To,
The Dy. G.M.
PGCIL Bilaspur
Dear Sir,
On dt 29/06/10 the undersigned had visited PGCIL substation Bharari
office for collecting the Coordinates of centre point of terminating bay of
our 400KV Tr line at Bharari Substation. The PGCIL office had express the
inability to provide the coordinates, however they have given us the location
of the Centre line of the bay allotted to ACBIL. Based on this information
the survey up to the dead end tower at Bharari s/s , the proposed alignment
of our 400KV line carried out. The coordinates of 6 Nos. of the angle point
tower is submitted to you for your kind approval to start the construction
work of our tower foundation.
Thanking you