Installation of Panels

Consignee (In Charge) Name &


Sr.No Staion Contact No Completion targeted
Address
Date

Shri. Balakrishna Naik, Section SE/S&T/MNI -


Engineer/S&T Dept. MANGAON 09422438531
1 Mangaon 9/7/2010
Railway Station, Konkan JE/S&T/VEER -
Railway, MANGAON Taluka. 09423048071

Cancaon
2 Mr.Byju John, SE/S&T/Karwar 9422970618 2/6/2010
a

3 Kumta Mr.Byju John, SE/S&T/Karwar 9422970618 4/6/2010

4 Honnavar Mr.Mestry, SE/S&T/Bhatkal 9422970620 26/05/2010

5 Senapur Mr.Mestry, SE/S&T/Bhatkal 9422970620 28/05/2010


Cgarging/Disch
Wiring Tentative dates for
arging
Compleion completion of IPS Remarks Remarks
completion
Targeted Date Commissioning
targeted Date

ALL WORK
IPS
COMPLETED,
9/7/2010 25.07.2010 26/07/2010 Commisining
Commisoning is
is pending.
Pending

ALL WORK
IPS
COMPLETED,
2/6/2010 30/06/2010 26.07.2010 Commisining
Commisoning is
is pending.
Pending
ALL WORK
IPS
Completed COMPLETED,
4/6/2010 27.07.2010 Commisining
15.07.2010 Commisoning is
is pending.
Pending
ALL WORK
IPS
Completed COMPLETED,
26/05/2010 29.07.2010 Commisining
17.07.2010 Commisoning is
is pending.
Pending
ALL WORK
IPS
COMPLETED,
28/05/2010 21.07.2010 31.07.2010 Commisining
Commisoning is
is pending.
Pending