1.
a)Site visit to asses the level
b)Site visit to measure earth resistivity
c)Site visit to ascertain the bearing capacity.
2.
a)From the above steps, assess the quantity of leveling
b)Design the suitable safety & protective earthing systems
c)Size of the foundation from virgin soil
c)Earth pits
d)Oil drain tank
e)Water tank for drinking & earthing watering
f)Control Room
g)Fencing
h) Internal road
I) Cable trench
6.Send all technical specifications & equipment drawing for approval from
concerned authorities.
7.Construct site office, closed stores & open storage area in a convenient place under 24
hours security.
16.On receipt of structures they have to be sorted out to sizes and kept on wooden
runners.
18.Line stringing within switch yard shall have to be completed before equipment erection
to avoid any possible damage.
22.Cable trench work along with fixing of cable trays & cable tray earthing to be taken up
& completed.
24.Internal plastering & painting from control room shall have to be over.
26.Cable laying and termination according to approved cable schedule shall have to be
taken between equipment & control room equipment.
28.As the transformer erection & assembling are covered in equipment erection, filtration of
oil can be planned as per requirement.
29.Equipment testing and interfacing tests shall be programmed after item 26. This may be
arranged in two stages also.
30.All relays shall be tested according to approved Quality assurance plan and specially on
service settings.
35. Commissioning of sub station and watch for 24 hours before loading. All protocols
shall be observed before taking the power into sub station.
EHV LINES
1.Soil testing.
3.Preparation of Topography.
4.Detailed survey.
7.Detailed survey report shall have to be submitted to concerned authorities and obtain
clearances from Railway & Telecommunication departments. Required number of copies
to be submitted.
8.If passes through notified forest area clearance has to be obtained from Forest
department.
9.Design of tower in accordance with soil, elevation and other meteorological conditions.
11.Submit the drawings & technical specifications for other materials like conductor,
insulator, spacers (for bunched), clamps, corona rings, vibration damper, mid span
sleeves etc. and get them approved.
14.On receipt of material at stores, sorting & stacking will be done in line with good
engineering practices.
25.Earthing of tower.