Formwork: Board are ready Manpower : 43 Carpenter Available Futher requirement : 50 MT - 50 m mobile crane Target working duratuion - 4 days
2 Payment
3 Further issue # Procurement & Store person not available # Draftsman will be deployed urgently. # Concrete pumping issue to be finalized - SNB Under job # After raft materials @Grocon - Material available - Under sorting @ Column- By Peri not available - Lead time - 12 Weeks - We have to find alternate arrangement for column & shear wall, possible with existing timber beam @ Slab formwork - Ulma is consistantly failing, BG us under negotiation by Mr. Mukherjee - Intial levels will be done by Cup-lock system- Times Engineering has been coordinated. @ Steel material to be procured - Drawings are available up to Ground floor. # Passenger Hoist - Probable date from Dubai - End of Sept ?? - Balance planning 4 # Planning - Replacement of Sridhar