UDK: 69.003.12.001.8
Autori:
Prethodno priopenje
nives.ostojic@gradst.hr
Kljune rijei:
planiranje izgradnje, visokogradnja, tuneli, autoceste, S-krivulja, regresijski modeli, prognoza dinamike
trokova
Preliminary note
The methodological procedure for forecasting cost distribution over time is given for
the project realization phase using cost s-curves for three different types of structures:
building, tunnel, and motorway. Three different approaches are used, and their results are
correlated and presented in form of mathematical regression expressions and appropriate
diagrams. The proposed methodology can be used for cash flow forecasting during all
phases of construction projects, specially in the earliest phase in which detailed information
about the project is scarce.
Key words:
construction planning, building engineering, tunnels, motorways, S-curve, regression models, cost
scheduling
Vorherige Mitteilung
647
Graevinar 8/2012
1. Uvod
Istraivanje raspodjele trokova u vremenu kod graevinskih
projekata predstavlja vanu temu za investitora i izvoaa.
Podatak o trokovima dobiva svoju punu vrijednost istom kada
mu se pridrui podatak o vremenu troka. Poznato je da se u
znatnom dijelu graevinskih projekata ugovara i trokovna
dinamika koja proizlazi iz usklaenih i od strane investitora i
izvoaa odobrenih planova i trokovnika radova. To je vaan
podatak za sve sudionike u graevinskom projektu, te je stoga
i predmet brojnih istraivanja. Dio istraivanja usmjeren je
na traenje zakonitosti odnosa ovih varijabli tijekom raznih
faza projekta, odnosno za odreene vrste graevinskih
projekata, pri emu se trai teorijska kumulativna S-krivulja
koja najbolje prikazuje standardnu raspodjelu trokova u
vremenu. S-krivulja predstavlja kumulativni novani tijek u
odreenom razdoblju, pri emu je na apscisi prikazano vrijeme
"t", a na ordinati trokovi "v". U ovom radu se detaljno istrauju
mogunosti modeliranja kumulativnih trokova faze izvrenja
projekta u vremenu primjenom tri razliita pristupa. Za
odabrane vrste graevinskih projekata potrebno je identificirati
utjecajne parametre i zakonitosti raspodjele u uvjetima
razliitih organizacijskih scenarija odreenih specifinostima
izvrenja, odlukama naruitelja projekta, djelovanjem vanjskih
i unutarnjih rizika i utjecajima projektne strukture. Poznato je
da su svi ovi imbenici bitno razliiti od projekta do projekta
to uzrokuje iznimno veliku kombinatoriku sluajeva koja se
ne moe pojedinano razmatrati. Stoga je sluajnim izborom
istraivanih projekata osigurana podloga koja daje rezultat
u uvjetima izostanka ekstremnih utjecaja, tj. u standardnim
uvjetima izvrenja. Trokovna dinamika u posebnim i
ekstremnim utjecajima na izvrenje moe biti predmet
nastavka istraivanja po specifinim situacijama, pri emu se
rezultati ovog istraivanja mogu koristiti kao temeljna podloga.
S krivulje
PROVJERA MODELA
LITERATURA
USPOREDBA MODELA
MEUSOBNA
USPOREDBA
SVIH MODELA
BEST-FIT
ANALIZA
IZVRENI PROJEKTI
KVALITATIVNA
ANALIZA MODELA
ZAKLJUCI
MATEMATIKI OBLIK
PODRUJA
S KRIVULJE
648
Graevinar 8/2012
Tablica 1. Pregled razvijenih matematikih modela za procjenu S-krivulje prema izvorima iz literature
Autor
Godina
Izraz
Bromilow
1978.
Y= [ ao+a1(w/t)+a2 (w/t)2+a3(w/t)3+a4(w/t)4 ] C
Hudson
1978.
Y= S [x + C x2 Cx (6x3 9x2 + 3x ) K]
Peer
1982.
Tucker
1988.
Y= a (1-e(-((x-d)/y)b)
Miskawi
1989.
Boussabain i Elhag
1996.
649
Graevinar 8/2012
(1)
Y i tuneli
(2)
(3)
650
(4)
- za izvedene tunele
(5)
Graevinar 8/2012
(6)
+ 0,000000002 x6i
(7)
- za izvedene tunele
Y i tuneli
(8)
(9)
tunel
-- ukupno trajanje izvoenja radova: 304 dana,
-- ukupni trokovi: 67 mil kuna,
-- vrijednost kvartila: 1. kvartil (18,43 %), 2. kvartil (64,38 %) i 3.
kvartil (90,33 %);
Yi P + 4 =
1
1
x
101 + (0, 612158 x (0, 919930) )
(10)
(11)
(12)
+ 0,0000000021 xi6
651
Graevinar 8/2012
120
100
v trokovi [%]
60
S-krivulja,
literatura
40
S-krivulja, baza
podataka
S-krivulja, teoretski
model
20
0
0
20
40
60
80
100
-20
t vrijeme [%]
120
100
v trokovi [%]
80
Konana S-krivulja
za tunele
60
gornji interval
povjerenja, p=95 %
40
donji interval
povjerenja, p=95 %
20
-20
20
40
60
80
je
0.991.
(15)
+ 0.0000000015 xi6
je
0,968.
Kumulativno
dana
15. travanj
15
15
3,79
1. svibanj
31
46
11,62
1. lipanj
30
76
19,19
1. srpanj
31
107
27,02
1. kolovoz
31
138
34,85
1. rujan
30
168
42,42
1. listopad
31
199
50,25
1. studeni
30
229
57,83
1. prosinac
31
260
65,66
1. sijeanj
31
291
73,48
1. veljaa
28
319
80,56
1. oujak
31
350
88,38
1. travanj
31
381
96,21
1. svibanj
15
396
100,00
100
t vrijeme [%]
652
+ 0,0000000004 xi6
Mjesec
0
0
(14)
0.968.
80
je
Kumulativno
dana [%]
Graevinar 8/2012
Procjena S-krivulje
15. travanj
432.034,71
-711.592,68
1.572.064,30
1. svibanj
1.206.154,36
69.864,29
2.341.022,70
1. lipanj
2.275.759,41
1.163.386,95
3.390.930,52
1. srpanj
4.044.816,74
2.928.859,20
5.163.409,57
1. kolovoz
6.541.022,28
5.432.585,76
7.648.907,67
1. rujan
9.506.437,62
8.398.668,01
10.611.709,18
1. listopad
12.865.766,73
11.754.706,02
13.976.597,05
1. studeni
16.087.754,63
14.984.630,17
17.197.351,37
1. prosinac
19.066.656,85
17.966.659,52
20.182.645,56
1. sijeanj
21.431.438,65
20.327.950,76
22.560.751,31
1. veljaa
22.922.298,69
21.827.744,32
24.053.146,53
1. oujak
23.884.222,58
22.781.149,27
25.047.690,22
1. travanj
24.353.873,31
23.281.972,94
25.552.355,92
1. svibanj
24.651.643,68
23.451.941,28
25.815.139,20
v-trokovi [kn]
300.000.000
250.000.000
200.000.000
PROCJENA
S-KRIVULJE
150.000.000
DONJA GRANICA
PROCJENE
100.000.000
GORNJA GRANICA
PROCJENE
50.000.000
0
10
11
12
13
14
15
t-vrijeme [mjeseci]
Slika 4. G
rafiki prikaz prognostike trokovne S-krivulje na primjeru
objekta visokogradnje
5. Zakljuak
Cilj ovoga istraivanja bio je definiranje prognostikih
S-krivulja za karakteristine tipove graevinskih projekata
653
Graevinar 8/2012
LITERATURA
[1] Upravljanje rizikom i promjenama u projektno usmjerenom
graevinskom poduzeu, Znanstveni projekt, Ministarstvo
znanosti , obrazovanja i porta RH, 2007-2012.
[9] Singh, S., Pua, W. W.: Cash Flow Trends for High Rise Building
Projects, Proceedings of the 4th International Syposium on
Organisation and Management of Contruction, Waterloo
(Canada), (1984), pp. 841854.
[10] Kenley, R., Wilson, O.: A Construction Project Cash Flow Model
An Ideograhic Approach, Construction Management and
Economics, 4 (1986), pp. 213-232
[11] Kaka, A. P., Price, A. D. F.: Net Cashflow Models: Are They
Reliable?, Construction Management and Economics, 9 (1991),
pp. 291-308
654