You are on page 1of 7

MOE Headquarters - South Surra

Concrete casting Report

Blinding K140 SRC Date : 18/12/2010


For Raft Foundation

S.No. Date START TIME -END TIME DURATION Quantity (M3) App. Area (M2) Cumulative Qty. Cumulative App. Area

1 14/10/2010 16.00 19.00 3.00 63 900 63 900


2 17/10/2010 15.00 19.00 4.00 55 775 118 1675
3 21/10/2010 10.30 13.30 3.00 50 700 168 2375
4 27/10/2010 16.00 19.00 3.00 68 950 236 3325
5 30/10/2010 4.00 6.30 2.30 10 246 3325
6 31/10/2010 15.00 18.30 3.30 60 850 306 4175
7 2/11/2010 16.00 19.00 3.00 90 1250 396 5425
8 3/11/2010 16.00 19.00 3.00 60 850 456 6275
9 7/11/2010 16.00 20.00 4.00 120 1300 576 7575
10 8/11/2010 15.00 18.30 3.30 25 340 601 7915
11 9/11/2010 15.00 18.30 3.30 9 610 7915
12 10/11/2010 5.00 7.00 2.00 10 620 7915
13 13/11/2010 10.00 12.00 2.00 12 632 7915
14 14/11/2010 14.30 17.30 3.00 14 150 646 8065
15 22/11/2010 10.00 14.00 4.00 90 1200 736 9265
16 25/11/2010 10.00 14.00 4.00 16 200 752 9465
17 29/11/2010 16.00 22.30 6.30 80 900 832 10365
18 30/11/2010 15.30 24.30 9.00 63 750 895 11115
19 1/12/2010 16.00 22.00 6.00 67 750 962 11865
20 2/12/2010 17.00 23.00 6.00 85 1150 1047 13015
21 5/12/2010 16.00 23.00 7.00 165 2300 1212 15315
22 6/12/2010 16.00 23.00 7.00 65 850 1277 16165
23 8/12/2010 16.00 23.00 7.00 76 950 1353 17115
24 9/12/2010 16.00 21.00 5.00 79 950 1432 18065
25 10/12/2010 16.00 22.00 6.00 60 825 1492 18890
26 13/12/2010 18.00 24.00 6.00 90 1200 1582 20090
27 14/12/2010 17.00 23.00 6.00 108 1250 1690 21340
16/12/2010 16
28 18/12/2010 20.00 24.00 4.00 101 1791

Prepared by: Prem kumar


MOE Headquarters - South Surra
Concrete casting Report

SCREED 1:3
For Water proofing Protection layer. Date : 18/12/2010

S.No. Date START TIME -END TIME DURATION Quantity (M3) App. Area (M2) Cumulative Qty. Cumulative App. Area

1 26/10/2010 15.30 19.00 3.70 16 330 16 330


2 1/11/2010 16.00 19.00 3.00 38 760 54 1090
3 7/11/2010 11.00 13.00 2.00 48 960 102 2050
4 21/11/2010 19.00 22.00 3.00 80 1500 182 3550
5 24/11/2010 17.30 20.30 3.00 60 1175 242 4725
6 29/12/2010 16.30 21.00 4.70 80 1550 322 6275
7 2/12/2010 16.30 22.00 5.70 70 1350 392 7625
8 13/12/2010 18.00 24.00 6.00 30 1350 422 8975
16/12/2010 65

Prepared by: Prem kumar


MOE Headquarters - South Surra
Concrete casting Report

Raft K350 SRC


For Raft Foundation Date : 5/2/2011

S.No. Date START TIME -END TIME DURATION Quantity (M3) App. Area (M2) THICKNESS (METERS) Cumulative Qty. Cumulative App. Area

1 14/11/2010 6.00 13.00 7.00 780 475 1.5 780 475


2 25/11/2010 16.00 2.00 10.00 1000 650 1.5,1.8 1780 1125
3 3/12/2010 5.00 6.00 25.00 1819 2050 0.8,1.2 3599 3175
4 16/12/2010 8.00 5.00 21.00 2600 1900 0.8,2.2 6199 5075
5 19/12/2010 15.30 1.30 10.00 765 950 0.8 6964 6025
6 23/12/2010 5.00 5.00 24.00 1860 1642 1.0,1.6 8824 7667
7 25/12/2010 2.00 2.00 24.00 2232 1280 1.5,1.8,2.0 11056 8947
8 31/12/2010 5.00 7.00 26.00 2816 1725 1.5,1.8,2.0 13872 10672
9 6/1/2011 22.00 14.00 16.00 1364 1135 0.8,1.2,1.5,2.0 15236 11807
10 14/1/2011 17.00 6.30 13.30 1380 880 0.8,1.2,1.5,2.0 16616 12687
11 15/1/2011 16.00 3.30 11.30 1330 1035 0.8,1.2,1.5,2.0 17946 13722
12 20/1/2011 16.00 4.30 12.30 1555 1054 0.8,1.2,1.5,2.0,2.2 19501 14776
13 27/1/2011 16.00 14.00 22.00 2610 1320 0.8,1.8,2.2 22111 16096
14 28/1/2011 11.00 24.00 13.00 956 2000 0.8,1.2,2.0 23067 18096
15 1/2/2011 16.00 10.00 20.00 1232 740 0.8,1.2,2.0 24299 18836
16 3/2/2011 16.00 8.00 16.00 1700 1150 0.8,1.5,1.8,2.0 25999 19986

Prepared by: Prem kumar / Bilal


Date : 26/12/2010

RAFT CASTING REPORT


S.NO LOCATION AND LEVEL CONCRETE QTY START FINISH DURATION SLUMP (AVG.) CUBES REMARKS
ZONE AXIS LEVEL GRADE TYPE M3 DATE TIME (Hrs) DATE TIME (Hrs) TIME (Hrs) MM NO.
1 33 A-C/2-6 -14.00 350 SRC 780 14/11/2010 6.00 15/11/2010 20.00 16.00 14 48
ONE CONCRETE TRANS MIXER
REJECTED BECAUSE OF
COLLEPSED SLUMP ( MIXER NO.
18)
2 3 A4-C/P8-P12 -14.00 350 SRC 1000 25/11/2010 16.00 26/11/2010 10.00 18.00 13 90

CONCRETE WAS DELAYED FROM


5 P.M TO 6 P.M BECAUSE OF
WRONG QUANTITY
CALCULATION.
3 5 A-J/P1-P4 -14.00 350 SRC 1819 3/12/2010 5.00 4/12/2010 6.00 25.00 14 153
CONCRETE LEAKAGE DURING
CASTING AT AXIS J,K/P8 NEAR
4 7,12 C-J/P2-P7 -14.00 350 SRC 2603 16/12/2010 8.00 17/12/2010 11.00 27.00 14 234 CONSTRINCTION JOINT
RATE OF CONCRETE DELIVERED
5 30,31 V-Z/P5-P13 -18.50 350 SRC 1856 23/12/2010 5.00 24/12/2010 5.00 24.00 14 162 AT SITE WAS LOW

RATE OF CONCRETE DELIVERED


AT SITE WAS LOW, 3 NOS OF
CONCRETE TRANS MIXERS WERE
RIJECTED BECAUSE OF
COLLESPECTED SLUME ( MIXER
NO. 83,87,94)
6 16,18 K-N/P4-P8 -14.00 350 SRC 2215 26/12/2010 2 26/12/2010 2 24 14 192

Prepared by: Prem kumar


Date : 26/12/2010

STAFF AND EQUIPMENT PRESENT AT SITE FOR RAFT CASTING


1 2 3 4 5 6
ZONE 33 3 5 7,12 30,31 16,18
S.NO MAK (STAFF)

1 SITE ENGG. 3 3 2 4 3 3
2 FORMEN 2 1 2 2 3 3
3 SURVEYOR 1 1 1 1 1 1
4 ELECTRICAIN 1 1 1 2 1 1
5 CASTING CREW 12 15 25 35 25 25
6 HELPERS 10 10 10 10 10 10
7 STEEL FIXER 1 1 1 2 2 2
8 CARPENTER 1 1 1 2 2 2

EQUIPMENT

1 PUMP 3 4 4 5 3 3
2 VIBRATOR 4 4 6 10 6 6
3 POWER FLOATRER 3 3 5 8 6 6

C7A,GC (STAFF)

1 SITE ENGG. PREM KUMAR PREM KUMAR PREM KUMAR PREM KUMAR PREM KUMAR PREM KUMAR
Time Time Time Time Time Time
06.00 to 14.00 06.00 to 14.00 05.00 to 18.00 08.00 to 18.00 16.00 to 21.00 13.00 to 18.00
2 CIVL INSPECTOR - 1 JAVID IQBAL JAVID IQBAL JAVID IQBAL JAVID IQBAL JAVID IQBAL JAVID IQBAL
Time Time Time Time Time Time
16.00 to 02.00 16.00 to 02.00 05.00 to 23.00 07.00 to 5.00 016.00 to 23.00 17.00 to 23.00
3 CIVL INSPECTOR - 2 KHAN KHAN KHAN
Time Time Time
12.00 to 7.00 22.00 to 7.00 23.00 to 7.00
5.00 To 8.00
Prepared by: Prem kumar

Date : 25/12/2010

STAFF AND EQUIPMENT PRESENT AT SITE FOR RAFT CASTING


1 2 3 4 5 6
ZONE 33 3 5 7,12
S.NO MAK (STAFF)

1 SITE ENGG. 3 3 2 4
2 FORMEN 2 1 2 2
3 SURVEYOR 1 1 1 1
4 ELECTRICAIN 1 1 1 2
5 CASTING CREW 12 15 25 35
6 HELPERS 10 10 1 10
7 STEEL FIXER 1 1 1 2
8 CARPENTER 1 1 1 2

EQUIPMENT

1 PUMP 3 4 4 5
2 VIBRATOR 4 4 6 10
3 POWER FLOATRER 3 3 5 8

C7A,GC (STAFF)

1 SITE ENGG. PREM KUMAR PREM KUMAR PREM KUMAR PREM KUMAR
Time Time Time Time
06.00 to 14.00 06.00 to 14.00 05.00 to 18.00 08.00 to 18.00
2 CIVL INSPECTOR - 1 JAVID IQBAL JAVID IQBAL JAVID IQBAL JAVID IQBAL
Time Time Time Time
16.00 to 02.00 16.00 to 02.00 05.00 to 23.00 07.00 to 5.00
3 CIVL INSPECTOR - 2 KHAN
Time
12.00 to 7.00
5.00 To 8.00
Prepared by: Prem kumar