PRIME COST SUMS

These are included in the contract to cover specialist work. Prime Cost (PC) sums include work or materials by a specialist contractor or statutory body, e.g. gas, electricity, water and sewer connections.

A P.C. sum may be included in contract documents for items such as; 1. Structural steelwork 2. Windows 3. Lifts 4. Generators 5. DOE water connection 6. NIE electrical connection 7. Phoenix gas connection

The P.C. sum will have a cost associated with it that has already been determined. When a new house is purchased there may be a P.C. sum for the kitchen or bathroom. The main difference between provisional and P.C. sums is; provisional sums are estimated to allow for unforeseen work whereas P.C. sums are already accurately priced by a specialist.

If a provisional sum is not used then the amount is not paid to the contractor