Professional Documents
Culture Documents
PROJECT 1
1.1 BRIDGE
A bridge is a structure providing passage over an obstacle without closing the way beneath. The
required passage may be for road, a railway, pedestrians, a canal or a pipeline. The obstacle to be
crossed may be river, a road, railway or a valley.
So there is bridge proposed over lahru nallah. Lahru bridge falls on a new connectivity to village
lahru through road named as Nanikhad to Lahru having length 1.300 km. This proposed bridge
plays a very important role in this connectivity because there is no alternative available for the
people of that area to approach the state highway.
A Bridge is an important structure in the transportation system , as its capacity governs the
capacity of the system , its failure or defective performance will results in serious disruption of
traffic flow and also cost per km of bridge structure is many times that for the road or rail track
on either side of the bridge. Therefore it is very important to devote special attention in design to
ensure adequate strength and durability, consistent with safety and cost.
1.3 ABUTMENT
An abutment is the substructure which supports the superstructure of bridge and at the same
time, laterally supports the embankment which serves as an approach to the bridge. Bridge
abutment can be made of masonry, plain concrete or reinforced concrete.
So here we have design the plain cement concrete abutment:
An abutment generally consists of the following three distinct structural elements:
(a) Breast wall
(b) Wing wall
(c) Dirt wall
LOCATION OF PROJECT 1
Proposed bridge is located in link road Nainakhad to Lahru km 0/00 to 1/300 at RD 0/185, falls
in sub division BANIKHET Division DALHOUSIE , HPPWD DALHOUSIE, District
CHAMBA (H. P.)
Location of bridge in relation to the alignmemt of the approaches and good bridge site:
As the span of proposed bridge is less than 60m, so alignment of approaches governs the
location of bridge.
HFL = 917.50 m
OWL=914.30m
LWL= 913.80m
Linear water way at HFL (L) =11.60m
Nallah bed slope =1 in 5.396
Allowable safe bearing capacity =50 Tonne /sq.m
Seismic zone: V
Silt factor ( Ksf) =9.37 [ 1.76 times the square root of partical size
in mm]
S = Slope of stream
R = hydraulic mean depth in m.=wetted area in m2/wetted perimeter in meters
FIG. 1.22
DISCHARGE SUMMERY
Discharge at Bridge Site
384.88 cumec
Discharge at 50 m Upstream
375.34cumec
360.92cumec
366.71cumec
Discharge at 50 m Downstream
384.06cumec
349.82cumec
379.11cumec
Maximum Discharge
384.88 cumec
=
1.30 X 384.88 = 500.34 cumec[ For catchment area
below 500 Sq.Km. Design Discharge must be increased by
30% as per IRC:78-2000]
Founding Level
Deck level
= 921.00 m
Deck slab
Cantilever portion
Footpath, if provided, kerbs and handrails
Longitudinal girders
Cross beams
Wearing course
Figure 2 showing the standard cross section of 13.75 T- Beam Bridge having 4.25 m carriageway
LIVE LOAD ON SUPERSTRUCTURE:
According to IRC : 6-2000 CLAUSE 207.4, when the carriageway width is less than 5.3 m
then the loading to be operate on bridge is one lane of Class A
FIGURE4 Showing the placement of loads of CIASS A TRAIN for maximum Reaction.
SELF WEIGTH OF ABUTMENT AND BACKFILL :
The design of abutment is performed by assuming the preliminary dimensions of abutment
section depending on the type of structure, substructure and foundations and checking for
stability against overturning, base pressure and sliding.
TABLE NO. 2 Calculation of quantity of self weight and backfill, lever arm, moment about toe
is given below:
Longitudinal forces due to tractive effort and braking action of vehicles: as per IRC 78:
2000
Longitudinal forces are caused in the road bridges due to any one or more of the following :
(c)Longitudinal force due to friction at bearing level: As per IRC 78 : 2000 CLAUSE 706.2
At fixed bearing : Fh/2 + (Rg + Rq) or Fh - (Rg + Rq) whichever is more
At free end : (Rg + Rq)
Where : Fh = braking force
Rg = dead load rexn
Rq = live load rexn at free end
= coeff. of friction ( For ex. sliding bearing of steel on cast iron or steel = 0.50
)
Here we are using fixed bearing at one end and free bearing at other end : therefore
maximum frictional force comes out to be at fixed end
Frictional force at bearing level = 8.64/2 + 0.50 (50 + 11.72) or 8.64 0.50 (50 + 11.72)
= 35.18 tonnes or -22.22 tonnes (so value taken is 35.18
tonnes)
This force acts at 11.96 m above the base, therefore moment about base:
Moment(Mh) = 35.18*11.96 = 420.75 Tm
Ft&s = (10*50) 100 = 5 tonne having lever arm w.r.t. base equal to 11.96m
Moment (Mt&s) = 5*11.96 = 59.80 Tm
For the purpose of determining the earthquake force, the Indian codes like IRC : 6-2000 and IS :
1893-2002 etc divide the country into four zones designated as zones II to V . The classification
Zones I used in the earlier versions of the codes has now been dropped, meaning that no area in
the country is considered free from earthquake.
Here bridge so proposed falls in the zone V so allowance should be made in the design for
the seismic force, both components of seismic force horizontal and vertical acting
simultaneously.
The horizontal seismic force (Feq) to be resisted may be computed from equation
Feq = Ah ( G + La )
Where G = dead load above the section considered
La = appropriate live load under seismic condition
Ah = horizontal seismic coeff.
= (Z/2)(Sa/g)/(R/I)
Z = zone factor taken as 0.36, 0.24, 0.16 and 0.10 for zones V, IV, III AND II respectively
I = importance factor, taken as 1.5 for important bridge, and as1.0 for other bridge
T = Fundamental period of bridge member, in seconds, for horizontal vibrations
R = Response reduction factor, taken as 2.5
Sa/g= average response acceleration coefficient for 5% damping depending on T
In the absence of calculation of T for small bridge, the value of Sa/g is taken as 2.5
FOR small bridge : the value of Ah generally taken as 0.15
THE VERTICAL SEISMIC FORCE IS TAKEN HALF THE HORIZONTAL SEISMIC FORCE
Therefore Moment due to horizontal seismic force about the base = 6507.228 kNm or 650.72
Tm
Moment due to vertical seismic force about the toe = 2601.61 kNm or260.16 Tm
NOTE : see table 2 for details of horizontal and vertical seismic forces and their respective
moment
S.No.
Description
Seismic Consideration
Against Overturning
1.50
Against Sliding
1.50
1.25
WITHOUT SEISMIC CONSIDERATION: For span loaded condition:(a) Check for overturning:
Mv = 200 +125.92+3149.20+965.82+64.03 = 4504.97Tm
Mh = 420.75 +59.80+1271.70+245.07 = 1997.30 Tm
FOS = Mv/Mh = 2.26 > 2.00 HENCE OK
WHERE Mv is total moment due to vertical force about toe
Mh is total moment due to horizontal force about base
Location of resultant from toe :
X0= (Mv M h)/Total Vertical force(V)
= (4504.97 - 1997.30)/ ( 811.66+50+31.48+10.14) = 2.78m
Eccentricity of resultant :emax = B/6 = 8.00/6 = 1.33
e = B/2 X0 = 8.00/2 2.78 = 1.22 < 1.33 HENCE OK
HENCE OK
Pmin = 903.28/(5.15*8.00) *[1-6*1.22/8.00] -[31.48*0.825/(5.15*8.002)6]
= 1.39 T/m2 > 0
NO TENSION
WITHOUT SEISMIC CONSIDERATION: For span unloaded condition:-