Design Safety Review

Project Reference:
Project Title:
Designer:
Planning Supervisor:
Principal Contractor:
Project Principal:
Attendees:

Location:
Date:
Brief Project Description

Question
1. Designer experience
and training

Guidance

Has a competence
assessment been made?

2. Designers CDM duty to


clients

Has client been made


aware of their duties under
CDM?

3. Principles of design
safety applied in all phases
of a project design

At Feasibility, Preliminary,
Detailed and during
construction?
H&S adequately
considered in optioneering and
in the justification of preferred
option(s)?
Level of detail appropriate
to project phase?
DRAs for each
area/element of the works?
Which format of forms
utilised for Design Risk
Assessments?
Evidence of DRA carried
out concurrent with and not post
design?
Design risk assessment
kept up to date?
How is it ensured that
residual risk is communicated?

4. Design Risk
Assessment (DRA)
process and
documentation

322166794.doc

Response / Comments

Page 1 of 3

Design Safety Review


(e.g. action/close-out column on
DRA)
5. Application of hierarchy
of risk control

6. Design Risk
Assessment
Considerations

7. Checking and review

8. Management of latestage design change

9. Communication of
residual risk

10. Cooperation with other


Designers and Planning
Supervisor

322166794.doc

Evidence of risks being:


eliminated by designing
them out when possible?
- reduced if cant be
eliminated?
Future cleaning and
maintenance work
Persons in the structure at
any time
Modification or demolition
of the structure
Consider risks to all
involved
DRAs included in design
review meetings to ensure that
all hazards have been identified
and that mitigation measures
proposed do not introduce
hazards in other elements or
disciplines on the project?
-

Have any late changes in


design been reviewed for their
impact on Health and Safety?
DRAs updated?
Additional residual risks
communicated?
Does the design identify
residual risks?
Is adequate information
provided on residual risks?
How? (e.g. SHE boxes
used on drawings)
DRAs and residual risk
information forwarded to the
Planning Supervisor?
Is a Lead Designer
appointed?
Regular meetings / liaison
with Planning Supervisor / other
designers?

Page 2 of 3

Design Safety Review

Project Principal Comments

Commitments:

322166794.doc

By whom:

By when:

Page 3 of 3