Location
Owner
Subject
: Fabrication Safety Shower and Eyewash for Sulfuric Acid Storage Facility
: MVC Plant Site, Iligan City
: Mabuhay Vinyl Corporation
: BM and Cost Estimates
UNIT COST
AMOUNT
TOTAL
B) LABOR
ITEM NO.
1
2
3
ITEM DESCRIPTION
QTY
Skilled
Semi Skilled
Unskilled
B) LABOR OVERHEAD
ITEM NO.
ITEM DESCRIPTION
1
Skilled
2
Semi Skilled
3
Unskilled
C) OTHER OVERHEAD
ITEM NO.
ITEM DESCRIPTION
1
Equipment Rental
2
Fixed Overhead (7%)
4
Prepared By:
No of Days
1
1
12
12
1
1
No of Days
12
12
QTY
QTY
No of Days
Rate/day
342.00
312.00
269.00
TOTAL
AMOUNT
4,104.00
3,744.00
7,848.00
OH/day
75.24
68.64
59.18
TOTAL
AMOUNT
902.88
823.68
1,726.56
Rate/day
TOTAL
910.56
SUMMARY
Total Labor Cost
Supervision Cost
Profit
Labor Overhead
Other Overhead
TOTAL
12%VAT
TOTAL PROJECT COST
SAY
7,848.00
1,962.00
1,471.50
1,726.56
910.56
13,918.62
1,670.23
15,588.86
15,600.00
Approved:
JVT LIAN
Project Staff
AMOUNT
910.56
ED PAGALING
Sr. IE