PROGRESS STATUS AND ACTION PLAN

400 KV D/C (QUAD) GURGAON-MANESAR TRANSMISSION LINE


Action Plan As per LOA Qty As per Survey Qty Completion Achieved as Balance As target as per on 30th on 30th L2 Shedule Sep'11 Sep'11 Achieved up to 22.10.11 Balance As on 22.10.11 Present Gangs Availability Cummulative Progress

DESCRIPTION

Unit

Oct'11

Nov'11

Dec'11

Jan'12

Remarks

Survey

Km

18

16.86

Jan'10

16.86
2 Locations in Progress and 14 locs.in ROW (5 locs Forest clearnce yet to be received,balance 9 locs in Severe ROW) to be resolved by PGCIL. 2 towers in progress and no front for tower erection 0.150 kms Paying out is in Progress

Foundation

Nos

50

53

July'10

33

20

35

18

2 Gangs

Tower Erection Nos Stringing SUPPLY Stubs Towers Earthwire Hardware Nos Nos Km Km

50 18

53 16.82

Oct'10 April'11

21 0

32 16.82

25 0

28 16.82

7 1.902

12 5.135

4 4.456

5 5.327

2 Gangs 1 Gang

50 50 37

53 53 34.748 4663

Feb'10 May'10 Aug'10 Sept'10

53 41 34.748 90%

0 12 0 10%

0 12 0 10%

53 53 34.748 100%

0 0 0

Sets 4066

Issues to be resolved by PGCIL: Foundation: 1. Fourteen locations are in ROW (5 locations for Forest clearnce yet to be Received and 9 locations in ROW) 2. Frequency changes in route length and tower supply is getting delayed still route is not finalized

PROGRESS STATUS AND ACTION PLAN


400 KV D/C MANESAR-NEEMRANA TRANSMISSION LINE
Action Plan

DESCRIPTION

Unit

As per LOA Qty

As per Survey Qty

Completion Achieved as target as per on 30th L2 Shedule Sep'11

Balance As on 30th Sep'11

Achieved Cummulat Balance up to ive As on 22.10.11 Progress 22.10.11

Oct'11

Nov'11

Dec'11

Present Gangs Availability

Remarks

Survey Foundation Tower Erection Stringing


SUPPLY

Km Nos Nos Km

90 256 256 90

67.037 196 196 67.037

Oct'10 Feb'11 April'11 May'11

67.037 186 175 22.849

0 10 21 44.188 2 5 6.213 188 180 29.062 8 16 37.975 3 7 15.000 4 9 15.000 7.975 1 Gang 2 Gangs 4 Gangs
29.062 Kms Paying Out,29.062Kms Final Sag Completed and 5.46 kms Paying out is in Progress 1 Loc. In Progress and 7 Locations ROW problem to be resolved by PGCIL

Stubs Towers Earthwire Hardware

Nos Nos Km Sets

256 256 183 26116

196 196 135.63 23280

Nov'10 Jan'11 Feb'11 Feb'11

196 189 135.633 100%

0 7 0 0

196 189 135.633 100%

0 7 0 0 7
Material in Transit

Issues to be resolved by PGCIL: Foundation: 1. Seven locations are in ROW to be resolved by PGCIL Stringing: 1. 11 KV shut down to be arranged by PGCIL on priority basis