Professional Documents
Culture Documents
Rev: B
Page 1 of 41
DESIGN BASIS
FOR
(Civil, Structural & Architectural)
Andheri (East)
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 2 of 41
DESIGN BASIS
FOR
(Civil, Structural & Architectural)
Client
256324
Date
Originator
Checked
Approved
Description
24/03/09
GBP
PKB
KGN
26/06/09
DIN
PKB
SMA
Group Disclaimer
"This document has been prepared for the titled project or named part thereof and should not be relied upon or
used for any other project without an independent check being carried out as to its suitability and prior written
authority of Mott MacDonald being obtained. Mott MacDonald accepts no responsibility or liability for the
consequences of this document being used for a purpose other than the purposes for which it was commissioned.
Any person using or relying on the document for such other purpose agrees, and will by such use or reliance be
taken to confirm his agreement, to indemnify Mott MacDonald for all loss or damage resulting therefrom. Mott
MacDonald accepts no responsibility or liability for this document to any party other than the person by whom it
was commissioned..
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 3 of 41
List of Contents
Page No
Scope
2.1
Specifications:
2.2
7
7
8
8
8
9
9
9
Materials of Construction
Design Loads
10
5.1
General
10
5.2
10
5.3
10
5.4
11
5.5
11
5.6
11
12
6.1
Vertical Loading
12
6.2
12
6.3
13
6.4
13
6.5
13
13
7.1
General
13
7.2
14
14
14
14
14
14
14
Contingency Loads
15
8.1
15
RCC Structures
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 4 of 41
Structural Steel
15
15
10
15
11
16
12
17
13
18
14
18
15
18
16
Load Combinations
18
16.1
General
18
16.2
18
17
18
19
20
21
20
17.1
General
20
17.2
Foundations
20
17.3
21
17.4
21
17.5
Anchor Bolts
22
17.6
22
17.7
Staircase
22
17.8
Concrete Grade
23
17.9
Reinforcement Bars
23
23
23
Masonry Structures
24
18.1
General
24
24
19.1
General
24
19.2
Miscellaneous
25
25
20.1
General
25
20.2
25
26
21.1
26
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
23
24
25
Rev: B
Page 5 of 41
Joints
27
Drainage General
27
22.1
Drain details
27
22.2
28
29
23.1
Site Grading: -
29
23.2
Roads:-
29
29
24.1
General
29
24.2
30
24.3
Analysis & design procedure for ring walls & RCC pile caps for Steel Tanks:
30
24.4
30
Design Philosophy/Criteria
31
25.1
Architectural Design
25.1.1 Spatial Requirements
25.1.2 Functional Spaces
25.1.3 Circulation Spaces
25.1.4 Amenity Spaces
25.1.5 Utility Spaces
25.1.6 Sizes of Spaces
25.1.7 Day Light and Natural Ventilation
25.1.8 Natural Ventilation
25.1.9 Acoustics and Sound Insulation
25.1.10 Safety Requirements
31
31
31
32
32
33
33
33
33
33
34
25.2
Site Planning
34
25.3
Building Services
25.3.1 Water supply, Distribution and Drainage Sanitary Services
25.3.2 Electrical Services
25.3.3 Air conditioning and Heating
35
35
35
35
25.4
Aesthetics
35
25.5
36
36
36
36
37
38
38
39
39
39
39
39
39
40
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 6 of 41
Mounded Bullets
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
40
40
40
40
40
40
41
41
41
41
41
Rev: B
Page 7 of 41
Scope
The engineering design basis defines the minimum design criteria that shall form the basis for carrying
out detailed civil, architectural and structural design of all structures like Fire water tank foundations,
TW Gantry , Tank Truck Gantry, connecting platforms, Pipe tracks, plant buildings (like DG
Sheds/Pump Sheds/MCC-Air Compressor Room etc.), non-plant buildings (like
Administration/Security/Amenity/Planning buildings etc.) included in bid document.
This document also includes the design criteria that shall form the basis for carrying out design and
engineering of items under general civil (viz. roads, paving drainage etc.).
This document shall be read in conjunction with technical specifications and scope of works.
This specification describes the materials, loads, design requirements and methods to be used for design
of structures / buildings as described below:
(Reference drawing: Overall Plot Plan Drg. No 256324-500-PIP-3000)
The various structures, buildings and equipment included in the scope are:
SCHDULE OF LPG FACILITIES
As per Plot Plan
LPG PUMP DETAILS
As per Plot Plan
Following technical specifications shall be referred along with this design basis.
2.1
Specifications:
Sr.
No
2.2
Title
STD. Specification
No.
1.
2.
3.
256324-500-SP-CIV-003
4.
256324-500-SP-CIV-004
5.
256324-500-SP-CIV-005
256324-500-SP-CIV-001
(For general notes, legend and abbreviations refer Drg. No. (256324-500-CIV-2801)
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
- Pt II , 2005
Concrete Design:
IS 456 2000
Special Publication,
SP 16:
IS 13920 :1993
- Code of practice
2.2.4
- Pt I , 2002
IS 4326 :1993
2.2.3
Page 8 of 41
Loads:
IS 875 : Part 1: 1987
2.2.2
Rev: B
IRC 6 -2000
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
IRC 58 -2001
IS 1172-1993
Foundation Design:
IS 1080 :1985
IS 1904 :1986
IS 2950, Part 1 1981
IS 2911 Pt. 1 Section- I
1979
IS 2911 Pt. 1 Section- II
1979
IS 2911 Pt. IV
1985
IS 6403 1981
2.2.6
Misc. Specifications:
OISD-STD-109-Aug1999
OISD-STD-118-July2008
OISD-STD-163-Sept 2004
OISD-STD-164-July 1998
Masonry Design:
IS 1905 :1987
2.2.7
Page 9 of 41
IRC 37 -2001
IS 1742-1983
IS 2065-1983
IS 8835-1978
2.2.5
Rev: B
Materials of Construction
The materials used for construction shall be strictly as per the relevant technical specifications
and as per the relevant I. S. Codes & specifications.
All non plant buildings shall be R.C.C. frame type buildings with foundations as per soil
report. For e.g. the non plant buildings include following;
Administration Building, Security Office, Drivers Block, Weighbridge & Weighbridge Cabin
etc,
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 10 of 41
All plant buildings shall be R.C.C. frame type buildings with foundations as per soil report.
For e.g. the plant buildings include following;
DG Sheds, MCC & Air Compressor Room etc.
All Pipe/Cable Tracks shall be Slippers with Either Open/Pile foundations as per soil report.
All Tanks shall be supported on pile foundations with ring beam as per final soil report.
The shed type buildings shall be following
Tank truck Gantry sheds, Cylinder Storage Shed, DG Shed, Cylinder Loading Platform,
Cylinder unloading Platform etc.
Design Loads
5.1
General
5.1.1
Structures shall be designed to have sufficient structural capacity and integrity to resist safely
and effectively all loads and effects of load combinations that may reasonably be expected.
5.1.2
The design loads used for the structures, buildings and foundations shall conform to the
requirements of the governing codes and specifications. As a minimum the design loads shall
include dead load, operating loads, live load, rain load, wind load and seismic load. Where
applicable, the design loads shall also include thermal load, anchor loads, hydro test load,
impact load, vibration load, surcharge load and bundle pull loads.
5.1.3
5.2
5.2.1
Dead load comprises of the weight of all permanent construction including walls, fireproofing, floors, roofs, partitions, stairways, fixed services and other equipments excluding
their content.
Dead loads (D) shall consist of total loads due to the structure (framing, walls, roofing etc.),
equipment, piping, insulation, refractory, overburden soil, and other load permanently
supported by the structure. If in-situ hydro test is planned, the dead load shall include water
filled vessels and piping. Foundation dead loads shall contain the weight of the soil
immediately above the foundation.
Weight of the structure: The self-weight of the structure shall be calculated based on the
following unit weights of the structure:
Items
Steel
Reinforced Concrete
Plain Concrete
Water
Soil (dry earth )
Soil in Ground Water
Bricks Masonry
Dry Sand
5.3
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 11 of 41
The empty weight of the static process equipment including all fixtures, platforms, ladders,
attached piping, pipe supports & insulation (if applicable) shall be considered. If piping
weight is not indicated separately or included in the weight of the equipment, the same shall
be considered as 10% of the weight of the equipment. The empty (dead) weight shall be
considered as per inputs received from vendors. Static equipments viz. Vessels, tanks etc.
Dead/Empty Weight of equipment Weight of dynamic/rotary equipment like pumps/motors,
D.G. Sets, and skid-mounted equipment shall be derived as far as possible from
manufacturers data and includes piping data. Insulation installed on piping and equipment
shall be also considered.
Empty/dead weight Fabricated/Erected equipment weight from manufacturers data.
5.4
5.5
5.6
5.6.1
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 12 of 41
Longitudinal & transverse friction force in (both directions) 10 % of design vertical load of
pipes for four or more pipes supported on a tier. (This is done due to reversible flow directions
and forces)
Longitudinal & transverse friction force in (both directions) 10 % of design vertical load of
pipes for four or more pipes supported on a tier. (This is done due to reversible flow directions
and forces)
Longitudinal friction force (30 % of design vertical load of pipes) & transverse force (10 % of
design vertical load of pipes) for single to three pipes supported on a tier for global design
where as for local beam member design for single pipe frictional force of 30% to be
considered in longitudinal and transverse direction or as per piping/stress load inputs. The
local beam member design shall not be combined with seismic/wind loads.
For Pipe-racks; longitudinal friction force shall be considered as uniformly distributed over
the entire span of the beam at each tier and transverse friction force shall be considered as a
concentrated load at each tier level.
Friction forces on T-supports & trestles shall be considered as longitudinal 30% of the vertical
loading & transverse 10% of the vertical loading. Both longitudinal and transverse friction
forces shall be considered to act simultaneously.
5.6.2
5.6.3
Special consideration shall be given to unusual loads such as large valves, unusual piping or
electrical configurations, etc.
5.6.4
Anchor loads (TA) shall be as per the Stress analysis piping loads provided by Stress Group.
5.6.5
6.1
Vertical Loading
Actual weights of pipes coming at each tier shall be calculated. In calculating the actual weight of
pipe, the class of pipe, material content and insulation, if any, shall be taken into consideration.
Minimum Insulation density shall be taken as 2600 N/m3. In case of gas/steam carrying pipes,
the material content shall be taken as 1/3rd volume of pipe filled with water. The total actual
weight thus calculated shall then be divided by the actual extent of the span covered by the pipes
to get the uniform distributed load per unit length of the span. To obtain the design uniformly
distributed load over the entire span, the udl (uniformly distributed load) obtained as above shall
be assumed to be spread over the entire span. However, minimum loading for any pipe rack shall
not be less than 2.0 KN/m2. In case, the calculated loading is higher than 2.0 kN/m2, this shall be
rounded off to the nearest multiple of 0.25 (i.e. 2.25, 2.50, 2.75 kN/m2).
6.2
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 13 of 41
loading of the pipes for four or more pipes supported on a tier for global design, and 30% of the
design vertical loading of the pipes in longitudinal direction & 10% of the design vertical loading
of the pipes in transverse direction for single to three pipes supported on a tier. Longitudinal
friction force shall be considered as uniformly distributed over the entire span of the beam at each
tier and transverse friction force shall be considered as a concentrated load at each tier level.
Friction force on T-supports and trestles shall be taken as 30% and 10% in longitudinal and
transverse directions respectively of the vertical loading. Both longitudinal and transverse friction
forces shall be considered to be acting simultaneously.
For local beam/member design shall be checked for frictional forces 30% of the vertical loads in
both longitudinal and transverse directions acting simultaneously. The local beam design shall not
be checked for seismic/wind loads acting simultaneously along with the frictional forces.
6.3
6.4
6.5
7.1
General
7.1.1
Live loads (L) shall consist of loads due to the intended use and occupancy of the structure.
Minimum live loads due to use and occupancy shall be as follows, unless otherwise specified
on process / assignment drawings. Reduction in Live load shall be per Cl 3.2 of IS: 875 - Part
II.
Area
Specified Uniform
Loads
(KN/m2)*
Specified Point
Loads
(KN)**
2.2
5.0
9.0
1.5
3.75
Ladder Rungs
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 14 of 41
5.0
6.7
1.0
None
Vessel platform
5.0
None
Access platform
3.0
None
10.0
9.0
Toilet bathroom
2.0
9.0
5.0
4.5
Minimum specified uniform loads and minimum specified concentrated loads do not act
concurrently.
**
Distribute concentrated loads over 300mm x 300mm area. For evaluation of local effects
of crushing (Ref. Cl 3.1.1 IS 875 Part II).
7.1.2
For railings, a horizontal force of 1.0kN at any one point or uniform load of 0.75kN/m shall be
used.
7.1.3
For structural calculations, the actual loading situation shall be adhered to if these are more
stringent. If heavy equipment has to be supported, the weight of this equipment in excess of
the live load specified above shall be taken into account.
7.1.4
For garages and fire stations, the live loads shall also include the maximum weight of the
trucks and/or fire fighting equipment.
7.2
7.2.1
DG house
Operating area
Maintenance area
7.2.2
Service Platform
Vessel/Tower
Isolated platform (for valve operation)
Access way
Cross over
7.2.3
3.0 KN/m2
3.0 KN/m2
2.5 KN/m2
2.0 KN/m2
Substation/Control Room
Panel floor
Partitions
7.2.4
7.5 KN/m2
7.5 KN/m2 (or as specified by machine vendor)
10.0 KN/m2
1.0 KN/m2
Office building
Office area
Lobby
Exit way
Partitions
3.0 KN/m2
5.0 KN/m2
5.0 KN/m2
1.0 KN/m2
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
7.2.5
Rev: B
Laboratory
4.0 KN/m2
Upper floors
7.2.6
Page 15 of 41
Staircase
5.0 KN/m2
5.0 KN/m2
3.0 KN/m2
2.5 KN/m2
Office
Substation/Control Room
Laboratory
Service platform
Contingency Loads
8.1
RCC Structures
All floor slabs and beams shall be designed for a concentrated load of 10 KN acting
simultaneously with the uniform live load, but not with actual concentrated loads from
equipment, piping etc. This load shall be placed to result in maximum moment and / or
maximum shear, it shall not be considered for the design of columns, foundations and in
overall frame analysis. For floor slabs, the load shall be considered to be distributed over an
area of 0.75 m x 0.75 m.
8.2
Structural Steel
For process plants, the following contingency additional loading shall be applied to individual
beam elements. These shall be applied as point loads to produce worst shear and bending
stresses:
Platform Walkways
3 KN
5 KN
Primary beams
10 KN
10
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 16 of 41
The effects of wind induced vibration shall be taken into effect as required by the applicable
codes, specifications and recommended practices listed in Section 2.1.
Basic wind loading parameters at HPCL site: Basic wind speed at Visakhapatanam, Vb = 50 metres / sec
k 1 = Probability factor (Risk coefficient for different class of structure in different wind speed
zone)
k 2 = Terrain, height & structure size factor , for terrain category 2 , Structure class B,
(structure Size between 20m & 50m) at height 10 m = 0.98
k 3 = Topography factor = 1.0
Design wind speed, Vz = k1*k2*k3*Vb = 49 metres /sec
Design wind pressure, p z_gen = 0.6*Vz 2 = 1441 N/m 2 = 1.44 Kn /m 2 for general buildings at
structures at height 10 m above FGL
The sheds with louvers as cladding shall be considered as fully clad.
The design life span of all structures (units & offsite) shall be taken as 50 years. Temporary
structures shall be designed for a design life span of 25 years. Design life span for boundary wall
shall be as provided in IS: 875.
To account for surface area of piping, platforms and other attachments fixed to the equipment
the surface area of the equipment (vessel/column) exposed to wind shall be increased by 20% or
as specified in the mechanical data sheet of the equipment.
11
11.1
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 17 of 41
are made of ductile materials can withstand earthquakes with spectra four times higher than the
design spectra without collapse; and damage in such cases is restricted to cracking only.
In view of above it may be noted and the term "failure" used in the definition of categories
implies cracking and not complete collapse. Pressurised equipment where cracking can lead
to rupture may be categorised by the consequences of rupture.
Such equipment / structures where cracking will not lead to hazards are to be placed in
category-III and where it may lead to hazards within the complex are to be placed in category
- II. Category -I earthquake is an extreme event with little possibility of its occurrence.
Nevertheless in the remote case when it occurs, structures / equipment whose failure can lead
to loss of life at large are to be designed so as to avoid failure.
Following is the grouping of the areas/structures.
Category I: Blast Resistant Control Building
Category II: All equipments and their supporting structures, Bullets, Tanks & their
foundations etc.
Category III: Pipe-racks, Control Room-Substations Buildings, DG Sheds, F.W. Tank etc.
Category IV: Non-plant Buildings viz. Pump houses, Admin Building, Security Room,
Planning Room etc.
11.2
Seismic load (S) induced on structures, buildings, equipments, and foundations shall be
calculated in accordance of the requirements the IS standard as mentioned in Section 2.
11.3
Factors for the calculation of the seismic loading, i.e. seismic zone, soil profile, etc. shall be as
per Geotechnical Investigation and in accordance with the requirements of the IS standard as
mentioned in Section 2.
11.4
The Fundamental natural period shall be as per, Ref. Cl 7.6, IS 1893: 2002
For percentage of live load to be considered during seismic action for load evaluation, Ref
Table 8, IS 1893, Pt 1, 2002.
The seismic base shear VB = Ah* W
12
12.1
The calculation of thermal loads (TL) shall be as per the requirements of the governing codes
and specification.
12.2
Thermal Loads caused by expansion and contraction due to a change in temperature from the
erection condition shall be carefully considered. Included are forces due to anchorage of
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 18 of 41
piping and equipment, sliding and rolling of equipment, and expansion and contraction of
structures.
12.3
Thermal loads due to the constraints and frictional forces of piping shall be considered as
follows:
(a) A minimum of 10% (in both longitudinal & transverse directions) of the gravity load for the
pipe supports / sleepers carrying 4 or more lines.
(b) A minimum of 30% of the gravity load in longitudinal direction & 10% in transverse
direction on pipe supports / sleepers carrying less than 4 lines.
Equipment on structural supports shall be analyzed for thermal loads to be resisted by the
structure and provisions shall be made to relieve the forces too large for the equipment or the
supporting structure. The friction factors to be used are the ones defined hereunder.
Steel To Steel = 0.3
Steel to PTFE Pad = 0.08
Steel to Concrete = 0.4
13
14
15
16
Load Combinations
16.1
General
16.1.1
Structures, buildings and foundations shall be designed for all individual load cases and the
various load combinations that may act together.
16.1.2
Load combinations using Working Stress Design or Limit State Design shall be as per the
requirements of the IS standard as mentioned in Section 2.
16.2
16.2.1
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 19 of 41
Dead Load
Live / Imposed Load
Equipment Load (Empty Equipment)
Equipment Hydro test Load (Equipment with water load)
Equipment Operating Load (Equipment with operating fluid)
Wind Load
Seismic / Earthquake Load
Operating Load of piping and fluids
Thermal Load
Thermal Anchor Load
Bundle Pull Load
Vibration Loads
Earth Pressure Load
Surcharge Load
factor for Load
Strength load combinations for buildings with or without equipment shall be as per IS: 4562000.
1.5*D
1.5*D + 1.5*L
1.5*D + 1.5*L + 1.5*E
1.5*D + 1.5*EH
1.5*D + 1.5*L + 1.5*EO
1.5*D + 1.5*(W or S)
0.9*D + 1.5*(W or S) reversible wind/seismic forces
1.5*D + 1.5*E + 1.5*(W or S) reversible wind/seismic forces
0.9*D + 0.9*E + 1.5*(W or S) reversible wind/seismic forces
1.5*D + 1.5*EO + 1.5*(W or S) reversible wind/seismic forces
1.2*D + 1.2*L + 1.2*(W or S) reversible wind/seismic forces
1.2*D + 1.2*L +1.2*E + 1.2*(W or S) reversible wind/seismic forces
1.2*D + 1.2*L +1.2*EH + 1.2*(W or S) reversible wind/seismic forces
1.2*D + 1.2*L +1.2*EO + 1.2*(W or S) reversible wind/seismic forces
16.2.3
Service load combinations for general buildings shall be as per IS: 456-2000.
1.0*D
1.0*D + 1.0*L
1.0*D + 1.0*L + 1.0*E
1.0*D + 1.0*EH
1.0*D + 1.0*L + 1.0*EO
1.0*D + 1.0*(W or S) reversible wind/seismic forces
1.0*D + 1.0*E + 0.8*(W or S) reversible wind/seismic forces
1.0*D + 1.0*EO + 0.8*(W or S) reversible wind/seismic forces
1.0*D + 1.0*L + 0.8*(W or S) reversible wind/seismic forces
1.0*D + 0.8*L +1.0*E + 0.8*(W or S) reversible wind/seismic forces
1.0*D + 0.8*L +1.0*EH + 0.8*(W or S) reversible wind/seismic forces
1.0*D + 0.8*L +1.0*EO + 0.8*(W or S) reversible wind/seismic forces
16.2.4
IS: 800 Allowable stress design method shall be used with following load combinations for
design of structural steel open structures/sheds/pipe-racks. This is done in view of use of
STAAD PRO software for the analysis & design.
D + OP + TA + TL + V
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 20 of 41
D + OP + TA + TL + V +E
D + OP + TA + TL + V +EH
D + OP + TA + TL + V +EO
D + OP + L + TA + TL + V
D + OP + L + TA + TL + V +E
D + OP + L + TA + TL + V +EH
D + OP + L + TA + TL + V +EO
D + OP + TA + TL + EO
D + OP + TA + TL + EO + W reversible wind forces
D + OP + TA + TL + EO + S reversible seismic forces
D + OP +H + L
D + OP + H + B
0.9*D +0.9*OP +W reversible wind/seismic forces
0.9*D + 0.9*OP +S reversible wind/seismic forces
16.2.5
Strength load combinations for design of foundations shall be as per IS: 456-2000.
1.5*D + 1.5*OP + 1.5*L
1.5*D + 1.5*OP + 1.2*EO + 1.2*TA + 1.2*TL + 1.2*V + 1.2*B
1.2*D + 1.2*OP + 1.2*EO + 1.5*L + 1.2*TA + 1.2*TL + 1.2*V
1.2*D +1.2*OP + 1.2*EO + 1.2*TA + 1.5*W + f1*L + 1.2*B
1.2*D +1.2*OP + 1.2*EO + 1.2*TA + 1.5*S + f1*L + 1.2*B
1.2*D + 1.2*H + 1.5*L + 1.5*W reversible wind forces
1.2*D + 1.2*H + 1.5*L + 1.5*S reversible seismic forces
1.2*D + 1.2*EO + 1.5*L + 1.2*B + 1.2*H
0.9*D + 0.9*E + 1.5*W reversible wind forces
0.9*D + 0.9*E+ 1.5*S reversible seismic forces
16.2.6 Service load combinations for foundations shall be as per IS: 456-2000.
1.0*D + 1.0*OP + 1.0*L
1.0*D + 1.0*OP + 1.0*EO + 1.0*TA + 1.0*TL + 1.0*V + 1.0*B
1.0*D + 1.0*OP + 1.0*EO + 1.0*L + 1.0*TA + 1.0*TL + 1.0*V
1.0*D +1.0*OP + 1.0*EO + 1.0*TA + 1.0*W + f1*L + 1.0*B
1.0*D +1.0*OP + 1.0*EO + 1.0*TA + 1.0*S + f1*L + 1.0*B
1.0*D + 1.0*H + 1.0*L + 1.0*W reversible wind forces
1.0*D + 1.0*H + 1.0*L + 1.0*S reversible seismic forces
1.0*D + 1.0*EO + 1.0*L + 1.0*B + 1.0*H
1.0*D + 0.8*E + 0.8*W reversible wind forces
1.0*D + 0.8*E+ 0.8*S reversible seismic forces
16.2.7
16.2.8
1.0 for floors in places of public assembly, for live loads in excess 5 kN/m2, and for
garage live loads;
0.5 for other loads.
16.2.9
Where loads other than those mentioned in Section 16.2.5 are to be considered in design, each
applicable load shall be added to the above load combinations with a factor of 1.0 for service
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 21 of 41
load combinations and 1.5 or 1.2 for strength load combinations. For permanent loads for
strength design factor 1.5 shall be used & for transient loads .factor 1.2 shall be used.
17
17.1
General
17.1.1
All structures shall be analysed/designed in STAAD PRO and mainly in limit state as per IS:
456-2000, by allowable stress design as per IS 3370. Generally the concrete beam members
shall be so designed that the span/depth ratio is 10.
17.2
Foundations
17.2.1
All major foundations shall be on piles for LPG. For minor structures shallow spread
foundations or mat/raft foundations shall be designed if specified in soil report.
17.3
17.3.1
The minimum width for a strip footing is 1000 mm. The minimum width for a spread footing
is 1200 mm. The minimum thickness of footing shall be 300mm.
17.3.2
17.3.3
The top of concrete elevation shall be a minimum of 300 mm above grade for pedestals, piers
and pads and 150 mm above finished floors (concrete grade slabs).
17.3.4
For the support of items at close spacing, such that the footings or pile caps utilize more than
50 percent of the gross plan area, it is common to use a mat type of spread footing, or pile cap,
that supports several items.
17.4
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 22 of 41
e) The capacity of the piles shall be as per final soil investigation report.
TABLE FOR PILE CAPACITIES
Sr.
No.
1
2
17.5
Size in
MM.
500
Dia.
600
Dia.
Pile Description
Length
Type
In
Metres
24
Driven Cast In
Situ
24
Driven Precast
75
50
1200
100
60
Remarks
Anchor Bolts
For reference of standard details of anchor bolts refer standard drawing.
17.5.1
Anchor bolts shall be designed to resist the applied tensile loads and shear.
17.5.2
Anchor bolts that resist tensile loads shall be designed with an anchor head or plate to transfer
the load through tension in the concrete.
17.5.3
Anchor bolts for all equipments viz. vertical vessels/tanks & structural steel structures like
columns of pipe-racks, sheds, trestles, portals shall have double nuts.
17.5.4
Anchor bolts on horizontal vessels shall have 1 nut per anchor bolt at the fixed end and 2 nuts
per anchor bolt at the sliding end, 1 loose nut and 1 locknut.
17.6
17.6.1
All reinforcement shall have clear concrete cover requirements as per following table &
General Notes, Legend & Abbreviation Drg. No. 256324-500-CIV-2801 whichever is more.
Cast-in-place Concrete
Minimum cover (mm)
Cast against and permanently exposed to 75 bottom for open footing, (Ref Table 16, IS
456)
earth for major foundation
50 top & sides
100 at bottom for pile-caps
Exposed to earth, weather or water for less 50 for foundations, walls, beams, columns in
important structures
contact with earth
70 pedestals/columns in contact with earth
Not exposed to weather or in contact with 40 for beams & 50 for columns/pedestals
the ground
above ground
25 for walls & slabs above ground
Precast Concrete
Exposed to earth, weather or Wall panels
water
Other members
Not exposed to earth, weather Slabs, walls, joints
Minimum
(mm)
40
50
30
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
cover
Rev: B
Page 23 of 41
50
75
50
75
17.7
Staircase
17.7.1
Minimum width of stairs shall be 900 mm. Stairs shall have a maximum riser height of 175
mm and a minimum tread width of 250 mm for equipment support platform, maximum riser
height of 150 mm and a minimum tread width of 300 mm for buildings. No of risers shall be
restricted preferably to 12 depending on occupancy. At least one staircase shall be provided
for access to the roofs for maintenance.
17.7.2
Stairway in a single run shall have the same slope. The vertical rise of the stairways shall not
exceed 2.5 m for a single flight.
17.8
Concrete Grade
The minimum M30 grade of reinforced cement concrete shall be used for all structures and
foundations except for grade slabs / paving for which M20 may be used. Severe condition of
exposure as per IS: 456 shall be considered for concrete mix designing for all RCC structures
except for RCC in pavements which shall be designed for moderate exposure condition.
If soil investigation report recommendations require a higher cement content and/or specific
type of cement the same shall have precedence.
75 mm thick lean concrete of grade M10 (nominal mix) shall be provided under all RCC
foundations except under base slab of liquid retaining structures where 100 thick concrete of
mix M-10 (nominal mix) shall be used. The lean concrete shall extend 75 mm beyond the
foundation for normal foundations and under liquid retaining structures.
Concrete for encasing shall be M20 with 10 mm down aggregate.
Plain cement concrete (PCC) of grade M10 (nominal mix) of minimum 150 mm thickness
shall be provided under all masonry wall foundations.
17.9
Reinforcement Bars
High strength deformed steel bars of grade Fe 500- corrosion resistant conforming to IS: 1786
shall be used.
M.S. round bars (Grade-I) conforming to IS: 432 may be used for holdfasts of inserts.
17.10
300 mm
750 mm
300 mm
125 mm
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 24 of 41
resting on beams
Cable / Pipe Trench / Launder Walls &
100 mm
Base Slab.
Pre-cast Trench Cover / Floor Slab
100 mm
230 mm
75 mm
150 mm
17.11
17.11.1
The deflections of the structures and buildings based on the worst load combination shall be
limited to an acceptable level as defined below.
17.11.2
20
26
Total vertical deflection due to all loads including the effects of temperature, creep &
shrinkage
= Span/250
17.11.4
The calculated lateral deflections due to load combinations for building shall not exceed the
following:
(a) Occupied buildings = h/250
(b) Wall stanchions = h/350 or 20 mm whichever is less
18
Masonry Structures
18.1
General
Where needed, masonry structure design shall be in accordance with the applicable codes,
specifications and recommended practices listed in Section 2.2.6
19
19.1
General
18.1.1
All steel structures shall be modelled, analyzed in STAAD PRO and designed as per IS 8001984.
All structures shall be framed in transverse direction and braced in longitudinal direction.
Both induced stresses and deflection shall be kept within provisions of IS codes & good
engineering practices.
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 25 of 41
Structural Components
The minimum thickness of structural sections shall as given below;
Trusses/bracings
6 mm
6 mm
Columns, beams
7 mm
8 mm
Above 12 m span
10 mm
Stiffeners
8 mm
Base-plates
12 mm
Chequered plates
6 mm on plain
Grating
25 mm
19.2
Miscellaneous
18.2.1
Gutter shall be made of mild steel quality of minimum 6 mm thickness; the section shall be
trapezoidal with proper supporting arrangement from purlin at regular interval of 1m to 1.5 m
spacing.
18.2.2
18.2.3
Down comer pipes at suitable positions as per design shall be fixed below gutter made of mild
steel of 3.55 mm thickness and minimum 150 mm diameter.
18.2.4
Wind bracing/tie runners of minimum size L50X50X6 shall be provided at 4 points in a truss
(one at each corner) for structural roof system i.e. this shall be designed as structural members
for proper transfer of wind forces to the foundation.
18.2.5
20
20.1
General
20.1.1
The deflections of the structures and buildings based on the worst load combination shall be
limited to an acceptable level as defined below. Generally the structural steel members shall
be so designed that the span/depth ratio is 20.
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 26 of 41
20.2
20.2.1
Calculated deflection of crane beams or girders (without impact) shall not exceed the
following:
a) Vertical (Ref. Table 6, IS 800 - 2007)
20.2.2
20.2.3
21
21.1
Concrete Paving
Area Around
Non plant
Bldgs.
Acid/
Alkali
Proof
Coating
Roads
Approaches to
units
Fire water
Tanks
T/T Loading
Gantry Sheds
Pump Sheds
Asphalt
(Bituminous)
Paving
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Transformer
Yard
Page 27 of 41
Notes:
1) Existing services where interfering with the new construction should be located and rerouted
as instructed by HPCL.
2) Micro grading shall be carried out by the Contractor over graded areas to bring the FGL to
indicated levels including provision of required slopes and finishes.
3) 75 thick PCC (1:3:6) over compacted earth shall be provided under pipe track areas to
prevent vegetation growth in case the area is not concrete/asphalt paved.
20.1.1
Paving within areas for Maintenance / Dropout/ Loading / Unloading / Vehicular movementType 1 (200 mm thick RCC M20)
20.1.2
20.1.3
Hard surface of 75 thick PCC (1:3:6) over compacted earth shall be provided below all new pipe
rack. This shall extend as indicated in respective layouts and it shall have approach @ 500 m c/c
from nearest road.
20.1.4
Hard surface in PCC 1:3:6 (100 mm thick) over suitable bedding (gravel soiling) of suitable size
(1 m x 1 m or as specified) shall be provided with proper approach near drain point of offsite
piping, near drinking water installations, at washing facilities and at other places as required /
instructed by Engineer in charge, with suitable curbing and drainage arrangements as required for
the fluid being handled.
20.1.5
Suitable drainage arrangements will be provided within curbed areas around pumps, for draining
leaks, floor washes, rainwater falling in the area etc. Finishes, slopes will be as per materials
handled in the area.
20.1.6
20.1.7
Hard stands should be designed and provided based on required crane capacity, demolished and
surface made good on completion.
Provision of trenches, drains, sealing of trench covers, inserts, thickening for pipe / equipment
supports etc. shall be made while constructing pavements, as detailed in drawings.
20.1.8
Acid / alkali / chemical resistant coating as specified in equipment layout shall be applied in
areas where they are likely to come in contract with concrete.
21.2
Joints
Expansion joint of 20 mm shall consist of 20 thick impregnated fibre board, filled at top with
joint sealing compound 20 x 25.
Equipment / column pedestals will be separated from paving with 20 thick sand fill and sealing
compound 20 x 25 as shown in standard / drawings.
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 28 of 41
22
Drainage General
22.1
Drain details
Surface drainage includes all surface water discharge from clean plant areas attributable to
rainwater, firewater (except from bunds) and overflow water from water tank to drain via open
surface water drains, trenches and natural water courses to ultimate discharge point avoiding
accidental oily contaminated water system.
Drain section shall be rectangular type in and around units and in other areas. Material of
construction shall be brick drains with 20thk. Cement mortar plaster (1:4) and neat cement
punning shall be provided.
Hot dipped Galvanised electro forged steel grating covers, or pre-cast RCC (M20) covers of
designed thickness, hand railing, chain link fencing wherever necessary shall be provided to
minimise the risk of falls by personnel. Oil water separator shall be provided with trenches,
sumps, valves and pipes including connecting to nearest OWS network for disposing the
collected oil to OWS. The separated oil to be transferred to slop tank and the remaining water to
the nearest storm water drain outlet/nallah.
Design rainfall intensity of 75 mm /hr shall be considered for design of storm water drainage
system.
Generally, the slope of the paving shall be 1:100 but the maximum drop in paving shall be
limited to 150 mm. Two way slopes in paving shall be avoided as far as possible.
Slope of main drain along shall be 1:1000. Slope of secondary drain shall be 1:750. Slope of
tertiary drains along east-west shall be 1:500.
22.2
Rev: B
Page 29 of 41
R= Hydraulic radius
S= Slope
n= Roughness Coefficient
Roughness Coefficient shall be considered as follows;
a) Plastered surfaces = 0.013
b) Cast in situ concrete = 0.015
c) Concrete/Brick Lining = 0.017
The following points are to be followed while sizing the storm water drains
Minimum velocity in drains = 0.6 m/s
Maximum (Scouring) velocity in drains = 2.4 m/s
Preferred (Self cleansing) velocity in drains = 1.0 m/s
Minimum depth of drains = 300 mm
Minimum width of rectangular drains = 300 mm (for depths 500 mm)
Minimum width of rectangular drains = 500 mm (for depths 500 mm)
Contaminated rain water / Oily water drainage are routed underground to OWS tanks as
appropriate. Sewage to be passed to septic tank & then routed through soak pit & sewage
treatment plant
Concrete pavement run-off surfaces shall slope at 1:100 to perimeter channels. Systems shall
be sized to cope with worst of storm water run-off or fire water run-off.
23
23.1
Site Grading: The site is rough graded to RL 4.2 considering HFL RL 3.5
23.2
Roads:All roads shall be asphalt roads and shall be designed for heavy vehicular traffic movements
per IRC loadings.
Design of cross section of roads, including roads for crane access shall be as per IRC 37.
However, the minimum section to be adopted shall be as given below under minimum cross
section. Ruling gradient shall be 1 in 30.
Main plant road widths shall be 7.5 m inclusive of 0.75 m wide shoulders on either side. The
internal access roads to individual areas shall be minimum 4.0 m wide with 0.75 m wide
shoulders. Design life of the same shall be 15 years (Ref. Cl 3.3.3 IRC 37-2001- pavements for
Nationals and State highways shall be designed for a life of 15 years).
Category
i.
ii.
Width
Carriageway Width
7.5 m
6m
4m
2.5 m
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 30 of 41
Camber: 1 In 50
Radius Of Curve: 6 m for 6 m wide road
Extent: As per Plot Plan & Equipment (Unit Area) Layouts
24
24.1
General
These buildings house electrical switchgear and motor control centres with associated HVAC,
telecoms and battery accommodation. The buildings shall provisionally be designed as indicated
in equipment layout.
The screeded concrete floor shall be finished with an epoxy based hardener and sealant with
corrosion resistant finishes used in battery rooms. Overhead monorail of nominal capacity if
indicated in equipment layouts shall be provided in the main switchgear rooms per detailed
design requirements. There shall be cut-outs provided in cellar floor slab for supporting the
panels. The c/c distance between the stub columns shall be 2.0 m on which the cable trays shall
be supported. There shall be channels/insert plates all around cut-outs to support panels. In cable
cellar, cable tray support shall be of structural steel fixed with mild steel base plate at
bottom or top, at regular interval as per electrical requirement.
Access to the raised floor level shall be via concrete stair and platforms with equipment access
and demountable steel handrails. All doors shall be insulated metal construction with the
addition of removable transformer panels for equipment access where required. A roller shutter
door shall be provided for equipment entry to the main switchgear room.
Fire rated concrete walls shall be provided between the transformers and cable basement and the
transformer compound where required, for the separation of the larger non-sealed type of
transformers.
All mesh infill panels; gates, doors, locks etc. shall be specified to meet the requirements of
relevant codes and standards.
24.2
24.3
Analysis & design procedure for ring walls & RCC pile caps for Steel Tanks:
a)
Ring walls shall be designed to transfer vertical loads due to tank shell wall, roof, and
incident load due to water or product /oil stored and abutting on ring wall top inside the
shell to firm bearing strata. The vertical load due to product stored or water in tank
during hydro test is transferred directly through tank base plate to firm bearing strata.
b)
Ring walls shall also be designed to resist all horizontal loads due to earth pressure,
surcharge pressure due to product stored or water stored in tank. Simultaneously ring
walls shall also resist all horizontal loads due to wind & seismic forces and moments
thereof. Hoop tension due to surcharge pressure shall be the primary stress in ring walls.
c)
Sand fills or compacted earth fills shall be provided on the inside of the ring wall from
conical tank bottom till founding level of ring wall.
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 31 of 41
d)
For tanks which are supported on piles they are provided with RCC pile caps with or
with out ring walls. Ring wall shall rest on the RCC pile cap at a minimum depth of
1.2m below Finished Ground Level (T/o pile cap at 1.2 m below FGL).
e)
Pile cap shall take all vertical & horizontal loads from ring walls as described in i) & ii)
above as also the weight of product liquid or water during hydro test transferred directly
through tank bottom plate & sand fill. Load from ring wall shall be applied as a
concentric uniform load along centreline of ring wall. Product load & water load shall
be applied as area load on top of pile cap. Bending moments due to wind or seismic
horizontal loads shall be calculated at bottom of pile cap level.
f)
Pile group shall be designed to resist both vertical loads resulting from external loads,
self weight & vertical surcharge pressure as also all unbalanced external horizontal
loads, earth pressure & horizontal surcharge pressure. Pile group shall be preferably
arranged concentrically with ring wall centreline as the guiding circle. Critical
horizontal & vertical loads to be calculated in corner piles and they shall be kept within
safe pile capacities obtained from pile test report.
g)
Pile cap shall be designed as bending member & pile shall be considered as hinged
support with provision for tension reinforcement at bottom of pile cap.
h)
Tanks may be resting on different systems of foundation: a) On RCC piles and pile caps.
b) On earthen tank pad with or without ring wall.
24.4
Underground RCC tank has to be stable against buoyant water pressure from below.
Critical load case shall be for tank empty condition. Factor of safety for buoyancy
during operation of the tank shall be 1.2. Factor of safety against buoyancy for tank
empty condition during construction shall be at least greater than 1.05.
ii)
For tanks with top slab, wall shall be taken as propped at top & fixed at bottom. For
tanks without top slab or major portion of top slab is cut out due to system requirements
the wall shall be designed as pure cantilever.
iii)
If soil water is present and Ground water table (GWT) is above top of tank foundation
raft, outside water pressure shall be added on to earth pressure to find out wall
reinforcement for tank empty condition.
iv)
Evaluate dead load of RCC tank wall, RCC tank top slab & RCC tank raft.
v)
vi)
Evaluate earth pressure & surcharge pressure from outside. These loads shall be critical
for wall reinforcement when tank is empty. Underground RCC tank shall be a rigid
structure and earth pressure coefficient shall be earth pressure at rest (Ka=0.5) bearing
against tank wall.
vii)
viii) The coefficient for wall moments & shear shall be taken from IS: 3370 (Pts I IV) &
Reynoldss /Moodys charts. The boundary conditions for the tank walls considered as
plate elements shall be fixed at bottom & hinged (tank slab at top) or free (no slab at
top).
ix)
x)
For underground RCC tanks resting on piles, piling arrangement shall be provided in
parallel lines & in staggered fashion on either side of the walls. The middle raft shall be
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 32 of 41
provided with additional piles at centre or the slab can be suspended as dictated by the
criticality of load.
xi)
If the tank bottom slab is suspended the section shall be thinner at middle & thicker at
edges below wall (i.e. for the pile cap portion).
xii)
25
Design Philosophy/Criteria
25.1
Architectural Design
Architectural design of buildings/sheds shall be in accordance with this design basis and
references as stated herein, in addition to the applicable statutory requirements, layout
planning requirements and so on.
25.1.1
Spatial Requirements
Spatial requirements inside a building/shed shall be decided based on activities to be
performed in the building and consequent occupancy pattern, equipment layout etc. Spaces
can be generally classified as follows, which shall be provided in all the buildings/sheds.
25.1.2
Functional Spaces
Functional area of any building/shed is constituted by the main activity for which the building
is required. Various spaces/rooms shall be judiciously sized and shall be integrated logically
to generate the total building plan taking into account the following parameters.
Activities, group of activities and consequent work-flow pattern
Site conditions i.e. dimensions, contours etc.
Climatic conditions vis--vis orientation
Safety regulations
Lighting and ventilation
Acoustics
Services
Security
Economy
Aesthetics
Any specific requirement pertaining to particular buildings
All other established architectural design parameters
The objective of spatial arrangement shall be to satisfy functional requirements and physical
comfort and safety regulations as well as aesthetics which has significant role in creating a
favourable working and living condition.
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 33 of 41
Circulation Spaces
Following spaces are classified as circulation spaces. These spaces shall be provided as per
required building services for integrating various types of spaces and as means of
access/exit/escape.
Corridors & passages
Staircases
Entrance lobby/Foyer including Reception & waiting
Gangway/walkways
Equipment loading/unloading platforms
Emergency Exits
25.1.4
Amenity Spaces
Following spaces are classified as amenity spaces. Out of the following areas, Toilet, Drinking
water, First Aid enclosures shall be mandatory requirement for human occupied
buildings/sheds. Other facilities shall be provided as required.
Toilet (Gents & Ladies)
Drinking Water Facility
Locker & Change Room
Rest room/Lunch room
Canteen/Pantry room
Wash rooms & space for drying clothes
First-aid room
25.1.5
Utility Spaces
Utility spaces are space requirements, which materialise due to provision of services like airconditioning, pressurisation, fire fighting, electrical, telephone etc.
25.1.6
Sizes of Spaces
Sizes of various types of spaces shall be decided based on occupancy / equipment/
panel/furniture layout, clearance, maintenance & safety requirements & ventilation
requirements.
Following are the limiting sizes/dimensions for various purposes, which shall be adhered to:
Minimum area of any habitable room
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 34 of 41
Scale of accommodation for industrial work spaces = @ 14m3 per occupants. Minimum clear
heights such workspaces shall be 3.6 m. Height above 4.25 m shall not be taken into account.
25.1.7
25.1.8
Natural Ventilation
Established level of ventilation in terms of air changes per hour shall be maintained for all
spaces. Following references shall be adhered to for the purpose.
National Building Code of India
State Factories Act
Natural ventilation shall also be supplemented by mechanical or electrical means of
ventilation in all areas of habitation.
25.1.9
Rev: B
Page 35 of 41
Site Planning
Site planning of buildings shall take into account aspects like inter-relationship of the building
with the whole system, movement pattern, traffic and road network, safety regulations, service
network, fire safety, climatic and environmental aspects, site conditions like site dimension,
contour, drainage, noise level, view, future expansion, visual aspects etc.
Main and service/maintenance entrances of buildings shall be provided with vehicular access.
Parking space in accordance with traffic load shall be provided to all buildings. Road network
and open space around the buildings shall be designed considering movement and functioning
of fire tenders.
Climatic factors like wind direction, solar geometry shall be taken into account in orienting
the building. Orientation of building shall also consider noise and smell propagation, views,
and visual effect from various directions.
Sufficient open space shall be provided for planned expansion of building. Sufficient open
space shall also be provided around the buildings for lighting and ventilation in accordance
with Factories Acts.
Site plan shall also take into account landscaping aspects. The inherent characteristics of site,
such as contours, land form, vegetation and terrain shall be fully utilised in the design.
Open Space Requirement
Open spaces in a plot and around buildings proportional to the height of the structure shall
satisfy the requirements of the local byelaws.
25.3
Building Services
Following services shall be provided for all building/sheds as essential services.
25.3.1
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 36 of 41
Electrical Services
This service shall be provided as essential service for all buildings/sheds. Electrical services
for buildings shall consist of electrical supply and distributions. Electrical lighting
installations, telephone network, fans, exhaust fans, lighting protection system etc. including
all accessories, cabling etc. All electrical switches / sockets shall be of modular type (AnchorRoma or equivalent as per Electrical design basis or drawings).
25.3.3
25.4
Aesthetics
Apart from the fulfilment of functional & safety requirement, aesthetic requirement of the
building/sheds shall be taken care of in the design. As specific guidelines for achieving
required aesthetics are difficult to establish, following guidelines shall be followed:
Preliminary Drawings including schematic plans, elevations/views indicating architectural
treatment proposals shall be submitted for Owner's approval.
Following elements shall be considered as contributory elements to aesthetics and their design
etc. shall be subjected to the Owner's approval. Any change/modifications sought for
aesthetics improvements with regards to these elements shall be carried out. Any incidental
elements like brickwork, RCC work etc. required for such changes/modifications shall also be
added.
Building/shed shape and features
Canopies, overhangs & shading devices
Gutters
Entrance/exit steps, door
Window/Ventilator composition
External wall location with respect to columns
Colour scheme, grooves in plaster
Spatial arrangement
25.5
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 37 of 41
Plinth protection
All the buildings & sheds shall be provided with minimum 1000 mm wide plinth protection
around the building/shed.
25.5.2
25.5.3
Stairs width
= 1200 mm minimum
= 1000 mm minimum (Emergency exit)
Tread
= 260 mm minimum
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
25.5.4
Rev: B
Page 38 of 41
Riser
Slope of Ramp
= 12 Nos. In general
= 16 Nos. Emergency Exits
Landing width
= 1000 mm minimum
Walls
Following schedule shall be adhered to for wall material and thickness:
External Walls = 230 mm thick brick wall
Internal partition wall= 230/115 mm thick brick wall depending on the overall length and
height of the wall (Refer note below)
Transformer Perfect Party/Fire resistant Walls= 350 mm (including plaster) thick brick wall or
200 mm thick RCC wall
Concrete wall (Blast resistant) = Minimum 230 thick RCC wall as per structural design
Notes:
115 mm Thick brick partition walls (with nominal steel requirement as per structure design)
shall be provided with 230 mm thick brick pillars or RCC transoms/mullions for stability.
Wherever conduits or pipes are required to be concealed within partition wall, the wall
thickness shall be increased suitably.
Wherever, bricks are not commonly available, suitable alternative material (fly ash bricks)shall
be used after obtaining owners approval.
Fly Ash bricks of the first quality (class 5.0 as per IS:12894,)
Compressive strength of the Brick 50 kg/cm2 .
External wall = 230 mm thick
Half Fly ash brick wall = 115 mm
115 mm Thick brick partition walls (with nominal steel requirement as per structure design)
shall be provided with 230 mm thick brick pillars or RCC transoms/mullions for stability.
25.5.5
Doors
Doors shall be provided for access, security and safety at all entry & exits of rooms, functional
areas & the buildings. Air tight door shall be provided in pressurized area and in gaseous
protection area. Fire door shall be with two hours rating as per statuary requirement.
Emergency door shall be opened outwards. Sizes of the doors shall be determined on the basis
of the following schedule:
Equipment, Panel area: Size of maximum equipment including packing.
Other areas: Volume of movement through door, W.C., Bath etc.
Cubicle Door: 800 mm x 2100mm (masonry wall opening size)
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 39 of 41
Windows/ ventilators
Windows/ ventilators shall be provided in all areas for natural lighting, ventilation and
visibility at working level. For the purposes of ventilation, total operable area of the
windows/ventilators shall be as per Factory Act subjected to a minimum of 15% of the floor
area to be ventilated. However, for control room and in office areas, etc. where visibility from
inside is also important, increased window area shall be provided as per OISD guide line.
Areas accommodating panels/equipments shall be normally provided with ventilators at high
level for unobstructed distributed lighting. Wherever due to limitation of external wall area or
any other reasons, stipulated area of window/ ventilation cannot be provided, suitable
mechanical devices shall be provided. For Workshop/Warehouse sheds etc. with precoated/corrugated GI roof sheeting etc. suitable monitor may added in provide additional
ventilation.
Blast resistant Control room windows openings through wall may be provided as per OISDSTD 163.
Notes:
Requirements of window/ventilations area as stipulated above is for maximum room height of
4000 mm. For heights more than 4000 mm, additional window/ventilator shall be provided in
the same manner at every work area/platforms at all levels.
Fly mesh shutters shall be provided for windows/ventilators in Kitchen, Pantry, Dining hall etc.
Ventilator shall be able to serve as smoke vents in the event of fire.
Fireproof windows shall be provided as per TAC, electrical, process etc. statutory
requirements.
All windows/ventilators will be glazed, anodized Aluminium window/ventilator.
All glazing on external faces of building shall be toughened glass (5 mm thick).
25.5.7
Canopy/Overhang
RCC/steel Canopy/Overhangs shall be provided at all entrances for rain and sun protection,
accentuation of the entrance and pedestrian movement as per the following schedule:
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 40 of 41
For all offices, control rooms, composite buildings/sheds accommodating offices, canopy shall
be provided at all entrances. Size of the canopy shall be decided based on vehicle parking and
pedestrian movement in addition to aesthetics of the building/shed.
Overhangs shall be provided over all exits. Size of the overhang shall be decided on the
aesthetics of the building/shed subjected to minimum of 1000 mm.
Blast proof Control Rooms shall not have any projections with outer face of its walls except
with false treatment for aesthetics of the building.
25.5.8
Shading Devices
RCC Shading devices shall be provided over all windows, operable ventilators for rain and sun
protection. These devices shall be in form of horizontal projections, vertical projected fins in
addition as per building facade treatment. Minimum projection shall be 600 mm.
25.5.9
Parapet
Parapets shall be of RCC for all buildings with minimum 300 mm high for non-approachable
roof and 1000 mm high for approachable roof.
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 41 of 41
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc
Rev: B
Page 42 of 41
26
Mounded Bullets
There are two separate mounds for storage of LPG & Propylene. One consisting of 3 x 1300 MT
LPG Bullets. & another consisting of 2 x 250 MT Propylene Bullets. The Mounds consisting of
RCC retaining wall on all four sides. Inside the retaining wall sand is filled in layers & LPG /
Propylene tanks are placed on filled sand. The sand is filled over these tanks again. & the top is
stone finished.
P:\Andheri\IndiaProject\256324 HPCL- LPG\10 Procurement\TENDER\07 PEB\Final Tender to be uploaded-24-Aug09\Editable\Annexure - X- Attachments\Civil design basis.doc