Professional Documents
Culture Documents
Project Management With Certain Time Estimates: - Summary of Steps
Project Management With Certain Time Estimates: - Summary of Steps
Estimates
Summary of steps:
Determine activities that need to be accomplished
Determine precedence relationships and completion
times
Construct network diagram
Determine the critical path
Determine early start and late start schedules
3
1
6
4
4 weeks
10 weeks
2 weeks
3 weeks
5
4 weeks
16 weeks
4 weeks
1 week
4 weeks
10 weeks
2 weeks
3 weeks
5
4 weeks
16 weeks
4 weeks
1 week
C.P. = 40 weeks
4 weeks
10 weeks
2 weeks
3 weeks
5
4 weeks
16 weeks
4 weeks
1 week
New information
suggests that Activity 4
will take 5 weeks instead
of 4
4 weeks
10 weeks
2 weeks
3 weeks
5
5 weeks
16 weeks
4 weeks
1 week
C.P. = 40 weeks
4 weeks
10 weeks
2 weeks
3 weeks
5
4 weeks
16 weeks
4 weeks
1 week
4 weeks
10 weeks
2 weeks
3 weeks
5
6 weeks
16 weeks
4 weeks
1 week
C.P. = 41 weeks
Determining Slack
Slack - The amount of time an activity on a non-critical path
can be delayed without affecting the duration of the project
(i.e., without putting it on the critical path)
Uses four calculated values
THIS IS CALLED
THE FORWARD
PASS
Calculating Slack
Slack - The amount of time an
activity on a non-critical path
can be delayed without affecting
the duration of the project (i.e.,
putting it on the critical path)
Computed by either:
Late Start - Early Start
or
Late Finish - Early Finish
Activities that have zero slack are, by definition, on the critical path
o 4m p
Te
6
Where:
Te
= Expected Time
o
m
p
= Optimistic estimate
= Most likely estimate
= Worst-case (pessimistic) estimate
Optimistic
3
8
1
Estimates
Most Likely
4
10
2
Pessimistic
5
12
4
Activity #1
3 4(4) 5
Te
4.00 weeks
6
Activity #2
8 4(10) 12
Te
10.00
6
Activity #3
1 4(2) 4
Te
2.17
6
weeks
weeks
4 weeks
10 weeks
2.17 weeks
3 weeks
5
4.17 weeks
16.17 weeks
4.17 weeks
1.17 weeks
Where:
Z
Te = Expected Time
D = Project duration I am thinking about
po
6
2
Activity #2
Activity #3
Optimistic
3
8
1
Estimates
Most Likely
4
10
2
53
0.11 weeks
12 8
0.44 weeks
4 1
6
2
Pessimistic
5
12
4
0.25 weeks
D Te
Z
Where:
Z = Number of standard deviations D is from
Te
Te
= Expected Time
4 weeks
10 weeks
2.17 weeks
3 weeks
5
4.17 weeks
16.17 weeks
4.17 weeks
1.17 weeks
4 weeks
10 weeks
2.17 weeks
3 weeks
5
4.17 weeks
16.17 weeks
4.17 weeks
1.17 weeks
Where:
Z = Number of standard deviations D is from Te
Te = Expected Time
D = Activity duration I am thinking about
39 40.68
1.05 Standard deviation difference between
1.6
most likely and desired duration
1.6 = the square root of 2.56!!!
Crashing Projects
A methodical approach to reducing project duration
Focus on the time of activities on the critical path
Looking for greatest improvement with least cost
Additional labor, machinery
Overtime and temporary employees
Premiums paid to outside contractors for early delivery
Steps
Create network
Identify critical path
Identify costs of reducing each activity on path
Reduce most cost effective activity
Look for critical path changes
Beware of multiple critical paths
B
7
C
7
D
10
E
12
A-B-C-F-H
Critical Path = 35 days
F
8
H
5
G
9
B
7
C
7
X
D
10
E
12
F
8
H
5
G
9
B
7
C
7
X
D
10
E
12
F
8
H
5
G
9
= 34 days
B
7
C
7
X
D
10
E
12
F
8
H
5
G
9
Both C.P.
Path 1 Only
Path 2 Only
Caveats