You can search for Jobs by all the ways To the left or click New for a new Job
Either enter a job Number or let the Number be created Standard or Non Standard Job Enter in the assembly The class will default Or choose another
Set the job to released As it is easier when you Reproduce as you cant Do anything with the job In Unreleased status
Enter in the quantity The MRP net defaults Click in the Start date The Date Popup will appear
Routing Tab
If you had an alternate Routing, Reference or Serialization Start Op. This would be listed
The Completion Subinventory And the locator is populated Or you can populate it here
Job History
Job history will show The remaining qty, Completed, scrapped Good way to see what has been completed on a job
If the customer has Projects installed and The Project,Task will appear . Also with the Unit Number And if the customer is Using Schedule Groups
Operations Tab
Operation tab shows The Dept from the routing And other info brought over
There are Diff. Stages a qty can be At: * Queue * Running * To Move * Rejected * Scrapped and * Completed
The dates can Be changed but They have to be Consecutive or They changes Will error. Also The changes Have to be in Combination with Changes to the Resource dates From the resourc tab
Cont..Quantities Tab
Amount per Assembly, Required, Issued and On Hand
Cont..Supply Tab
Resources Tab
Cont..Quantities Tab
Cont..Scheduling Tab
Cont..Costing Tab
Move Transactions
Note: If the job is Unreleased the you will Get the error below
Notice which one has Qty in them. You can Only move from an op With qty in it
Cont
As from before the Steps come into play. You can Move from queue to queue Running, To Move, Reject and Scrap
28_DJ_Move
When doing a completion Transaction the To seq. gets Populated with the To Move Step but the from sequence You have to populate
On a return the from step will populate with the To Move step and is not Updateable. You will have to Populate what step you Want the return to go to Which operation.
NOTICE: If you do not have quantity at the To Move step it will error. So be careful that you have completed some components when you do a return.
Material Transactions
Enter in the job number Or the Assembly and search On the job number
Next we want to process Any material transactions On the job. Issue the Material to the job
Components Screen
Only Push Components will show On the screen that need to be processed
Component Issue
If you do not have enough quantity for your Component the following warning will appear. If you allow negative inventory you will be able to Proceed if not you will have to add inventory
NOTE: Be careful what you change on this Screen as it may effect transactions and data In the system
To view your Material transactions you go to WIP>Material Transactions>View Material Trans Remove the first Transaction Date then enter in the Source as Job or Schedule Then enter in the Job name as the source
Cont..
When viewing the material transactions The item item will appear,subinv, locator if there is one.
Cont
Some important information is the Transaction Id And quantity. The Id can be used to track the Transactions in the tables and other forms
Completion Transactions
To fully complete your Job you have to complete The assembly. This is Where that occurs
The Job qty, complete Qty and the available Will populate
Cont
The subinventory Will autofill as Well as the uom Input the qty
Discrete Job
To Close the Discrete Job Go to either the Close Discrete Job (Form) or the SRS
The Form will let you close a Job one by one. The SRS will let you close Multiple jobs and is a concurrent program
Cont
The popup for the Report Type And after you click OK the request Will be processed
Cont