Professional Documents
Culture Documents
PMC For Projects
PMC For Projects
501+
Introduction
...
...
244
2.
...
...
245
3.
...
...
247
4.
...
...
249
5.
...
...
256
6.
Contract Condition
...
...
258
7.
Cost Variation
...
...
259
8.
...
...
263
9.
...
...
264
10.
Trial Stretch
...
...
265
11.
...
...
266
12.
Cash Flow
...
...
266
13.
...
...
266
14.
Fulfilment of Objectives
...
...
267
15.
...
...
267
SYNOPSIS
This article on Highway Construction Management has been written to bring
forth the actual problems connected with Highways Project of large size with illustrations
from one of the packages of Golden Quadrilateral Delhi-Kolkata Section. Efforts have
been made to indicate in this Paper, the necessity of in depth review of DPR, Correlate
the field conditions with provisions of DPR to minimize the possibility of complications
of delay, claim, arbitration and other eventualities due to inconsistent/erroneous
provisions and effect cost economy without detriment to specifications.
+ Written Comments on this Paper are invited and will be received upto 31st December
2004.
* Resident Engineer, Meinhardt Singapore (Pte) Ltd., Allahabad.
244
SHARMA ON
1. INTRODUCTION
This article is related to Project Construction Management of Large
Highways Packages. Observations gained out of construction scenario going
on in Golden Quadrilateral (GQ) Delhi-Kolkata (D-K) Section of NH-2 with
special reference to contract package III-A (km 115.000 to 158.000) have been
taken for all references. Construction Management is an art of blending progress,
quality and cost of project to set target/standard/financial ceiling. Devoid of
any of the tri-lateral objectives is defeating construction philosophy. Progress
inter-alia time is immediately transparent but quality has hidden aspect of
durability which is not immediately exhibited from present indication. Cost has
also incidence of claim/arbitration taking its toll afterwards. Skill of Construction
Management lies, therefore, in formulation of correct orientation of construction
philosophy, enforcing testing & quality system and interpreting contract/
specification clauses to meet the above objectives in short & long term.
Highway construction has distinctive role of managing varied engineering
discipline like, Hydrology, Mineralogy, Geotechnology, Concrete Technology
for structures and pavement, Asphaltic concrete, foundation & Bridge
Engineering, Mechanical faculty of planning big plants/equipments,
Environmental management, Safety measures, Accounting, Computerisation of
design/drawing/reporting/billing/correspondence, Personnel and procurement
management and so many other things. Besides, spread of work on a longer
length, Highway construction management has a difficult job in organizing
different activities compared to other construction project located at one
place.
Construction/Contract Management should, therefore, essentially start
with referring to and studying the, Detailed Project Report (DPR), Contract
Drawings, Survey Data, Contract Documents, Quality Assurance Plan (QAP),
Specifications and to analyse data/provisions/conditions for their total
coherences. Simultaneously field reconnaissance has to be made to link up the
conformity of DPR stipulations with site condition.
For fulfilling aforesaid responsibility, persons entrusted with the task are
called upon to look into project/contract document very analytically/critically in
order to avoid/eliminate all possible factors likely to cause delay, public
inconveniences & unwanted cost/claim. With this end, descriptions made in the
following chapters have been presented to acquaint with the actual problems
encountered while dealing with Highway Construction management. The thrust
of this article is, therefore, to bring forth with actual field problems instead of
theoretical matters with graphs/equations. In this exercise, there may be a few
errors/inconsistencies. Learned readers will not mind.
OF
245
Rigid Pavement
3000 m
4%
2.5%
3%
1000
8750
8750
4%
2.5%
3%
Soft Shoulder
Soft Shoulder
Bituminous Carpet
Pavement Quality Concrete
Drainage layer
Granular sub-base
Subgrade
Subgrade
127
Kanpur
Rigid
Legends:Rigid Pavement
Flexible Pavement
148.140
Alld.
148.140
147.640
158
144
138.200
139.585
129.400
130.400
Kanpur
Crusher
Plant at 122
157.05
156.45
150.5
150.0
146.00
Saini
139.6
Ajuha
Kokhraaj 158.000
Junction of IIIA &
Allahabad by pass
WMM
Plant at 154
Kalyanpur
138.0
130.8
129.200
127.00
Flexible
115
Rigid
Gulamipur
Rigid
143.00
Khaga 115.000
Junction of IIC & IIIA
Malka
Rigid
Hot Mix Plant &
Camp Office at 142
Legends:Rigid Pavement
Flexible Pavement
157.05
156.45
150.5
150.0
146
143
138.0
139.6
129.200
115
130.800
Alld.
246
SHARMA ON
NHAI Chairman
Supervision Consultant
CGM
Team Leader
PIU
Project Director
Site Office
Resident Engineer
Highway
Engineer
Bridge
Engineer
Material
Engineer
Survey
Engineer
Quantity
Surveyor
Environment
Officer
OF
247
Actual achievement indicates wide gap with respect to target and leads to
inferences of either lack of seriousness for implementation or theoretical
approach being adopted in framing/approving of program ignoring or
under-estimating ground realities knowingly or inadvertently. This is not
only the case of one package III-A but almost all the packages have the
same condition rather even worse than III-A Table 3(a).
(ii)
(iii) Working site & decisions are not made available in advance.
(iv)
(v)
(vi)
248
TABLE-1. DETAILS
OF
Sl.
No.
Contract Name
Length
in km
Employer
Design
Consultant
Supervision
Consultant
Contractor
1.
Package II-A
61.6
NHAI
Sevedrup
BCEOM
ITD-SDBCJV
2.
Package II-C
77
NHAI
3.
Package III-A
43
NHAI
Meinhardt
Singapore
(Pte) & Quest
International
IRCON International
4.
Package III-C
72
NHAI
do
do
5.
Package IV-B
45
NHAI
Cowi - Span
ICT
LG
6.
Package IV-D
40
NHAI
do
ICT
Oriental
7.
Package V-A
60
NHAI
Ghereji - Dosctt
SMEC
Oriental
8.
Package V-C
78.5
NHAI
do
SMEC
PCL
-do-
Centrodorstroy, Russian
SHARMA ON
477.5 km
-do-
OF
OF
WORK PROGRAM
OF
III-A
249
14.2 R1
Cumulative
Achievement
Sl.
No
Period
Cumulative
%
Mar 01
0.20
0.00
June 01
0.90
0.00
Sept 01
1.40
0.00
Dec 01
8.60
0.27
Mar 02
26.60
June 02
36.10
Sept 02
40.80
3.67
3.70
3.83
Dec 02
59.10
22.14
11.35
11.23
Mar 03
77.80
47.91
19.16
19.37
10
June 03
85.10
73.17
29.57
28.67
11
Sept 03
87.30
87.02
36.28
30.82
12
Dec 03
96.60
100.00
60.38
41.05
13
Mar 04
100
78.69
59.06
14
June 04
95.54
1.04
2.24
2.24
2.97
Sl.
No.
Consultant
package
number
Contract Name
1.
TNHP/SC/1
2.
TNHP/SC/2
3.
TNHP/SC/3
OF
CONSTRUCTION
Length
km
TIME AND
PROGRESS
End
61.60
77.00
March01
April01
Aug.04
Oct.04
87.80%
83.30%
44.59%
14.93%
43.00
72.00
Feb.01
April.01
Feb.04
Oct.04
105.55%
83.30%
59.06%
25.34%
IVB km 65 to 110
IVD km 140 to 180
45.00
40.00
March01
March01
March04
March04
100%
100%
30.35%
52.12%
Total
338.60
Period Quarterly
TNHP
Progress of Package
II A
June02
Sep.02
Dec.02
March03
June03
Sep.03
Dec.03
March.04
OF
% Progress
achieved
as on 31.3.04
SHARMA ON
Start
% Period
elapsed as
on 31.3.04
No.
1.
2.
3.
4.
5.
6.
7.
8.
TNHP
Completion Period
OF
250
TABLE-3(a). D ETAILS
II C
III A
III C
IV B
31.68
33.12
42.06
53.53
64.12
69.06
77.31
91.22
7.90
11.30
16.20
22.63
28.28
32.12
38.14
44.59
6.53
10.11
24.90
39.32
48.83
60.97
74.74
84.03
1.40
1.89
2.63
4.07
6.94
9.04
12.59
14.93
2.24
3.70
11.32
19.13
29.54
36.25
60.35
78.66
2.96
3.88
11.22
19.36
28.66
30.82
41.68
59.06
1.87
7.74
22.98
40.2
49.67
68.20
75.81
1.79
3.24
6.04
13.67
16.94
21.15
25.34
9.86
9.86
26.76
42.78
59.59
59.59
73.41
88.34
7.03
7.86
9.40
13.99
17.88
20.20
23.00
30.35
OF
251
Recommendation of raising road level from 122 to 125 [Sl 1.1] was
reasonable but it failed to consider the identical problems of adjoining
km. Besides it had no back-up of any HFL/water level consideration. This
TABLE-4. R ECOMMENDATION & DECISIONS
Item
No.
Decision of NHAI
1.1
2.1
2.2
7.0
11.1
13.1
Accepted
14.1
Accepted
Accepted
Accepted
252
SHARMA ON
It did not deal with the problem of flexible pavement, culverts and general
road profile. These were taken care of subsequently.
4.2. Subsequent Review and Changes by Client/Supervision
Consultant
4.2.1. Review of road level: The finished Road Level (FRL) for New
Carriageway (NCW) had been decided principally to match with the existing
road level which was practically either at ground level or only about 30 to
40 cm above. This was not at all adequate for giving specified free board. Rather
subgrade layer was falling below ground level. This was tending to be unsound
pavement design of placing new lanes rigid pavement on subgrade/drainage
layer lying in wet/saturated zone. IRC:37-2001 provided minimum free board
of 60 cm from bottom of subgrade in stead of from top of Subgrade adopted
previously. This point was actively taken-up by supervision consultant during
the site visit of Chief General manager (CGM) in the month of Nov.2001 who
was convinced for providing FRL to take care of free board. In this context
instruction was issued by CGM to revise FRL to incorporate provision of IRC:372001 for free board. This led to refixation of FRL in supersession to Road
Level approved in contract drawing. The burden for refixing the FRL was
entrusted to Supervision Consultant (SC). This exercise was taken up and FRL
of entire road was modified/approved. This decision had far & wide effect in
project worthiness. At the same time it caused quantity push. Provision of
embankment soil in DPR/BOQ was totally unrealistic to only 72,244 m 3 on
assumption of av. 10 cm. filling on side land which remains lower to ground
level due to taking out soil for repair/maintenance of road. This was not enough
to compensate even the clearing/grubbing quantity. Provision of embankment
quantity of DPR was thus imperative to be revised. Variation in quantity to
5,22,000 cum has to be, therefore, considered against, provision of 72,244 m3.
4.2.2. Review of rigid pavement to flexible km 115 to 127: In view of
preponing completion schedule to December 2003, contractor proposed for
change in Rigid Pavement to Flexible Pavement in Right Side km 115 to 127. It
was accepted in principle and detailed proposal was asked from contractor.
This was submitted by Contractor and was examined by SC and reviewed by
client. After analyzing all the points and its cost implications, flexible pavement
composition on CBR of 5 per cent and traffic intensity of 150 msa was approved
OF
253
DBM 300 mm
Overlaying
Widening
BC 40
Selected
Soil
WMM 300 mm
DBM 260
GSB 300 mm
WMM 320
Subgrade 500 mm
GSB 450
DBM 300 mm
WMM 320 mm
GSB 460 mm
Subgrade 500 mm
BC 50
Selected
Soil
DBM 170
WMM 250
GSB 300
Subgrade 500
Overlaying
DBM 130
BC 40
Widening
DBM 300
Selected
Soil
WMM 250
GSB 200
Subgrade 500
as
254
SHARMA ON
Cover 50 mm
Main Carriageway
Mild Steel
Railing 1.2 m High
Main Bars
16 mm 100 mm
Vertical Bars
16mm 300 mm c/c
4% 4%
250
Main Bars
14 mm 150 mm
10 mm Distr. Bars
200 mm c/c
500
16 mm 100 mm c/c
300
150
Retaining
wall
Cross-Section
10 mm Distr.
Bars 250 mm c/c
Main Bars
16 mm 100 mm c/c
2000
200
50 x 6 Flat Steel
M-15 Concrete
6 mm dia bar
150
200
800
2000
75
150
Hume Pipe
425
300
Elevation Detail
OF
255
BOQ item no. 5.(46) incorporates rate/m for M.S. prefabricated mesh
fencing for 18000 m@ Rs.1127/= per meter for total value of Rs. 20.556
million. Again item no 7.02 (a) to (d) provides concrete quantity to be
paid in cum valued for Rs. 65.112 million for length of 18000 meter.
Logic of Retaining wall in 18000 metre and again provision of railing
with foundation shown over retaining wall is not understandable. Further
the operational problem was not at all taken into consideration while
incorporating items in contract. To avoid the above problems, solid
separation barrier was thought befitting to be provided in view of site
conditions and cost effectiveness as well.
4.2.5. Drains: Contract drawing indicated below Figs. 8 (a) & 8 (b)
provided trapezoidal section of reinforced concrete for length of 18,000 m on
linear meter basis. Reinforcement details are not clear. 6mm rod was also
indicated as main reinforcing bar. Contractor suggested for change in shape of
drain from trapezoidal to rectangular in view of working facility, and also to
decrease the land requirement which is too tight in market area.
12 mm T @ 100 c/c
8 mm T @ 200
1500
12 @ 200 c/c
12 mm T @ 200 c/c
1000
150
100 150
8 @ 150 c/c
RCC (M15)
4-8 T on each
800
50
6 mm @ 300 c/c
800
50
50
100
8 mm T @ 300 c/c
550 mm Hounch
100 Crushed
Granular Material
700
250
6 mm @ 200 c/c
600
600
8 mm T 150
12 @ 100 c/c
8 mm T 150 c/c
38T
256
SHARMA ON
4.2.8. Bridges & culvert: D.P.R. for Bridge & Culvert was lacking in
giving clear details and conclusive findings about reconstruction/repair/retention
amongst existing 62 number culverts. Quantity provided in BOQ was neither
clear nor realistic and repair suggested was all the more unpractical for small
box culverts at 60 locations. Treatment of Fusion Bonded Epoxy Coated
[F.B.E.C.] steel costing Rs. 51.08 lakh was also provided in BOQ for repair.
Measures suggested for widening by dismantling wing wall and then
reconstructing narrow strip of abutment & slab and wing wall was neither a
good technical solution nor practical step. Repair of cracks, leached spalled &
honey combed concrete surface including exposed steel and other infirmities
were suggested by injection of epoxy resin, guniting cement mortar with
compressor in small culvert of about 2 m x 2 m size without considering the
complexity of carrying out such small works at various locations. Invert level
of existing culvert had undergone vast changes with respect to local levels.
Under such site condition and practical problems, it was examined with cost
analysis, working problem, durability aspects and was found much more worth
to reconstruct the existing culverts than to repair & keep in weak condition.
With exercise made on above line, it was found that the cost of fresh construction
of culverts on left and right side remain within budgetary ceiling after taking all
plus & minus fluctuations related to Bridges & Culverts work.
Drawing for box culverts were not furnished separately for each culvert.
Instead, a statement giving box thickness & reinforcement for different sizes
were supplemented. Construction work in field can not go with statement but it
will require drawing with every minor details duly approved & authenticated.
In the event, drawing for each box culvert has to be framed, checked and
approved after working out details from statement with needed inter/
extrapolations.
5. QUANTITY REVIEW BY SUPERVISION CONSULTANT
OF
257
Earthen shoulder
330 mm PQC
150 mm DLC
200 mm DL
12.61 m
500 mm Subgrade
13.61 m
Qty in thousand m
18 km. length is over and above. The total quantity thus comes to 477,358 cum.
As against this quantity, provision in BOQ stands for only 117,854 m 3. Similar
is the instance importantly in embankment, DL/GSB as indicated in Fig. 10.
5,22,000
4,77,358
3,04,086
204,615
1,17,854
72,244
Work items
Fig. 10. Quantity fluctuation
258
SHARMA ON
only. When the required CBR value for pavement as per design was 5 per cent
against which as per contract condition soil having minimum value of 6 per
cent is to be used, necessity of cement modified soil for increased value of CBR
is not established. In this view, the provision of cement modified soil was not
favoured which was financially also not beneficial with rate of Rs. 273/- per
cum against soil Subgrade of Rs.117/- per cum. This item of 50,486 cum was,
therefore, not activated resulting into substantial saving.
5.3. Loosening/Re-compacting (L/R) Subgrade with 10 per cent
Sand
BOQ item (2.05) is related with L/R with 10 per cent sand [quantity 44,833
cum] with rate of Rs.74/- per cum. CBR of soil of existing layer to be loosened
and re-compacted was tested out and was observed to be more than6 per cent.
As CBR of virgin soil to be loosened and re-compacted is found itself more
than required, necessity of operating this item was not considered worth and
was deleted. The rate of loosening/recompacting without sand was freshly
analysed and decided at Rs.33.97 per cum which goes in appreciable saving.
5.4. DPR provided two number of subways for pedestrian crossing. The
operational functioning of subway was dependent on pumping of accumulated
water and electric supply for all the 24 hours. These two things are impractical
to be achieved at such small places. Maintenance of such subway was thought
totally impractical. This was, therefore, deleted. The BOQ (item 8.10) provision
for this item was Rs.77.90 lakh.
5.5. Similarly there was provision of signaling arrangement at intersection.
In view of frequent & long power cut, this was thought un-operable and was
deleted. BOQ item no 8.11 provided Rs. 27.06 lakh for this work.
6. CONTRACT CONDITION
OF
259
is silent on how and what to deal with and to draw inferences from the result.
Similarly New Clause 602.10.5.6 has also been introduced indicating that in
case of temp exceeds 700 C, trial stretch has to be condemned. The above two
clause requires to be clubbed to stand in proper order.
6.2. Change in Contract Condition
6.2.1. Mile stone: Contract provides Mile Stone completion in three
section which was changed to two section as given in Table-5.
TABLE 5
Contract Mile Stone
Sl.
No.
Section
1.
2.
3.
Date
Sec.I km
15 months 15 months
115 to 129 9.05.02
30.09.02
Left Carriageway
km 115 to 158
31.12.03
31.12.03
Sec.II km
129 to 145
Sec.III km
145 to 158
Right
Carriageway
km 115. to 158
30.06.04
Before
EOT
Date
After
EOT
11 months
09.04.03
10 months
09.04.04
11 months
31.08.03
10 months
30.06.04
6.2.2. Minimum amount for IPC: As per appendix to Bid, the minimum
amount required was 10 million which was changed to 5 million till 30 per cent
progress achieved.
7. COST VARIATION
Write-up above will lead that this contract package III-A had undergone
a substantial changes. Consistent process was, however, maintained to monitor
the cost incidence on the project regualarly before any variation is finalized.
Quantity recapitulation was made a normal process. At present the latest cost
projection after taking into consideration of all plus and minus variations already
accrued and likely to take place. Cost variation at present indication may be to
the order of (-) 4.12 per cent as presented in Table-6.
7.1. Work Supervision and Quality Assurance
7.2. Procedures
The important & crucial part of construction management is the
expediency and degree of supervision to sustain the progress and quality in
order to avoid/eliminate chances of rejection of work done on account of nonconformity. To meet this objective, the following procedures were adopted.
260
SHARMA ON
(i)
(ii)
(v)
(vi)
(x)
Sl.
No.
Item
BOQ Provision
in million
Anticipated cost
in million
1.
Site clearance
11.888
9.552
2.
Earth work
49.600
95.886
3.
Shoulder, subbas,
base
332.243
364.133
4.
Bituminous road/
concrete pavement
1005.997
961.488
5.
189.900
108.900
6.
Road Junction
5.667
2.930
7.
Drainage &
protection work
98.384
91.077
8.
Traffic sign,
56.970
markings & other
road appurtenances
46.473
9.
Miscellaneous
152.968
79.231
10.
Day work
12.623
0.490
1798.55 million
1,724.53 million
Remark
OF
261
2332
2144
2000
1500
1508
1198
1198
1082
1376
1051
1000
500
0
April-June 02
Aug-Sep'02
Oct-Dec'02
Jan-mar03
Apr-June'03
Jul-Sep-03
Oct-Dec'03
262
SHARMA ON
20000
125
15441
15000
100
100
12745
92
75
10000
50
5000
25
0
Embankment
Embankment
Subgrade
Subgrade
7.4.2. Similar tests for other activities of work were performed. Only
gist of test done for important items is furnished to show the quantum in
Table 7.
OF
263
TABLE -7
Sl.
No.
Work Particulars
Sample
result
Specimen
test
1.
Drainage layer
393
2246
2.
187
1033
3.
WMM
89
486
4.
2247
5.
962
All the important plants like Concrete Batching & Mixing, Asphalt,
Crusher were imported one. Paving machines for Cement Concrete PQC, DLC,
Asphalt and WMM were also imported one. Performance of all the plants &
paver were seen and approved, Table 8.
T ABLE -8
Sl. Name of Machine
No.
Capacity
Number
Remark
1.
Concrete Batching
& Mixing Plant
120 m 3/h
Italy
Concrete Batching
& Mixing Plant
20 m3 /h
India
2.
Crusher
125TPH
Finland
3.
160TPH
Korea
4.
Paver-2 Slipform
Paver (CCPT)
200 m /h
Germany
5.
50 m3 /h
6.
1nr. - 9 m wide
Switzerland
1nr. - 9 m wide
Switzerland
60 m /h
7.
80 m /h
1nr. - 9 m wide
Switzerland
8.
Roller (Vibratory
Compactor)
80 m3 /h
10
India
9.
100TPH
India
264
SHARMA ON
Particular
Number of Meeting
MEETING
1.
4 nrs
2.
DRB Meeting
4 nr
3.
16 nr
4.
6 nr
SITE VISIT
5.
7 times
6.
MOEF Visit
2 times
7.
3 times
8.
9.
596 nr
10.
81 nr
11.
33 nr
12.
Quarterly progress
10 nr
13.
Environment Report
10 nr
QUALITY A UDIT
14.
15.
CRRI Audit
2 times
(i) 12 May to 16 May 03
(ii) 24-25 August 2003
Once on 12.3.2004
OF
265
Trial Stretch for all important activities like DLC, PQC, DBM, GSB, DL
was made away from permanent work. DLC, PQC trial stretch was made at
plant site simulating the condition for main work. After watching the performance
of Plant, Paver, & workmanship, of trial stretch, (Photos 1 to 3) approval was
given for proceeding on permanent work.
266
SHARMA ON
11. SETTING UP OF SITE LABORATORY
For Routine tests site laboratory was established. One main laboratory
for Soil, Aggregate, Bitumen was set-up at km 142. Another main laboratory
for concrete work (PQC) was established at km 126.800. Two mini laboratory
was also set-up at WMM site km 123 and 154.
12. CASH FLOW
1798.55
1800
1600
1400
1200
1000
800
600
400
200
0
1217.45
Progress Payment
Item
Contract amount
Payment Amount
Amount in million
Amount in million
360
359.71
355
350
344.72
345
340.36
340
335
330
Total Advace
Items
Ceiling amount
Payment amount
Recovery amount
OF
267
From the facts placed in chapter it is evident that none of the project
is free from time over run and Quantity/cost variation. Time & Cost over run
for III A with respect to contract is shown in Fig. 16.
As Per Contract
As Anticipated
Ex
tra
n
io
ill
m
3
.5 t
s
24
17 Co
Hi
Qu gh Q
ali
A,
ty
Q4
Time
46 months 24 day
1850
36
40
Cost in million
Time in months
50
30
20
10
1798.55
1800
1724.53
1750
1700
1650
Cost
Original Cost
0
Construction period
Original time
Anticipated Cost
Anticipated time
Fig. 16.
The condition of all the 8 packages taken under TNHP will still be worse
compared to package III A which is small one and having lesser problem.
Some of the package may take 60 to 70 per cent excess time with respect
to contract period.
15. CONCLUSIONS AND OBSERVATION
(i)
268
(ii)
SHARMA ON
(b)
(c)
(iii) Main contractor take leisurely view in completing pre construction work
even after taking Mobilisation advance and remain looking for subcontractor to do whole or part of these works. The practice of disbursement
entire amount of Mobilisation is not conducive. It requires phasing
installment-wise after utilization.
(iv)
(v)
Awarding contract without any rider of lower limit of bid price with respect
to estimated cost is one of the important factors for delay, litigation and
other malaises. Bidding price below the limit of schedule amount is, in
general, expression of emotive disposition of contracting unit for entering
into agreement anyhow and settle the matter subsequently by fair or foul
principle. To curb this tendency and for getting workable rate, present
system requires to be modified with rider of lower limit of rate for quoting/
acceptance.
(vi)
OF
269
and may not also present good account either for Design or Supervision
Consultant. The present system of preparation of DPR is giving more
attention on artistic presentation instead of quality technical content
befitting to field reality. Quantity calculation specially of embankment,
excavation, dismantling, Bridges/Culverts suffer & differ most glaringly.
(viii) Supervision Consultant duty and responsibility in all fairness extends to
analyse the provision of DPR very critically and correlate with field
conditions and effect such changes procedurally for maximum benefits
out of the project. Illustrations of the contract package IIIA may strengthen
this argument.
(ix)
(x)
(xi)
1.
2.
3.
IRC:372001.