LIST OF COMPLETED PROJECTS UNDER ROBERTO Y.

UY ADMINISTRATION
January 1 to December 31, 2014
NAME OF PROJECT

Length

Location

Appropriation

Source of
Funds

Mode of
implementation

Date
Started

Date
Completed

%
Accomp.

Obay

180,000.00

56-00-10-04 /
8751-200-811

Admin.

24-Mar-14

30-Apr-14

100.00%

Obay

105,000.00

8918(1)815

Admin.

26-Nov-13

24-Jan-14

100.00%

Remarks

DISTRICT I - A
POLANCO
1
POLANCO
2

Construction of Reinforced Concrete Pedestal


for Diesel Tank at PEO, Motorpool, Obay,
Polanco, Z.N.
3 Single Phase Lateral Line (2.22 km) Const. at
Purok Saging, Brgy. Isis
4

2.220

km.

Isis

1,429,730.15

20% E.D.F.

Admin.

5-May-14

2-Jun-14

100.00%

1.769

km.

Isis

1,275,565.58

20% E.D.F.

Admin.

10-Mar-14

28-Apr-14

100.00%

Const of Water Supply System, San Pedro,


Polanco

San Pedro

1,120,000.00

8918(4)874

Takay Labor

3-Mar-14

2-Jul-14

100.00%

Const. of 2 sets Portable Batching Plant at


PEO, Obay, Polanco

Obay

170,000.00

8918(2B)230

Admin.

10-Jan-14

20-Apr-14

100.00%

Single Phase Lateral Line (1.769 km) Const. at


Sitio Muguay, Brgy. Isis

Single Phase Lateral Line (1.43 km) Const. at


Sitio Macasawad, Brgy. Isis

1.430

km.

Isis

935,819.77

20% E.D.F.

Admin.

3-Jun-14

18-Jun-14

100.00%

Single Phase Lateral Line (0.3 km) Const. at


Purok Sari-sari, Brgy. Isis

0.300

km.

Isis

193,816.03

20% E.D.F.

Admin.

24-Jun-14

27-Jun-14

100.00%

Single Phase Lateral Line (2.081 km) Const. at


Sitio Palayan, Brgy. Isis

2.081

km.

Isis

1,317,565.91

20% E.D.F.

Admin.

18-Jun-14

24-Jun-14

100.00%

Obay

191,700.00

8918(1)815

Admin.

1-Jul-14

13-Aug-14

100.00%

Maligaya

600,000.00

8918(1)874

Takay Sand

16-Oct-14

7-Nov-14

100.00%

10

Const of Reinforcement Slab Concrete &


Canopy A & B of Fuel Tank @ PEO, Obay,
Polanco
11 Construction of Water Supply System at
Maligaya, Polanco, Z.N.

Completed
(Present
Admin.)
Completed
(Present
Admin.)
Completed
(Present
Admin.)
Completed
(Present
Admin.)
Completed
(Present
Admin.)
Completed
(Present
Admin.)
Completed
(Present
Admin.)
Completed
(Present
Admin.)
Completed
(Present
Admin.)
Completed
(Present
Admin.)
Completed
(Present
Admin.)

You might also like