Professional Documents
Culture Documents
CCPUMPp
CCPUMPp
Sheet 1 of 15
LIST OF CONTENTS
1.
PLANT DETAILS
2.
OBJECTIVES
3.
PROPOSALS
4.
SERVICES REQUIRED
5.
6.
7.
8.
9.
10.
SAFETY PRECAUTIONS
EMERGENCY PROCEDURES
STATE OF THE PLANT
METHOD
COMPLETION CRITERIA
APPENDICES
a) DRAWING
b) LOG SHEETS
Signatures
NTPC
Station: NTPC - Simhadri BHEL Ref No. PS - DC - 186 500 0038
NTPC Ref No. SIM / 1 / TS / 1 / 38
Plant Area: BOILER
BHEL
Sheet 2 of 15
PLANT DETAILS
STATUS
Signature
NTPC
Station: NTPC - Simhadri BHEL Ref No. PS - DC - 186 500 0038
NTPC Ref No. SIM / 1 / TS / 1 / 38
Plant Area: BOILER
PROCEDURE FOR COMMISSIONING OF CC PUMPS
b)Auxiliary cooling water system
BHEL
Sheet 3 of 15
This system is supplied with LP coolant from ECW System / station auxiliary
cooling water system and also from a separate emergency cooling water from
over head tank source. This supplier cooling water to
1.3
1.4
1.5
1.6
i)
ii)
The boiler circulating pumps are operated through H.T.Motors which are
provided with cavity in which DM Water is filled by a specific procedure
described in Section 8.0 and this cavity filling is for cooling the motor while
the motor is in operation.
When the unit is in operation, Circulation pumps are operated in parallel or all
the three pumps together as per the actual requirement.
Plant item completion lift for the system for Mechanical, Electrical and C&I
areas are to be prepared at site.
Schematic drawing of Circulation Pumps (Drg.No.4:PS:tsx:0069:00)
enclosed in Section 10.0
Signature
NTPC
Station: NTPC - Simhadri BHEL Ref No. PS - DC - 186 500 0038
NTPC Ref No. SIM / 1 / TS / 1 / 38
BHEL
Sheet 4 of 15
OBJECTIVE
To commission the C.C. Pumps and make it available for commissioning and
operation of the unit.
3.0
3.1
3.2
3.3
3.4
4.0
SERVICES REQUIRED
4.1
4.2
4.3
4.4
4.5
4.6
Signature
NTPC
BHEL
Sheet 5 of 15
SAFETY PRECAUTIONS
5.1
5.2
5.3
Agencies working in the boiler area / are informed about the test / cleared
from the test area (As per the actual requirement).
5.4
5.5
Required approach stair cases, platforms and hand rails are erected prior to
testing.
Signature
NTPC
BHEL
Sheet 6 of 15
EMERGENCY PRECAUTIONS:
6.1
The group conducting the test should be aware of action to be taken on the
event of injury to personnel.
6.2
extinguishers.
6.3
The test team should be aware of the steps to be taken to trip the running
equipment in case any emergency / abnormal observations are notified to
them.
Signature
NTPC
BHEL
7.1
7.2
Sheet 7 of 15
7.3
All permanent supports are provided in the pump suction manifold, suction
and discharge lines and other associated lines.
7.4
All local instruments of the pumping unit including fill and purge lines and
auxiliary cooling water system are installed. (Required list is to be prepared at
site). Pressure and temperature indicators are to be duly calibrated.
7.5
7.6
7.7
Temperature measurement pads are fixed on the pump casing and suction
manifold and suitable thermocouples are installed.
Signature
NTPC
Station: NTPC - Simhadri BHEL Ref No. PS - DC - 186 500 0038
NTPC Ref No. SIM / 1 / TS / 1 / 38
BHEL
Sheet 8 of 15
7.9.1 Cavity temperature controller is calibrated and set at 135 F and 140 F for
alarm and Trip respectively.
Signature
NTPC
BHEL
Sheet 9 of 15
Signature
NTPC
Station: NTPC - Simhadri BHEL Ref No. PS - DC - 186 500 0038
NTPC Ref No. SIM / 1 / TS / 1 / 38
BHEL
Sheet 10 of 15
METHOD
8.1
8.1.1 Preparation of fill and purge system and auxilliary cooling water system
Fill and purge water is taken from 2 independent sources viz.
1.
2.
motor inlet shall be flushed without connecting the inlet line to the motor.
---
--
Signature
NTPC
Station: NTPC - Simhadri BHEL Ref No. PS - DC - 186 500 0038
NTPC Ref No. SIM / 1 / TS / 1 / 38
BHEL
Sheet 11 of 15
8.2.1 Auxiliary cooling water for HP cooler and fill and purge line cooler shall be
supplied from two sources.
a)
From station auxiliary cooling water source.
b)
Emergency cooling water from over head tank.
Auxiliary cooling water piping is to be flushed with same quantity of water
used for station auxiliary cooling water purpose. In order to achieve effective
flushing the auxiliary cooling water line is flushed in the following stages.
Signature
NTPC
Station: NTPC - Simhadri BHEL Ref No. PS - DC - 186 500 0038
NTPC Ref No. SIM / 1 / TS / 1 / 38
BHEL
Sheet 12 of 15
8.3.1 Charge the HP fill and Purge line manifold through temporary low pressure fill
source.
Motor cavity is to be filled at rate less than 2.6 litre / min with D.M. Water
(Condense quality DM water). This rate has to be ensured before admitting
the water into the motor by opening the fill and purge line Valves No. C43,
C58, C61 and the Drain Valve C73 and closing the Valves C59 and C62.
(The Valves nos. are given for Pump A. For corresponding valves for Pump
B and C please refer the drawing enclosed). The flow through the drain
Valve C73 is to be measured and set the opening of the Valve No. C58 such
a way that the recommended flow rate is achieved. Then admit the purge
water in to the motor after closing the drain valve no. C73 through the filter
and Orifice O.
8.3.2 Venting:
With the purge water flow established as described in section 8.3.1, keep
open the vent valves C90, C91, C92, C144 and C145 till air free water
comes out through the valve. Then close the vent valves.
8.4 Trial run of pump
8.4.1 Ensure motor cavity of all pumps are filled as described above before taking
up trial of any pump.
8.4.2 Fill the boiler drum upto normal operating level. This is to ensure availability
of sufficient NPSH for pump to run without cavitation.
8.4.3 Ensure the cooling water flow through the motor cooler.
8.4.4 Ensure the pump discharge valve fully opened.
Signature
NTPC
Station: NTPC - Simhadri BHEL Ref No. PS - DC - 186 500 0038
NTPC Ref No. SIM / 1 / TS / 1 / 38
BHEL
Sheet 13 of 15
Motor Current.
Differential Pressure: When the check valves are open the differential
pressure should rise immediately to approximately 10 P.S. I.
Note: If the differential pressure doesnt rise, stop the motor immediately. It
may be an indication that the motor is running in reverse direction. This is
corrected by interchanging of the position of the motor leads at the terminal
box/ H.T breaker end as the case may be .
8.4.8 After further 10 minutes pause flick start the motor for 5 seconds (3 rd) and
observe the motor current and differential pressure.
8.4.9 After further 10 minutes pause, energise the motor (4 th) and run for 20
minutes.
Signature
NTPC
BHEL
Sheet 14 of 15
Signature
NTPC
Station: NTPC - Simhadri BHEL Ref No. PS - DC - 186 500 0038
NTPC Ref No. SIM / 1 / TS / 1 / 38
BHEL
Sheet 15 of 15
COMPLETIONCRITERIA
9.1
Signature
NTPC
BHEL
Log Sheet
Station
Unit
Date:
Activity :
Sl.
No
Pump in
Service
Time
A
Differential
Pressure
Current
C
Time
Remarks
Signature
NTPC
BHEL