1. INTRODUCTION
2. ABOUT THE WORMS
3. LOCATIONS
4. USES
5. COMPONENTS OF A COMMERCIAL UNIT
5.1 Sheds
5.2 Vermi-beds
5.3 LANDS
5.4 BUILDING
5.5 SEED STOCK
5.6 Fencing and Roads/Paths
5.7 WATER SUPPLY SYSTEM
5.8 MACHINARY
5.9 TRANSPORT
5.10 FURNITURE
5.11 OPERATION COST
6. PROJECT PROFILE
7. EXTENSION SERVICE
8. ANNEXURES I-VI
PROJECT
VERMI-COMPOSTING UNITS
1.0 INTRODUCTION
4.0 USE
5.1 Sheds
5.2 Vermi-beds
5.3 Land
About 0.5-1 acre of land will be needed to
set up a vermiculture production cum extension centre. The
centre will have at least 8-10 sheds each of about 180-200
sq.ft. It should also have a bore well, and pump set or watering
arrangement and other equipments as described in the scheme
economics. The land can be taken on lease of at least 10-15
years. Even sub marginal land also will serve the purpose.
5.4 Buildings
5.8 Machinery
Farm machinery and implements are required
for cutting (shredding) the raw material in small pieces,
conveying shredded raw material to the vermi-sheds, loading,
unloading, collection of compost, loosening of beds for
aeration, shifting of the compost before packing and for air
drying of the compost, automatic packing and stitching for
efficient running of the unit. Costs of providing necessary
implements and the machinery have to be included in the project
cost.
5.9 Transport
5.10 Furniture
Annexure-1
Annexure-II
Annexure-III
Annexure-IV
Annexure-V
Repayment schedule
Interest (%)- 15
Repayment
Year Loan Net Principal Interest Total Net Surplus
Outstanding Income outgoing
1 339400 79200 - 50910 50910 28290
2 339400 137000 31000 50910 81910 55090
3 308400 137000 36000 46260 82260 54740
4 272400 137000 41000 40860 81860 55140
5 231400 137000 47000 34710 81710 55290
6 184400 137000 54000 27660 81660 55340
7 130400 137000 62000 19560 81560 55440
8 68400 137000 68400 9510 77910 59090
* including capitalization of operational cost for 2 cycles
(Rs.1,47,200/-