You are on page 1of 2

DAILY WORK REPORT

Project name: Rehabilitation of PASAR Plant Various Offices (RPPVO)


Location: Isabel, Leyte
NTP Date: FEBRUARY 16, 2015
BUILDING
NAME
DATE START
DAY NO.
DATE

: Refinery Building Office


: March 10, 2015
: 45
: May 5, 2015

WEATHER CONDITION :
FAIR
SUNNY
LIGHT TO MODERATE
RAINFALL
HEAVY RAINFALL
TYPHOON

AM

PM

CONSTRUCTION ACTIVITES
TASK
Sacking of chipped tiles and concrete
Hauling of debris
Demolition of Shower Room
Installation of partition wall frame
Installation of board on wall frame
Painting Works
Layouting for finishing of walls
Piling of CHB
Plastering and finishing of Walls
MANPOWER UTILIZATION
QUANTITY
1
2
1
2
1
2

REMARKS
In progress
In progress
In progress
In progress
In progress
In progress
In progress
In progress
In progress

% COMPLETE
49.7%
16%
85%
45%
10%
16%
51%
10%
5%

DESIGNATION/POSITION
Supervisor
Labors (Helper)
Safety officer
Partition Wall/Ceiling installer
Painter
Mason

EQUIPMENT UTILIZATION
QUANTITY

ITEM DESCRIPTION

1
1
1

Chipping hammer
cutting hammer
Drilling hammer

INSPECTED BY SAFETY
OFFICER
YES
NO
X
X
X

MATERIALS/ EQUIPMENT DELIVERY


QUANTITY

ITEM DESCRIPTION

WORK OPERATION CONCERNS:


None.

SAFETY AND HEALTH REPORT


INCIDENT TYPE
LTI (LOST TIME INCIDEMT)
MTI (MEDICAL TREATMENT INCIDENT)
RWI (RECREATIONAL WATER INCIDENT)
PROPERTY DAMAGE
FIRST AID INCIDENT
NEAR MISS

PREPARED BY:

CHARRA JOY WALES


SUPERVISOR, ASI
TO:
ENGR. REY ROSALES
PROJECT IN CHARGE, PASAR

TO DATE

REMARKS
None
None
None
None
None
None