Professional Documents
Culture Documents
7FA PowerIowaBlackStart
7FA PowerIowaBlackStart
Total Plant
Cost
$400 million
$5 million
Power Output
550 MW
12.6 MW
Plant Configuration
2 x 1 combined cycle
6 diesel generators
Machines
GE 7FA (CTG)
GE D11 (STG)
Caterpillar 3516B
Fuel
Fuel oil
On-line Date
Table 1: A profile of Emery Generating Station and its black start equipment.
Load Description
Load Type
Load Size
Resistive
200 kW
Motor
100 hp
Air Compressor
Motor
100 hp
Motor
3400 hp
Condensate Pump
Motor
350 hp
Motor
1600 hp
Motor
400 hp
Resistive
805 kW
Motor
250 hp
Motor
90 hp
Motor
50 hp
Motor
500 hp
12 Pulse Inverter
3500 kW
Burns &McDonnell
Turbine Loads
Loads
Purposes
Other Plant
Loads
Battery charger
Selected HVAC
Heat tracing
Space heaters
Selected lighting
Automatic Loading
Although the term black start headlines
this project, the diesel generators also serve
as standby generators that automatically
start and provide power to essential plant
equipment during temporary power outages.
The automatic starting and loading of one
diesel generator is the first step in the black
start sequence, but since most power outages
are not widespread blackouts, the sequence
will usually end after normal power is restored,
allowing a conventional plant startup to be
completed. During power outages, the diesel
generators provide power to essential loads that
keep the turbines on turning gear, maintain
lube oil pressure, and keep the generator seals
pressurized to allow for an immediate restart
once power is restored. Without power for
these essential loads, the turbines would have
to cool down for several days before the rotor
bow could be worked out and the generators
would have to be refilled with hydrogen before a
restart. (See Table 3.)
GE Controls Changes
Since the combustion turbines were not
purchased with black start capabilities, some
equipment and software changes were required.
The combustion turbine and control system
needed the ability to start up in an island
mode, close the generator breaker to a dead
bus, remain in island mode after the generator
breaker closed, and continue in island mode
while switchyard and transmission system
breakers closed. To accomplish this, undervoltage relays were added in the GE generator
control panel, additional control wiring was
added between the turbine control system
and the generator breaker, and software
modifications were made that allowed an
operator to select island mode start and enable
dead bus closing from the operator station.
Burns &McDonnell
TECHBriefs
Bur ns & McDonnell 9400 Ward Parkway Kansas City, Missouri 64114
ADDRESS SERVICE REQUESTED
Detailed Design
Numerous equipment shop drawings were
reviewed for technical compliance and
then used to complete the final design of
everything from equipment foundations to
relay settings. Details were coordinated for
the design of the fuel system, building layout,
HVAC, underground conduit, circuit breaker
controls and synchronizing schemes. Although
the result was one of a kind, the formula for
success wasnt anything new. As always, it
took detailed interface engineering, timely
decisions, and change management as well as
close coordination with the client, vendors and
contractors.
Test Run
A test run was conducted on Aug. 21, 2004,
with harmonic analysis equipment in place.
(See Table 4.) Switchyard breakers were opened
to simulate a blackout and the first diesel
generator went to work automatically providing
power to essential loads. After an operator
pressed the black start button, all six diesel
generators went into action. The plant auxiliary
equipment was started as normal and at 10:03
a.m., an operator gave a start command to
4080 kW
8300 kW
Peak current
1919 A
1400 A
Minimum voltage
3260 V
3627 V
0.9%
6%
1.7%
3.7%
Burns &McDonnell