You are on page 1of 4

QUANTITY CALCULATION OF PEIR

CUTTING EDGE:
Unit weight of steel=7850kg/m3
Inner perimeter=3.14x5.65
=17.74m
Angle section according to IS:800 chosen in case of the
cutting edge
130x130x10
Now from steel table the weight for this angle
section=19.9kg/m
Total weight along the inner
perimeter=17.74x19.9=353.0459kgs
External perimeter=5.665x3.14=518.1kgs
Spacing between bars=250mm
=17.78/.250
=71 bar
So the 71 bars are used in the bottom of the cutting
edge.
Weight of the bars=.5x.130x.130x.010x71x7850
=47.750kgs
Total weight of the bars=(353.0459+47.750+518.1)
=918.90kgs
Rate of one metric ton=80000

Rate of one cutting edge=80000x.91890


=73450
Rate of four abutment=4x73450=294160

QUANTITY CALCULATION OF THE BOTTTOM


PLUG
PHOTO
Volume of the first part=3.14x3.7^2x300
3.22m3
Volume of the
frustum=1.2/3(3.14x18.5^2+3.14x2.85^2+
(3.14^2+18.5^2+2.85^2)^1/2)
=46.23m^3
Volume of third part= 3.14x.942[.818+.14]
=4.04m3
Total volume of the bottom plug
=46.23+3.22+4.04=53.49

QUANTITY CALCULATION OF THE WELL


STEINING
External diameter of the well=5.65m
Internal diameter of the well=3.7m
Height of the well steining =16.90
Perimeter=3.14/4[5.5^2-3.7^2]
=12.96m^2
Total volume of the well
steining=16.90x12.996=219m3
WELL CURB
= [.975x.300+(.6x.975)]x3.14X5.625
= 15.49m3
QUANTITY OF PEIR PHOTO
=3.14X2.0^2X5.385
16.90M3
QUANTITY OF PEIR CAP

=[.750X8+.750X2.9+2.2X.750]X2.8
=27.51M3
6 nos. of braket in a single peir
Volume of
brakets=6x.750x.750x.350=1.1025m3
Total volume of peir+ foundation+ peir cap+
cutting edge=335.04m3
Weight=335.04x25
=8376KN/m3
=8376X1000=8376000N
Total weight one peir =853 TON