Professional Documents
Culture Documents
PDSA Cycle
Self-Learning Packet
This material was prepared by Quality Insights of Pennsylvania, the Medicare Quality Improvement Organization for
Pennsylvania, under contract with the Centers for Medicare & Medicaid Services (CMS), an agency of the U.S.
Department of Health and Human Services. The contents presented do not necessarily reflect CMS policy. Publication
number 10SOW-PA-IIPC-KD-022813. App. 2/13.
Content
Page
Introduction ..
12
13
Process Variations
16
18
20
Team Process
21
22
Team Roles
24
26
Do
32
Study ..
34
Act ..
34
36
38
40
42
Objectives
1.
2.
3.
4.
5.
Introduction
,By reading this self-learning module the reader learns about the history and pioneers of quality
management, landmark studies and findings by the Institute of Medicine, critical key quality
concepts and theories, the Plan-Do-Study-Act (PDSA) improvement method, and how to apply
basic continuous quality improvement (CQI) concepts to improve processes of care. Processes of
care occur in various health care settings, from the physicians office or the hospital, to nursing
homes or the home health care setting.
The work of continuous quality improvement is often like a puzzle: first one must decide to
work on a puzzle, find a suitable location, examine all the component pieces of the puzzle, start
the puzzle by fitting the pieces together, maintain the puzzles integrity while building the
picture, and continue to make progress by trying different pieces in different spots until the
puzzle is completed.
This independent study activity will examine the Quality Improvement Process and Methods
(PDSA cycles) used in quality improvement efforts.
Quality Management Pioneers
The human need for excellence has existed since the dawn of time. However, the means for
meeting those needs the processes of managing for quality have undergone extensive and
continuous change (Juran, 1977). Prior to the 20th century, the principles for managing quality
had been based on the ancient principles of product inspection by customers and the
craftsmanship concept. However, during the 20th century, quality management underwent drastic
changes as pioneers emerged in industry. The most notable pioneers were Shewhart, Deming and
Juran. Quality processes, methods and tools rooted in industry would be translated to
significantly impact health care by the late 20th century.
Shewhart
Walter Shewhart was a quality engineer with Bell Laboratories in the 1920s and 1930s, and was
also a professor at MIT. He is attributed with developing the Plan-Do-Study-Act, or PDSA,
cycle. He also noted that there is normal variation in any task or process.
Please try to write the letter a 10 times. You will find even though the writer (you), the pen,
and the paper are the same, and you are writing the letter a at almost the same time, that they
do not all look the same. This is a simple demonstration of normal variation.
Shewhart studied variation and determined that developing standard procedures minimized the
occurrence of events outside the normal variation. Later, Shewhart and W. Edwards Deming
became colleagues and Deming used the PDSA as a central component of his teachings on
quality.
Deming
W. Edwards Deming, who was a student of Walter Shewhart, was one of the most influential
persons working in quality improvement in the last half century. A statistician, he worked with
the people of Japan to improve their manufacturing processes. Because of his influence there,
products from Japan changed from the perception of low quality goods to desirable commodities.
4
KEY POINTS:
An additional impetus for health care organizations to adopt quality principles has been the Joint
Commission on Accreditation of Healthcare Organizations' standards. While the JCAHO
standards have evolved during the past decade, swayed in part by the Baldrige Criteria, health
care organizations have been slow to use this organizational assessment as a way to drive
performance improvement.
The demand from JCAHO for performance improvement drove many health care organizations
to learn as much as possible about continuous quality improvement. They began implementing
ideas such as: teams and facilitators with training on conflict resolution; problem solving with
use of statistical tools and standardized problem-solving procedures; data collection, including
patient, physician and employee satisfaction surveys; process management using clinical
algorithms and practice guidelines with training on pathway development; and planning using
balanced scorecards and performance measurements. With continuous quality improvement
often delegated to levels below senior management, organizations struggled to integrate and
justify their many initiatives.
Institute of Medicine Reports
In 1999, the Institute of Medicine (IOM) in Washington, D.C., released To Err Is Human:
Building a Safer Health System, an alarming report that brought tremendous public attention to
the crisis of patient safety in the United States. In 2001, IOM followed up with Crossing the
Quality Chasm: A New Health System for the 21st Century, a more detailed examination of the
immense divide between what we know to be good health care and the health care that people
actually receive.
The report calls the divide not just a gap, but a chasm, and the difference between those two
metaphors is quantitative as well as qualitative. Not only is the current health care system
lagging behind the ideal in large and numerous ways, but the system is fundamentally and
incurably unable to reach the ideal. In order to begin achieving real improvement in health care,
the whole system has to change.
The report identified six aims as critical to addressing the gap and closing the chasm. The
following is a brief overview of the aims for health care quality improvement.
Six Aims for Improvement
First, the health care must be safe. This means much more than the ancient maxim, First, do no
harm, which makes it the individual caregivers responsibility to somehow try extra hard to be
more careful (a requirement modern human factors theory has shown to be unproductive).
Instead, the aim means that safety must be a property of the system. No one should ever be
harmed by health care again.
Second, health care must be effective. It should match science, with neither underuse nor
overuse of the best available techniques every elderly heart patient who would benefit from
beta-blockers should get them, and no child with a simple ear infection should get advanced
antibiotics.
Third, health care should be patient-centered. The individual patients culture, social context,
and specific needs deserve respect, and patients should play an active role in making decisions
about their own care. That concept is especially vital today, as more people require chronic
rather than acute care.
Fourth, care should be timely. Unintended waiting that doesnt provide information or time to
heal is a system defect. Prompt attention benefits both the patient and the caregiver.
Fifth, the health care system should be efficient, constantly seeking to reduce the waste and
hence, the cost of supplies, equipment, space, capital, ideas, time and opportunities.
Sixth, health care should be equitable. Race, ethnicity, gender, and income should not prevent
anyone in the world from receiving high quality care. We need advances in health care delivery
to match the advances in medical science so the benefits of that science may reach everyone
equally.
We cannot hope to cross the chasm and achieve these aims until we make fundamental changes
to the whole health care system. All levels require dramatic improvement, from the patients
experience probably the most important level of all up to the vast environment of policy,
payment, regulation, accreditation, litigation, and professional training that ultimately shapes the
behavior, interests, and opportunities of health care.
KEY POINTS:
improve services/care and outcomes. Staff is empowered to join in the efforts to implement
change impacting both service and care.
An organization that is committed to quality provides an environment where staff feels vested in
their work and proud to be a part of the organization. Further, the environment fosters teamwork
and continually asks the question, How can we do better? The quality management process
encompasses the entire organization and identifies problems that are caused by inefficiencies.
The key elements of quality management are: creation of a supportive, customer-focused, and
quality-driven internal environment fueled by leadership commitment; systematic identification
of the processes that are critical to meeting customer needs and expectations; and use of
statistical tools to describe, measure, and continuously improve the efficiency and effectiveness
of the key processes. Quality activities to improve organizational performance should involve
more than clinical aspects of care.
Total quality management is applicable to all health care settings including, but not limited to,
the physicians office, hospital, nursing home and the home health agency.
Doing the Right Things Right
Old assumption: quality fails when people do the right things wrong
New assumption: more often, people do the wrong things right
In health care, the delivery process is not the same as manufacturing because the customer, the
patient/resident, receives the product as it is being produced. There is little or no opportunity to
inspect it before delivery. Therefore, the product needs to be planned carefully so that it meets
standards and expectations. Quality in health care means doing the right things right and making
continuous improvements. The process that meets customer expectations is the right thing.
People and departments, whose performance conforms to those processes, are doing things right.
When you clarify and improve processes, performance improves.
Performance
+
Wrong
things
done right
Process
Right
things
done right
Wrong
things
done
wrong
Right
things
done
wrong
10
11
Doing the right things right also pays off financially. By improving processes, the results will be
a reduction of costs. The bottom line will reflect increases in revenue from increased occupancy,
and reduction of staff turnover and recruitment costs. Doing the right things right leads to cost
reduction and increases business.
The Cycle of Quality Management, Structure, Process and Outcome
The quality management cycle, also known as the Juran Trilogy (Juran and Godfrey, 1999),
does not work in a linear specific event or time order. The approach is circular, and each part of
the circle is dependent upon the other for information. The components of the quality cycle
include the following:
Quality Planning team focus is on a specific organization function and uses information
generated by quality control/measurement (customer perceptions, processes, and
outcomes) and quality improvement to identify important priorities, determine if a
process exists, and to monitor the effectiveness of any new or completely redesigned
process.
Quality Improvement teams use quality control/measurement information, collecting
additional information, and performing in-depth evaluation to achieve specific
performance goals determined in quality planning or to improve or further improve an
existing process. The team analyzes causes of existing process failure, dysfunctional or
inefficient processes and systematically institutes solutions to chronic problems. Quality
improvement teams routinely analyze and disseminate variance and/or best practice
information to patients, families, and staff and utilize the scientific/problem-solving
method to improve process performance and achieve stated goals.
Quality Control/Measurement performed organization-wide by all departments and
encompasses all ongoing activities designed to measure actual performances. Quality
control/measurement activities include data collection, data aggregation and analysis.
Findings are distributed to the team so that everyone involved in analyzing,
understanding, interpreting, and acting upon measurement information is included. The
information can relate to either a particular existing or new process or global indicators of
organizational performance. Organizational functions and related processes, and
measurement indicators may change over time based on the assessment of findings.
Thinking of a circle, the quality process starts with the planning phase and moves into the quality
improvement phase, which gets information from the planning phase to implement changes to a
process. The process is then studied by gathering data and analyzing it to identify improvement.
This is the third phase of the cycle. Each relies on information provided by the other parts. Since
the cycle is circular and continuous, it does not start and stop.
Another component of the quality cycle is structure, process, and outcome. According to Avedes
Donabedian, who developed the Structure Process Outcome paradigm, structure process and
outcome are merely kinds of information used to draw conclusions about quality of care. They
are valuable to understanding quality because they are causally related:
12
Structure
Process
Outcomes
Structure, process, and outcome each represent complex sets of events and how each relates to
the other and needs to be understood before quality measurement and assessment starts. Even
when these causal relationships are understood, they should be looked at as probabilities, not
certainties. There are individual variables called patients and practitioners in the process, and
even the probability that a particular outcome is an indicator of quality can vary widely.
Structure refers to the attributes of the settings in which providers deliver health care,
including material resources (e.g., electronic health records), human resources (e.g., staff
expertise), and organizational structure (e.g., hospitals vs. clinics). For example, a
cardiologist may use a disease registry to track whether a patient with cardiovascular
disease is receiving drugs for lowering cholesterol.
Process denotes what is actually done to the patient in the giving and receiving of care.
Building on the example above, the provider could review whether an eligible patient has
been placed on an angiotensin-converting enzyme inhibitor to help prevent future heart
attacks.
Outcome is the direct result of a patients health status as a consequence of contact with
the health care system. In the above example, the patients receiving the preventive
medications mentioned above could decrease the chance of dying from a heart attack.
The Process Approach
In quality management, an effective approach is the result of having organizational commitment
to quality, a team of believers, a clear understanding of the needs and issues, and a plan of action.
Health care quality has to include all key management, clinical, and support functions. Four
factors that influence the degree to which services can achieve desired outcomes are disease
process and severity, processes of care, patient/resident compliance, and random and unidentified
variables. We have the greatest control over processes of care. Processes are sequentially related
steps intended to produce specific outcomes (Goonan, Juran Institute, 1993). The more complex
the process, the more difficult it is to manage its quality and the greater the opportunity for
deficiencies.
The Process of Quality within the System
To better understand how to apply quality improvement concepts, it is essential to understand
what a process is and how it functions within a system.
13
A process is best described as a series of steps that begins with a demand (input), some action
resulting in a product or service (output), delivered to a customer. It can be summarized as a
series of steps that changes supplier inputs into outputs for a customer.
Health care providers like doctors, nurses, medical assistants, laboratory persons, admitting
clerks, etc., are the suppliers to our patients or clients. We provide some product or service to the
customer.
Supplier
Input
Actions
Output
Customer
An example of a patient care process may be a home health nurse, who visits the patient at home
and provides assessment and care for an infected wound. The nurse is the supplier, and the
patient or client is the customer. The assessment and wound care are the action steps that use
nursing skills and provide a professional evaluation and record of the wounds progress.
There are also customer-supplier relationships that occur within a health care organization before
the ultimate product or service gets to the patient. An example of this would be the education of
a new patient care employee. Once an employee has completed the interview process, and has
accepted the job, there are multiple processes to educate and train the new employee. They often
spend several days learning about their new employer. They may complete a formal orientation
program, followed by a specific orientation to the area in which they will be working. This
orientation may include the process for teaching about the organizations mission, vision, etc.,
the job evaluation (or performance) process, the process for giving patients medications, the
process for admitting a patient, and so on. All of these separate processes are integrated into the
system of new employee orientation.
Nurse
Nursing skills
Assess and
provide
wound care
Evaluate and
record wound
progress
Patient
A series of processes form a system. What Dr. Deming stressed was that all of these processes
are interrelated within a system. The interrelationship is very important because a defect in one
process can result in a defect in other parts of the system. For example: if the new employee
does not understand the process for obtaining new medications, then the system that provides the
correct medication at the correct time, to the right patient, may break down. Therefore, trying to
improve one part of a system (or one process) has an affect on other parts of the system, and may
not always result in an improvement. A visual representation of this may be squeezing a balloon.
The balloon gets thinner at one end while the opposite end is under stress and may burst.
14
Deming wanted management and workers to view the organization as a system with
dependencies and interdependencies. An example of this could be a hospital that changes the
discharge/transfer forms for patients going to a nursing home. The use of this form in the
hospital may affect many different people in many departments (discharge planners, the
ambulance transport team, the discharge nurse, the pharmacy, etc.). Likewise, the nursing home
that is receiving the patient may have changes because the form is different (the admissions
department, the nurses receiving the patient, the pharmacy, etc.).
System
Input
Output
Input
Action
Output
Input
Action
Output
Action
To further define the connections between processes and systems, multiple processes are how the
work within a system is accomplished. Lets consider a patient coming to a hospital for surgery.
There are processes that the admissions department follows to admit a patient for surgery (these
processes may be different than those for a patient being admitted for care of pneumonia). The
operating room and laboratory also have processes to get the right patient the right procedures
and tests to prepare the patient for a safe surgical experience.
Your quality improvement efforts will be most effective by focusing efforts on the processes
performed each day. It is important to define the area for quality improvement and realize the
impact of a change in one process may have on other processes and within a system.
Experts believe that 70 to 90 percent of all quality problems are built into the work process and
systems. Inefficient and ineffective processes are at the heart of quality problems. Many
processes become overly complex as an organization grows, develops, and changes over time.
Example of Processes in a System
Aim: to improve the number of patients who receive preventive tests according to guidelines
System
Registration
Process:
Patient
registers
Record pulled
Patient info
checked
History and
Physical Process:
Patient put in
exam room
Vital signs
checked
Meds verified
Complaints
documented
Examination
Process:
Patient seen by
physician
Patient
examined
Prescriptions
Laboratory
Process:
Lab specimen
obtained
Analysis done
Results sent to
office
15
The above diagram is an example of multiple systems in the physician office setting. Noted here
are the registration process, the process for patient assessment of history and physical, the
examination process, and the laboratory process.
In summary, a process can be defined as a group of smaller tasks performed each day to bring
about an end result such as registering patients, identifying needed health services, refilling
prescriptions, ordering tests, etc. An example of interrelated systems would be in the physician
office, where they provide multiple processes that are interrelated, and considered the system.
Furthermore, a physicians office may be one of many offices owned by a health care
organization, and in this circumstance would be considered a system within a system.
KEY POINTS:
Process Variations
Process variation occurs in all processes, and no process functions exactly the same way over
time. How do we meet the demands for accountability and improvement when processes always
vary? First we must understand variation.
Random or Common Cause: is intrinsic to the process itself. It is the naturally occurring noise
of the process. An example of common cause: the patient/resident response to medication will
always vary within a group of patients/residents and even for one patient/resident over time.
Common causes refer to situations that are usually within care systems and processes (within the
normal bell-shaped curve) that are ongoing, chronic, and persistent. These common causes may
contribute to what is considered to be a normal range of variation within a process. The goal of
quality improvement is not to eliminate, but to reduce variation in a process enough to produce
and sustain stability. Common causes may also contribute to what are considered to be the less
than desirable parts of a process. Usually finding and resolving common causes of problems or
variation is more time-consuming and may be more difficult for departments, services, and QI
teams. The resolution of common causes of problems is important to continuous, incremental
improvement of quality of care and services.
16
Common Cause
Special cause is extrinsic to the process and related to identifiable patient/resident or clinical
characteristics, idiosyncratic practice patterns, or other factors that can be tracked or assigned to
root causes. Special causes refer to sentinel events, one-time occurrences, or other unique, outof-the-ordinary circumstances that give rise to a variation from what are normally expected.
Special causes are more easily identified and resolved by QI teams. Special causes account for
what are called outliers problems that happen in the tails of a normal, bell-shaped curve
representing a particular process.
Case review and root cause analysis are needed to identify special cause and take action. Such
variations, if negative (referred to as a Sentinel Event), can be quickly changed, and eliminated.
Positive variations can be analyzed for replication as better or best practice.
Variance is at the tails
Special Cause
17
KEY POINTS:
The Customer
Quality is defined by the customer and that customer may be internal to the organization.
Likewise, the customer may be the ultimate receiver of products or services provided by an
organization or company.
Excellence in quality and customer favoritism (which helps the organization to flourish) requires
continuous quality improvement. If organizations fail to examine and act on their opportunities
to improve systems and processes, they may be left behind their competition. Customers will
choose to go elsewhere for their goods and services.
It is health care professionals who can make the difference by becoming involved in making the
health care environment a more effective and efficient business. That is, a safer environment
where we do the right things and we do things right.
Quality Improvement, an Integral Part of the Organization
Continuous improvement is best accomplished by improving processes in which people work
and not just correcting the shortcomings of the people doing the work. An effective method for
getting the job done is to eliminate inefficiencies and to ensure that quality is built into the way
things are done. This means looking at out-of-date systems and processes replacing oldfashioned methods with new methods that get the appropriate results. Through continuous
quality improvement, the gap will narrow between performance and expectations. It will push
the standards upward that will result in better outcomes. Staff should be competent to follow
processes and procedures so that things are done correctly. In the clinical area, doing the right
things right is analogous to doing appropriate things effectively. Understanding the variability of
processes is a key to improving quality. In health care, there are uncontrollable variations related
to differences among individuals, organ systems, and diseases. Quality improvement stresses
understanding complex processes, measuring performance using reliable statistical methods, and
using the resulting information to build quality into the process. According to Juran, 80 percent
18
of an organizations quality problems center on work processes and not people. It is the work
processes that should be the primary target for continuous improvement initiatives.
Quality and continuous improvement must be an integral part of the job of everyone in the
organization. There is no short term or quick fix approach to make quality and continuous
improvement happen. Pioneers in quality improvement have shown that it takes between five
and 10 years to achieve breakthroughs in quality and to build continuous improvement into an
organizations culture. Strategies must be long term and enduring. John Guaspari, an expert on
quality states, Make no mistake, realizing significant improvements. is hard, hard work
involving a serious amount of grunting and sweating and heavy lifting on the part of all. It will
also mean doing things differently which is to say, it will mean change.
Change is a constant in health care. Services, techniques, and rules are continually changing.
Turnover and evolution in the workforce is continuous. Relationships are constantly changing.
These changes can be barriers to quality improvement. Turf wars can prevent people from
crossing department lines to solve problems that can impact team process. Staffing and time can
also be a barrier to quality improvement. If staff does not have the time to participate on quality
improvement teams, it can have a demoralizing effect. However, some changes make quality
improvement easier, such as regulatory requirements and the demand of payors for data
regarding quality. Positive change through empowerment and staff inclusion in decision-making
can have a significant impact on the quality improvement process.
Organizations that embrace quality improvement look at processes across the entire organization
and do not compartmentalize issues into silos. Implementing a culture of continuous quality
improvement means that changes can take place anywhere and at any level within the
organization. As stated by Phillip B. Crosby, Quality is the result of a carefully constructed
culture; it has to be the fabric of the organization not part of the fabric, but the actual fabric. It
is not hard for a modern management team to produce quality if they are willing to learn how to
change and implement. (Crosby, 1979)
KEY POINTS:
19
Middle managers are the ones who have to do the actual work, and they need to be reassured of
the commitment of senior management. Middle management needs to transmit that credibility to
the rest of the employees. The determination they show is what will convince people that the
facility is really serious about quality. Improvement should occur at the process and systems
levels simultaneously. The cycles of improvement need to be incorporated into everyones daily
work life. It should not be thought of as just another project. Teams should actively seek new
ideas, try ideas quickly and focus on results. Leadership needs to support the improvement
process by enrolling all staff in the process. Support also means providing resources such as
training, materials, and equipment as well as freeing up staff to participate on teams. The
leadership must oversee the process to ensure that the teams are able to accomplish their goals.
Leaders should not delegate this process to other staff members without providing oversight,
which includes sitting on teams and requiring ongoing reporting. Senior leaders should require
team leaders to report their progress and findings to the quality improvement committee.
KEY POINTS:
Leadership
o Key role is fostering quality improvement throughout the
organization
o Central responsibility to develop a quality culture
o Responsible for developing and fostering the organizations
mission and vision statements
o Provides oversight of the quality improvement processes and
team
o Communicates quality improvement is not optional
o Demonstrates commitment to quality improvement through
investment of time, funds and education
Team Process
Developing a Team
Organizations that have implemented teams have a competitive advantage over those who do
not. Teams are now considered to be a superior way to organize work. Teams are more flexible
than the traditional department and can respond faster to issues. Teamwork creates synergy,
which generates better ideas. A team is a small group of people who come together to share ideas
and make decisions in order to achieve a goal. The team may include staff nurses, nursing or
medical assistants, housekeepers, dietary staff, social workers, rehab staff, front office staff, back
office staff and management. Teams should not consist only of management staff. A team is
usually made up of six to seven people; however, in smaller organizations this may be less. The
benefits of teamwork include shared knowledge and experience, and more creativity and
flexibility. Teams create a learning culture, increase the likelihood that errors will be discovered
sooner, and increase commitment and accountability. They also reduce the need for supervision.
21
In spite of their many advantages, there are some disadvantages to teams. They are finding time
to meet, some members hate going to meetings, relationship building is hard for team members,
decision-making can be a slow and painful process, and overall corporate culture may not be
supportive to team decisions.
What makes a good team?
What a team does is think! Think of your team as a collective brain that comes together to make
decisions. If the team is a thinking brain, the output is ideas and solutions that are arrived at by
collaboration of the whole team. Members need to form an atmosphere of cooperation rather
than competition. There needs to be participation by all members of the team and a belief that
each member is accountable for the success or failure of the team. Members need to feel a sense
of trust so that there can be communication and a free expression of opinion. The team needs to
recognize that disagreement may be a positive factor. A good team evaluates the performance of
the team periodically to see if it is on target.
Phases of Team Development
When someone joins a team, he or she needs to understand that teams go through a series of
stages in development. Teams behave differently at each stage. Those stages are forming,
storming, norming, and performing. The team leader who is developing a new team needs to pay
attention to each of the stages.
Stage 1: Forming When the team first forms, team members feel excitement, anxiety
and uncertainty. Because of this uncertainty, most new members will sit back and size up
the situation. Very few will take the initiative to jump right in. They will depend on the
team leader to give them direction and structure. New members want to fit in or find a
position on the team.
The team leader needs to recognize what people want and provide structure. The team
leader needs to provide the members with a sound orientation, a clear framework for the
team to operate, a definition of goals and clarification of the roles so the team has a clear
understanding of what they will be doing. This is a stage where the individual moves to a
team member.
Stage II: Storming Storming is an expected part of team formation. Storming is the
most difficult stage that the team goes through. After the team forms and starts to meet,
the members realize that its not as easy as it seems, and they may become disappointed
and disillusioned. They may become frustrated with the amount of work that is expected
of them. Teams can storm about any part of the process, the work, the timeframe or
meeting time. They argue with each other and become testy or overzealous. Cliques can
form. Power struggles are also common and could be directed at the team leader.
At this stage, its understandable to think the team will dissolve. It should be looked at as
teenagers spreading their wings. The members are expressing resistance to working
collaboratively with each other. They are beginning to understand each other. An
effective leader will become the facilitator and use this opportunity to allow members to
problem-solve their issues. If the leader has specific goals and plans, this stage may be
22
less severe. The worst thing the team leader can do at this stage is to jump in and solve
the problems for the team.
During this period, the productivity of the team will stall. The team becomes distracted
because of its internal problems. When the team works through these tough times, they
develop self-esteem and confidence in their ability. They begin to work together and
share control.
Stage III: Norming During this stage, the members become a team. Individual roles
become clear and team members are more satisfied. Animosities are replaced with trust,
respect and support. They are accepting the ground rules, understanding their roles in the
team structure and the other members. There is an increased level of satisfaction as the
team begins to solve major problems. The team develops cohesion, a common goal. They
accept membership in the team. There is a relief that everything is going to work out.
The team leader should implement correct interventions to solve issues and to help
members develop new skills, including providing support as the team makes
improvements. Through facilitation, the team leader gradually shifts the power from
themselves to the team. The team starts to make progress.
Stage IV: Performing In this stage, the team is ready to get on with the work of the
organization. Team members are now experienced at working together and feel progress
is being made. They start to solve problems and implement change. There is a return of
the excitement and energy in participating in team activities as members feel confident in
their abilities and share in the leadership role. The team satisfaction increases with the
progress made as they work interdependently and recognize each others strengths and
weaknesses. There is constructive self-change.
The team leader needs to be careful not to take back control as the team members begin
sharing the leadership role. Mutual respect and a letting go of power should be a
dominant theme in this stage. The team leader needs to build openness to change by
updating methods and procedures to support cooperation, help the team to understand and
manage change, advocate for the team to senior management and other teams, and
monitor the teams work progress and celebrate its achievements.
Teams move though these stages at different speeds. Some teams can go through the stages in
several meetings or it could take some teams several months. It is not unusual for a team to go
through the stages several times if members change. The team leader should be persistent and
patient with the team as they move through the stages. These individuals will grow into a team.
Team members need to be aware of the stages the group will go through as it may relieve some
fears that the team will not succeed, including emphasis on the point that all teams have high and
low cycles. The mood of the team usually reflects its fortune. No matter how well a team works
together, progress is never smooth. Its the team leaders responsibility to provide the direction
and support, which allow the team to become a high performance team.
23
Team Roles
Now that a goal has been set, the next step is establishing team roles. Formal roles are roles with
explicit responsibilities that are set prior to the teams forming. They include the team leader
who directs the groups efforts and runs the meetings. If the team leader is unavailable, the
facilitator can assume the role. The recorder/note taker takes notes and records decisions. The
timekeeper keeps the team on schedule. Informal roles are roles that members take on
themselves. These include the initiator, the person who proposes new ideas, the synthesizer who
blends the ideas together, the coordinator who leads in coordinating activities, the harmonizer
who resolves differences by finding common ground, the supporter who offers praise and builds
solidarity and the clarifier who summarizes whats been done.
Team Rules
To encourage a positive team environment, team members need a clear set of rules or norms.
Usually the only rules that work for a team are the ones they create for themselves, and these
should be posted each time there is a meeting. A few examples of team rules are:
Decision-making
A team needs to learn to make effective decisions. Besides voting, there are other decisionmaking approaches that can be used. The team needs to decide which option is best prior to any
decision-making discussions. There are advantages and disadvantages for each option. Examples
are:
Unanimous These decisions are usually made quickly and they occur with more simple
issues.
One person decides The team decides to defer to one person on the team to make this
decision. Not all decisions need to be made by the entire team. Input from other team
members may be considered before the decision is made.
Compromise This is the negotiated approach when team members are polarized. A
middle position is found between the two sides.
Multi-voting This is a way of rank ordering a long list of options based on a set of
criteria. All choices are ranked in order of priority, with one being the best.
Majority voting Team members choose the option they favor and the option with the
most votes is considered the best choice. The quality of this method is enhanced if there
is discussion and idea sharing prior to the vote.
24
KEY POINTS:
Teams
o Collective brain that comes together to make decisions
o Develop through phases: Forming, Storming, Norming,
Performing
o Establish team roles and team rules
o Learn to make effective decisions
o Use several methods to effectively problem-solve
25
The P is for Plan. When beginning a QI journey, planning is the most important, intense, and
longest piece of the cycle. This learning module will review the components of planning in
detail.
The D is for the Do phase when the QI team actually implements a change and collects
information about the change. Sometimes this change is a test or a pilot, to learn what are the
best methods and changes to make.
The S, or Study phase, requires the team to examine the effects of the do phase, analyzing and
evaluating the data and observations about the change that was made.
The A, or the Act phase, means that the QI team will decide what the next step is in its QI
puzzle. Based on what they learned, should they continue on the journey, alter the plan to
improve the results, or abandon this plan and make a fresh attempt during the next PDSA cycle?
P
A
D
S
Plan
Planning is the beginning of the journey and the most important and longest part of the journey.
Planning for a successful QI project involves eight steps. Like getting organized to put together a
1,000-piece puzzle, we must develop a concrete plan for the QI project. There are multiple steps
in developing a well-organized, comprehensive plan.
Planning Step 1: Focus - Determine the Focus of the Project
Keeping in mind that we cannot improve everything at the same time, strategic questions should
be asked:
26
It is helpful to examine many aspects of what you may think needs improvement. For some, the
area of focus will be determined by what causes the most problems or is associated with the
highest costs. It is important to look at what information or data might be available to help define
the problem as high cost, high volume or problem prone.
Sometimes the focus of improvement is mandated by administration or regulatory agencies.
Sometimes it is a quick and easy fix, which is what some call the low hanging fruit. This is
something that has the potential to be improved or fixed with minimum effort, cost (resources,
time and personnel) and disruption.
Once the improvement focus has been determined, the next step is to organize a quality
improvement team.
Planning Step 2: Establish a Quality Improvement Team
Keeping in mind the team concepts presented previously, formation of a quality improvement
team begins during the planning phase. The team is defined as a designated group of people in a
system that comes together for a period of time to focus on improving a process. All QI teams
usually consist of a leader and a QI facilitator with additional team members determined by the
size of the organization and the size of the project. Often the leader of the QI team is assigned
this accountability by the organization. The facilitator is a person skilled in quality improvement
techniques who supports the improvement process.
For example, some larger physician offices, nursing homes orhealth care systems may have a
permanent quality improvement team or committee established, while in a smaller physicians
office, hospital or nursing home, a team may consist of just two or three people. Whether your
team is large or small, quality improvement is the result of team members working together to
make a positive difference.
The composition of your team depends primarily on the focus of the improvement effort and the
size of your organization, agency or office. It is important when forming a team that many of the
members represent persons knowledgeable about the process being improved.
Equally important to successful health care QI is support from physicians and administration.
Any process improvement that impacts the work of the health care providers or needs financial
backing is best served by obtaining that support during the planning phase. Although physicians
and administrators may not be able to attend every team meeting, providing frequent
communication and keeping them updated will help to keep the teams work running smoothly.
Many teams include a patient or client. As the ultimate customer of the process, patients can
offer some unique perspectives on the QI effort and its impact. Important questions to consider in
selecting the right team are:
It is critical to involve some people who know the work that is being evaluated. They have
insights from living in the real world that others would not be able to contribute. Also critical
is to include those people who have the power to make things work in the organization, or the
power to veto (reject or derail) the entire QI effort.
A champion is someone who will help to promote the QI project. This person should be invested
in the need to improve, have the respect of others, be willing to take risks, and be respected by
others in leadership positions.
As explained earlier, when we change one process it usually affects other processes or parts of
the system. Therefore, it is very helpful to include a representative from areas that will be
affected by the quality improvement change. Sometimes it is best to have these representatives
be ad hoc members who participate in the team meetings, as needed.
Critical to the team function is defining and clarifying team responsibilities. All of the team
members should be committed to improving the area of focus.
Some teams establish ground rules to promote teamwork. Establishing ground rules in the
beginning will assist the team in functioning in a consistent manner. Other team responsibilities
include reviewing the literature and gathering data for making quality improvement decisions.
Many strategies for effective team meetings can be found in the book The Team Handbook by
Scholtes.(2003) (See reference list at the end of independent study module.)
Keeping leadership advised of the teams progress is an important element. By preparing brief
summary reports on a monthly basis, the QI team can keep the project in the minds of busy
leaders. Good communication will greatly enhance the projects implementation and early
adaptation of a new process by the staff.
Planning Step 3: Establish the Goals The AIM Statement
The third step is to set a goal or a target. Goals help to keep everyone on track. Goals define the
desired result or purpose and are guides to action. Everyone should know their accountability for
the goal(s) and meet those expectations.
In their text The Model for Improvement, Langley, (1996) et al., describe three questions for
quality improvement. (See the reference list at the end of independent study module.) They
recommend that the QI team constantly ask, What are we trying to accomplish? to keep
everyone focused on the goal. With active committed team members who are energized to make
things right, teams often get sidetracked into areas that need improvement, but that are not the
focus of this team at this time. A good strategy is to validate side issues by noting them in a
parking lot. A parking lot can be a part of the teams meeting minutes. This way the concern is
noted and documented. This method often allows the team to move forward with the current
goal.
28
Interview workers about the steps in the current process how do they do it?
Get the patients/residents point of view how do they see it?
Make a process flow chart of all the steps use a sticky note for each step.
Look for variations (differences) in the processes.
Check for unnecessary steps (such as charting the same thing in multiple places).
Once the current process has been charted and examined, the team should look for areas of
redundancy, variation and steps that are not necessary. (Refer to Appendix A for Brainstorming
and Flow Charting Procedure Guidelines.)
Planning Step 5: Examine Solutions
The fifth step in planning is sometimes the most fun brainstorming solutions. The QI team may
examine the quick and easy fixes, the low hanging fruit. One of these might be to remove
redundancy identified in the process flow chart. One trap that many have tried is to do more of
the same. With this approach they add more people, more steps in a process, or more time. This
does not really improve the process and often only adds cost.
This is the time to use your creativity. Look beyond the obvious solutions. Do not be limited by
the seemingly impossible. Sometimes great changes come from thinking broadly and using ones
imagination. Consider the hospital that eliminated the admitting department. They designated a
29
bed manager position who assigned rooms to patients, and the unit secretary completed the
admission paperwork when the patient arrived in the room. This enhanced patient satisfaction,
eliminated wait times in admitting, and facilitated getting admitting paperwork started.
A good strategy is to ask, What if ? or pretend you are starting from scratch or that you have
an unlimited budget. These methods often stimulate the creative side of problem solving. It is
best to list all ideas, even those that are outrageous, because they help stimulate others to think
outside the normal boundaries.
Planning Step 6: Select a Change
After generating and examining the possible solutions to improve quality, the team must decide
what they will do next. Do not eliminate all of the possibilities. If the first change does not work
out, the others may be very useful in redesigning an improvement. There are two questions that
are recommended by the authors of The Model for Improvement (Langley, 1996 et al.) that the
team can ask:
What are we trying to accomplish? (Remember this question from earlier in the module?
This will keep the QI team focused on the priorities.)
What change can we make that will result in improvement?
Furthermore, the team may decide to implement the change as a test or pilot. Testing the change
on a small scale allows the QI team to gain knowledge about how the change will work with
minimal risk. The knowledge gained with each test will facilitate acceptance when the final
change is implemented. Doing a pilot test permits the team to check out different alternatives and
explore the possibility of combining several points with a small risk for negative results.
Planning Step 7: Determine Measures
Types of data defined:
Measurement This is the measurement of data by the number of each observation or unit.
Examples: time, overtime hours, costs
Count This data consists of counts of observations by categories. Rates or percentages that
are calculated using count data in the numerator fall into this type of data. Examples:
medication errors, daily census, falls, pressure sores, weight loss
Subjective Data This is often used to measure courtesy, level of quality or customer service
satisfaction. It is the customers perceptions or reactions to a process, product or services.
The seventh step in the Plan portion of PDSA is to plan for data needs. The Model for
Improvement authors give us a third and final question to evaluate this: How will we know that
a change is an improvement? (Langley, 1996, et al.) If we do not make observations about the
change, we will not be sure that the change we made was a good change. All we will know is
that it is different. To make our test of a change as objective (free from bias or opinion) as
possible, we need to gather objective information about the change. When we only use personal
30
observations, we may influence the results by seeing what we want to see or what we expect to
happen.
Objective data means that personal or subjective influence has been minimized, or eliminated. If
personal, subjective or opinion information is used, it must be noted as such and carries less
weight than objective data. To decrease bias, the QI team may decide to develop an assessment
form in order to consistently gain information about the change from affected workers, or use
patient or staff satisfaction surveys. (See Attachment B: Developing a Check Sheet)
To gain objective data, the QI team may decide to use before and after measures like time to
complete a process, number of people involved in a process, number of forms completed
accurately, scores on tests, quality indicator rates, etc.
Determine who will collect the data, what type of data collection form will they use, when the
data collection will occur, etc. An experienced person should plan to collate and review the data,
and then present the information to the team.
Planning Step 8: Detail the Test Plan
The final step in the planning phase is to develop a detailed plan for the change or test. The QI
team should identify the work efforts required for the test of change. From this list of work, they
should develop an implementation action plan that notes who is responsible for what activities
during the test of change. Each QI team member needs to be involved and take accountability.
Sometimes posting a flowchart of the new process is helpful. However, if the flow chart is too
complicated, it may just raise anxiety.
If the QI team discusses possible barriers that may arise, then they will be more prepared for
those surprises that always happen. Having discussed them will facilitate rapid response and
solutions.
The personnel involved in the test will feel more positive about the stress of a change if they are
kept informed, if the QI team is visible and concerned about the test personnel, and if they are
recognized for their efforts. Sometimes a treat for the test personnel (like pizza or candy) buys a
lot more than a thank you snack. It often says, We know this is stressful, and we appreciate your
commitment to make this work and to improve patient care, and we care about you.
At the end of planning, the QI team is very focused on the work of improvement and is able to
work together as a team. Specific purpose and goals have been determined and sanctioned by the
team and by administration. The QI team has detailed knowledge of the process they are
improving, and a plan that will test a change. The team has developed a concrete plan to evaluate
the change with measurement tools and a plan for analyzing the data that they collect.
31
KEY POINTS:
After planning, the quality improvement team should
have a:
P
D
A
S
Do
The test or change is implemented at this time. The QI team should follow the detailed action
plan developed in the planning phase.
Consider the following:
The change should be monitored closely while gathering information about the change process.
Data collection forms should be completed as the change is being carried out. This data should
be reviewed as soon as possible to allow the QI team to make any necessary changes quickly.
Tracking successes and barriers that occur during the change will help the team to develop
lessons learned from the change process. These data will be most helpful in the next PDSA cycle
and in future QI projects.
32
Important to the success of the PDSA methodology is that a team should not wait for a proposed
process to become perfected before trying it. The PDSA methodology supports trying changes
early on a small scale and making adjustments based on what is learned during each trial. Some
tips to keep in mind as you test your quality improvement change are:
First, go ahead and try the change. Do not wait until it has been perfected. Observe the
consequences of your trial, and improve the process as you go. Remember to start with smallscale trials. As you improve the new process, increase the size of your trials.
As noted during planning, data needs to be collected during the implementation phase. The goal
is to make data collection easy to do and focused on the important information needed to
determine success or failure.
Some data may already be available. Information on the number of patients or clients is usually
available. In the home care arena, times for patients visits are already tracked, the number of
laboratory studies would be easy to capture, the number of cases in an Emergency Department is
routinely tracked, etc.
The KISS rule applies here: Keep It Short and Simple; or some may call it Keep It Simple, Silly.
Consider the following:
Upon conclusion of the Do phase, The QI team should have data and information about the
change. The outcomes of the Do phase of PDSA should include an identified list of driving and
restraining forces. Driving forces are things, people, or conditions that help the change be
successful, while restraining forces are those that prevent positive progress and become barriers.
P
A
D
S
33
Study
The team will examine and evaluate the data to determine what was learned from the test or
change. Studying the result means that the team will examine all aspects of the change. They will
focus on:
Each pilot test allows the team to learn about the change process and add to the knowledge they
have gained.
QI team members should be able to understand the data results and have a clearer understanding
of the issues with changing a process.
The team develops a statement regarding the success or failure of the change and can make
recommendations for further improvement.
After studying the results, the team should have:
P
D
S
Act
Here the team decides the next steps for the project. There are several options the team needs to
consider before taking the next step.
34
After evaluating all the information and data collected about the change, the project QI team
usually makes one of the following three decisions:
Adopt the change as it was conducted. This occurs when the change resulted in
improvement. The next PDSA cycles would be focused on making the change a
permanent part of the process and spreading it to other areas.
After the final change has been determined by pilot testing, the decision to adopt the
change is made. The improvement will be implemented on a larger scale and the new
process must gain acceptance and be fully integrated into the system through a spread
initiative. There are several steps to consider when planning for spread within the
organization. First, senior leadership must assess the organizations readiness to
undertake a spread initiative and provide the support and resources for success. There
should be alignment between the goals of the initiative and the organizations key
strategic objectives.
Development of the spread team with an executive leader, day-to-day manager,
representatives from the pilot areas and other clinical experts, as well as IT and support
staff is critical for agreement on the key strategies that are to be spread. This team will be
responsible for the communication and measurement plans. Lessons learned from full
system implementation will help with future quality improvement initiatives.
As the change is made permanent, a method to evaluate the change over a period of time
must be developed by the team. The purpose of this monitoring and evaluation is to make
sure that the goal is being maintained or sustained, also known as holding the gain.
It is human nature to return to the comfortable and familiar way of doing things. With a
plan to monitor the change, the QI team will have information to assess the permanence
of the change. The team may determine to measure and evaluate the change weekly or
monthly at first and then fall back to a quarterly or yearly review. Whatever method or
time period is selected, it is important to review the data periodically to ensure that your
change is still an improvement over time.
Here are a few suggestions:
Make reversal to the previous way of doing things as difficult as possible. Most of
us do not like to change at first. Make it difficult to slip back into the old way of
doing things.
Make someone responsible for reviewing the process and the data on a regular
basis.
Establish the new process as the standard operating procedure. It needs to be
documented as a procedure or expectation; the way things are done.
Encourage staff to use the new process by posting the data showing before and
after results, followed by periodic updates from monitoring.
35
Adapt (or alter) the current change based on what was learned. This often means
tweaking the change, or making some small improvements, or some additions to the
original plan based on what was learned. The next PDSA cycle would be to revise the
plan, implement the revised plan, gather and evaluate data, and decide again to adopt,
adapt or abandon the change. This process is repeated until the team is satisfied with the
results and ready to make the change permanent.
Abandon the change as perhaps there was not much to salvage from the first PDSA
cycle. Sometimes it is easier to start fresh, than to do major reconstruction of a plan.
Depending on the change results and the evaluation of driving and restraining forces
affecting the change, perhaps a new test site should be selected, or resurrect one of the
other solutions identified in the planning phase. Sometimes interviewing the workers
from the test site can give the team valuable insights and positive suggestions.
Act
Plan
Study
Do
This diagram is a picture of The Model for Improvement by Langley, (1996) et al. The three
important questions at the top of the model were discussed during the Plan and Do phases of
PDSA. The three questions are:
36
The large arrows indicate that the QI team needs to continually ask these questions as they
progress through the PDSA cycles. The model emphasizes rapid trial and learning from each
PDSA test. This integration of the three questions helps to guide the QI team throughout the
improvement work. They keep the team focused on the specific goal and help the team to plan
and evaluate the change for improvement. Quick small-scale trials are emphasized while
continuing to improve the change as you go.
S
Future
Cycles
Cycle 3
Cycle 2
Cycle 1
The above model visually depicts the rapid trial and learn aspect of The Model for Improvement
by Langley, (1996) et al. As you can see, the PDSA cycles continue to repeat until the change is
ready to be implemented on a larger scale. The improvement ramp begins on the left with
improvement ideas that were selected and developed by the QI team. As the team progresses
through each PDSA cycle, they test and learn more about what works and why it works.
For example, your QI team may desire to improve patient registration and design a new form.
During the first PDSA cycle the new form is tested on a few patients. Several problems arise and
are discussed in the study phase. The team decides (act phase) to adapt the first form. After
making adjustments, the registration form is tested again (the second PDSA cycle), for an entire
day. The registration process flow improves substantially but a few barriers remain. The team
determines that it must make a few more changes, and returns to the planning stage for the third
PDSA cycle.
After a few cycles, the team implements a patient registration form that improves the overall
patient registration process. With each test and learn PDSA cycle, more knowledge is gained
about the best process for registration. Finally, at the top of the ramp, as more and more is known
about the best process, the team has reached the goal: a change that resulted in improvement.
The act decision is to adopt this final change.
37
Cycle: 1
Date:
38
Barriers
Teams working on reducing MRSA infections and transmission have learned a great deal about
barriers to improvement and how to address them. Some common challenges and solutions:
1. Lack of support by leadership
Solution: Use opinion leaders (physicians) and data, if possible; a business case for the
project may help to win leadership support.
2. Uneven physician acceptance of new practices
Solution: Use physician opinion leaders, review the medical literature and feedback data on
a physician-specific level. Remember that physicians may fall anywhere on the Adoption of
Innovations curve; work first with your early adopters and use their stories to convince the
majority.
3. Lack of clear ownership for care practices
Solution: Work with physician leaders to develop standard approaches to postoperative care,
including clear designation of the physician owner.
Sample from:
IHI, 5 Million Lives Campaign
How-to Guide: Reduce Methicillin-Resistant Staphylococcus Aureus Infection
This document is in the public domain and may be used and reprinted without permission provided appropriate
reference is made to the Institute for Healthcare Improvement.
Summary
The QI with PDSA puzzle is complete. The purpose of this report was to provide health care
providers with an opportunity to learn about the quality improvement process and the application
of the PDSA cycle. Our goal was to assist you in supporting quality improvement efforts in your
health care organization.
39
40
Flowcharting
After you have completed the brainstorming, the next step is to flowchart the current process to
understand where the problem is occurring. It is important to flowchart the process as it is, not
what you want or think it should be. This helps to provide understanding and allows the team to
focus on the area that is not performing correctly.
If you dont have a process for the area you chose to improve, then flowchart what you think the
process should be.
A flowchart is a picture of the steps of a process, and it is used to examine the sequence of steps
and identify repeated steps, unnecessary steps, and any inefficiency in the process. It creates a
common understanding of the process flow. It assists in understanding the actual steps of a
process and how one part can affect another part of the process.
Procedure
1.
Determine the frame or boundaries of the process.
2.
Come to an agreement on where the process starts and where it ends.
3.
Determine the steps.
4.
After brainstorming, put each step on a sticky note. Have everyone on the team
participate.
5.
Sequence the steps on a flipchart.
a. chronologically from the start of the process to the end of the process
b. what it is, not what it should be
6.
Draw the flowchart using the appropriate symbols. Start out simple, using oval (start,
finish), box (action step), and diamond (decision) shapes. Connect the direction of the
flow with arrows.
7.
Test the flowchart for completeness.
a. Review all the steps for completeness (correct symbols, closed loops, arrows
pointing in the right direction).
b. Make sure the flowchart has enough detail to find improvement opportunities.
8.
Finalize the flowchart.
a. Look for problem areas and get feedback from the team.
9.
Interpret the flowchart.
a. Is the process functioning the way it should?
b. Are people following it?
c. Is there complexity?
d. Are there redundancies?
e. How different is the current from the ideal?
f. Where can it be improved?
After completing and analyzing the flowchart and identifying the areas for improvement, the
next step in the process might be doing a root cause analysis or, having identified the areas,
select one area to work on.
41
Distinguish between fact and opinion (opinion example: How do residents perceive
the quality of the meals prepared by the facilitys dietary department?)
Gather data about how often a problem is occurring (fact example: How often are
residents receiving meal trays with hot food that is less then 140 degrees and cold
food that is greater than 40 degrees?)
Gather data about the type of problem occurring (example: What is the average
timeframe that residents trays are stored in carts on the nursing unit before being
delivered? Or, what is the average timeframe that residents trays sit in carts in the
kitchen before being delivered to the nursing unit?)
42
References
Source
Berwick, D. M, Nolan TW, Whittington, J (2008), The Triple Aim: Cure, Health, And Cost,
Health Affairs, 27, No. 3 (2008): 759-769. http://content.healthaffairs.org/cgi/content/full/27/3/759
Accessed online September 9, 2010.
McLaughlin, D, Kaluzny, A. (2006) Continuous Quality Improvement in Health Care, 3rd Edition,
Jones & Barlett, Sudbury, Mass.
Committee on Quality of Health Care in America, Institute of Medicine (2001). Crossing the
Quality Chasm: A New Health System for the 21st Century. Last accessed online February 2, 2009.
www.nap.edu/catalog.php?record_id=10027
Batalden PB, Buchannan ED, (1989) Industrial Models of Quality Improvement, in Providing
Quality Care: The Challenge to Clinicians. By N. Goldfield and D.B. Nash (eds), the American
College of Physicians, Philadelphia, PA, 1989.
Donabedian, A, (1992), The Role of Outcomes in Quality Assessment and Assurance, QRB Qual
Rev Bull.18(11):356-360.
Roberts, James S., Jack G. Coate, and Robert Redman, 1987. A history of the Joint Commission on
Accreditation of Hospitals. JAMA 256 (7): 936-40.
Blanchard, K, Carew, D, and Parise-Carew, E (2009), The One Minute Manager Builds High
Performing Teams, Harper Collins, New York, NY.
Brown, J. (2010/2011), The Healthcare Quality Handbook, A Professional Resource and Study
Guide, 25th Edition, Pasadena, CA.
Clawson, J G (2008), Level Three Leadership, Getting Below the Surface, 4th Edition, PrenticeHall, Inc, Upper Saddle River, New Jersey.
Crosby, P B (1979), Quality is Free, McGraw-Hill, Inc. New York, NY.
Crosby, P B (1984), Quality Without Tears, The Art of Hassle-Free Management, McGraw-Hill,
New York, NY.
Deming, E W (1990), Out of Crisis, Massachusetts Institute of Technology, Cambridge, MA, 10th
ed.
Dlugacz, Y D, Restifo, A, and Greenwood, A (2004), The Quality Handbook for Healthcare
Organizations: A Managers Guide to Tools and Programs, Jossey-Bass, San Francisco, CA.
Goonan, KJ (1993), Clinical Quality and Total Quality Management, Juran Institute, Wilton, CT.
Guaspari, J. Quality Improvement Quality 101. Missouri Primary Care Associates. accessed on
line February 12, 2009. www.mo-pca.org/quality_101.htm
Juran, J M (1989), Juran on Leadership for Quality: An Executive Handbook, The Free Press, New
York, NY.
Juran, J M., and DeFeo, JA, (2009), Jurans Quality Handbook, McGraw-Hill, Sixth edition, New
York, NY.
Kohn, LT, Corrigan, JM, and Donaldson, MS Editors; Committee on Quality of Health Care in
America, Institute of Medicine (1999). To Err is Human: Building a Safer Health System. Last
accessed online October 5, 2010.
Langley GJ, Nolan KM, Nolan TW, Norman CL, and Provost LP. (1996), The Improvement
Guide. Jossey-Bass Publishers, San Francisco, CA.
Kaplan, Robert S., Norton, David P., ( 1996) The Balanced Scorecard. Harvard Business School
Press, Cambridge, MA.
Scholtes, PR, Joiner, BL., and Strubel, BJ (2003), The Team Handbook, Oriel, Inc., 3rd ed.,
Madison, WI.
Publish Date
2008
2006
2001
1989
1992
1987
2009
2010/2011
2008
1979
1984
1990
2004
1993
2009
2009
1998
1999
1996
1996
2003
43