Professional Documents
Culture Documents
Abstract
The objective of this work is to present a study regarding to solutions for shore approach of offshore pipelines in
Brazilian scenarios. An overview of offshore pipeline installation in Brazil is presented and the developments and
solutions adopted during the last few decades are discussed.
The benefits of HDD as an alternative solution for shore approach of offshore pipelines in Brazilian scenarios are
presented. Of course, the challenges involved in HDD shore crossings are also highlighted.
Issues related to the quality and reliability of HDD projects are discussed. Experiences and lessons learnt from
HDD shore crossings in Brazil are presented and discussed, as well as, critical points in design, planning and executing
these projects.
Introduction
When compared to the pipelaying history from the first developments until the present, the offshore pipelaying
history in Brazil is very recent. This is particularly true when considered pipelines that come to crossing the landfall.
A historical study of the marine pipelines installed on the Brazilian coast lead to the first challenges faced in the
initial phases of the import lines installation. These lines where necessary to supply the refining complex still in
implementation and, in a second phase, at the beginning of the offshore discoveries in Brazil, to ensure the transport of
production to refineries in the country.
Although the Brazilian continental proportion with oil and gas field discovered all over the coast, the Brazilian
pipeline mesh is still very small. However, promising growth potential of that mesh is foreseen for the coming years,
which include pipelines that come to shore. It should be noted that with the no flaring and the gas valorization policies,
which are fully in line with the optimization of the world energy resources, and reduction in CO2 production, the
transportation of the gas associated with the deep water oil fields development, is a new challenge which must be
addressed. In general, deep water fields have been oil fields with associated gas, where the valorization of the gas has
been a secondary issue. This situation is now changing and the demand for gas gathering and gas export pipeline
systems linking deep water fields to onshore terminals and liquefaction plants will increase, making the offshore pipeline
installation and the shore approach solution a critical factor in this process, not only due to technical challenges, but also
due to environmental issues (Silva et al., 2011).
The environmental protection concerns are significantly increasing in Brazil and there are very restrictive
requirements from the environmental agency. These requirements are even more restrictive when related to coastal
zones, for several reasons regarding to fauna and flora as well as regarding to economic activities such as fishery and
tourism. Therefore, all the maximum requirements leading to the minimal impact and potential degradation of these
locations are applied for shore approach projects.
In this context HDD emerges as an alternative method in which the environmental issues can be minimized.
The directional drilling method for performing pipeline crossings of a wide variety of surface obstructions was
developed in the 1970s. Since then, the advantages of the HDD technique have been considered by the pipeline
industry. The technology has been applied as the most environmentally responsible and economical method of installing
pipeline beneath obstacles on many projects worldwide.
______________________________
1
When an export pipeline coming from offshore to onshore facilities is designed a shore approach solution need to
be provided and the shore approach is a very complex project in the offshore pipeline installation. At this phase the
pipeline on-bottom stability is analyzed for surf zone, the possibility of using concrete coating is verified as well as the
necessary burial depth, the pipeline installation stress analysis is performed, the potential for local scour is also verified.
Also in this phase, all the conditions related to the pipeline installation are studied. The installation method is defined,
considering time and preliminary costs, the feasible methods, environmental legislation, regulations and order
requirements from regulatory agencies (such as ANP and IBAMA1) and the Brazilian Navy. The burial technique is also
defined.
The main methods used in Brazil for shore approaches are shown in Figure 1.
The first shore approaches in Brazil occurred in Dom Joo Mar field, at Todos os Santos Bay, in So Francisco do
Conde/BA, Northeast Brazil. Those shore approaches occurred at mud areas, in a region with rocks formations on the
seabed and maximum water depths of 15 meters. Similar shore approaches, in sheltered waters, occurred later in the
Guanabara Bay, Rio de Janeiro, in maximum water depths of 21 meters.
3.1 Dom Joo Mar 1954
The first oil discovery in offshore waters occurred in the Dom Joo Mar field, an area of 47 km2. Two thirds of this
field is under Todos os Santos bay waters. The offshore part of the field was developed in two steps: Dom Joo Mar
North in 1954 with the DJ-129 well, and Dom Joo Mar South in 1955 with the DJ-105 well.
The D. Joo Mar field was not in the open sea. Its geographical constitution had typical sheltered waters
characteristics, surrounded by mangroves and protected from oceanic influence by a natural coastline. There were no
beaches, or surf zone waves, only small waves caused by winds or high speed vessels. Meteocean and environmental
characteristics very different from an offshore field, as it is known today. The first pipelay operations in the Todos os
Santos Bay sheltered waters, had neither detailed studies for installation nor well-defined criteria for projects. There
were no criteria, for instance, for on-bottom stability calculations, mechanical design, routing selection or free spans.
The most important thing at that time was to support the production, providing the required flow rate from the start point
to the target point. Initially, these pipelines had neither concrete coating nor anticorrosive coating. These pipes were the
same type used in drilling wells, they were threaded onboard without protective coatings. In the early 70s, just after
some pipes began to present pitting damages, nearly two decades after installation, the replacement of these pipes have
started, at this time a protective epoxy coating was used. After that, other materials were also used as anticorrosive
coatings.
3.2 REDUC / Ilha Dgua / Pier Principal and Ilha Dgua / Ilha Redonda 1961
The historical documentation of submarine pipelay operations in Brazil points to the construction, in 1961, of
pipelines from the Duque de Caxias refinery, in Rio de Janeiro, to the interconnection at the Ilha Dgua, where the gas
and the crude oil were imported for refining, and, subsequently, the sub products of the refinery processes were
exported, Figure 3.
4
In the Brazilian offshore scenario, this idea came from Shell, in joint venture with Petrobras in 1990. There were
times of high risk contracts and the two companies worked together after the discovery of the Merluza field in the Santos
Basin, So Paulo.
4.1 Merluza shore approach, 16 Praia Grande / SP 1990/1991
The consortium Petrobras and Pecten (Shell) provided the first application of this installation technique for shore
approaches in Brazil. It occurred on the coast of Santos, So Paulo state, during the construction of a 16, 212 km long
gas pipeline (PMZL-1 / Praia Grande). The sore approach project (1200m) came from IntecSea (1989), and the pipeline
was launched by Castoro VIII, Saipem.
This first HDD for shore approach in Brazil came to fulfill the need of crossing an extensive beach area with
shallow water, clay soil and high marine traffic (in the route of vessels to the Santos Port). The preliminary survey, two
shallow holes, indicated a sandy soil in the average depth of the drill path.
The first bore hole, started from shore to sea, had a very shallow drill path, just following the coast topography
with 4 to 5 meters depth of cover. After 500m of drilling pilot hole mud came up on the beach and was abandoned after
numerous unsuccessful attempts with additives (mica and crushed shells).
The second bore hole was started and due to high torque to rotate the column a tripping out of the column was
necessary and a 10, 156m in length casing was installed. This high torque motivated a discussion regarding to change
the punch-out but there was no agreement between all parties and the operation continued. After punch-out, a reamer
was connected to start the back reaming and the pullback operation simultaneously. The very high torque needed to
rotate the 1200m column and reamer during this operation caused a column break at joint 32 from the probe.
Unfortunately, all attempts to remove the column have failed and part of the pipeline and almost the entire drill string
was lost.
The third bore hole was started using a new column. At the punch-out, with a 800m pilot hole, it was connected a
22 reamer on the drill string and a barrel reamer at the product pipe end, once again to try a simultaneous back-reamer
and pullback from sea to shore. During pullback, the product pipe got stuck because the column break. At that point the
pipeline was crossing the beach at a depth of 5 to 6m, near the low tide line. A cofferdam was built to find the pipeline
pull head, a tie-in was performed and the pipeline was continued in a 3m depth trench to shore.
6
Figure 8 HDD at Cacimbas beach, drill rig onshore and at the support barge.
This project presented several problems: at first, the punch-out point occurred far from the planned target area.
Therefore, a new pilot hole had to be performed. The second bore hole collapsed during the reamer phase, and tools got
stuck but could be recovered. After that, a third bore hole was started. The third bore hole followed the planned path and
reached the target area. Even so, due to the bad weather and long time waiting for better conditions, the opened hole
started to collapse at the exit point. The exit point was partially repaired and the pullback operation was started. During
the pullback operation, the drill column and product pipe got stuck. It occurred remain only 300m to complete the
operation. With approximately 300 m of drill column and about 900 m of the product pipe inside the hole, numerous
efforts to release the entire column were considered, including the use of a big hammer at the offshore side to kick the
pipeline tail. In this scenario, at the same time that the shore rig pulled the column, the offshore rammer was used,
unfortunately without success. With the columns (drill column + product pipe) still stuck, there was also a new attempt
7
There are several advantages of the directional drilling installation method over alternative construction methods.
Environmental issues are minimized as operations are limited to relatively small areas when compared to the complete
crossing length as in other methods.
HDD provide an optimum depth of cover in the design of a crossing leading to maximum protection for the
pipeline from anchors and future dredging and reduces long-term maintenance costs. Beach erosion risks are minimized
and construction activities in surf zones can be avoided.
However, HDD is a very complex procedure not well understood by most contractors. Only few companies have
the required competence in this procedure. The experience the lessons from previous projects can be decisive for a
successful operation.
The main lessons that can be learnt from previous HDD shore approaches in Brazil are: there is mandatory a
detailed site investigation including geophysical, geological and geotechnical studies to proper understand the soil
characteristics. It is necessary to provide compatibility between geological and geotechnical investigations
(identification of soil discontinuities, fractures and features of the site). It is also mandatory to have complete and
detailed plans and procedures, including contingency scenarios. Attention shall be given to some issues in the design
phase: definition of important parameters, such as, bending radius, pipe stress analysis, equipment selection, geometry
and shape of hole, tracking and surveying, available equipments at the support barge, diving team, pipeline on-bottom
stability, risk analysis, etc. (Silva et al., 2009)
Sea states must also be considered in the planning for pipe fabrication and handling procedures. Tidal currents can
jeopardize a poorly stabilized or inadequately protected pipestring. For large diameter pipelines, the inherent
buoyancy of the pipe requires that special attention be applied to provide stability prior to installation and secure
handling during the pullback operation.
The submerged weight of pipe in seawater is an important consideration. The submerged weight was sufficient for
on-bottom stability during lay and handling during the HDD operations. The buoyant weight of the pipeline in the
drilled hole is also a determining factor for pull force requirements and rig selection.
The logistical challenges associated with working in remote HDD locations are similar to those encountered on
shore approaches. Planning of the work and maintaining contingencies become very important processes.
A mechanical failure or delay during the pullback operation can be catastrophic. For shore approaches remedial
measures are generally more limited than those available onshore. As is always the case, the possibility of
recovering from a "stuck pipe" situation greatly diminishes with time. In a marine environment where currents or
tidal movement may be acting at the exit point, the time factor is of great importance since silting action is an
added risk.
There is no easy fast way to tackle rock formations. The task need to be performed using good quality tools in a
patient and controlled drilling operation. The initial increased outlay will nearly always be offset by the savings
through superior penetration rates, less tripping and decreased risk of tool failure (and subsequent fishing time).
It is impossible to prepare for every occurrence in a drilling activity. However an ability to quickly react in order to
change adverse conditions is vital. With this general thought in mind, brainstorming sessions during the planning
stage can often save time when a particular occurrence takes place.
Regarding to environmental matters, the licenses and permitions to work issues need to be considered in the
schedule. The licensing process in the oil segment consists of several stages. For each project, several licenses are
necessary, a Preliminary license as well as Installation and Operation licenses, to be issued the regulatory agencies. In
shore approach projects, there are always a municipal, a state and one or more federal agencies involved, acting in its
coverage area, whether onshore or offshore, according to the law. The project should estimate and considered the time
to obtain such licenses, based on the legislation and the complexity of the project. In some cases, additional studies can
also be required by such agencies prior issue of environmental licenses, which can cause a delay to the project.
Final Remarks
The HDD has the advantage of causing minimal intervention and disturbance at the beach when compared to other
alternatives to shore approach. It requires, however, some characteristics of the seabed in order to allow the necessary
marine operations. The HDD utilization in the Brazilian coast is increasing. Moreover, studies of on-bottom stability
associated with lift and drag forces acting on the pipelines as well as thermo-mechanical studies related to HT/HP
pipelines have pointed to important issues leading to the scenario of using horizontal directional drilling to cross the surf
zone due to the guarantee of stability and protection of the product pipe.
As discussed in this work a horizontal directional drilling shall not be started without an appropriated investigation
of the site. The selection of this method should be done only after the complete understanding of the geophysical
correlation with the geological and geotechnical data (with precise description of the different structural discontinuities,
associated fractures and features of the investigated area), to properly support the horizontal directional drilling design,
planning and execution.
Site investigation is the best investment in a HDD project. These investigations enable a suitable design for the
HDD profile. Of course, as any other method, to ensure a successful installation, a detailed procedure shall be prepared
for the operation, complying contingency procedures for all phases of the operation. And in general, when problems are
identified it is often too late to initiate corrective action.
Besides all potential problems, risks and challenges, HDD is foreseen as a very suitable and attractive method for
future shore approaches in Brazil.
References
Bernardi, T.P., Neto, V.A., Siqueira, J., 2009, Shore Approach of Camarupim Pipeline. Rio Pipeline Conference &
Exposition 2009, Rio de Janeiro, Brazil.
Duyvestyn, G., 2005, Design and Construction Challenges for HDD Shore Crossings. Proc. of No-Dig Conference,
North American Society for Trenchless Technology NASTT, Orlando, Florida, USA.
Silva, D.M.L., Souza Jr., H.A., DAngelo Aguiar, L.A., Souza, A.P.F., 2011, Challenges on Designing Pipelines for the
Brazilian Pre-Salt Scenarios. Rio Pipeline Conference & Exposition 2011, Rio de Janeiro, Brazil.
Silva, D.M.L., Rodrigues, M.V., Vens, A., Medeiros, A.R., 2009, Methodology for Definition of Bending Radius and
Pullback Force in HDD Operations. Rio Pipeline Conference & Exposition 2009, Rio de Janeiro, Brazil.
10