Production schedule

Development/ research

• Brainstorm genres - 16 September 2010

• Research movie trailers - 16-17th September 2010

• Research my genre trailers – 21st -22nd September 2010

• Audience research - 30th September 2010

• Pre audience questionnaire – 1-5th October 2010

• Pre practice trailer/ audience testing 7-13th October 2010

• Audience feedback of practice trailer 17th October 2010

• End of extended research – 20th October 2010

• Research into target audience socio economic group/bbfc – 30th October


2010

• Treatment/more research into target audience 2nd November 2010

Pre production

• Synopsis 1st draft - 7th November 2010

• Synopsis 2nd draft – 12th November 2010

• Script – 18th November - 2010

• Location notes and pictures - 23rd November 2010

• Cast notes and pictures - 25th November 2010

• Storyboard - 28th November 2010

• Storyboard 2nd draft - 2nd December 2010

• Score notes - 7th December 2010

• Cutaways – 10th December 2010

• Shot list – 11th December 2010

• Call sheets 13th December 2010

Production
• Creation of production logo – 14rd December 2010

• Risk assessment – 16th December 2010

• Filming- oakspark high school lift - 17th December 2010

• Filming -oakspark high school lift - 19th December 2010

• Filming- Piccadilly circus – 28th December 2010

• Filming –Leyton – 1st January 2011

• Filming Leyton – 2nd January 2011

• Filming Gansthill – 2nd January 2011

• Extra filming time 4th January 2011

• Extra filming time 5th January 2011

Post production

• Actor release forms – 7th January 2011

• Location release forms – 7th January 2011

• Capture footage onto Mac 8th January 2011

• Film editing – 10th – 24rd January 2011

• Start ancillary tasks 26th January – 4th February 2011

Distribution

• Upload trailer onto video to YouTube - 5th February 2011

• Upload soundtrack to sound cloud - 5th February 2011

• Evaluation 6th - 18th February 2011