PDF Gantt Chart
PDF Gantt Chart
M T W T F
1 Identify Basic Requirements 7 days? Tue 2/16/10 Wed 2/24/10
2 Identify the Company 1 day Tue 2/16/10 Tue 2/16/10
3 Ask for Authorization 1 day Wed 2/17/10 Wed 2/17/10 2
4 Signing of Endorsement Letter 5 days Wed 2/17/10 Tue 2/23/10 2
5 Initial Interview 1 day? Wed 2/24/10 Wed 2/24/10 4
6 Develop Initial Prototype 2 days? Thu 2/25/10 Fri 2/26/10 1
7 Consideration of Interview Notes 1 day? Thu 2/25/10 Thu 2/25/10 5
8 Building Concept/Workflow 1 day? Thu 2/25/10 Thu 2/25/10 5
9 Designing Graphical User Interface 2 days Thu 2/25/10 Fri 2/26/10 5
10 Knowledge Worker Reviewing 1 day? Mon 3/1/10 Mon 3/1/10 6
11 Presentation of Prototype 1 day Mon 3/1/10 Mon 3/1/10 9
12 Evaluation of Prototype 1 day? Mon 3/1/10 Mon 3/1/10 9
13 Revise and Enhancing the Prototype 2 days? Tue 3/2/10 Wed 3/3/10 10
14 Analyze the Evaluation Notes 1 day? Tue 3/2/10 Tue 3/2/10 12
15 Rebuilding/Addition of Concept 1 day? Tue 3/2/10 Tue 3/2/10 12
16 Redesign Graphical User Interface 2 days Tue 3/2/10 Wed 3/3/10 12
Page 1
Sun Feb 21 Tue Feb 23 Thu Feb 25 Sat Feb 27 Mon Mar 1 Wed Mar 3 Fri
S S M T W T F S S M T W T
Page 2