DESCRIPTION
Unit
Oct'11
Nov'11
Dec'11
Jan'12
Remarks
Survey
Km
18
16.86
Jan'10
16.86
2 Locations in Progress and 14 locs.in ROW (5 locs Forest clearnce yet to be received,balance 9 locs in Severe ROW) to be resolved by PGCIL. 2 towers in progress and no front for tower erection 0.150 kms Paying out is in Progress
Foundation
Nos
50
53
July'10
33
20
35
18
2 Gangs
Tower Erection Nos Stringing SUPPLY Stubs Towers Earthwire Hardware Nos Nos Km Km
50 18
53 16.82
Oct'10 April'11
21 0
32 16.82
25 0
28 16.82
7 1.902
12 5.135
4 4.456
5 5.327
2 Gangs 1 Gang
50 50 37
53 53 34.748 4663
53 41 34.748 90%
0 12 0 10%
0 12 0 10%
53 53 34.748 100%
0 0 0
Sets 4066
Issues to be resolved by PGCIL: Foundation: 1. Fourteen locations are in ROW (5 locations for Forest clearnce yet to be Received and 9 locations in ROW) 2. Frequency changes in route length and tower supply is getting delayed still route is not finalized
DESCRIPTION
Unit
Oct'11
Nov'11
Dec'11
Remarks
Km Nos Nos Km
90 256 256 90
0 10 21 44.188 2 5 6.213 188 180 29.062 8 16 37.975 3 7 15.000 4 9 15.000 7.975 1 Gang 2 Gangs 4 Gangs
29.062 Kms Paying Out,29.062Kms Final Sag Completed and 5.46 kms Paying out is in Progress 1 Loc. In Progress and 7 Locations ROW problem to be resolved by PGCIL
0 7 0 0
0 7 0 0 7
Material in Transit
Issues to be resolved by PGCIL: Foundation: 1. Seven locations are in ROW to be resolved by PGCIL Stringing: 1. 11 KV shut down to be arranged by PGCIL on priority basis