Soal 1 (1 menit)
Jika persediaan di gudang ada 200 unit,
yang dialokasikan 50 unit, safety stock
25 unit, tingkat cacat 10% maka berapa
jumlah Planned On Hand ?
200 50 25 20 = 105 unit
Soal 2 (1 menit)
Jika kebutuhan kotor 200 unit, besar
Planned On Hand periode sebelumnya
100, dan schedul receipt sebesar 50,
maka berapa kebutuhan bersihnya ?
200 100 50 = 50 unit
X, Y
80
60
50
70
30
110
X
LT = 1
A(2)
LT = 3
OH
SS Schedule
R
Lot
Sizing
125
25
LFL
50
25
LFL
150
50
LFL
100
50
150
40
150
150
50
200
Y
LT =1
B (2)
LT = 2
C (2)
LT = 1
B (3)
LT = 2
50, T= 2
75, T=3
100
2
80
GR
1
110
SR
50
POH = 100
NR
10
POR
30
30
60
4
60
5
50
6
70
60
50
70
50
70
30
GR
2
80
SR
POH = 25
80
POR
95
80
60
60
30
1
110
NR
30
50
6
70
60
50
70
50
70
30
30
30
2
120
3
100
4
140
GR
1
60
SR
POH = 100
40
100
140
NR
POR
140
80
60
6
60
60