Professional Documents
Culture Documents
Launching Technique For The Viaduc de Millau: Tony Brooks
Launching Technique For The Viaduc de Millau: Tony Brooks
Introduction
The Viaduc de Millau is part of the A75 linking Paris with
Barcelona (Figure 1). It is currently the highest bridge in the
world at 343m high with a construction cost of approx 310
million Euros (AUD $525 million). It was opened to traffic
on 17 December 2004, just 39 months after work began.
While this engineering feat set a number of benchmarks
in construction, the purpose of this article is to describe
how the viaduct deck was launched across such a wide gap
between supports. There are a number of articles about the
various aspects of construction of this structure, however
the focus will be on the equipment used to launch the
structure as this method has a broader application to
bridges and structures generally which lends itself to
the launching technique.
Traditionally, one method of launching involves sliding the
bridge deck over PTFE1/polished stainless steel bearings.
However in this case, specially designed hydraulic lift and
transfer units, called translators, controlled the deck launch.
While this technique has occurred before, it has never been
attempted on a project of this size and complexity.
Tony Brooks
Regional Manager Australia and New Zealand
Enerpac
Abstract
The 2460m long Viaduc de Millau in France is a continuous,
eight span cable stayed viaduct symmetrically supported from
seven pylons. The deck has a lightweight steel trapezoid shape
with component parts that were prefabricated offsite with final
assembly on site at the bridge approaches. The deck was launched
in two halves from the north and south abutments, supported by
the permanent piers and temporary piers. The 717m northern half
of the deck and the 1743m southern half, once welded together,
formed a continuous deck structure. The decks were launched in
small 600mm increments with the total distance of each launch
stage being 171m. Maurer Shne and Enerpac manufactured
specially designed translators for the project. Under demanding
environmental and structural conditions, these translators allowed
the launching of a deck structure to be synchronized in such a
way to produce minimal side loads on the very slender support
piers. This launching system is applicable to a wide variety of
industry applications.
Background
This 2460m long cable stayed bridge crosses the Tarn River
and is located 5km west of the town of Millau in France. The
roadway, with two lanes on each side, crosses the river at 270m
above ground. At its highest point, the viaduct is higher than
the Eiffel Tower. Conceived by British architect, Norman Foster,
and designed by French structural engineer, Michel Virlogeux,
this suspension bridge is supported by seven pylons, instead of
the two that are common for this kind of construction.
04&%STANDSFORPOLYTETRAkUOROETHYLENEANDISCHARACTERISEDBYVERYLOWFRICTIONPROPERTIES
Queensland Roads Edition 12, Department of Transport and Main Roads, October 2012
41
42
The sloping base plates of the bottoms of the side box girders
consist of 12mm sheet steel on the greater part of the spans,
and 14-16 mm sheets around the pylons. Longitudinal
trapezoidal stiffeners, 6 mm thick, are fitted at variable centres.
The bottom of the box girder consists of metal sheets of between
25 and 80mm thick. Rigidity is provided by three longitudinal
trapezoidal stiffeners 14 or 16mm thick. Two vertical webs 4m apart
and consisting of metal sheet between 20 and 40mm thick run the
entire length of the structure in order to spread out the localised
forces of the temporary piers during the launching of the deck.
These webs are stiffened on their lower part by two longitudinal
trapezoidal stiffeners. The transverse stiffening of the deck is
provided by lattice diaphragms at 4.17m spacing on the spans.
Queensland Roads Edition 12, Department of Transport and Main Roads, October 2012
Assembly
Translators
Traditionally a launched bridge would be pushed or pulled
into position with the bridge deck sliding over low friction
plain bearings or rollers. However in this case because of the
bridges length and weight, weather conditions, geometry
and height of the piers, a mechanical launching device
called a translator was developed for this project by Maurer
Shne of Germany and Enerpac in Spain (Figure 7 and 8).
By referring to Figure 7 the operation of a translator is
explained in detail.
Figure 5 Launching from the southern end with a single pylon in place.
Queensland Roads Edition 12, Department of Transport and Main Roads, October 2012
43
44
Queensland Roads Edition 12, Department of Transport and Main Roads, October 2012
Figure 8 Two blue translators form part of an assembly during installation (advance cylinders missing).
14,400t. Other less loaded locations used 280t jacks with
a stroke of 300mm. Hydraulic valves are used to make the
different groups of jacks independent of each other to enable
control of the height and angle of the deck.
During the launch, the balance jacks of the two translators on
the same side of the deck are hydraulically linked to ensure
equal pressure is maintained by all jacks on that side of the
deck. This is to allow for variations in longitudinal rotation
of the deck due to deck deflection. This load sharing feature
ensures that the supporting load was evenly distributed over
each pair of longitudinally aligned translators. The translator
jacks on either side of the decks longitudinal centreline
were not normally hydraulically linked as this would create
a virtual pin joint and allow the deck to roll about its
longitudinal axis. As a safety measure, the balance jacks
could be mechanically locked off by a large nut mounted to
each jacks piston.
The outer advance cylinders on each translator have a
positional transducer that indicates the amount of travel.
This allowed the synchronised control of the translators at all
locations via a central computer. The horizontal deflection
Queensland Roads Edition 12, Department of Transport and Main Roads, October 2012
45
Figure 9 Pictorial view of the lifting and advance of the launch nose.
function in a similar manner to a strand jack (1). This system
is comprised of four 270t cylinders with hollow pistons and
205mm of travel. The cylinders work in pairs and transfer the
load to pull bars that fastened to the structure. In conjunction
with Figure 9, a brief summary of the operation of the launch
nose is given below:
1. The launch nose and deck stop short of the translator
assembly on top of a pier (or temporary piers as the case
may be). The translator is in the start position and the
orange column is above the translator.
2. The bar jacks advance and lower an orange column onto
each translator. Further advancement of the bar jacks raise
the launch nose so that its underside and the underside of
the deck are above the advance plate.
3. The raise cylinder on the translator is extended advancing
the blue wedge plate. The full weight of the launch nose is
now taken on the advance plate.
4. The advance cylinder on the translator is now retracted
advancing the deck. This operation must occur synchronously
with all other translators to launch the deck by 600mm.
5. The bar jacks retract the orange column until the launch
nose sits on the launch plate. The orange column is then
lifted clear. The weight of the advance nose is now taken
by the translator.
6. The lift cylinder is retracted which lowers the launch
nose onto the translator cradle. The advance cylinder is
46
Queensland Roads Edition 12, Department of Transport and Main Roads, October 2012
References
1. Chapman C. Strand jacks in the construction industry,
Queensland Roads, Edition 9. Sept 2010.
'JHVSFm-BVODIOPTFkUUFEUPMFBEJOHFEHFPGEFDL
Queensland Roads Edition 12, Department of Transport and Main Roads, October 2012
47