Professional Documents
Culture Documents
WMU BIM Guideline v6-1-1 PDF
WMU BIM Guideline v6-1-1 PDF
TABLE OF CONTENTS
SECTION A: BIM PROJECT EXECUTION PLAN OVERVIEW.................................................................................. 2
SECTION B: PROJECT INFORMATION................................................................................................................ 3
SECTION C: KEY PROJECT CONTACTS ............................................................................................................ 4
SECTION D: PROJECT GOALS / BIM USES ....................................................................................................... 5
SECTION E: BUILDING INFORMATION MODELING FILE TYPES ............................................................................ 6
SECTION F: BIM AUTHORING AND COLLABORATION SOFTWARE REQUIREMENTS .............................................. 8
SECTION G: COLLABORATION PROCEDURES .................................................................................................. 10
SECTION H: FILE NAMING CONVENTION ISSUE 4 ............................................................................................ 11
SECTION I: QUALITY CONTROL .................................................................................................................... 15
SECTION J: TECHNOLOGY INFASTRUCTURE REQUIREMENTS .......................................................................... 16
SECTION K: MODEL STRUCTURE ................................................................................................................... 17
SECTION L: PROJECT DELIVERABLES ............................................................................................................ 18
SECTION M: DELIVERY STRATEGY & LOD LEVEL OF DEVELOPMENT............................................................. 19
SECTION N: BUILDING INFORMATION MODEL REQUIREMENTS - DETAILS........................................................... 20
| October 2011
| October 2011
2.
Project Name:
3.
4.
5.
6.
Existing Conditions:
7.
NUMBER
2011
Each Project must complete AIA E202 document to define project Level of Development LOD.
8.
Include BIM milestones, pre-design activities, major design reviews, stakeholder reviews, and any other major events
which occur during the project lifecycle. See contract documents for official project schedule.
PROJECT PHASE /
MILESTONE
ESTIMATED COMPLETION
DATE
PROJECT STAKEHOLDERS
INVOLVED
PROGRAMING
SCHEMATIC DESIGN
DESIGN DEVELOPMENT
CONSTRUCTION DOCUMENTS
CONSTRUCTION
CLOSEOUT
LIFECYCLE
| October 2011
Role
Organization
Project Manager
AE Firm
Project Manger
Construction
Project Manager
WMU
Contact Name
Location
Phone
BIM Coordinator
Discipline Lead
ARCH
Discipline Lead
MEP
Discipline Lead
Structure
Owners
Representative
Commissioning
| October 2011
PRIORITY
GOAL DESCRIPTION
(HIGH/ MED/
LOW)
2.
PROJECT PHASE
Provide WMU a LOD 300 model including Arch, MEP, and Structure for construction
Construction
Construction
Reference all building components per the Western Michigan University BIM guideline
Lifecycle
Lifecycle
Design
PLAN
DESIGN
PROGRAMMING
DESIGN AUTHORING
SITE ANALYSIS
DESIGN REVIEWS
CONSTRUCT
SITE UTILIZATION
PLANNING
CONSTRUCTION SYSTEM
DESIGN
OPERATE
BUILDING MAINTENANCE
SCHEDULING
BUILDING SYSTEM
ANALYSIS
3D COORDINATION
3D COORDINATION
ASSET MANAGEMENT
STRUCTURAL ANALYSIS
DIGITAL FABRICATION
SPACE MANAGEMENT /
TRACKING
LIGHTING ANALYSIS
3D CONTROL AND
PLANNING
DISASTER PLANNING
ENERGY ANALYSIS
RECORD MODELING
RECORD MODELING
MECHANICAL ANALYSIS
OTHER ENG. ANALYSIS
SUSTAINABLITY (LEED)
EVALUATION
CODE VALIDATION
PHASE PLANNING
(4D MODELING)
PHASE PLANNING
(4D MODELING)
PHASE PLANNING
(4D MODELING)
PHASE PLANNING
(4D MODELING)
COST ESTIMATION
COST ESTIMATION
COST ESTIMATION
COST ESTIMATION
Project Scope and objectives should determine the proper application of modeling and weigh all factors including
time, cost, and effort vs. net benefit.
3.
WMU will make Revit 2011 .rvt model files available for existing buildings that have been modeled. WMU takes
no responsibility for the accuracy of these models therefore each should be field verified for accuracy.
| October 2011
Models are Revit Architecture project files with Worksets enabled in order to create a central file.
Architecture Model file (.rvt) contains all architectural features for a building including but not limited to:
2.
The Revit
Models are Revit Structure project files with Worksets enabled in order to create a central file. The Revit Structure
Model file (.rvt) contains all structural features for a building including but not limited to:
3.
Foundations
Columns, beams, and joists
Column grid
Brace frames and shear walls
Structural slab
Specialties
Misc. structural components.
Mechanical, Electrical, and Plumbing Model Autodesk Revit MEP .rvt
Models are Revit MEP project files with Worksets enabled in order to create a central file. The Revit MEP Model file
(.rvt) contains all mechanical, electrical, and plumbing features for a building including but not limited to:
Rain Leader
Overflow drain
Vent
Waste water
Domestic cold water
Domestic hot water
Fire protection
Gases
Fire alarm system
Mechanical ductwork
6
| October 2011
4.
Mechanical equipment
Electrical Conduit
Electrical lighting
Fire/smoke dampers
Valves with valve tags
Plumbing equipment and fixtures
Electrical equipment
Electrical panels and schedules
Specialties
Equipment clearances for access, service space requirements, gauge reading, valve clearances, and other
operational clearances and access panels.
Models are Revit MEP project files with Worksets enabled in order to create a central file. The Revit MEP Model file
(.rvt) contains all mechanical, electrical, and plumbing features for a building including but not limited to:
5.
6.
Models are to be Navisworks Manage .nwc files. Models will then be converted to .nwd files and made available per
the project coordination schedule for design and construction professionals to perform clash detection, scheduling and
visualization using Navisworks Manage.
7.
WMU to decide.
| October 2011
AutoCAD MEP
Autodesk Civil 3D
Projects will remain on the same software release throughout the life of the project.
3. Coordination Software
All internal and external model coordination and conflict detection are required to use the following software in its
native file format in its current version*:
| October 2011
| October 2011
3.
MEETING TYPE
PROJECT
STAGE
FREQUENCY
PARTICIPANTS
LOCATION
PROGRAMMING
ONCE
WMU/AE/CONST
WMU
PROGRAMMING
ONCE
RESPONSIBLE PARTY
WMU
DESIGN COORDINATION
DD/SD/CD
BI-WEEKLY
RESPONSIBLE PARTY
WMU
CONSTRUCTABILITY
COORDINATION
CONSTRUCTION
BI-WEEKLY
RESPONSIBLE PARTY
WMU
Model & Document Delivery Schedule of Information Exchange for Review, Coordination, Submission
and Approval:
INFORMATION
EXCHANGE
DUE
ONE-TIME or DATE or MODEL
FREQUENCY START
FILE
DATE
FILE
SENDER
FILE
RECEIVER
MODEL
SOFTWARE
FILE
TYPE
2D FILE
TYPE*
DESIGN INTENT
AE FIRM
COLLABORATION
SITE
BI-WEEKLY
Thursday
5:00pm
ARCH
REVIT
.NWC/.
DWF
MEP
COORDINATION
MEP
CONSULTANT
COLLABORATION
SITE
BI-WEEKLY
Thursday
5:00PM
MEP
REVIT
.NWC/.
DWF
MEP
COORDINATION
MEP
CONSULTANT
COLLABORATION
SITE
BI-WEEKLY
Thursday
5:00PM
MEP
AUTOCAD MEP
.DWG/.
DWF
STRUCTURE
COORDINATION
STRUCTURE
CONSULTANT
COLLABORATION
SITE
BI-WEEKLY
Thursday
STRUC
5:00PM
REVIT
.NWC/.
DWF
COORDINATION*
CM/GC
COLLABORATION
SITE
BI-WEEKLY
FRIDAY
CONST NAVISWORKS
12:00PM
.NWD
COLLABORATION
SITE
BID
BID
CONST
REVIT
.NWC
SHOP DRAWINGS
CONSTRUCTION
COLLABORATION
SITE
AS
REQUIRED
CONST
ARCH
REVIT
.RVT
SHOP DRAWINGS
CONSTRUCTION
COLLABORATION
SITE
AS
REQUIRED
CONST
MEP
REVIT/AC MEP
.RVT/.
DWG
SHOP
DRAWINGS
CONSTRUCTION
COLLABORATION
SITE
AS
REQUIRED
CONST
STRUC
REVIT
.RVT
SUBMITTALS
CONSTRUCTION
COLLABORATION
SITE
AS
REQUIRED
CONST
NA
NA
* In addition to the BIM model file types, documents will be issued in 2D in both Autocad DWG and PDF.
General Contractors and Construction Managers are required to coordinate models between disciplines to perform
clash detection in order to reduce RFI and change order submissions using Navisworks Manage.
10
| October 2011
General
The purpose of this guideline is to provide guidelines and direction for standardizing electronic file information
into retrievable formats. Building Information Management Systems require unique file names to function
properly and allow searches to find the information the requestor desires. These guidelines/standards will be the
first step in developing our Building Information Management Systems (BIM).
This guideline should be followed by all personal in the Facility Management Department and anyone providing
services, documents or work for the University. Deviations from this guideline shall require approval in writing
from the Facilities Management Associate Vice President and Document Management Team.
Applicability: As of March 24, 2010 this is now the standard for all files on the Facility Management file
server.
This document will be updated regularly as we implement our document consolidation process.
2.
| October 2011
milestone reasons. Therefore if you are developing a document and are not done with it you would enter only a
year in the title until you issued it for comments or use. Also you may enter master in field 4, to distinguish a
file as the master version.
12
| October 2011
13
| October 2011
14
Utilites
Study
Site
Master Plan
Maps
Landscape
Concepts
Admin
Bldg #,
KPH bldg#,
0060 klnd
Location
(10
Characters)
Field 1
(12
Sprinkler, Plantings;
Signage;
Standards, Guidelines;
Floor # (ie: 03, 02, MZ, 01, UL, ML, LL, GF,
B0, B1, B2, Operating, Turf):
Sub-Location
Characters)
Field 2
Rxxxx.
09013;
Project No.
Shop drawing
title;
Email Subject;
File
Description;
Subject;
Package Title;
Sheet Title;
Description
(100
Characters)
Field 3
Doc Revision
(25 Characters)
Field 4
Review, Approved,
Approved as Noted,
Rejected.
Rev #, Req # PO #,
CO#, Contract #, Doc #
RFI#;
Sht # or Dwg #;
2006 10
2008
2009 11 19
Date
(yyyy mm dd)
(25 Characters)
Field 5
Table 2.1
File Extension
period
underscore
underscore
period
underscore
underscore
DIRECTORY
| October 2011
2.3 Examples
The following are examples of files following this naming scheme.
Table 2.2
File Name
001_Arch_BuildingElevations_A0101_1948 01.pdf
Site_Civil_Gate Fence Details_C0103_1998 05 15.dwg
File Description
Scanned print of architectural Elevations, drawing A01-01,
dated Jan., 1948.
Civil Drawing file of Gate and Fencing Details, Drawing no.
C01-03, dated May 15, 1998.
038_15xxx_Boiler O-M__2004 12
15.pdf
KPH04_email_Rxxxx.Fire Pump
Size_1303_2008 12 14.pdf
Admin_forms_R9068_Project Request
form_rev 0_2009 09 16.pdf
Project Request form for Project R9068, dated Sep. 16, 2009
038_16524_Rxxx.Electrical panel board Sangren Electrical Panel Shop drawing for Project Rxxxx
shop drawing_review_2010 04 01.pdf
submitted fro review on April 1, 2010.
Admin_forms_WMU FM Electronic File
Conventions_master_2010.docx
046_Bidding_R8838.WMU DD
Addendum #6 MEP Drawings __2010
01 27.zip
038_RFP_Sangren Civil
Eng_Draft_2010 04 02.pdf
Sangren Request for Proposal for Civil Eng firm, draft, dated
April 2, 2010.
QUESTIONS
Questions, comments, mistakes that identified in the use of this process should be directed to the FM Document
Management Committee.
Committee members are: Eric Dantes, Mike Hodgkinson, Dan List, Doug Lloyd, Steve Macomber, and George
Wilson.
15
| October 2011
The building information modeling process is suited to improve coordination of the design/construction process.
Western Michigan University requires the following quality control process.
2.
The following checks should be performed to assure quality. Required files/documents will be uploaded to the
Western Michigan University designated collaboration site per the schedule requirements.
CHECKS
RESPONSIBLE
PARTY
SOFTWARE
PROGRAM(S)
FREQUENCY
VISUAL CHECK
AE Firm
Revit
Navisworks
Project
Review
VISUAL CHECK
AE Firm
PDF/DWF
Project
Review
COORDINATION
CM/GC
Navisworks
Manage
Project
Review
AE Firm
Revit
Project
Review
AE Firm
Navisworks
Manage
Project
Review
STANDARDS CHECK
MODEL INTEGRITY
CHECKS
3.
DEFINITION
Models should include all appropriate dimensioning as needed for design intent, analysis, and construction.
PHASE
DISCIPLINE
TOLERANCE
DESIGN DOCUMENTS
ARCH
SHOP DRAWINGS
MECH CONTRACTOR
16
| October 2011
Software:
All project participants are required to have the following software in order to participate in the WMU BIM design and
construction process. BIM software use is as follows:
2.
BIM USE
DISCIPLINE
(if applicable)
SOFTWARE
VERSION
DESIGN AUTHORING
ARCH
Revit Architecture
Current
DESIGN AUTHORING
MEP
Revit MEP
Current
DESIGN AUTHORING
MEP
AutoCAD MEP
Current
DESIGN AUTHORING
Structure
Revit Structure
Current
DESIGN AUTHORING
Civil
Civil 3D
Current
COORDINATION
Construction
Navisworks Manage
Current
Computers / Hardware:
All project participants are required to have the necessary hardware in order to participate in the BIM design and
construction process. Hardware required is as follows:
17
BIM USE
HARDWARE
OWNER OF HARDWARE
SPECIFICATIONS
All Phases
Responsibility of
Design/Construction Firms
Design/Construction Firm
| October 2011
All Revit Central files will be named using the following instructions.
FILE NAMES FOR MODELS SHOULD BE FORMATTED AS:
ARCHITECTURAL MODEL
Building#_Arch_WMUProjectNumber.Description_Rev#_YYYYMMDD
CIVIL MODEL
MEP MODEL
Building#_Civil_WMUProjectNumber.Description_Rev#_YYYYMMDD
Building#_MEP_WMUProjectNumber.Description_Rev#_YYYYMMDD
Building#_Structure_WMUProjectNumber.Description_Rev#_YYYYMMDD
STRUCTURAL MODEL
ENERGY MODEL
Building#_Energy_WMUProjectNumber.Description_Rev#_YYYYMMDD
CONSTRUCTION MODEL
COORDINATION MODEL
Building#_Const_WMUProjectNumber.Description_Rev#_YYYYMMDD
Building#_Coordination_WMUProjectNumber.Description_Rev#_YYYYMMDD
LIFECYCLE MODEL
Building#_Lifecycle_WMUProjectNumber.Description_Rev#_YYYYMMDD
2.
Model Structure:
Model will be separated by the following disciplines for design and construction coordination by all project participants
throughout the design and construction process.
3.
Architectural
Mechanical, Electrical, Plumbing MEP
Structure
Civil
GIS Coordinates
All models should be created using True North coordinates vs. Project North. Firms are required to verify building
true north coordinates. Western Michigan University will make every effort to assist in this process.
18
| October 2011
1.
STAGE
FORMAT
NOTES
Programming
Schematic
Design
RVT
RVT
Construction
NWD
Closeout
RVT
As constructed model to be
delivered at project completion.
Design
Development
Construction
Documents
APPROXIMAT
E DUE DATE
Record Model
Submittal and Shop Drawings
Closeout
Final 2D Drawings
Closeout
DWG
PDF
Asset Management/Model
Coordination*
Post Closeout
RVT
Lifecycle Management*
Post Closeout
.RVT
* To be performed by WMU.
19
| October 2011
The intent of the building information modeling process is to improve project visualization, coordination, and
construction process. All models will be made available to design and construction project participants throughout
the design and construction process.
2.
Team members will not be selected entirely on their ability to participate in the BIM process. However those firms
that do not have the capacity or capability will be required to partner with a firm that can provide the required BIM
deliverable.
3.
The following outlines Western Michigan Universitys definition of Level of Development LOD for building
information model BIM deliverables. As defined by the AIA document E202 2008.
LOD 100 The model equivalent of conceptual design, the model would consist of overall building
massing and the downstream users are authorized to perform whole building types of analysis (volume,
building orientation, cost per square foot, etc)
LOD 200 Model that includes basic elements including windows walls and doors. This level of
modeling is for visualization and basic energy analysis and is similar to the schematic design or design
development. It consists of generalized systems or assemblies with approximate quantities, size,
shape, location, and orientation.
LOD 300 Model elements are suitable for construction and are the equivalent of traditional
construction documents and shop drawings. This model level would be suitable for analysis and
simulation of detailed elements and systems.
LOD 400 Model level of development considered suitable for fabrication and assembly. This model
will include all as-constructed details for Western Michigan Universitys use to manage the facility. This
is the equivalent of as-built drawings in the traditional construction process.
LOD 500 The final level of detail represents the project as it has been constructed including property
assets itemized with key parameters required by Western Michigan University added to the model.
20
All as-built record drawings and documentation at the time of turnover must be
provided in Revit. Elements included in the model must be detailed in both the 2D
and 3D documentation for internal WMU use. Elements must be clearly marked or
tagged and visual in both the 2D and 3D documentation.
All record drawings must be submitted in AutoCAD DWG, as full set PDF files, and
the Revit RVT file(s)
| October 2011
Finishes Flooring, Base, Paint, Wall coverings, Ceiling type and information
2. CONVEYANCE SYSTEMS
Elevators Package Units; Make, Model, Serial number, Parts catalog, O&M\
o
ADA Lifts Package Units; Make, Model, Serial number, Parts catalog, O&M
Dock Lifts and Levelers Package Units; Make, Model, Serial number, Parts catalog, O&M
Escalators Package Units; Make, Model, Serial number, Parts catalog, O&M
Components- Strobe, Sensor, Horn, Pull station and other features; Cut sheet for each location
21
| October 2011
Security Systems
Card Access- Component information, Cut sheets or O&M where applicable, each location
Cameras- Component information, Cut sheets or O&M where applicable, each location
Motion Sensors- Component information, Cut sheet/O&M where applicable, each location
Motorized openers- Component information, Cut sheet/O&M where applicable, each location, O&M,
Programming and setup information
4. OFFICE/CLASSROOM TECHNOLOGY
Office Technology
o
Smart boards- Component information, Cut sheets or O&M where applicable, each
location
Projectors- Component information, Cut sheets or O&M where applicable, each location
Screens- Component information, Cut sheets or O&M where applicable, each location
Classroom technology
Projectors- Component information, Cut sheets or O&M where applicable, each location
Screens- Component information, Cut sheets or O&M where applicable, each location
Multi-System Interaction- Product and System programming files and product information for all
interactive carts and podiums designed to merge multiple inputs.
Supply Fans Make, Model, Serial number, Motor HP, Belt size and quantity, Fan curve
Return Fans - Make, Model, Serial number, Motor HP, Belt size and quantity, Fan curve
22
| October 2011
Exhaust Fans - Make, Model, Serial number, Belt Size, Bearing number, Sheave numbers, Sequence
of operation, O&M
Motor - Make, Model, Serial number, HP, Frame
Outside Air Supply Systems, Heat Recovery Units Make, Model, Serial number, O&M
Fans - Make, Model, Serial number, Motor HP, Belt size and quantity, Fan curve
Emergency Fire System AHU Interaction Make, Model, Serial number, Sequence of operation,
Graphical system riser representation
Smoke Purge Fan- Make, Model, Serial number, fan cureve, Belts size and quantity
Thermostat and remote Sensors- Make, Model, Serial number, Unit(s) controlled, Spaces
controlled at each location
Remote Static pressure sensors- Make, Model, Serial number, Unit(s) controlled, Sequence of
operation or space/equipment controlled, at each location.
8. HEATING FUNCTIONS
Steam Delivery and Condensate Return
Pumping traps, Receivers- Make, Model, Serial number, Sequence of Operation, O&M
Spence type PRVs- Make, Model, Serial number, Sequence of Operation, O&M
Pumps- Make, Model, Serial number, Sequence of operation, Pump curve, O&M
Heat Exchangers- Make, Model, Serial number, Sequence of operation, Pump curve, O&M
Fin Tubes and Radiant Panels- Make, Model, Serial number, Sequence of operation, Pump
curve, O&M
Unit Heaters- Make, Model, Serial number, BTUs, Sequence of operation, O&M
Cabinet Unit Heaters- Make, Model, Serial number, BTUs, Sequence of operation, O&M
Gas fired units - Make, Model, Serial number, Sequence of operation, O&M
23
| October 2011
9. COOLING FUNCTIONS
Chillers and Refrigeration Systems Make, Model, Serial number, Unit(s), Spaces controlled, at each
location, Steam Absorption Units, Electric Chillers
Cooling Towers- Condenser Motors, Sumps, Drains, Condition Direct Expansion Refrigeration
Chilled water pumps- Make, Model, Serial number, Sequence of Operation, Pump Curve with
design operation, O&M Hyperlink
Split Systems and Package (Leibert type) AC Units- Make, Model, Serial number, Capacity in
BTU, O&M Hyperlink
o
Back flow Preventers- Make, Model, Serial number, Sequence of Operation, Certification, O&M
Booster/Circulation Pumps- Make, Model, Serial number, Design Criteria, Sequence of Operation,
O&M
Pressure Relief Valves- Make, Model, Cut sheets each location, O&M
Sanitary System
Sump Pumps- Make, Model, Serial number, Sequence of operation, Pump curve, O&M
Storm System
Roof Sumps - Component information, Cut sheets where applicable, each location
Sump pumps- Make, Model, Serial number, Sequence of operation, Pump curve, O&M
24
| October 2011
11. ARCHITECTURAL
Building Envelope Systems
Roof System- Manufacturer, Type and Material information, Green Roof Details
Air Dryers- Make, Model, Serial number, Sequence of Operation, O&M, Capacity, Mfr. Information
Monitoring and Alarm Systems- Make, Model, Serial number, Mfr. Information, O&M
13. ELECTRICAL
Electrical Distribution System
Emergency Generators- Make, Model, Serial number, O&M, Parts list, Service History
25
| October 2011
Emergency Lighting Components- Make, Model, Serial number, Mfr. Information, O&M
Lighting Systems
26
| October 2011