Professional Documents
Culture Documents
8) Qap Itp For Gen Civil & RCC (10 Pages) PDF
8) Qap Itp For Gen Civil & RCC (10 Pages) PDF
GENERAL NOTES:
Inspection & Test Plan (ITP) given herein is indicative only.
Contractor shall prepare and submit ITP for all activities. The
provisions indicated herein for stage wise inspection are minimum
and the Engineer-in-charge may decide to increase the Hold
Point/Witness Point basis the work being carried out at site.
Contractor has to prepare ITPs for any of the activities not covered
herein, submit the same to HPCL and obtain their approval.
Contractor to prepare required reporting formats and job procedure
for each activity i.e. Setting out of work, levels at 5 m grid, prior to
excavation, submission of murrum samples meeting tender
specifications along with soil lab test report, concreting, etc., to
HPCL for approval well in advance prior to commencement of
activity. Any deviation to ITP shall be subjected to HPCL's written
approval. Contractor to carry out 100% examination; satisfy that the
specifications as per PO are complied & thereafter submit to HPCL
for witness/review as applicable.
2.0
LEGEND:
2.1
The Contractor shall not process the activity/item beyond the Hold
Point without written approval from Engineer-in-charge.
2.2
W: Witness Point
Any point which requires witness by HPCL when activity is
performed.
2.3
2.4
2.5
3.0
S.NO
ACTIVITY
CONTRACT
OR
HPCL
1.1
WC
HP
1.2
WC
HP
1.3
WC
HP
1.4
WC
HP
HP
S.NO
1.6
ACTIVITY
CONTRACT
OR
HPCL
A) Embankment formation :
B) Compaction :
W
HP
HP
HP
S.NO
1.8
ACTIVITY
CONTRACT
OR
WC
WC
HPCL
W
W
HP
S.NO
ACTIVITY
CONTRACT
OR
HPCL
2.1
Laying of PCC beneath foundations Checking of layout
and materials, compaction of sub grade
HP
HP
Mix proportion
WC
HP
WC
WC
W
HP
WC
Curing
S.NO
2.2
ACTIVITY
CONTRACT
OR
HPCL
WC
hold point clearance for center points for side walls and WC
Rafts and center lines for haunch
HP
formwork WC
HP
HP
HP
W
HP
S.NO
2.2
ACTIVITY
2.3
CONTRACT
OR
HPCL
HP
HP
WC
Measurement of finished dimensions. It shall be the sole
responsibility of the contractor to ensure the members are WC
in a proper grade & levels as per the approved drawing.
WC
WC
HP
WC
HP
WC
HP
Cube test sample collection from the mix, curing and its
testing as per IS: 456, submission of following laboratory
reports ,
HP
S.NO
3.1
ACTIVITY
CONTRACT
OR
HPCL
Plastering :
HP
HP
W
HP
S.NO
4.0
ACTIVITY
CONTRACT
OR
HPCL
BACK FILLING:
Back filling in foundation trenches after construction of
foundation or wherever required as per the directions of
HPCL engineer in charge, using the serviceable earth
WC
HP
HP