Professional Documents
Culture Documents
By : Rizka Muharyana
01071003094
Abstract
The purposes of this paper are to find out the weaknesses of revenue recognition
in long-term contract by percentage of completion method both with the physical
approach and the cost approach, also to provide alternative solutions to
overcome these weaknesses. The percentage of completion used in physical
approach is derived based on the physical progress of work, whereas in the cost
approach the percentage of completion is derived based on the number of actual
costs incurred for the contruction project during the period.
In the discussion part of this paper will be explained the weaknesses of the
percentage of completion method both with physical approach and cost approach.
The weakness in the physical approach was ignore the aspect of actual costs that
actually incurred for the project during the period while the weakness in the cost
approach was ignore the physical aspects of project’s completion progres. To
overcome these weaknesses was chosen an integrative approach alternative based
on elementary costs that combine both approaches and eliminates the
weaknesses of each. This method uses the physical percentage of completion of
the projects during the current period, actual costs and income measurement
basis using elements of costs that actually already used in the project during
current period and did not use the estimation cost as the two previous
approaches.
1. Introduction
1.1 Background
apartments and others. Just like most other companies, construction companies
also aim to get income. Recognition of income is closely related with the
1
and expenses will affect the inaccuracies in the measurement of income. This
construction company that are the completed contract method, especially for
short-term contracts (less than one accounting period) or contract that has a high
used if the construction project takes a long term completion (more than one
approaches that consist of physical approach and cost approach. But the two
approaches have generate the numbers not reasonable, feasible and accurate so the
revenue recognition was less representative for the current period (Narsa, 1999).
If the condition run just like that then the information presented will mislead the
If used the physical approach to recognize revenue in the current period, the
(results achieved) without considering the cost or effort that has been expended or
incurred for the project during the period. Conversely, if the cost approach was
used, the amount of revenue recognized for the current period merely based on the
cost and effort that has been expended or incurred without linking it to physical
progress or the actual results in the current period. Two of these cases clearly
2
shows that there is no matching process between revenues with expenses within
the meaning of a causal and positive correlation. As a result the revenues which
are presented does not reflect the company’s performance, because what is
But besides these weaknesses there is one more weakness that has huge
influence on the feasibility and fairness of the revenue figure which has not been
amount of revenue to be recognized in the period. Base that used is the selling
price of projects and total project costs by contract (Narsa, 1999). This way is less
rational because when we observe that the huge projects in reality takes a long-
term completion time and some even for several years and use the cost elements
in the large number. The elements of that cost are not incurred in a lump-sum
from the beginning contract but their spending are gradually (step by step) in
accordance with the progress of the project. Thus, it would be rational if the
calculation is based on the cost of elementary, namely the total of cost elements or
the cost that the elements have been used in the project (Narsa, 1999).
3
1.3 Study Purposes
construction contracts.
1. For the author, adding more in-depth insight and knowledge about revenue
method
more depth
2. Discussion
cooperation between the various parties to achieve the objectives and work that
has been agreed. Work under the contract referred to the project.
4
According to the IAI (Tampubolon, 2006) construction contract is a
of an asset that is closely linked to each other or depending each other on terms of
other in terms of design, technology and function or purpose and use of principal,
such contracts such as construction of oil refineries or other parts of the complex
plan of or equipment.
development projects take more than one accounting period. Beside that, actually
there is a contract that less than one year but at the financial statement preparation
the contract has not been completed. In order for achievement of the project is
reflected in the financial statements, it must be allocated over the total revenue
expected from the project to periods during the life of the project.
In the unit price contract, the assessment price of each unit of work has
been done before construction begins. The owners have been count the
5
use of these types of contracts is the owner can not know with certainty the
actual cost of the project until the project is completed. To avoid this
accurately.
In this type, the contractor will receive payment for expenses plus a fee for
overhead and profit. Generally, these profits are calculated based on the
In this method, the contractor did not get a chance to raise fees to
This method can convince the owner (the employer) that the total
project cost will not exceed a certain amount. The owner put the
6
b. Cost plus percentage
all the real costs incurred and will receive compensation based
The contractor will receive back all of costs incurred plus the
This type of contract states that contractors will build the project in
accordance with the design at a certain cost. If there are changes in the
contract, negotiations between the owner and the contractor will be held to
establish payment that will be given to the contractor for the job. The cost
for each job whether more or less will be negotiated between the owner
construction project which is divided into four main categories: the residental
construction.
the characteristics and conditions of the project itself. Viewed from the
perspective of the project owner (owner) this is closely related to the anticipation
and the handling or solve of the inherent risks or problem in the construction.
7
2.3 Definition of Revenue
transactions during a certain period with the relevant historical cost of good
sold.
that contribute services or conduct other activities that form the basic
inflows of assets for companies that occurs after the sale of goods or
provision of services. Assets may include cash from the sale of goods and the
revenue and other revenues. Revenue from merchandise sales and services
that from the company’s core activities called main revenue, while other
income obtained from the rental of excess office space and other companies.
8
From the definitions above can be concluded that revenue is an increase from
the inflow of cash, receivables, etc. or the use of corporate resources that
generate interest, royalties and dividends that could alter or affect the amount
of capital ownership, but not the addition of new capital from their owners
and are not a major asset additions that caused the increasing in liabilities.
bridges and others. Contract that require the completion period of more than
Revenue and gross profit are recognized only at the time the contract is
9
If there is uncertainty contained in the contract
Construction cost plus gross profit earned are accumulated in the inventory
conditions for applying this method in the construction contract, such as:
completed
period)
The contract clearly states the rights that can be carried out on
completion
10
Contractors can be expected to perform its contractual obligations
The definition is very general, meaning that only mentions that revenues
implies that between revenues and costs must be related. So what will be
definition. If the discussion is outside the definition, the author argues that
efforts for improvement should still be done. The approach that the author
(Narsa, 1999).
1. Physical Approach
With this approach the size of the results is made regarding the results
11
resulted unit and value added (value added). There are two possibilities or
physical completion according to Smith & Skousen (Narsa, 1999) such as:
a. Calculated by comparing the units that have been produced with a total
usually used for the type of contract that each activity or each unit of the
usually used for the type of contract that is difficult in specifying the unit
or quantity.
The above ways are not shows the alternatives than can be choose one of
them, but each one is used for certain conditions. If a physical approach in
Rn = Xf x (C + E) ......................................(1)
physical progress that has been achieved or units that have been produced
12
2. Cost Approach
(Narsa, 1999):
the latest estimation of the total estimated costs to complete the project.
These methods rely on the efforts that have been poured into the project,
compare the efforts that have been poured to complete the project.
Actually the essence of both approaches on both the cost to cost method as
contained on them are basically the same, namely forming the overall cost
revenue, then mathematically have the same model with the physical
Rn = Xc x (C + E)..................................... (2)
13
Rn = current period revenues
comparing the costs incurred until the current period with the estimated
The two approaches both physical approach and cost approach in the
illustration, it will show that there are enormous differences between the two,
both concerning the amount of revenue and the amount of expense recognized
In the cost approach, there is the necessity to estimate the total cost
which is still needed to complete the work in the future. In this estimatimation
there are many factors and variables that must be considered or taken into
consideration because the factors and variables have very strong influence
on the size of the numbers generated in the percentage. Thus the measurement
results are likely to deviate from actual circumstances. In addition, in the cost
approach the total cost incurred during the current period directly charged
field.
14
Opposite situation occurs in the physical approach. The amount of
compared with treatment in the cost approach. Cost charged is not the cost
that really happened, but based on the estimation. As a result the possibility of
manipulation in the financial statements using one of the two approaches are
very large.
a.In the physical approach, the amount of revenues during the current period
is not related with the aspects of real costs that occur in the same period.
b.In the cost approach, the amount of revenues during the current period, is
not related with the physical aspect of progress that shows the number of
c.Both the physical approach and cost approach does not rely on the
costs are the costs that had actually been used in the project.
cost approach
both aspects of the approach together by combine them here in after referred
15
The core of the integration approach is, combining two existing approaches,
taking into account the aspects of cost and results together. Then, in its
means will only take into account the total of the costs elements or elements
of costs that already used or occured during the project. This means that the
earning process. So with this concept, it is very logical that revenue will
the two previous approaches (physical and cost approach) and eliminate the
achieved in the current period. And not forget how much the total effort
that has been done. Thus, the possibility of manipulation in the income
b. Costs that will be charged to current period are those costs that are
actually happened and occured for the project during the current period.
elementary, namely the total of cost elements or elements have been used
in the project.
16
In line with these treatments, then it can be determined a formula that can be used
Rn = Xf x (C + E).............................. (1)
Rn = Xc x (C + E)...............................(2)
Rn = Xf x (C’ + E).............................(3)
Equation (1) and equation (3) look similar, but actually very different the
similarity only the use of physical completion percentage (Xf) and total expected
income (E). As for the C’ represents the total cost of elementary namely the total
This formula combines a physical approach and cost approach with cost element
that really - really has been used in the project. This integration approach is more
realistic and closer to reality because not only consider physical progress aspects
but also the cost aspect. Where the cost base is used is the costs that have actually
been used in the project and not the estimation cost as the previous approach.
3.1 Conclusion
contracts both with the physical approach and cost approach still have
weaknesses.
approach is ignore the aspects of the real costs that actually incurred
17
during the period and only focus on the assessment of physical progress in
revenue base measurement using cost elements that actually already used
in the project during current period and did not use the estimation cost as
3.2 Limitations
1. Author did not take an object that can be used as a reference company in
18
and integrative approach based on elementary cost in the percentage of
contract method
3. Author did not give examples of cases for the implementation of the three
4. Did not present the impact of this change in approach to the income
statement
REFERENCES
Narsa, I Made. 1999. Jurnal Akuntansi dan Keuangan, Vol.1 No.2 Nopember
1999:84-102
19