Professional Documents
Culture Documents
WTC2013 - BROX - Evaluation of Overstressing in Deep Tunnels - Feb 15 2013 PDF
WTC2013 - BROX - Evaluation of Overstressing in Deep Tunnels - Feb 15 2013 PDF
ABSTRACT: An increasing number of tunnels of being planned and constructed at significant depths more than
1500 m and up to 2500 m for new water transfer and transportation infrastructure. A key risk associated with deep
tunnels is overstressing due to the impact on worker safety and tunnel stability. The occurrence of overstressing
in deep hard rock tunnels is also important to recognize and evaluate prior to tunnel construction for
constructability in terms of minimizing the risk of method of excavation, construction schedule and construction
costs. Overstressing in the form of spalling and slabbing has been known to have occurred in an increasing
number of deep tunnels. Observations and anecdotal information of spalling and slabbing have been back
analyzed from several deep tunnel projects in relation to an empirical method for the prediction of spalling to
assess the validity of the empirical method for tunneling practitioners to adopt as a practical approach for
assessing the potential for overstressing in deep hard rock tunnels. A new overstressing classification has been
developed based on evaluation and observations of overstressing in a number of deep tunnels and has been
confirmed to be in good agreement with observations and anecdotal information. Unique graphical presentations
have been developed for the characterization of overstressing to assist in its early identification, severity, and
quantification as a risk evaluation tool.
Introduction
An increasing number of long tunnels are being planned at great depth in bedrock as part of
infrastructure requirements for civil, hydropower and mining projects. Tunnel boring machines (TBMs)
are strongly considered for long tunnels due to the schedule and overall cost benefits. Drill and blast
excavation has however been adopted for some long tunnels due to geological risks and improved
technology for high speed productivity. Recently completed and ongoing deep hard projects include
the 57 km twin Gotthard Rail Base Tunnel in Switzerland, the Olmos Water Supply Tunnel in Peru,
the 46 km Pahang Selangor Water Supply Tunnel in Malaysia, and the 15 km Ceneri twin rail tunnel in
Switzerland. Figure 1 shows severe overstressing in a the 5 km, 5 m diameter Piora Mulde TBM
exploration tunnel in Switzerland at a depth of 1700 m. The stability of and support requirements for
tunnels at great depth are a function of intact rock strength and the prevailing in situ stresses. Tunnels
at great depth may be subject to brittle failure as spalling due to overstressing of varying degrees
since de-stressing of the rock conditions only occurs to a very limited extent near the advancing face
unlike for drill and blast excavation.
The recognition of the potential for overstressing in deep hard rock TBM excavated tunnels is
important for worker safety, tunnel stability and support requirements, constructability evaluation of the
method of excavation, and construction schedule and construction costs. Overstressing is a serious
condition in tunnel construction that can significantly influence the safety and choice of tunneling
operations. Extreme occurrences of overstressing may result in rockbursting which has now occurred
and has also been suspected in several deep recent and onging tunnels projects.
Finally, unique graphical presentations have been developed for the characterization of overstressing
to assist in its early identification, severity, and quantification during the early stages of planning and
design for new deep tunnels.
-1-
Overstressing in the form of spalling and slabbing is known to have occurred from direct observations
and from anecdotal information in several deep hard rock tunnels around the world as listed in Table 1
below.
Table 1. Examples of Overstressing
Project
Year
Excavation
Method
Length
[km]
Size
[m]
Overburden
[m]
Actual
Overstress
Alfalfal
Lesotho Transfer
1990
1990
4.5
45
5
5
1150
1300
Rockburst
Severe
Rio Blanco
1990
TBM
11
6.5
1200
Severe
Kemano T2
Vereina
Manapouri
Casecnan
Loetschberg
El Platanal
Ashlu
Olmos
Jinping
Seymour Capilano
Qinling
Pahang Selangor
1991
1996
2002
2002
2005
2008
2009
2010
2011
2011
2012
2013
TBM
TBM
TBM
TBM
D&B/TBM
Drill & Blast
TBM
TBM
TBM
TBM
TBM
TBM
8
21
10
21
34
12
4
14
16
14
28
46
6
6.5
10
6.5
8
6
4.1
5
12
4
12
5
650
1500
1200
1400
2000
1800
600
2000
2500
550
2200
1200
Minor
Extreme
Minor
Moderate
Rockbursts
Rockbursts
Moderate
Rockbursts
Rockbursts
Rockbursts
Severe
Moderate
-2-
In Situ Stresses
3.1
Topographic Stresses
Topographic stresses can result from the re-distribution of stresses by the erosion of valleys in steep
mountainous and fjord areas. Higher than expected topographic stresses commonly exist along steep
valley sidewalls and at the toes of steep mountainous terrain where the overlying and upward
extending mountain rock contributes to the in situ stresses at depth. In some cases the maximum
boundary stress around a tunnel sited near the toe or sidewall can be as much as 2.5 times the
vertical rock cover.
This was first recognized in Norway in the early 1990s where rockbursts occurred during the
construction of new highway tunnels (Myrvang and Grimstad, 1983). The presence of higher than
expected theoretical stresses at the toe of major slopes or near the side walls of major valleys has
been confirmed on numerous projects from the measurements of minimum stresses performed as part
of the design of the length of steel linings for hydropower projects. Many of the project examples are
sited in mountainous terrain with high relief greater than 1500 m where overstressing has occurred.
3.2
While stress measurements are an important aspect of tunnel design it is recognized that it may be
difficult to perform for deep tunnels due to limited access, availability of experienced specialist
contractors, and the appreciable costs associated with the testing. Hydraulic fracturing testing can be
performed in deep boreholes and is a cost effective method whereby numerous tests can be
performed to give multiple results for greater confidence for interpretation and evaluation of the full
state of in situ stress. Where existing excavations may be present it is worthwhile to consider to carry
out overcoring in situ stress testing that can provide a more reliable estimate of the in situ state of
stress.
Evaluation of Overstressing
An evaluation of overstressing has been performed for all of deep tunnel examples listed in Table 1
above. This evaluation considered the empirical approach of spall prediction suggested by Diederichs
et al. (2010) shown in Figure 2 that provides a relationship between the estimated depth of spalling
and the ratio of the maximum boundary stress to the uniaxial compressive strength (max/c). This
approach suggests that overstressing as spalling can be expected to occur when
max/CI > 1.0,
(1)
where CI is defined as the Crack Initiation Strength and typically equal to about 40% of the uniaxial
compressive strength (UCS) and the maximum boundary stress is defined as
max= 31 - 33 = 3(3k-1),
(2)
where 1 is the maximum principal stress, 3 is the minimum principal stress, and k is the stress ratio.
Examples of the evaluation of overstressing following the empirical approach are presented for a
selected number of case projects of Table 1. (Rio Blanco, Olmos, Loetschberg).
Each of the observed cases of overstressing was evaluated by simply plotting the inferred or implied
maximum boundary stresses along the tunnel alignment in relation to the Crack Initiation Strength (CI)
as determined from uniaxial compressive strength testing of rock cores from drillholes completed both
prior to and during tunnel excavation along the tunnel alignment or from block samples that were
tested during construction for the respective tunnel projects
Figures 3, 4 and 5 present plots of limited Crack Initiation Strength (CI) data versus maximum
boundary stresses (max) for variable stress ratios of 1.02 for the Rio Blanco Tunnel, stress ratios of
1.2, 2.0, and 2.5 for the Olmos Tunnel, and stress ratios 1.2 and 2.0 for the Loetschberg Tunnel
respectively. No stress measurements were performed prior to the construction of these projects.
Overcoring stress measurements were performed during the excavation of the 11 km, TBM excavated
Rio Blanco water transfer tunnel due to overstressing experienced during construction. Figure 4
presents Crack Initiation Strengths (CI) from numerous UCS data from rock cores versus maximum
boundary stresses based on a measured stress ratio of k = 1.03.
-3-
Moderate overstressing was observed along long sections of the central part of the tunnel alignment of
the Rio Blanco Tunnel at the El Teniente Mine in Chile and the empirical assessment is in good
agreement with these findings.
-4-
-5-
Severe overstressing including rockbursts occurred along appreciable areas of the eastern high cover
section of the tunnel alignment during the excavation of the 14 km TBM excavated Olmos water
transfer tunnel in Peru. The empirical assessment is also in good agreement with these findings from
this project where very challenging excavations were experienced.
Severe overstressing including rockbursts also occurred along appreciable areas of the southern high
cover section of the tunnel alignment during the excavation of the 34 km TBM excavated section of the
Loetschberg rail tunnel in Switzerland. The empirical assessment is also in good agreement with these
findings from this project where very challenging excavations were experienced.
The plots of Crack Initiation Strengths (CI) versus the inferred maximum boundary stresses from site
specific in situ stress testing or implied topographic stresses provide a simple method of evaluation of
the observed overstressing. This approach serves to indicate the level of stress ratios existing at these
sites to have caused the observed overstressing. Based on the good agreement of the empirical
approach of assessment to the observations of actual overstressing this approach appears to be valid
for the prediction of overstressing of new deep tunnels.
Overstressing Classification
A classification for overstressing has been developed based on the observations of overstressing from
the project cases and consideration of historical work on the subject (Hoek and Marinos, 2009). The
ratio of the maximum boundary stress to the uniaxial compressive strength (max/c) is suggested as
the key parameter for the identification and severity of overstressing as follows:
Table 3. Overstress Classification
OS
Class
max/c
Description
0.45
Minor
0.60
Moderate
0.90
Severe
1.20
Extreme
1.60
Possible
Rockbursts
The quantification of overstressing can be assessed by identifying the extent over which values of the
ratio of max/c exceed 0.45 along a tunnel alignment with further characterization of the severity of
overstressing subject to the increasing ratio of max/c and the linear extent defined by station
chainages.
The occurrence of overstressing in TBM tunnels requires special tunnel support systems to effectively
contain spalling and slabbing rock fragments and under extreme conditions to protect workers from
possible rockbursting. Table 4 presents suggested tunnel support systems that have been used in a
number of TBM tunnels constructed to adequately support overstressing conditions.
-6-
Overstress Depth
Support Types
~ 1.0
Spot Bolts
1.25
Pattern Bolts/Mesh
1.60
Pattern Bolts/Channels
1.95
Steel Ribs/Mesh
2.40
Extreme overstressing and rockbursting conditions can be effectively supported with nominal impact to
TBM productivity using the McNally Roof Support System as proven on the 13 km, Olmos Water
Supply Tunnel in Peru.
Conclusions
The empirical method to estimate overstressing as spalling presented by Diederichs et al. (2010) is in
good agreement with observations of varying degrees of overstressing including rockbursting from
several interantional deep tunnel projects. This approach has been validated through evaluation of
these projects relating the Crack Initiation Strength (CI) to the inferred and calculated maximum
boundary stresses based on consideration of topographic stresses in steep valleys and in situ stress
measurements at the case projects.
Higher than expected in situ stresses and related maximum boundary stresses are believed to exist
around tunnels that are sited near the toe and aligned parallel to steep valleys. These higher than
expected stresses can result in significant overstressing over appreciable lengths of tunnels sited and
aligned in relation to such topography.
This validation serves to establish a practical approach to predict the potential for overstressing in
future deep, hard rock, tunnels, excavated either by TBMs or by traditional drill and blast. A
classification of overstressing has been proposed along with effective tunnel support systems. Unique
graphical presentations have been developed and serve for simple and quick characterization of
overstressing to assist in its early identification, severity, and quantification during the early stages of
planning and design for new tunnels.
This approach highlights the importance of having an appropriate amount of rock strength data prior to
construction from drillhole core or rock block samples along the tunnel alignment in addition to
measured in situ stresses in order to perform a comprehensive evaluation of overstressing.
Acknowledgements
The author would like to acknowledge various colleagues in the international tunneling industry who
have contributed project data to evaluate overstressing in the example projects and help to develop
the overstressing classification. These individuals and companies include Meridan Energy, the
Robbins Company, Felix Amberg, Renzo Cardoza, and Franois Vuilleumier.
-7-
References
Santiago O. Castro, Juan P. Soler, Carlos F. Andrade and Hugo A. Delucchi. 1996. Rock Mass Stress Release in
the Alfalfal Main Water Tunnel: Evidence and Remedial Actions.
Diederichs, M.S., Carter, T., and Martin, D. 2010. Practical Rock Spall Prediction in Tunnels.
Proceedings from the International Tunnel Association Conference, Vancouver, Canada.
Myrvang, A.M and Grimstad, E. 1983. Rockburst Problems in Norwegian Road Tunnels Recent
Case Histories. IMM Symposium on Rockburst Prediction and Control, London.
Hoek, E. and Marinos, P. 2009. Tunnelling in Overstressed Rock. Keynote address presented at
EUROCK2009, Rock Engineering in Difficult Ground Conditions Soft Rocks and Karst.
Dubrovnik, Croatia.
Gong, Q.M., Yin, L.J., Wu, S. Y. and Ting, Y. 2011. Rockburst and Slabbing Failure and its influence
on TBM Excavation at headrace tunnels at Jinping II hydropower station. Engineering Geology
(124) 98-108.
Franois Vuilleumier & Markus Aeschbach. 2004. The Loetschberg Base Tunnel Lessons Learned From The
Construction of The Tunnel, First Brazilian Congress on Tunnels and Underground Structures International
Seminar on South American Tunnelling.
-8-
Country
Year
Length,km
Furka
Switzerland
1982
15
Alfalfal
Chile
1990
LesothoTransfer
Lesotho
RioBlanco
Size,m
MaxDepth,m
Overstress
Actual
1400
Rockburst
1150
Rockburst
1990
45
5.0
1300
Severe
Chile
1991
11
6.5
1200
Severe
KemanoT2
Canada
1992
5.7
650
Minor
Vereina
Switzerland
1996
21
6.5
1500
Moderate
Manapouri
NewZealand
2002
10
10.0
1200
Minor
Casecnan
Philippines
2002
21
6.5
1400
Moderate
Loetschberg
Switzerland
2005
34
2000
Rockburst
ElPlatanal
Peru
2006
12
1200
Rockburst
Ashlu
Canada
2009
4.4
4.0
600
Moderate
Olmos
Peru
2010
14
5.0
2000
Rockburst
Jinping
China
2011
17
12.
2500
Rockburst
SeymourCapilano
Canada
2011
14
3.8
550
Rockburst
BrennerExploration
Italy
2012
10.5
6.3
1250
Rockburst
Cheves
Peru
2012
14
1400
Rockbursts
Qinling
China
2013
28
12
2200
Extreme
PahangSelangor
Malaysia
2013
46
5.0
1200
Moderate
Classification
Prediction