Professional Documents
Culture Documents
____________________
No. 97-1577
Plaintiff, Appellee,
v.
Defendants, Appellants.
____________________
____________________
Before
____________________
Steven J. Comen,
________________
Gouin,
_____
with whom
with
whom
CharCretia V. DiBartolo
_________________________
and
Cetrulo & Capone were on brief for appellant, National Union Fire
________________
Insurance Company
of Pittsburgh,
PA; Federal
Insurance Company
CAMPBELL,
Senior
Circuit
Judge.
Defendant-
_______________________
Water
Miller
Works Supply
Corporation
Act, 40 U.S.C.
or the "Act").
the district
opinion we
270a-270d
erred in
allowing
concentrate particularly on
Works did
close
under
the
court
sufficiently
("Water Works")
to the
not satisfy
recovery.
as to why
In
this
Hyman's contentions:
the Act's
ninety-day
not have a
relationship
to
Hyman
to
qualify for
or
I.
The
general contractor
on
project
to
build
a $70
Pursuant
to
obtained
a payment bond
Company
the
of Pittsburgh,
about
September 16,
undisputed.
Hyman
million
federal
processing
center
Office Project" or
requirements
or
BACKGROUND.
of
the
PA, Federal
construction
in
Waltham,
the "Project").
Miller
was the
Act,
Hyman
Fire Insurance
Insurance Company,
and
On
1994,
Hyman entered
into
an oral
-2-
promised to
serve as
demolition, excavation
and site
work
On
September 16,
1994, the
same
day that
to
Water Works,
purveyor of
pipe and
Hyman
credit
piping materials.
and the
it was
because
Hyman
it was
and
Holdings,
a non-union
Calvesco
shop.
agreed to
On September
replace
27, 1994,
Calvesco
A. Jackson Co.
with Iron
("Jackson"), a
On October 11,
that it
Office
Project.
Calvesco,
Works
had
Jackson,
Jackson requested
receive
Water Works's
extended
Water
as subcontractor on
Works
credit
it,
invoices.
only to
refused
that
to
supply
the Post
rather than
Because
Calvesco
Works
and
Jackson
Water
not
to
unless
materials
to the
Post
Office
Project
site
ship piping
at
Jackson's
-3-
Jackson placed
an order for
pipe.
Water Works
shipped the
material to
"Charles A. Jackson
Works
the
sent
invoice to
"Calvesco,
Inc.
Water
Attn: Jackson
Works
filled
seven
Office Project.
the
Post Office
Gateman
Water Works
at Calvesco.
of
$53,493.83
Office
and to
Jackson
to
the Post
send the
paid for
The
five of
first unpaid
the seven
Project manager
for
Jackson.
are the
invoice,
to
invoices to
this action.
order placed on
relating
Project site
subject
purchase orders
for
to an
The
second
unpaid
invoice,
During
telephone
outstanding
with
several
November and
employees
copy of
responded
this letter
of
Hyman
December invoices.
("Wernick") conversed on
to Calvesco.
to Hyman
and the
the
about
the
On March
7,
Sureties.
Hyman
-4-
by
indicating that
it had
turned
the matter
over to
its
On
Middlesex
April
County
5,
1995,
Water
Superior Court
Works
against
filed
suit
Calvesco and
in
its
settlement in
to pay Water
Works for
the cost of
its materials.
Calvesco has
judgment.
On the
action,
it also
filed
one-count
Miller
other actions
Office Project in
common to all
Calvesco
The
district court
action with
Hyman arising
the claimants.
entities, and
27, 1994,
with
Post
was Hyman's
through September
The district
twenty-five
from the
and Jackson
that Calvesco
1994
Works's federal
brought against
complaint
consolidated Water
Act
its state
Jackson serving
16,
as
subcontractor thereafter.
Water
Works argued to
that it
the
period
of
time
when
Calvesco
was
Hyman's
direct
-5-
subcontractor.
The district
court rejected
this argument,
Works and
satisfied
the
court
Miller Act.
held
that
Finding that
requirement in the
Water Works
could
Miller Act,
recover
from the
with
Water Works.
to recover
- $157.76.
The key
orders, in
was signed by
order, being
We
review
de novo
__ ____
questions
of
statutory
of law.
See Riva
___ ____
based
on undisputed
facts, is
-6-
commonly
reviewed de
__
novo.
____
Altech, Inc.,
____________
929 F.2d
1089, 1092
(5th Cir.
(10th
Cir. 1987).
We uphold
1991); United
______
district court's
factual
III. DISCUSSION.
A.
The
Miller
performing a contract
construction project
protection of
Act
requires
valued at over
to obtain
of the
270a(a)(2).
The
work on
Act
270b(a).
contractor
$25,000 on any
labor and
the project.
provides
general
a performance
persons supplying
prosecution
that
public
bond for
the
material in
the
See 40
___
persons
U.S.C.
who
have
Id.
___
The
persons
purpose of
the
Miller
Act
is
"to
protect
of nonfederal buildings."
-7-
United States ex
________________
F.3d 35, 35
liberal interpretation to
Carter, 353
______
U.S. at 216;
Act a
See, e.g.,
_________
v. United
______
States ex rel. Calvin Tomkins Co., 322 U.S. 102, 107 (1944).
_________________________________
Despite the
"highly remedial"
nature of the
Act,
Act
allows recovery
"direct
payment bond.
from the
bond
contractual relationship"
by persons
with
who have
either the
general
contractor
or
contractor.
interpreted
payment
40 U.S.C.
this
bond by
contractor is
first-tier
subcontractor
270b(a).
provision
to
anyone whose
The
the general
Supreme Court
preclude
relationship
of
recovery
to the
on
has
the
general
second-tier subcontractor.
434
upon
suppliers who
have a
direct
contractual relationship
general contractor.
In
order to
recover from
the payment
their claim
on
days from the date that they supply the last of the materials
-8-
make a claim.
40
U.S.C.
J.F. White
___________
_______________
B.
condition precedent
subcontractors.
notice provision is
to recovery
See
___
Ahern, 649
_____
by suppliers of
F.2d
date
after
which
subcontractors
the
without
materialmen or suppliers
general
fear
of
a strict
first-tier
at 31.
The
notice
it establishes a firm
contractor
further
may
pay
its
liability to
the
of those subcontractors.
See id.;
___ ___
920-21
____________________
1.
The relevant
notice reads
as follows:
prosecution of
project]
therefor
. .
payment bond
having
the work
. and
who
. shall
. . .
direct
provided
has
for [a
federal
paid
in full
not been
have the
right to
sue on
contractual
such
any person
relationship
with
giving
ninety days
written notice
from the date
to said
contractor within
on which such
person .
. .
is made,
stating with
substantial accuracy
the amount claimed and the name of the party to whom the
material was furnished
or supplied. .
prepaid,
in
an
contractor . . . .
40 U.S.C.
270b(a).
-9-
envelop
. . Such
notice
registered mail,
addressed
to
the
1.
While
adherence
to
the
notice
requirement
with
the terms
which notice
of the
must be
Miller Act
served.
is
in complying
regarding the
method by
18
not
1946)
(holding that
writing
exhibited
contractor in the
course of a discussion
notice
Act).
under the
Courts
the
notice be in
1092 (holding
meeting
writing.
that the
968, 969
to
(5th Cir.
the
general
served as adequate
have also
been
somewhat
"only reasonable
that
929 F.2d at
inference" from
from the
general contractor).
The language of
notice to
the party
to whom
furnished; it
does not
expressly require a
40 U.S.C.
270b(a);
Nevertheless,
correctly,
courts
held that
contractor pay.
have
"the
consistently,
written notice
-10-
and
Cir. 1959).
we
think
and accompanying
or impliedly,
that the
general
contractor."
supplier is
so that it
looking to
the general
(5th
Cir.
1976)
the
(internal quotation
marks
222, 223
omitted);
see
___
F.2d 1348,
Hyman
shown to have
notice as Water
Works was
notice" that it
letter to Calvesco.
of
a demand
Miller
sent to
Act's notice
a subcontractor
requirement.
decisions holding
does not
satisfy the
general contractor
sent to the
payment plan
a copy
of a
collection letter
that was
combined with a
joint
notice); United
______
States ex rel. Jinks Lumber Co. v. Federal Ins. Co., 452 F.2d
_______________________________
________________
-11-
payment,
Communications sent
to the general
supplier's
be supplemented by
make
it unambiguously
clear that
the
supplier is
seeking
The record
sent Hyman
the amount
here shows
not only
and details
that Water
of Water
Works
Works's claims
further
perceived, and
were in fact
initiated
perceived, as looking
matters on February
3, 1995,
only be
to Hyman
manager, Wernick,
by speaking
on the
telephone with two Hyman employees who were handling the Post
on that day,
been paid
several calls
by the subcontractor
proofs
of delivery
amount
Water
to Hyman,
Works
thus informing
claimed from
the
Wernick
invoices and
Hyman of
subcontractor.
the
The
to obtain
a copy
of Hyman's payment
-12-
bond for
"the express
purpose of filing
to release
district
the requested
court found,
Works,
a bond claim."
device
materials.
personnel refused
bonding information,
they countered
with
to
ensure
payment
but, as
a promise
the
that
for
Water
Works's
claims with
February
Hyman's
Hyman
9,
throughout the
Wernick
spoke
again
month
with
of February.
the
same
On
Hyman
with the
invoices.
subcontractor to
Finally on March
of the
unpaid
to Calvesco.2
a copy
had gone to
Hyman's three
Miller Act
Sureties.
indicating that it
sent to
Finally, on March
22,
patience,
expressing its
____________________
2.
Hyman argues that "the facts of the present case are even
more persuasive
than Maccaferri or
__________
purported demand
letter
not made
___
to
"Calvesco"
and
"Jackson"
seem
to
Hyman's
However, the
have
been
used
identified
agreement
that
Water
Works.
Jackson
Calvesco
been a party
for
Calvesco
and
to
as
Works,
Project.
sometimes
While Hyman
referred
personnel, like
to "Calvesco,"
the
name
-13-
reluctance
Works
to pay the
that it
had "turned
attorneys and, on
the
entire matter
their advi[c]e, we
over to
our
anyone
The above
Hyman
understood
that Water
Works
indication that
was looking
to
it for
notice."
Wernick's
of the bond,
calls to Hyman about the debt, suggested that Water Works was
be
inferred from
Hyman's promise to
decide
whether
constitute
demand
these
notice.
Water Works
upon
the
actions
Following
sent Hyman on
issue joint
by
subcontractor.
we need not
themselves
these
March 7
But
sufficed
and other
a copy of
Unlike
checks in
to
exchanges,
Water Works's
the
copy
in
Maccaferri, this
__________
indicated at
the bottom
to
think of
that copies
a reason
to notify
by name.
were
It is not
the Sureties
easy
unless Water
In
Maccaferri,
__________
the
Eleventh
Circuit
held
that
-14-
supplier
circumstances
were
being sent
Works's
other
far
less
indicative that
was no indication
copies.
demand upon
Here,
the surrounding
upon receipt of
a copy of
payment
was
were
Water
plainly that
interpretation.
In the
letter, Hyman
thanked Water
Works
the problems"
went
on to
relative to
speak
Hyman's strong
that it had
and,
of
the Jackson
Hyman's
reluctance to
claims.
difficulties
pay the
The letter
with
same bill
Jackson,
twice, and
to our attorneys
a clear
end,"
picture of our
the
letter
went
on,
every legal
remedy
inferred, and we
may,
invoices.
we
do."
in
response to
The
payment
by
Water Works.
contractor's
See
___
Altech,
______
letter held
to
fact,
But we
been in
(general
before
"we
"In the
be
held
will exhaust
district
court
was a
request for
929 F.2d
provide
at
1093
evidence of
notice).
-15-
We, therefore,
in this period
court that
to meet the
2.
began
made its
Project.
final
delivery of
Thus, by
letter of March
materials
7, 1995, a copy
to the
Office
Water Works's
Post
to Hyman
the earlier
notice, fit
In support of
rather
the ninety-day
court should
November 1, 1994,
time limit,
Hyman suggests
that each
order
under an
individual
ninety-day
limit.
See
___
Constr.
Co.,
_____________
(concluding
826
F.
that "[w]here
Supp.
647,
655
William L. Crow
_________________
(E.D.N.Y.
on a
series of
underlying contract");
United States ex
_________________
-16-
1993)
Supp.
657,
661 (S.D.N.Y.
argues,
1972).
Under
this
reasoning,
Hyman
Act
notice runs
weight
from each
order on
of authority contradicts
an open
contract, the
that position.
See United
___ ______
822
F.2d 547
(5th
Cir. 1987)
(collecting
cases from
the
Second, Fourth,
and Tenth
Circuits that
have held,
either
from the
920-21.
last delivery
In
although a
Noland,
______
of materials);
the
Fourth
notice provision by
Noland, 273
______
Circuit
reasoned
of a specific statutory
F.2d at
that,
of the
the general
provision must
is
to provide
recovery
materials but
for
not received
suppliers
who
compensation.
have
provided
See Noland,
___ ______
273
F.2d at 920-21.
We
agree
with
the reasoning
in
Noland.
______
Where
on an open
ninety-day
-17-
We therefore
conclude
to deny
an open account.
Hyman also
denied
recovery to
$157.76,
Water
Works for
the district
the December
court
order of
We are not
persuaded.
As
states that
an initial
the time
matter, we
note
270b(a).
last
that the
statute
the date of
the last
is made."
40 U.S.C.
But
even
if
the
statute
runs
problem.
Works
order,
recovery on
the December
from
last
In denying
Water
the district
court
between
the
distinguishing
order.
to the amount
-18-
of the November
order
The
First, Water
Office Project.
subcontractor
on the
insisted upon
Project.
Third,
five shipments
by Water Works.
not a
was December
29, 1994.
On these facts,
have
questioned if Calvesco
December order.
the
to
inference
materials
is
placed the
order
the court to
that
for
this
job.
Jackson placed
earlier ones.
While in the
court's denial
of the
The
this
absence of a
$157.76 stands, we
only
order,
as
it did
see no
reasonable
reason to
29, 1994
As
court
did
December
the notice
not
29,
err
1994,
in
was adequate
beginning
Water
Works
and
the
as the
notice period
satisfied
-19-
C.
district
the
from
notice
270b(a); see
___
Water
Works
agree
that they
had
no
relies upon
the
undisputed
Hyman and
direct relationship.
Hyman
40 U.S.C.
fact
have a direct
subcontractors.
that
Water
Works
As
allowed
recovery under
furnish materials
the
Miller
to a subcontractor
Act
by
suppliers
"from time to
who
time on
open account
F.2d at
F.2d
. without formal
417, 422-23
Water
was
subcontractor
1994.
the
contract."
Noland, 273
______
(9th Cir.
Works supplied
Jackson
1959).
materials
It is
to
demolition,
the
excavation
undisputed that
Project
and
that
and
site
work
Works's
the
. .
district court's
account
finding
of the
-20-
existence of
Works.
an open
are satisfied.
Since we
find
that the
district court
correctly
We
have
carefully
considered
Hyman's
other
Affirmed.
________
court
-21-