MACAWBER BEEKAY PVT. LTD.

OPERATION SEQUENCE (PER SHIFT OF EIGHT (8) HRS.) CHART FOR


ASH HANDLING SYSTEM - 2 X 135 MW VANDANA VIDHUT LIMITED
MB/P-5249/RL Dtd. 20.05.2010
Sl. DESCRIPTION OPERATION TIME (HRS.)
No.
(1) (2) (3) (4) (5) (6) (7) (8)
0.25 0.50 0.75 1.00 0.25 0.50 0.75 1.00 0.25 0.50 0.75 1.00 0.25 0.50 0.75 1.00 0.25 0.50 0.75 1.00 0.25 0.50 0.75 1.00 0.25 0.50 0.75 1.00 0.25 0.50 0.75 1.00

1.0 BOTTOM ASH HANDLING SYSTEM

1.1 UNIT - 1

1.2 UNIT - 2

2.0 FLY ASH SYSTEM UPTO ISH

2.1 UNIT - 1 3 Hrs.

2.2 UNIT - 2 3 Hrs.

3.0 SLURRY DISPOSAL SYSTEM OF FLY ASH

Sheet 1 of 1