Steep slope, lack of maintenance, pass of traffic,


Add materials and
inadequate cross-fall, side drainage, lack of surface compaction, sealing,
protection, lack of shouldering materials
paving, patching, grading,
grass cut

11.3 Overloaded Vehicle Control


Overloading has a highly negative effect on pavements, road safety and traffic capacity.
Negative effects can be assessed through the Vehicle Damage Factor (VDF) or Equivalent
Standard Axle Load (ESAL). As vehicle damage factors increase from 4th to 4.5th power of the
axle load, overloading control is extremely important for sustainability of pavement life.
The maximum allowable Gross Vehicle Weight (GVW) per revised resolution amending
the Implementing Rules and Regulations (IRR) of RA 8794 approved by DPWH and DOTC
on April 5, 2013, is 18 tons for 2-axle and 33 tons for 3-axle truck (Refer to Table 11.8) - an
increase from 15 and 21 tons (per Memorandum Circular No. 82-027, 1982), respectively.
This change in regulation gives a considerable burden on the pavement as illustrated in
Figure 11.6.

11 - 10

Road Project Management and Supervision Manual Vol.1 Main Text

Note: MVUV (Motor Vehicle User Charge): Max 13.5 ton/axle

Gross Weight
16.88 ton

5.1 Ton
(30%)

11.8 Ton
(70%)

Truck can
stand

Gross Weight
20.26 ton

6.1 Ton

Overload:
3.4 Ton
(20%)

20% of
Overload
gives

14.2Ton

2.3 times
of damage
to
pavement

Vehicle Damage Factor: 5.4


(Truck Factor)

Equation:
VDF =
Axle Load 4.5
8.16 Ton

The
4.5th
power

Vehicle Damage
Factor: 12.3
(about 2.3 Times)

Pavement
cannot stand

Budget
cannot stand

Figure 11.6 Effects of Overloading on Pavement

Since the Government cannot afford to re-design and strengthen all national
roads and bridges to withstand overloading, there is only one main remedy - control
overloading and apprehend/punish violators with the full force of the law.
The DPWH has 21 weighbridges strategically located along the national road
network under joint operation by the Philippine National Police (PNP), Land
Transportation Office (LTO) and DPWH. Upgrading of and additional weighbridges
are required while more efficient/effective way of operation supported by
transparency and accountability is of great importance.

Road Project Management and Supervision Manual Vol.1 Main Text

11 - 11

Table 11.8

Maximum Allowable Gross Vehicle Weight

MAXIMUM ALLOWABLE GROSS VEHICLE WEIGHT (GVW) PER RA 8794 (REVISED 2012)

Note: Special Permit to Travel shall be required for vehicles loaded with inseparable/or special cargoes exceeding
the corresponding GVW and vehicles with configuration different from those shown in the above matrix.

11 - 12

Road Project Management and Supervision Manual Vol.1 Main Text

Bibliography
1.

Handbook on Philippine Government Procurement (includes Amended IRR-A of


R.A.9184 and Latest GPPB Issuances), Technical Support Office, September 2007

2.

DPWH Standard Specifications for Highways, Bridges and Airport, Vol. II 2013 Edition

3.

DPWH Procurement Manual for Locally-Funded Infrastructure Projects through Public


Bidding, 20 January 2006

4.

Philippine Bidding Documents (As Harmonized with Asian Development Bank, Japan
Bank for International Cooperation, and World Bank), Procurement of WORKS, The
Government of the Republic of the Philippines, Second Edition, May 2005

5.

Conditions of Contract for CONSTRUCTION FOR BUILDING AND ENGINEERING


WORKS DESIGNED BY THE EMPLOYER, Multilateral Development Bank Harmonised
Edition, March 2006

6.

FIDIC Conditions of Contract for Works of Civil Engineering Construction, Fourth edition,
1987; Reprinted 1988 with editorial amendments; Reprinted 1992 with further
amendments

7.

Conditions of Contractfor Construction FOR BUILDING AND ENGINEERING WORKS


DESIGNED BY THE EMPLOYER, First Edition, 1999

8.

SOCIAL AND ENVIRONMENTAL MANAGEMENT SYSTEM (SEMS) OPERATIONS


MANUAL, DPWH, 01 April, 2003

9.

ROAD CONSTRUCTION MANUAL, DPWH, BUREAU OF RESEARCH AND


STANDARDS, 1990

10. DISTRESS IDENTIFICATION MANUAL, for the Long-Term Pavement Performance


Program, Federal Highway Administration, June 2003
11. Asphalt in Pavement Maintenance, Asphalt Institute, Manual Series No.16 (MS-16),
March 1983 Edition
12. Construction Program Management
Administration, August 2003

and

Inspection

Guide,

Federal

Highway

13. Road & Bridge Routine Maintenance Procedures and Planning Manual (Vols. I, II and
III), DPWH, April, 2006
14. Road Safety Audit Manual, Road Works Safety Manual, Highway Safety Design
Standards Manual and Highway Safety Design Standards Manual, DPWH, February
2004
15. Revised Procedural Manual for DENR Administrative Order No. 30 Series of 2003
(DAO 03-30)

Road Project Management and Supervision Manual Vol.1 Main Text