Professional Documents
Culture Documents
• C-1 (YUM):
– Corps needs to evaluate proposed fence alignment to determine if it will
impact flood level of the Colorado River (analysis required by IBWC)
• D-2 (TCA):
– NPS (Organ Pipe) Supt. Opposes fence & road over Sonoyta Hill. DoI is
assisting with acquisition of special use permit
• K-2B/C (EPT):
(b) (5)
– Sector’s preferred fence location estimated to cost per mile for 8
miles
• L-1A & L-1B (MAR):
– Sector desires retaining wall built into southern face of IBWC levee (similar to
Hidalgo County proposal)
– Corps needs to evaluate feasibility and develop cost estimates ASAP
• Misc Texas Segments w/ Proposed Floating Fence on Levee
– Corps needs to evaluate IBWC levee condition at proposed segments ASAP
Change Control
The Proposal
Hidalgo is proposing to build-up the levees and place a 18 foot concrete wall on the
southern side of the levee to replace the requirement for the fence SBI has proposed
on the north side of the levee. The RGV fence segments impacted by the proposal are
O4 – O10 which equals about 22 miles or 31% of the RGV fence requirements. These
are non-contiguous miles.
OBP operational requirements – The 18 foot wall and access points meets operational
requirements.
Project Schedule - Hidalgo county has developed a project schedule that will allow
completion of the proposed levee/wall segments that align with O-4 – O10 by Dec 08.
Project Funding - Hidalgo currently has all the funding to begin and complete these
project. They do not need SBI funds to begin and complete.
Project EA – IBWC owns the levee and has completed an EA to increase the height of the
levee but not add the wall.
Hidalgo IBWC MOA - Hidalgo and IBWC have a MOA that allow Hidalgo repair
the levees at their cost. Current MOA covers our segments O-4 & O-5. Ideally,
scope will be expanded to O-6 through O-10
(b) (4)
Strong Community Support - Hidalgo Co is at risk for a flood insurance
(b) (4)
cost – Bond authority of plus
DHS/CBP/SBI Benefits –
– Positive Community and Stakeholder relations
(b) (4)
– Fence cost are fixed at per mile incl. required BP gates
(b) (4)
– Elimination of real estate needs savings
Challenges –
Legal authority for DHS/CBP/SBI – Secretary needs legislative authority to enter into a
cooperative agreement with Hidalgo
Ability to overcome the T&E concerns of FWS (DOI). FWS have major concern about
the Ocelots + 1 T&E species that the wall will impact – tentative agreement in place relative
(b) (5)
to a Biological Opinion (will require approximately in compensation from CBP/SBI to
FWS to allow ~1400 acres of habitat to be purchased)
Ability to have SBI modify current EIS to include the wall as the recommended TI
solution – Currently adding the wall to the Draft EIS. Working FWS. We believe we can
modify the SBI EIS with the wall as the preferred option – this will cause a 30 day delay in
the ROD but would not impact the construction schedule.
Ability to maintain the S-1 Waiver authority – This is critical to meet schedule
The IBWC role during and after construction of the wall – Working issues
Cameron County
• Met with County officials on 26 Feb 08 and discussed the challenges to entering
into an arrangement similar to Hidalgo County