Material Code

Header Plant

Enter the number of the material for which you want to create or edit a bill of material.

Enter the plant for which you wish to create or process a bill of material.

Valid From date

Specifies the start date for the validity period of BOM

Work center Where the operation will be carried out or performed

here Header Information will come only for header material once on first row.

Operation Control key Desc of Operation It specifies how the operation will be carried out, mention PP01 if it is In House Operation and specify PP02 if that here at Operation operation will level all rows will be be externaly filled against header procured.

materials

Activity Std value 1 Std value 2 (Labor/ (Power etc) machine Hr) No of hours Machine power hours consumption required to for the perform this operation operation

Operation Details Prod. resource/ tool NO

Component Details Material Code Component material code which will be assigned to operation and will get consume when this operation will be confirmed in production order.

peration ows will be inst header