Bjame Andersen, Member IEEE
Authorized licensed use limited to: Illinois Institute of Technology. Downloaded on March 17,2010 at 04:41:11 EDT from IEEE Xplore. Restrictions apply.
Figure 2: important Components of One Link.
Key:
( I ) Ventilation ducts (6) IGBT inverter
(2) Earth switch (7) AF'IT
(3) DC capacitor units (8) Auxiliary power coupling
bus
(4) Stripline busbar (9) Coolant manifolds
( 5 ) Link assembly
BlocWDehlock
BypasdConduction
Positivelnegative
Inhibit Emergency Bypass
Unsafe to turn off
1357
Authorized licensed use limited to: Illinois Institute of Technology. Downloaded on March 17,2010 at 04:41:11 EDT from IEEE Xplore. Restrictions apply.
Link Control Electronic also receives GTO status requirements for the implementation, frequently
from the gate units, gate unit power supply status, and putting constraints over and above the International
dc capacitor voltage measurement. It acts on these Standards on the equipment to be supplied for their
signals, to generate the desired link state or, in the installation. Addiiionally, the Transmission Market
event of an internal fault, to place the link in has tended to be very conservative and cautious in the
emergency bypass. A high level of security is introduction of new equipment, understandably so
included to prevent shoot-through events (inadvertent when considering the impact, which the failure of
short-circuiting of the dc capacitor via two series equipment connected to the Transmission network
connected GTOs). could have on a large number of consumers.
Therefore, very stringent type test requirements are
Link Control Electronics also communicates to the often specified, and some Network Operators will not
control and protection system at ground level. The recognise type test evidence from other similar
following information is communicated to ground applications. For these reasons the cost of power
level every 67 microseconds: electronic equipment for Transmission systems has
tended to be relatively high.
GTO healthy/failed (for each GTO)
DC Capacitor voltage The use of PEBBs for a variety of applications brings
DC Capacitor over voltage ( 2 levels) a number of potential benefits as outlined above.
Status of emergency bypass However, powei electronic converters for
Power supply status transmission applications tends to he of large rating,
and manufacturers have already adopted a modular
Link Electronics also looks after the IGBT inverters, approach in the iniplementation of these converters
which provide auxiliary power to the gate units and thereby achieving some part of the potential benefits.
the rapid discharge circuit (IGBT switch with series Additionally, a power electronic converter designed
resistor) which provides an independent means for specifically for a given application is likely to be
rapidly discharging the dc capacitor. more efficient than one built from general-purpose
elements. To justify the development and use of a true
V. Chain Link Applications PEBB it is necessary to envisage that the market for
this can be at least a magnitude higher, than for
The chain link was initially developed for use in a products using the present approach. In other words,
STATCOM application. In this application the the cost reduction of the complete system must be
exchange of real power with the ac network is very substantial to encourage the required growth in
relatively small, being limited to the power necessary the market. This makes success more likely for
to compensate for losses and to change the dc PEBBs for Voltage Sourced Converters, where at
capacitor voltages, as is required to adjust the reactive present the power electronics can account for in
power output of the STATCOM. In fact, whilst the excess of 60% of total costs, compared to typically
chain link structure can provide a highly efficient less than 30% for line-commutated, current-sourced
structure for some applications, the distributed dc converters using thyristors.
capacitor makes it more cumbersome to use real
power transmission, e.g. dc transmission or other Manufacturers will naturally move in this direction if
applications involving the transfer of real power they consider this to provide cost benefits and/or
between different converters. market advantages. This may result in some device
manufacturers increasing their scope to become
Potential applications for the Chain Link are as providers of PEBBs and some of the present power
follows: electronic solution providers for transmission
networks becoming experts in the application of
8 STATCOM PEBBs.
SSSC (Series Static Synchronous Compensator)
Energy Storage using batteries or super To provide substantial cost reduction it will be
capacitors. necessary also to reduce the costs outside the PEBB,
e.g. by reducing engineering costs and using standard
VI. The Future of PEBBs in Transmission components. To do so it may be necessary to adopt
Networks some of the concepts used in the Industrial area. In
particular:
Traditionally Network OwnerslOperators have tended
to specify and procure tailor made solutions for Where possible treat the conveners as catalogue
network connected power clectronics. Some Owners items, e.g. STATCOM, UF'FC, SSSC etc. This will
and Operators have had their own detailed
1358
Authorized licensed use limited to: Illinois Institute of Technology. Downloaded on March 17,2010 at 04:41:11 EDT from IEEE Xplore. Restrictions apply.
necessitate establishing a range of standard ratings Transmission Markets focus primarily on meeting
and standard interfaces for each converter type statutory network performance at minimum cost, and
their equipment engineering expertise is reducing.
Perform rigorous type tests on the basic PEBB, Consequently, increased emphasis is being put on
defining test levels in accordance with intended contractual performance conditions. This may result
and defined applications of the PEBB by in the PEBB gaining popularity, as the Solution
comprehensive analysis. These type tests should Provider’s risk is reduced by the use of standard,
he part of the development programme, and proven building blocks.
should not be contract specific.
A range of standard routine tests for the PEBB, VIII. Bibliography
possibly specific to application in different
converter types, needs to be defined. DrBjarne Andersen
(M1999) was bom in
It will of course not he acceptable for PEBB based Copenhagen, Denmark in
systems to have lower reliability, availability or 1948. He graduated from
dependability compared to systems designed the the Technical University of
current way. Denmark with a MSc in
electrical power engineering
The technical expertise’ resident within the Network and a PhD in High Voltage
Operators has reduced as a consequence of the Technique before joining
unbundling and privatisation of the electricity supply ALSTOM T&D Ltd Power Electronic Activities
industry, and the subsequent need for cost reductions (PEA) in 1977. He bas spent most of his career
to meet shareholders’ expectations. Consequently, working on HVDC, SVC and FACTS systems. He is
specifications are becoming increasingly functionally currently the R&D Director. He is a Member of the
performance based, and the contractual conditions for IEEE and a fellow of the IEE, UK. He is a member of
the supply of the solution become more onerous and IEEE WG I5 and I8 of the Substation Committee. He
the most important part of the contract. This makes it is the Convenor of ClGRE Working Group 14-37
more likely that a manufacturer would want to use a VSC Transmission and the Regular Member for UK
standard solution to meet the requirements, since this of Study Committee 14..
will minimise the risks. It also makes it more difficult
for a small manufacturer without the large financial
backing of an international organisation to provide
such solutions.
VII. Conclusions