Name: Abrar Ahmed

Roll No. PE-06017


Subject: Project Planning and Management
Assignment: Network Diagramming
Date: 26/08/2010
Question/Answers:
1. Build a network diagram.

0 15 15 15 7 22 47 6 53 53 1 54
A E F G
25 25 40 40 25 47 47 0 53 53 0 54

0 47 47 54 33 87
B H
0 0 47 54 0 87

0 16 16 87 6 93 93 4 98
C I L
31 31 47 87 0 93 128 35 132

0 3 3 93 5 98
D J
44 44 47 93 0 98

98 31 129
K
98 0 129

132 16 148 129 3 132


O M
132 0 148 129 0 132

150 5 155 148 2 150 132 14 146


Q P N
150 0 155 148 0 150 136 4 150

NB: Cells filled with Red are on Critical Path

2. Calculate forward pass, backward pass, float, and critical path.


o For Forward Pass, Backward Pass, Float and Critical Path See Above

3. How long the project will take (Total duration of the project)
o 155 Days

4. What items are on the critical path?


o BFGHIJKMOPQ